Page 1: NPP Construction – Experience of CNEC

NPP Construction

Experience of CNEC

Sep.24,2014

Page 2: NPP Construction – Experience of CNEC

NPP Under construction

Content

Advanced Construction Technology

Project Management Experience

Project Contract System

2

Page 3: NPP Construction – Experience of CNEC

Rongcheng NPP

Fangchenggang NPP

Changjiang NPP

Hongyanhe NPP 3/4#

Haiyang NPP

Tianwan NPP

Fangjiashan NPP

Sanmen NPP

Ningde NPP 3/4#

Fuqing NPP 2-4#

Yangjiang NPP2-6#

Taishan NPP

Chashma NPP C3、C4 NPP

Pakistan

Ⅰ NPP Construction Performance of CNEC Ⅰ NPPs Under construction Distribution of NPPs Under construction (27

Units)

Page 4: NPP Construction – Experience of CNEC

Ⅰ NPPs Under construction

NPPs Under construction

4

25 NPP units in Mainland of China;

2 NPP units in Pakistan;

27 NPP units under construction in total,

globally accounting for 40%.

Page 5: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology Design research and application

Application 1: Engineering applications, such as simulation of significant hoisting plan, simulation of engineering construction progress combining 3D project model and P3 technology, inspection of installed items collision, virtual wandering of installation result, assistant of blocking construction etc..

Research focus: Key technologies, for example 3D model design (using advanced software as auxiliary tools, such as PDS, PDMS) , synchronization design in different place, onsite construction simulation etc.

M

od

el

of

Li

ng

’a

o

N

P

P

Ph

as

e I

5

Page 6: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Design research and application Application 2: By loading of various information, functions (such

as visual blocking construction, several disciplines construction management and coordination, information searching). The research and application of 3D dummy technology will greatly improve the project management level.

6

Page 7: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Reactor primary pipes automatic welding research: A complete narrow-gap automatic welding procedure is formed, and through onsite test and formal welding, this technology is proved to be advanced with reliable parameters and stable properties. It has been applied in China’s NPP site, such as Ningde, Hong Yanhe, Yangjiang, Fuqing, Fang Jiashan Project and so on.

Primary pipes

automatic welding

research

Construction technology research and application

7

Page 8: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Large cubic content of

concrete grouting

Construction technology research and application

The concrete grouting for Taishan 1# NI raft foundation lasts 86 hours, and 9300m³ concrete is poured, which create a record of the largest cubic content of NPP concrete grouting in once around the world. No obvious crack occurred in the concrete structure of the raft foundation which was grouted in one time.

8

Page 9: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Construction technology research and application

:Steel lining dome hoisted in a whole

Steel lining dome of Reactor Building (HRA) is the largest steel structure part to be whole hoisted during the steel lining construction. This dome weight is 231t.

9

Page 10: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Construction technology research and application

Containment shell slip-form construction with hydraulic lifting devices

The system of “slip-form construction with hydraulic lifting devices” settle a difficult problem during double-wall containment construction. This formwork system with advanced technology and high grade of automatic mechanization, reduces the labor hardness, and at the same time, ensures the construction quality of containment cylindrical.

10

Page 11: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Construction technology research and application :In the field of NPP pool construction around the world,

3D of IRWST pool adopts the technology of welding without backing, with all the welds passed the 100% radiographic test (RT).

11

Page 12: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

Construction technology research and application :Special technology systems and intellectual property

rights in Nuclear power construction field come into being; 298 items of patent and 31 items of software copyright are awarded, with several items of construction technologies kept ahead of the world.

