nvironmental protection eport 2004 › en › documents › enviromental_protection_rep… · 2...
TRANSCRIPT
1
Paks Nuclear Power Plant Inc.
ENVIRONMENTAL PROTECTION REPORT
2004
Paks 2005
Paks Nuclear Power Plant Environmental Report on
year 2004
2
Edited by
Sallai Orsolya
environmental protection engineer
Collated by
Volent Gábor Pécsi Zsolt
Head of Industrial Safety Department Environmental Protection Team Leader
Bujtás Tibor Demeter Károly
Head of Radiation Protection Section Head of Operational Department
Dr. Schunk János Radnóti István
Head of Chemistry Department Safety Manager
Signed by
Kovács József
Chief Executive
3
Co-Editors:
Sallai Orsolya
Pécsi Zsolt
Fink Gábor
dr. Schunk János
Köves László
Feil Ferenc
Ranga Tibor
Nagy Zoltán
Demeter Károly
4
Contents
1 Introduction ...................................................................................................................................... 5
2 Company Profile .............................................................................................................................. 5
3 Nuclear Enviromental Protection ..................................................................................................... 8
3.1 Radioactive Emission ............................................................................................................... 9
3.2 Enviroment Control ................................................................................................................ 12
4 Annual Evaluation Report on the Enviromental Protection Activities of Paks Nuclear Power Plant
in 2004................................................................................................................................................ 15
4.1 Water Quality Protection ........................................................................................................ 15
4.1.1 Surface Water Protection ................................................................................................ 15
4.1.2 Subsurface Water Protection ........................................................................................... 21
4.2 Atmospheric Purity Protection ............................................................................................... 22
4.3 Waste Management – Inactive Waste .................................................................................... 22
4.3.1 Hazardous Waste ........................................................................................................... 22
4.3.2 Industrial and production Waste ..................................................................................... 24
5 Abolishing the Consequences of the Serious Incident that Happened in Unit 2 of PNPP in April
2003 .................................................................................................................................................... 25
5.1 Ensuring the Autonomous Operation of the No. 1 Pit ........................................................... 26
5.2 The Licensing of the Restoration ........................................................................................... 26
5.3 The Fulfilment of the Removal Contract .............................................................................. 27
5.4 Other Activities Related to the Removal ............................................................................... 28
6 Radioactive Waste Management .................................................................................................... 28
6.1 Developments in connection with the Management and Interim Storage of Radioactive
Waste at PNPP .............................................................................................................................. 28
6.2 Low and Intermediate Level Solid Waste .............................................................................. 30
6.3 High Activity Solid Radioactive Waste .................................................................................. 33
6.4 Liquid Radioactive Waste....................................................................................................... 35
6.4.1 Evaporation Residues ..................................................................................................... 35
6.4.2 Evaporator acidifying solution ....................................................................................... 35
6.4.3 Spent primary loop ion-exchange resins ........................................................................ 36
6.4.4 Active solvent mixtures .................................................................................................. 36
6.4.5 Contaminated technological boric acid solutions ........................................................... 36
7 Enviromental Protection Management System .............................................................................. 38
7.1 Enviromental Politics of Paks Nuclear Power Plant .............................................................. 38
7.2 Enviromental Centered Goals and Programs ......................................................................... 40
8 Transport of Hazardous Products and the Safety Advisory System............................................... 44
9 Abbreviations and concepts ........................................................................................................... 46
1 Introduction
Paks Nuclear Power Plant (PNPP) is Hungary’s major electric power company.
Under the aegis of environmentally sound power production, the PNPP established the Environment
Centered Control System in 2001. In 2002 the Hungarian Standards Institution standardized the
Environment Centered Control System by the MSZ EN ISO 14001:1997 standard.
The second annual audit (and inspection) of the Environment centered Control System was carried
out by the Hungarian Standards Institution in November 2004. On the audit the operation of the
PNPP environmental protection management system was proved to be adequate. The continuous
5
improvement in environmental protection projects was averred, so the MSZ EN ISO 14001:1997
standard deed of assignment was confirmed again by the Hungarian Standards Institution.
2 Company Profile
The PNPP’s basic activity is electric power output. Last year the PNPP produced 36 % of the home
electric power production, i.e. 11 915 GWh (1 GWh = 1,000,000 kWh).
Since 1988 (one year after starting Unit 4) the amount of electric power output produced by the four
blocks of PNPP has fluctuated between 13,400 and 14,180 Gwh; except for the years 2003 and
2004 when, due to the incident in 2003, Unit 2 did not work most of the year in 2003 and in 2004 as
well, so the nuclear power plant functioned in a 3-unit mode because the consequences of the
incident had to be abolished. In 2004, the utilization rates of the units were the following:
Unit 1: 87,5 %
Unit 2: 29,3 %
Unit 3: 88,5 %
Unit 4: 85,7 %
The electric power output of PNPP from the start till nowadays is presented in Figure 1.
1. figure translation:
év = year
Figure 1. Electric power output of the PNPP.
Hungary’s total energy consumption is added up by home production and import. The proportion of
6
home production to import is illustrated in Figure 2, where “other home energy production”
includes coal-, oil-, gas-fired power plants and reviving energy sources.
