本公司致力于改善钢筋连接现状,开发核电市场。We remain committed to improving splicing quality for reinforcing bars , as a reuslt, we have already made a breakthrough in connecting the mesh in the construction of nuclear plant.

Hong Yan He Nuclear Power Plant 1/17

我们研发并设计了竖向网片施工方案,成功通过红沿河核电站试用。An innovative project for vertical-rebar mesh have been designed and made its first debut in Hong Yan He NuclearPower Station.

2/17

现场工作人员起吊网片In preparation for lifting the mesh

3/17

起吊网片Lift the mesh (6m×9m)

4/17

网片就位Position

5/17

挤压接头Splicing

6/17

挤压接头Splicing vertically

7/17

挤压接头Splicing

8/17

测试接头安装质量Inspection after splcing

9/17

连接完成Complete

10/17

竖向连接 Splicing horizontally

11/17

水平连接Splicing horizontally

12/17

水平连接Splicing horizontally

13/17

完成连接Complete

14/17

I级接头合格,符合JGJ107-2010技术要求。All the fitted products on site meet the JGJ107-2010 for I level.

15/17

16/17

现场随机取样进行检验,全部合格。All the ramdom samples taken from fitted products on-site arequalified.

17/17

现场对轴向偏差达40mm钢筋进行连接,并通过检测。The reinforcing bars with misalignment up to 40mm are well connected on site and meet the requirement.