12

Automatic

welding

technique for

reactor primary

piping

Automatic welding

technique for steel liner

in reactor building

……

Super-strength post-

pre-stressed tensile

construction technique

of large tonnage

Manufacture and

erection techniques

for reactor primary

piping

Integral erection

technique for dome

steel liner of reactor

building

Monolithic pouring

technique for mass

concrete floor in NI

building

slip form

construction

technique for NI

containment shell

Construction technique for

double dome of reactor

building

Transport and lifting

technique for super-

heavy equipment

Page 13: NPP Construction – Experience of CNEC

Ⅱ Advanced Construction Technology

New technology and new process research

13

No. Designation

1 Automatic welding technique research

2 NPP primary pipe ultrasonic test automatic process research

3 Reinforced concrete chloride elimination and superficial sealing technology research

4 Digitized NPP construction technology research

5 CV module installation technology research

6 Fiber concrete technology research

7 NI building main control room noise reduction by absorption technology research

8 Application research of PDMS and P6 combination in NPP construction

9 AP1000 NPP CA20 module vertical assembling process research

10 ……

Page 14: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

Nuclear safety culture system

One principle: Prevent Problems, Work Properly, Do It Right the

First Time, Keep Improving

Two “first” : Safety First, Quality First

Three “Serious”: Serious Plan before the Event, Serious

Implement during the Event and Serious Inspection after the Event

Four “all things”: All things have rules to follow, all things

have someone to take charge, all things have someone to inspect

and all things are well documented

Systematic nuclear safety culture system has been formed through nuclear power construction of 30 years

14

Page 15: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

QA system in nuclear power construction

Establishment of system document: documents of 4 levels

first level QA program

second level management procedure

third level Department work procedure

fourth level

Field operating procedure, quality records /sheets

QA program

procedure

Department work procedure

Field operating procedure

15

Page 16: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

QA system in nuclear power construction Quality risk precaution: stepwise establish and implement

quality risk analysis and precaution improvement measures

(network is as follows):

group

Team/department

group

workshop section workshop section

full-time QC

Poject

Team/department

quality risk

precaution

Annual analysis and precaution

Monthly analysis and precaution

Weekly analysis and precaution

Pre-shift analysis and precaution

Statement

control line from the top down

report line from down top

feedback & communication

line for engineering

16

Page 17: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

QA system in nuclear power construction

QA system: a mature QA system has been formed, and it is verified

that the system is effective by nuclear power under constructed and

constructed.

17

quality policy, target

quality planning

quality control

quality assurance

quality improvement

Quality Management

Page 18: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

Multi-project management system in nuclear power construction

18

Establish multi-project organization and management system

characterized by the following features.

Multi-project management

system

Intensification

Standardization Specialization

informatization

Page 19: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience

Standardization management • Establish standardization

management system

• Compile and issue universal

enterprise standards

• Compile and issue universal multi-

project management procedures

• Pursue safety management and behavior to

standardization

• Establish standard evaluation model for

project progress

• Establish continuously improving system

of innovation and experience feedback

19

Page 20: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience Specialization management

• Promote company development by

development of specialization, and cultivate

construction team of nuclear power

industrialization and specialization

• Implement specialization according to

structure of industrial chains, and establish

large relatively independent specialization

organizations: Nuclear power design institute,

Civil work company, installation company and

maintenance company

• Set up more detailed specialization teams

under large specialization organizations, such

as NDT center, EM2 team, steelwork

construction team, electrical team and

mechanization company, etc.

20

Page 21: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience Intensification management

• Establish intensification management

platform

• Intensive training & distribution for

talents

• Intensive procurement & distribution for

engineering materials

• Intensive procurement & distribution for

machines & tools and equipment • Intensive training & certificating

for welders

• Intensive transformation for

procedure qualification

• Off-site intensive prefabrication

for pipes

21

Page 22: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience Informatization management • Establish a unitive informatization

management platform

• Unitive informatization management

platform for schedule control based on P6

• OA office informatization platform covering

all of the company

• Human resource informatization

management platform covering all of the

company

• Multi-project video conference management

system • Independent research and

• development of

informatization

• management platform for

multi-

• project management 22

Page 23: NPP Construction – Experience of CNEC

Ⅲ Project Management Experience Continuous improvement and innovation of multi-project management

system 。

23

Continuous improvement and

innovation

Execute management mode of “standardization, intensification,

specialization and informatization”

In-depth study construction

technique and organization

model for new reactor types

Give full play to mature management experience of projects under construction, and establish

feedback mechanisms

Innovate organization & management model,

continuously improve & innovate management

system

Page 24: NPP Construction – Experience of CNEC

Ⅳ Project Contract System

EPC、PC

Consultant

BOT

24

Page 25: NPP Construction – Experience of CNEC

欢迎各国、各机构共享中国核建核电建设经验 Welcome each country & organization to share nuclear power construction experience of CNEC

25