2. figure translation:
atomerőműi termelés = electric power production of the power plant
egyéb hazai termelés = electric power production of other home sources
import = import
Figure 2. Hungary’s electric energy consumption
The four units of the PNPP started between 1982 and 1987. Their operating data are summarized in
Table 1 below.
(Table 1)
7
1. table translation:
típus = type
nyomottvizes, vízhűtésű, víz moderátorú VVER-440 V-213 energetikai reaktor = pressurized water,
water-cooled, water moderated VVER-440 V-213 energetic reactor
a primerköri hurkok száma = number of primary loops
hőteljesítmény = heat output
turbinák száma = number of turbines
blokkok névleges villamos teljesítménye = nominal electric capacity of the Units
az aktív zóna töltete = reactor core loading
42 tonna urándioxid = 42 tons of uranium dioxide
Table 1. Basic operational data of the PNPP.
3 Nuclear Enviromental Protection
In the evaluation of the operation of the PNPP besides nuclear safety and energy production
efficiency indexes, environmental effects also play an important role. The basic requirements
include to have detailed information on the nuclear environmental effects of the power plant. It is
also very important that the measure of the effects mentioned above don’t exceed the levels allowed
by the authority regulations. The main task of radiation protection activity was to prove that the
PNPP complies the derived emission limits and the primary dose restriction applied to the operation
of the power plant in 2004, too. For the documentation radiation indexes of the environment and
direct survey data were used.
In order to reach the goals mentioned above, the Radiation Protection Section accomplished a
comprehensive inspectorial program and took necessary actions. In 2004, similarly to past years,
8
the nuclear environmental protection was characterized by two-levelled control including
measurement taken by remote-controlled metering system and sampling based laboratory
measurement.
3.1 Radioactive Emission
The new emission limitation system appointed by the 15/2001 (VI.8.) decree took effect in 2004.
This limitation compares the proportion of airborne and liquid emission to that of isotope specific
emission limits. The aggregate emission data and their ultimate value criterion are presented in
Table 2. In summary it can be stated that the PNPP utilized 0.27% (0.15% liquid, 0.12% airborne)
of the emission ultimate value (emission criterion: 2.67 × 10-3
).
The emission ultimate value criterion of the PNPP in 2004: 2.67 × 10-3
, i.e. 0.27%.
The emission ultimate value criterion applied to a certain isotope and a emission type is the quotient
of the emission ultimate value and the amount of isotope emitted.
Calculation of the ultimate value criterion:
Elij = emission ultimate value applied to i radionuclide and j emission type (Bq/year)
Rij = yearly emission applied to i radionuclide and j emission type (Bq/year)
9
2. table translation:
Izotóp-csoportok = Isotope groups
Összes kibocsátás = Total emission
Kibocsátási határérték kritérium = Emission ultimate value criterion
Légnemű kibocsátások = Airborne emissions
Korróziós és hasadási termékek = Corrosion and fission product
Radioaktív nemesgázok = Radioactive noble gases
Radiojódok = Radioiodines
Trícium = Tritium
Radiokarbon = Radiocarbon
Összes légnemű kibocsátás = Total airborne emission
Folyékony kibocsátások = Liquid emissions
Alfa-sugárzók = alpha-emitters
Összes folyékony kibocsátás = Total liquid emission
Table 2. Summarized emission data.
Emission values of the PNPP are compared to international data in Table 3, which shows emission
indexes normalized for energy production of PWR (pressurized water reactor) nuclear power plant
units similar to the PNPP’s. International data are available from only the 1995-1997 period, so the
UNSCEAR1 used these data (except for emission indexes of radiocarbon, which are available from
only the 1990-1994 period) in its report in 2000.
It appears from the comparison that the amount of corrosion and fission products has seemingly
increased. According to the new regulations, emission data are calculated from isotope selective
measuring. Unmeasured isotopes are counted in with their detection ultimate value. In past years
these values were determined by measuring total-beta radiation.
In case of Paks liquid emission the amount of corrosion and fission products as well as that of
tritium is under the international average.
1 UNSCEAR stands for the United Nations Scientific Committee on the Effects of Atomic Radiation.
10
3. table translation:
Radionuklid = Radionuclide
Év = year
Légnemű kibocsátások = Airborne emissions
Összes aeroszol = Total aerosol 131
I egyenérték = 131
I equivalent
Összes nemesgáz = Total noble gas
Összes trícium = Total tritium
Total radiocarbon = Total radiocarbon
Folyékony kibocsátások = Liquid emissions
Korróziós és hasadási termékek = Corrosion and fission product
Trícium = Tritium
Table 3. Amount of the PNPP radioactive emission in consideration of UNSCEAR data mirror.
