nrrl bioreactor construction update week of february 11 · 2-inch pvc injection wells. temporary...
TRANSCRIPT
![Page 1: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/1.jpg)
Introduction
NRRL Bioreactor Construction UpdateWeek of February 11
(photos taken 02/13/02)
![Page 2: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/2.jpg)
Update Summary
NRRL Bioreactor Construction• Construction progress meeting held on
February 13. • Work continued on the placement of the
exposed geomembrane cap (EGC) on the south slope.
• Work continued on the construction of the toe drain and gas collector trenches on the west slope.
![Page 3: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/3.jpg)
Progress on South Slope
South Slope: February 5
South Slope: February 13
![Page 4: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/4.jpg)
EGC Placement
Feb 5
Feb 13
![Page 5: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/5.jpg)
Deploying Geomembrane
Deploying Geomembrane
![Page 6: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/6.jpg)
Deploying Geomembrane
![Page 7: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/7.jpg)
Deploying Geomembrane
![Page 8: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/8.jpg)
Deploying Geomembrane
![Page 9: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/9.jpg)
Deploying Geomembrane
![Page 10: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/10.jpg)
Deploying Geomembrane
![Page 11: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/11.jpg)
Deploying Geomembrane
![Page 12: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/12.jpg)
Placing Sandbags
Sand bags are used to hold geomembrane temporarily in place.
![Page 13: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/13.jpg)
Fusion Welding
![Page 14: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/14.jpg)
Fusion Welder
Geomembrane rolls are fusion weldedtogether with a doublehot wedge weld.
![Page 15: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/15.jpg)
Fusion Welder
Double Wedge Fusion Welder
![Page 16: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/16.jpg)
Anchor Trench
EGC Anchor Trench
![Page 17: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/17.jpg)
Extrusion Weld on Anchor Trench
The weld at the anchortrench overlap is an extrusion weld.
![Page 18: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/18.jpg)
Injection Wells
The EGC is installed on the surface of landfill, above the injection wells. The wells must be extended through thecap after placement in a manner that provides a gas-tight connection. The following slides illustrate this process
![Page 19: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/19.jpg)
Solid Wasteand Daily
Cover
Soil
2-inch PVC injection wells TemporaryCaps
Thermocouple Wire
Process of Constructing EGC
over Injection Wells
EGC – Wells 1
![Page 20: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/20.jpg)
VFPE Geomembrane Placed on Surface of Landfill
Process of Constructing EGC
over Injection Wells
EGC Wells 2
![Page 21: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/21.jpg)
Geomembrane Cut Around Wells
Process of Constructing EGC
over Injection Wells
EGC Wells 3
![Page 22: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/22.jpg)
Geomembrane Cut Around Wells
EGC – Wells 4
Process of Constructing EGC
over Injection Wells
![Page 23: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/23.jpg)
Extrusion Weld Boots
EGC – Wells 4
Process of Constructing EGC
over Injection Wells
![Page 24: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/24.jpg)
EGC and Wells
As soon as geomembraneis pulled over wells, locationis marked.
At a later time, the geomembrane is cut aroundwell.
![Page 25: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/25.jpg)
Temporary Well Boots
Temporary Well Boots
![Page 26: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/26.jpg)
Temporary Well Boots after Well Extension
![Page 27: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/27.jpg)
Permanent Well Expansion Boots
![Page 28: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/28.jpg)
Boot Construction 1
Construction of Expansion Boot: 1 Note: Geomembrane used
for boot is illustratedin red for clarity.
Note: Boots are prefabricatedon site.Geomembrane Collar Around Well
![Page 29: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/29.jpg)
Boot Construction 2
Construction of Expansion Boot: 2 Note: Geomembrane used
for boot is illustratedin red for clarity.
Note: Boots are prefabricatedon site.
Boot Base Sheet
Extrusion Weld
![Page 30: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/30.jpg)
Boot Construction 3
Construction of Expansion Boot:3 Note: Geomembrane used
for boot is illustratedin red for clarity.
Note: Boots are prefabricatedon site.
Note: Boot Collar is Shownslightly expanded for clarity.
Boot Bellows
Extrusion Weld
![Page 31: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/31.jpg)
Boo Construction 4
Construction of Expansion Boot: 4 Note: Geomembrane used
for boot is illustratedin red for clarity.
Note: Boots are prefabricatedon site.
Note: Boot Collar is Shownslightly expanded for clarity.
Neoprene Gasket
Clamp
![Page 32: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/32.jpg)
Prefab Boots
PrefabricatedWell Boots
![Page 33: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/33.jpg)
How Boot Works - 1
How Does Expansion Boot Work?
Initial Condition
![Page 34: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/34.jpg)
How Boot Works - 2
How Does Expansion Boot Work?
Landfill Settles
![Page 35: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/35.jpg)
How Boot Works - 3
How Does Expansion Boot Work?
Adjust Collar
![Page 36: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/36.jpg)
MTG
A similar booting system is used for the MTG sensors
![Page 37: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/37.jpg)
MTG 2
A similar booting system is used for the
MTG sensors
![Page 38: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/38.jpg)
West Side Toe Drain
Construction of Toe Drain and Gas Collectors on the
West Side
![Page 39: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/39.jpg)
Welding Gas Pipe
![Page 40: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/40.jpg)
Bioreactor Sign
![Page 41: NRRL Bioreactor Construction Update Week of February 11 · 2-inch PVC injection wells. Temporary Caps. Thermocouple Wire. Process of Constructing EGC over Injection Wells. EGC –](https://reader033.vdocuments.net/reader033/viewer/2022053101/605fcd204fb4553d613b5e0b/html5/thumbnails/41.jpg)