SEPTEMBER 2010

Managing Risk Through The Project Life-Cycle

Neil Douglas

Technical Director, Natural Power

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Content

1. Natural Power: An Overview

2. Project and Portfolio Due Diligence: Best Practice Life-cycle Approach

3. Trends and Innovation in Due Diligence

4. Emerging Challenges : Complexities in Onshore and Offshore Wind

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Core services:

Resource analysis, design and risk reduction

Project design, EIA and consents management

Construction and contract management

Turbine technology expertise

Asset management and performance analysis

360o Due diligence

Technical innovation for risk reduction

ForeSite - Power forecasting

WindCentre - 24/7 control room

Ventos – CFD for Complex Flow Analysis

ZephIR – wind lidar

OceanPod – Offshore data platform

Life-cycle renewable

energy consultancy and

management services

Established in 1996

140 staff in 12 offices

throughout Europe

and Americas

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

• Client base: International Utilities, Debt and Equity Providers, IPPs

• Key Experience:

• 20GW+ of bankable energy yield and due diligence studies

• 2000MW+ of project consent on behalf of a diverse client base

• 600MW of construction management projects

• 600MW of wind plant under our asset management services

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

• Partners in offshore wind and marine renewables with SeaRoc

• Marine operations management

• Port and vessels auditing

• Offshore engineering

• Offshore QHSE

• Data management

• SeaPlanner™

• Offshore wind farm project due diligence

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Project and Portfolio Due Diligence: Best Practice Approach

The 4 key criteria:

Consentable reasonable prospect of gaining workable planning permits

Buildable economic solutions to construction challenges

Financeable secure contracts (turbines, BOP, PPA) and bankable reports

Operable capable of low-risk, high-availability, long-term generation

Shift in focus throughout the project life-cycle

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

• Pipeline and pre-construction projects (typically acquisition transactions)

• Focus tends to be on...

• Development team: resources and ability to deliver

• PPA market (FiT, CfP, merchant, certificate)

• Land agreements and option leases

• Environmental constraints, policy, community, stakeholders =>Consents

• Wind quantity and quality: Energy, siting and warranties

• Confirming construction and access solutions

• Grid connection agreement process

• Cost of energy model - £/GWh

Focus on ensuring project is Consentable, Financeable and Buildable

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

• Construction phase projects (debt, equity and acquisition transactions)

• Focus on...

• Power Purchase Agreement

• Detailed energy yield analysis and site classification

• Turbine and service suppliers; contracts and warranties

• Balance of Plant suppliers and contracts

• Grid connection agreements

• Planning conditions (discharge and risks)

Focus on ensuring project is Buildable, Financeable and Operable

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

• Operational projects (refinancing/acquisition transactions and ongoing

investment management)

• Focus shifts to...

• Historical energy production and budget performance analysis

• PPA

• Operational costs

• Operational management strategies

• Turbine and infrastructure condition inspections

• End of warranty issues

Focus on ensuring project is Operable and Re-financeable

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Trends in the Finance Market

• Internationalisation and consolidation (Europe and US)

• Evolution of debt and equity provider risk profiles

• Shorter debt terms leading to more pro-active investment

• The rise of private equity

• Earlier and phased due-diligence

• More depth and detail required at financial close

• Life-cycle project assessment – a standardised Project Credit Rating

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Trends in the Project Market

• Fluid and growing market – consolidation

• Higher risk projects (consenting issues and technical complexity)

• Reduced number of wind projects that meet the highest standards

• More complex PPA structures

• Offshore – increasing interest from debt providers

• Biomass – significant expansion (feedstock the key)

• Marine – over the horizon (proving devices remains king)

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Trends in the Approach to Due Diligence

• All players are operating in a maturing market

• Well-established stable of recognised TAs and DD providers

• Second opinion on key project issues (energy yield, foundations, etc)

• Application of present day best-practice and tools/methods

• Smart, well informed investors

• Sophisticated knowledge and experience

• Application of lessons learned

• Pro-active portfolio and fleet management

• Debt investors thinking more like equity investors

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Innovation in Due Diligence: Technology

• Application of new technologies in risk management

• CFD for complex flow analysis

• Meso-scale climate modelling for use in yield prediction

• Lidar (laser anemometry) for high-density resource data collection

• Referenced and proven tools/methods/assumptions – No Black Boxes

• Sophistication in energy yield uncertainty analysis

• Beware single points – understand the curves

• Application of operational experience: reality v’s predictions

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Emerging Challenges: Complex Flow on Onshore Wind Farms

Risks:

• Increasing presence of complex flow due to forestry and complex terrain (higher

risk projects) = Turbulence, shear, inflow angle, veer

• Risk of turbine power curve under-performance and inaccuracies in EYA

• Risk of increased maintenance costs and turbine fatigue (and failures)

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Emerging Challenges: Complex Flow on Onshore Wind Farms

Mitigation:

• Thorough, high-density data collection

• Take an advanced modelling approach to understand the wind quality - CFD

• Reduces risks in turbine micro-siting, site classification and energy yield analysis

• Post-construction: detailed appraisal and turbine management

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Emerging Challenges: Project Complexity Offshore

• Cost of early wind data collection is often viewed as prohibitive (£3-5m)

• Wake models for vast and dense offshore projects: area of active research

• Significant implications for uncertainty of energy yield predictions

• 1% difference between P50 and P90 (10 year) for a 250MW = ~£800k of provable

revenue per annum

• Inter-dependancy between technical and operational disciplines offshore

• e.g. Vessels – MetOcean – Accessibility - O&M Strategy – Forecasting = GWh

• Mitigation: Application of state of the art modelling tools and methods

Insert your Company Logo here

APRIL 2010

SEPTEMBER 2010

Conclusions:

• Increasing sophistication in wind energy finance market

• Growing but challenging project market (both quantity and quality)

• Increasing capability of available tools to address risks and identify opportunity

• Trend towards a fluid market in repackaging

• Changes in risk profiles and terms

• More pro-active project management by lenders (both debt and equity)

SEPTEMBER 2010

Thank you.