Note: The international data are applied to pressurized water reactor units working the same way as
those of the PNPP (UNSCEAR Report 2000)
* : average of the 1985-2003 period
** : average of the 1988-2003 period
*** : average of the 1995-1997 period
3.2 Enviroment Control
The PNPP runs the Industrial Environmental Radiation Protection Control System (Üzemi
Környezeti Sugárvédelmi Ellenőrző Rendszer, ÜKSER). The radiation protection control of the
PNPP’s environment is carried out by telemetric systems, sampling inspections and lab-
examinations. The locations of the sampler and telemetre stations in an area of 30-km semi-
diameter is shown in Figure 3. The lab-examinations cover the environmental sphere and factors of
11
the food-chain that means data processing and measurement of approximately 4000 samples yearly.
The operation of the PNPP did not have directly measurable effects on the radiation rates of the
environment in 2004. The measurements of dose rate metering sondes at “A” and “G” type
measuring stations and TL detectors at other stations showed dosage rate and dose of the natural
gamma-radiation.
3. ábra szószedete
távmérő és mintavevő állomás (A típusú) = telemetre and sampler station (A type)
mintavevő állomás (B típus) = sampler station (B and C type)
vízmérő és mintavevő állomás = flood-measuring post and sampler station
meteorológiai mérőtorony = meteorological instrument tower
az ÜKSER központja (KAR) = the ÜKSER Centre
Környezetellenőrző Laboratórium = Environment Control Laboratory
Figure 3. Locations of sampler and telemetre stations near the PNPP.
Considering the correction derived from the change of the physical variables, the average dose rates
values measured by ALNOR TL dose-meter (Figure 4) correspond to the data of earlier years’
reference level period. It can be stated that it is not possible to conduct the adjunct of the nuclear
power plant from the data of the 2004 environmental dosage measurement. This phenomena is in
12
accord with the picture derived from the atmospheric emission of radioactive materials. According
to this picture the adjunct arising from the power plant is much less than the value of the natural
background radiation and its fluctuation, so it is undetectable by direct dosage measurement
methods.
4. figure translation:
dózisteljesítmény = dose rate
mintavevő állomások = sampler stations
Figure 4. Monthly average environmental dose equivalent rate of the environmental gamma
radiation measured by ALNOR TLD at telemetre and sampler stations in 2004.
Approximately 2.4-3.7 Bq/kg of radionuclide (60
Co) emitted from the power plant was found in
some of the Danubian mud samples taken from the discharge culvert and some further places.
Emitted radioactive isotope was not detected in the soil, grass, fishpond and mud samples taken
near the measuring stations. In the case of tritium the yearly average accrue of radioactive materials
emitted into the Danube was less than 1 Bq/dm3, while examining all other radionuclides it was less
than 0.1 mBq/dm3. The measurements were taken after total blending. Emitted radioactive isotopes
were not found in milk and fish samples.
The direct environmental presence of radioactive isotopes was undetectable or occasionally showed
low concentration in spite of the accurate examination methods. Concerning the surface air samples,
among the radioaerosols emitted form the power plant only the 54
Mn and 60
Co was detectable in
activity-concentration of 10 µBq/m3
at the outmost at “A” type measuring stations. The
radiocarbon was detected in concentration of 0.1-1 µBq/m3. The activity concentration of tritium
was estimated at 10 mBq/m3
while that of radioactive noble gases was approx. 100 mBq/m3
in the
same place. In the fall-out samples there were no detectable radioactive isotopes emitted by the
PNPP. The samples were taken from the area 1-2 kilometers far from the power plant.
13
In summary, according to the results of the 2004 environmental measurements, it can be stated that
the environmental effects of Interim Storage of Spent Fuel Cartridges of the PNPP were negligible.
The PNPP radiation protection organization using emission and meteorological data as well as
direction models calculated the public extra exposure dose. According to the calculation the public
extra exposure dose derived from liquid emission, applied to a critical public group is 57 nSv that
corresponds with the levels of extra exposure dose before 2003.
4 Annual Evaluation Report on the Enviromental Protection Activities of
Paks Nuclear Power Plant in 2004
4.1 Water Quality Protection
4.1.1 Surface Water Protection
The PNPP is the largest user of raw water, so it takes great care of water quality protection. The
amount of coolant and technological water taken from surface waters was 2.17 billion m3 in 2004. It
is similar to year 2003 and less than in the years before 2003 (Figure 5.). The reason for this
phenomenon was that Unit 2 did not produce electric power in most of the year of 2003 and 2004.
The social featured drinking-water utilization provided from confined-water wells was 238 583 m3.
Although the emitted cooling water did not lead to the thermal pollution of the Danube, it caused
heat-loading of the river. The degree of the warming up does not disturb the ecological balance. The
PNPP kept the heat-scale and the water temperature maximum licence in 2004, too.
Because of its good quality, it is possible to utilize the condenser water. It also provides fresh water
supply for the nearby fish ponds. In 2004 7.3 million m3 water was sent to supply the Fadd dead
channel in summer time.
14
5. figure translation:
felhasznált hűtővíz mennyisége [1000 m3/év] = amount of used cooling water [1000 m
3/year]
év = year
Figure 5. Cooling water utilization of the PNPP between 1996 and 2004.
Waste water of the social water use is emitted through the sewage clarification system of the power
plant. The technical control and the Low Danube Environmental Advisory Board (Alsó-Duna-
völgyi Környezetvédelmi Felügyelőség) regularly check the efficiency of the sewage clarification.
The efficiency of the sewage clarification and the quality of emitted water always met the
requirements. 258 000 m3 municipal waste water was issued in 2004.
The results of the 2004 municipal waste water tests are summarized in the table below.
4. table translation:
komponens = component
mért max. érték* = maximum value measured
hatósági korlát = official ultimate value
NH3 – NH4+ N-ben kifejezve = NH3 – NH4
+ given in N
olajtartalom = oil content
Table 4. Parameters of municipal waste water in 2004.
Most of the inactive waste water consists of acid and alkaline contamination waters generated
during desalted water production. The amount of waste water of the softening plant was 132 000 m3
in 2004. The neutralization of waste water takes place in a 10 000-m3
sludge tank. The water quality
and emission of the tanks is under regular technical control. The quality of waste water emitted after
neutralization and emission was satisfactory. The concentration of contaminating substances did not
each the limit values in the discharge culvert.
Emission data of the discharge culvert in 2004 are showed in the Table 5.
15
5. table translation:
komponens = component
mért max. érték = maximum value measured
hatósági korlát1 = official ultimate value
olajtartalom = oil content
összes oldott anyag = total solute
összes lebegőanyag = total suspended-matter
NH3 – NH4+ N-ben kifejezve = NH3 – NH4
+ given in N
Table 5. Water quality parameters of the values measured in the discharge culvert in 2004
14. oldal lábjegyzet: 2Maximum value measured by the Environmental Protection Authority.
3Official ultimate value according to the 3/1984. (II.7.) decree.
The waste water of the softening plant and discharge culvert is regularly checked once a week.
Quality parameters of the discharge culvert are presented in the figures (6 a-b-c) below.
16
6.a. figure translation:
hatósági korlát százaléka* = percentage of the official ultimate value
2004. január = January 2004
2004. február = February 2004
2004. március = March 2004
2004. április = April 2004
2004. május = May 2004
2004. június = June 2004
2004. július = July 2004
2004. augusztus = August 2004
2004. szeptember = September 2004
2004. november = November 2004
2004. december = December 2004
dátum = date
összes oldott anyag = total solute
olajtartalom = oil content
ammónia – ammónium = ammonia – ammonium
17
6.b. figure translation:
hatósági korlát százaléka* = percentage of the official ultimate value
2004. január = January 2004
2004. február = February 2004
2004. március = March 2004
2004. április = April 2004
2004. május = May 2004
2004. június = June 2004
2004. július = July 2004
2004. augusztus = August 2004
2004. szeptember = September 2004
2004. november = November 2004
2004. december = December 2004
dátum = date
összes lebegőanyag tartalom = total suspended-matter content
18
6.c. figure translation:
2004. január = January 2004
2004. február = February 2004
2004. március = March 2004
2004. április = April 2004
2004. május = May 2004
2004. június = June 2004
2004. július = July 2004
2004. augusztus = August 2004
2004. szeptember = September 2004
2004. november = November 2004
2004. december = December 2004
dátum = date
pH alsó korlát = pH lower bound
pH felső korlát = pH upper bound
Figure 6.a-b-c. Water quality parameters of the discharge culvert.
The figures and tables show that the ultimate values were not exceeded.
19
4.1.2 Subsurface Water Protection
The effects of the PNPP’s emissions are monitored by an expanded ground-water controlling well
system. Different parameters are examined – independently on the tested technology – in
approximately 50 ground-water controlling wells. The examinations are carried out accordingly to
water rights licence authorized by the partially determined environmental protection inspection of
the year 2000. In order to follow the proceeding of possible ground-water pollution, water-level of
80 wells are recorded regularly.
In order to prevent ground-water pollution the PNPP started to work out a program for the check of
the conduit-pipe systems, which endanger the open space environment and are neither under cyclic
control nor ranged among safety classes. The program successfully finished in December 2004. The
inspection of the oil extracting station and oil dump system was not doable in 2005, so it was
postponed to 2005. As a result of the condition tests a program for ensuring good condition of the
systems mentioned above was worked out.
In recent years the on-site damage prevention near the two transformers was efficient. The oil
contamination of the soil stopped. The results of the ground-water tests showed that the
contamination concentration was under the official ultimate unit. The Environmental Protection
Authority prescribed quarterly accredited sampling from the observation wells in the area of the two
transformers and TPH and Σ PAH content measurement. The results of the follow-up tests are
presented in the table below.
6. table translation:
Mintavétel időpontja = Date of sampling
kút = well
határérték = ultimate value
Table 6. The results of the follow-up tests ( TPH and Σ PAH content)
6. table footnote: 4
The ultimate values are equal to “B” type contamination ultimate values determined in the
10/2000. (VI.2.) KöM-EüM-FVM-KHVM decree.
20
4.2 Atmospheric Purity Protection
Due to the technology applied at nuclear power plants, the airborne emission is low.
Three traditional, inactive atmospheric load technologies are applied in the Paks in-plant area.
safe diesel generators working as emergency power supply (12 point emitters);
diesel-driven fire water pump (2 point emitters);
painting technology: paint room, paint-spraying booth (2 point emitters).
The PNPP has environmental authority license for all of the technologies mentioned above.
The gr. pollution emitted during the short test runs (200 hours altogether) is relatively small and
hardly has effects on the emission itself.
The concentration of air contaminant materials emitted by the point emitters was measured by
accredited measuring organization. The measuring was carried out by standard emission measuring.
In 2004 the official ultimate value was not exceeded and all operations of the PNPP met the
requirements of air purity protection applied to diesel generators and emergency power supply.
4.3 Waste Management – Inactive Waste
4.3.1 Hazardous Waste
In 2004, 361 455 kilograms of hazardous waste (principally dead oil, waste contaminated with oil,
electric waste, rejected technological chemicals and paint packs) were generated.
The PNPP provided the elimination of 343 629 kilograms of hazardous waste by passing it to
licensed contractors.
The hazardous waste generated on 2004 is showed in Figure 7.
21
7. figure translation::
olajos föld = oil-contaminated soil
egyéb = other
fénycső = luminous tubes
selejt tecnológiai vegyszer = rejected technological chemical
ioncserélő gyanták = ion-exchange resins
nyomdafesték hulladék = book-ink waste
bontott tetőszigetelés = demolished roof structure
ólom akkumulátor = lead accumulator
olajos iszap = oil-contaminated sludge
kommunális szennyvíziszap = communal sewage sludge
veszélyes anyagot tart. göngyöleg = hazardous paint pack
olajos fold = oil-contaminated soil
elektronikai hulladék = electronic waste
fáradt olaj = dead oil
Figure 7. Hazardous wastes occurred in large amount in 2004.
The category, “other” refers to hazardous waste including medical waste, chemicals, office
technology waste, waste containing asbestos, off-warranty period paint, dry batteries, spray bottles,
glue containing hazardous materials, drilling fluid. The weight of each waste type mentioned above
did not reach the 5000 kilograms.
22
Figure 8. The amount of hazardous waste between 1996 and 2004.
Figure 8 illustrates well that the total amount of hazardous waste was smaller than between 1996
and 1997. It is due to that the caustic mud was pronounced to be non-hazardous waste, the decrease
of the amount of waste derived from rejection and the end of changing accumulators. The amount
of nascent hazardous waste significantly increased in comparison with the year 2003, because the
replacing the temporary foundation of the transformers generated crushed stone.
Collection and storage of hazardous waste is provided according to the regulations in the licensed
Hazardous Waste Industrial Collector.
29,5 tons of hazardous waste were stored in the Hazardous Waste Industrial Collector on 31
December 2004. Most of the hazardous waste in the area of the PNPP is 150 tons of communal
sewage sludge, which is treated in the slime-thickener bed.
4.3.2 Industrial and production Waste
Industrial waste is collected separately from communal waste and stored in an appointed place for
selective waste collecting or in a store room.
In the area of the PNPP, the amount of non-hazardous industrial waste was 55,7 tons at the of 2003.
In 2004, 921 tons of non-hazardous industrial waste were generated during the operation of the
PNPP. In 2004 the PNPP sold 795 tons of non-hazardous industrial waste for further utilization and
placed 83.8 tons of inapplicable waste into industrial waste stores. The total amount of non-
hazardous waste remained from the year of 2003 and generated in 2004 was 976.7 tons.
The industrial waste traffic in 2004 is presented in the figure below.
23
9. figure translation:
lerakóban elhelyezett = placed in waste stores
telephelyen tárolt = stored in waste depots
hasznosított = utilized
Figure 9. Industrial waste traffic in 2004.
5 Abolishing the Consequences of the Serious Incident that Happened in
Unit 2 of PNPP in April 2003
The preliminary steps in the removal of the damaged fuel elements from the No. 1 pit in Unit 2
were taken under the direction and organization of the Restoration Project (RP) in 2004.
At the same time, at the beginning of the year the management of the power plant established a
preparatory team for the restoration of Unit 2, which worked parallel with the RP, coordinating their
tasks.
This chapter evaluates how the consequences of the incident are being abolished.
5.1 Ensuring the Autonomous Operation of the No. 1 Pit
In the first half of 2004, the autonomous coolant loop and the emergency boration system was
established, the reconstruction ensuring the jodine-filtered ventilation of the reactor hall was
prepared and the reconstruction was finished in December. In the course of the establishment of
these autonomous systems, there were some difficulties caused by the preparatory tasks – the
determination of the fund, the preparation of safety analysis – that enhanced the time-demand of the
process. After their installation the autonomous systems were working in order and on the basis of
operation experiences they were qualified as fit for the fulfilment of their functions.
The neutron-flux control system of the damaged fuel elements was too sensitive for electric
24
interferences as a result of temporary extension and so some boric acid was dissolved in the
cleaning tank, several times and practically without any real reason. After due consideration, the
obligatory dissolving of boric acid was excluded from the process of intervention so the new
regulations reduced the number of unwarranted interventions significantly. Besides, we were
examining the application of 3/2 logic in the case of the neutron-flux increase but the application of
this logic needs further analysis and a more realistic dilution model.
5.2 The Licensing of the Restoration
The licensing of the restoration was harmonized with the authorities which means that it has to be
carried out according to the relevant regulations of the Nuclear Safety Regulation (NSR). The
Nuclear Safety Management of the Hungarian Atomic Energy Authority (HAEA NSM) had
published its requirements in January 2004 on the basis of which the form and content of the
theoretical licensing documentation was worked out. Then the general designer of the nuclear
power plant, Erőterv started to draw up the documentation. The documentation was based on the
technological safety reports and technological plans drawn up by the Russian company TVEL.
However, to a significant extent, it became necessary to to work out the documents requiring home
resources. Because of the overall official requirements, the theoretical licensing documentation was
finished much later than it was planned. The theoretical licensing documentation was handed over
to the technical authorities for licensing and to independent experts so that they could report on it.
According to the plans the documentation would have been handed in to the HAEA NSM in
December but this did not happen because there were some difficulties in connection with the
design of the capsules that would serve for the storage of the damaged fuel elements. The nuclear
power plant requested from the Russian partner the the design of a new capsule-top that would
serve to close the the capsule as a result of which the capsules would become fit for longer storage
in the cooling pond. However, the original, hermetically closed construction was not abandoned
because it might be nedded for the transportation or the final disposal of the capsules.
Parallel to the working-out of the theoretical licensing documentation, the import /
production licensing of the facilities required for the removal (of the damaged fuel elements) had
started to be prepared on the basis of the export plans drawn up by the company TVEL. The
documentation was worked out by the company Transelektro and after the revision it will probably
be handed in to the authorities for licensing in the first quarter of 2005. Besides the working-out of
the licensing documentation of the facilities, the production / import licensing documentations of
the capsules and the tools and instruments needed for the removal also started to be worked out and
prepared for licensing. These documentations will probably be handed in to the authorities for
licensing in the second quarter of 2005.
5.3 The Fulfilment of the Removal Contract
On the basis of the contract about the removal, the Russian company TVEL had handed over the
technological safety founding reports in February 2004 and the technological plans at the end of
March. Although the handing over of the documents met the deadline, they had not been accepted
until the supplements and corrections necessitated by the deficiencies were finished. The
technological / execution plans were handed over two months later than the contractual deadline
and a significant correction was necessary in this case, too. The corrections can be attributed to the
uniqueness of the task and to the continuous improvement of the solutions. Besides, several
difficulties were caused by the misunderstandings arising from the translations and by the
25
differencies between the two planning cultures. Meeting the new official requirements in the
documents also needed considerable extra effort from both the Hungarian and the Russian partner.
The official requirements in connection with the content of the theoretical licensing documentation
and the specified technological requirements made it necessary to modify the technological content
of the contract and the timing of its fulfilment. These modifications were atteched to the contract as
a supplement.
As to the fulfilment of the contract, the designing of the capsules for the storage of the damaged
fuel elements caused some technological difficulties and in the case of certain solutions (catalyst,
wadding, emptying valves) the contractual guarantees are not fulfilled at the present. These
problems have to be settled before the import / production licensing because if these guarantees
failed to be realized, they would endanger the obtaining of the official license. In connection with
the capsules, the handling activities in the cooling pond after the encapsulation also began to be
worked out because they are not included in the removal contract.
The Russian partner began to work out the procedures and orders related to the direct execution
activities of the removal which were discussed at the end of this year. According to this discussion,
each partner began to work out the procedures and orders that should be prepared by them. These
procedures will be discussed in the beginning of the next year.
5.4 Other Activities Related to the Removal
Significant complementary activities are needed in connection with the process of removal which
are primarily necessary for the on-the-spot operation of the removal. The preparatory works of the
ventilation system (planned to be used during the removal), of the system for the keeping of the
water level and for the washing of the tools planned to be used for the removal, and of the safe-
guard measuring system were all started. Also, a contract was made with the company VUJE about
the decontamination of the No. 1 Pit before and after the removal, and about the decontamination of
the of the cleaning tank. As to the operating systems, the first versions of the technological plans
had been accomplished, they had been evaluated and revised on the basis of which the contractors
began to work out the technological plans of the final solutions and the licensing documentations.
Summary
The task set in connection with the removal of the damaged fuel elements in Unit 2 is carried out
slower than it was originally planned. The reason for this is the complexity and uniqueness of the
task. At the original programme the knowledge was not available on the basis of which it would
have been possible to define aims realistically – except for the main aim. Consequently, in many
instances the aims were modified or the activities were corrected which influenced the whole
procedure of the work. The encapsulation of the damaged fuel elements as soon as possible should
still be considered as the main goal because the present state means a certain risk factor for the
nuclear power plant and its surroundings. However, the encapsulation can only be accomplished
within the framework of an absolutely safe solution even if it takes more time than it was originally
planned.
26
6 Radioactive Waste Management
6.1 Developments in connection with the Management and Interim Storage of
Radioactive Waste at PNPP
'Radioactive Waste Management' is a term in the international practice which means the collection,
temporary storage, volume reduction, conditioning (i. e. the development of waste packages the
form of which is suitable for final disposal), characterization and on-site interim storage of the
radioactive waste produced in a nuclear power plant before the waste is transported to the final
repository facility. (It has to be noted that the spent fuels are not considered as radioactive waste.)
Because the regulatory control is getting tighter and tighter, and also because of the serious
incident of Unit 2 in April 2003, developments related to waste management form an important task
in Paks NPP.
The 'Atomic Energy Act' accepted at the end of 1996 together with the decrees and orders based on
it established the Public Agency for Radioactive Waste Management (PURAM) which has to take
charge of the final disposal of radioactive waste. In order to finance the tasks in connection with the
final disposal of radioactive waste, the interim storage and final disposal of spent fuel and the
decommissioning of the power plant, Paks NPP pays an amount annually to the Central Nuclear
Fund (CNF) based on the amount of waste produced.
The task of the NPP is the management and on-site interim storage of radioactive waste. This task
should be accomplished in the following way:
the radioactive waste should not disturb the operation of the power plant
the unavoidable investments should be minimal and cost-efficient (if necessary, the interim
storage facilities could be enlarged in a modular way; superfluous storage capacities should
not be built),
the present technologies of waste management should be utilized optimally even if new
technologies will have to be applied
waste packages should be developed so that the form of the waste intended for final disposal
together with the engineered barriers of the container and with the geological features can
ensure safe storage
the standards of waste management and interim storage should be in level with the
international reputation of the power plant
the necessary changes should not have a detrimental effect on the public approval of
radioactive waste management.
We were able to reach these aims with the help of technologies that were quite different from the
methods of low and intermediate level waste management specified in the original Russian
technical specifications.
The following improvements were accomplished in the last few years:
A significant amount of solid waste is compacted to the one-fifth of its original volume with
a 50-tonne press and put into 200 l metal vessels. (We have been using this technology for
the volume reduction of solid waste since 1988.)
For the storage of low and intermediate level waste we formed – through rebuilding – a
container which stores waste-packages in a modern, retrievable way.
The two container fleets in the auxiliary buildings, which store liquid radioactive waste,
27
have been connected with a tunnel bridge with the use of which storing capacity can be used
more optimally.
We have introduced a gamma-spectometric measuring system with the help of which the
isotope-content and -composition of low and intermediate level solid waste in the vessels
can be determined.
We have introduced a semi-automatic equipment selecting solid waste with the help of
which we have managed to reduce the amount of low and intermediate level solid waste by
about 10%.
We have developed a method of filtering through a kind of silica with the help of which the
amount of radioactive oils and solvents that require management have decreased
significantly.
With the help of underwater treatment with plasma, we have managed to reduce
significantly the amount of liquid waste produced during the chemical clean-up of the
equipments.
The production of liquid radioactive waste can be prevented by the installation of industrial
ultra-filtering equipments that can clean boric acid solutions used in the power plant. We
have installed such high-performance equipments in both of the auxiliary buildings, one in
each.
The following improvements are being implemented :
It will be possible to reduce the amount of liquid radioactive waste – which has
been produced and which is stored in containers in the auxiliary buildings – with
the use of a Finnish technology which is being installed at present.
Those mud-like radioactive waste the amount of which cannot be reduced further
will be solidified with a cementing equipment developed in Germany.
The serious incident in No. 1 sink of Unit 2 in 2003, the uncertainites about the accomplishment of
the planned final repository of low and intermediate level waste in Bátaapáti, and the exhaustion of
the on-site interim storage capacities resulted in the reconsideration of the waste management
strategy applied in the nuclear power plant. As part of this reconsideration, the realization or
planning of the following improvements have started out:
It is necessary to expand the capacity of the storing container fleet for liquid radioactive waste,
through the building of further containers. (This work is in progress and the system will be
ready for use in the beginning of 2005.) With this expansion the interim storing capacity of
liquid waste will expand by 3800m3.
The modular expansion of the capacity available for the interim storage of low and intermediate
level solid waste.
First of all, the possibilities of the reprocessing and volume reduction of the various types of
radioactive waste should be reviewed in a study plan; after that, it will be possible to decide on
the specific improvements. (Cutting up large pieces of solid waste, the treatment of high dry
matter content mud, the further volume reduction of the waste (pre-compressed by the 50-tonne
press) using a supercompactor; the treatment of waste containing long-lived isotopes, etc.)
Certain analyzing and preparatory tasks are in progress which aim at the installation of
technologies for the processing and conditioning of solid and liquid radioactive waste that was
produced in connection with the damaged fuel cells in No. 1 sink of Unit 2, and still being
produced in connection with their removal.
The Public Agency for Radioactive Waste Management is preparing the requirements of the
final disposal of low and intermediate level waste. Some of the temporary requirements
necessitate the installation of new technologies of waste management (eg. waste dryer
28
equipment). The related analyzing and preparatory tasks are in progress.
The problems that need to be solved in the future are difficult, but with the improvements that are
planned and that are already in progress we will be able to manage the situation.
6.2 Low and Intermediate Level Solid Waste
In 2004, 759 vessels containing low and intermediate level solid waste were produced which is 31%
(334 vessels) less than the amount produced in the previous year. During the major repairs and the
operation of the units, the amount of radioactive waste produced was in level with the previous
years (except 2003).
The Storage / Disposal of Solid Radioactive Waste
In 1996, the final repository at Püspökszilágy received the last transport of solid radioactive waste.
Since then, the vessels of solid radioactive waste are stored in interim storage premises and
temporary collecting facilities within the controlled area of the power plant until the commissioning
of the final repository.
The aim of the interim storage of radioactive waste is the temporary, controlled storage preliminary
to its final disposal. All of the amount of waste produced and managed during this year was placed
in an appropriate room (VK302/I).
The following table shows the amount of low and intermediate level solid waste stored in the power
plant at the end of 2004, broken down into storing rooms.
(table 7)
Table translate:
7. táblázat Átmeneti tárolók és ideiglenes gyűjtőhelyek töltöttsége = Table 7 The utilization of
interim storage and temporary collecting facilities.
Helyiség = Room
Összesen = Total
Kapacitás (db hordó) = Capacity (vessels)
2004-ban betárolt mennyiség (db hordó) = Amount placed in 2004 (vessels)
Tárolt mennyiség (db hordó) = Amount stored (vessels)
Szabad kapacitás (db hordó) = Free capacity (vessels)
29
The next figure (Figure 10) shows the amounts of low and intermediate level solid waste produced
in the period between 1998-2004 and after processing.
Figure translate:
10. ábra Az 1998-2004 között keletkezett és a feldolgozás utáni kis- és közepes aktivitású
szilárd hulladékok mennyisége = Figure 10 The amounts of low and intermediate level solid waste
produced in the period between 1998-2004 and after processing.
keletkezett hulladék = waste produced
feldolgozás utáni hulladék = waste after processing
(év) = (year)
6.3 High Activity Solid Radioactive Waste
Until 31th
December 2004, 91.2 m3 of high activity radioactive waste was produced during the
operation of Paks NPP. Out of this amount 2.386 m3 were produced in 2004, which required 4.645
m3 storing capacity.
Out of the whole storing capacity, 53.8 m3 are free on Extension I2, and 76.8 m3 are free on
Extension II.
2 Extension I = twin Units 1 and 2 of the nuclear power plant that have shared technological
systems
Extension II = twin Units 3 and 4 of the nuclear power plant that have shared technological
systems
30
This means that on Extension I. 48,21% of the whole storing capacity is available, and 72,59 % on
Extension II.
Table translate:
8. táblázat A 2004-ben képződött nagy aktivitású szilárd radioaktív hulladékok típusai
blokkonként = Table 8 The types of high activity radioactive waste produced in 2004, for each unit
Blokk = Unit
Hulladék típusa = Type of waste
Térfogat (m3) = Volume (m3)
Százalékos arány [%] = Rate [%]
szűrőbetétek = filters
blokk összesen = unit total
közbenső rúd = intermediate rod
I. kiépítés összesen = Extension I. Total
vegyes = mixed
összesen = total
The following features can be seen in the above table on the basis of the amount of high activity
radioactive waste and the place of its production:
In 2004, 0,659 m3 less solid radioactive waste was produced than in 2003, and almost solely in
Extension I.
The amount of waste produced can mainly be attributed to the planned replacement of 28
intermediate rods of Unit 2 in December.
The high activity solid radioactive waste was placed in storing wells developed in the controlled
area of the power plant (rooms A501/I, A501/II, A101/1-4) and in lead containers in room A216/3
and A216/6.
31
6.4 Liquid Radioactive Waste
The main types of liquid radioactive waste are:
evaporation residues (concentrates)
evaporator acidifying solutions
spent primary loop ion-exchange resins
active muds
active solvent mixtures
contaminated technological boric acid solutions.
6.4.1 Evaporation Residues
In the controlled area of the nuclear power plant chemical waste waters containing radioactive
isotopes are produced from various sources. In these low dry matter content (3-5g/l) water solutions
all those solved chemicals are present which are used for the primary coolant loop, for the
regeneration of deionizers, for the fine control of reactor performance and for decontamination.
After treatment with chemicals (with “metaborate”), the collected waste waters are evaporated to
200 g/l “boric acid concentrate.” There ins't an option for collecting waste waters selectively. Until
31th
December 2004, 4645 m3 evaporation residue was produced, out of which 2625 m3 were
stored in No. 1 auxiliary building and 2020 m3 in No. 2.
In 2004, 190 m3 evaporation residue was produced, 145 m3 on Extension I (out of which 125 m3
are containing alpha-emitters because they are from Unit 2) while 45 m3 on Extension II.
6.4.2 Evaporator acidifying solution
The evaporator acidifying solution is used for the cleaning of the evaporators of No. 3. water filterig
equipment and it is stored in No. 2 auxiliary building. In 2004, 20 m3 evaporator acidifying solution
was produced, so the container which was determined for its storage last year contained 250 m3
evaporator acidifying solution.
6.4.3 Spent primary loop ion-exchange resins
The number of regenerations and resin replacements carried out on the primary coolant loop
deionizers is much less than it was estimated. It was estimated that 89 m3/year/two Units ion-
exchange resins will be produced (41 m3/year high level and 48 m3/year low level) and will have to
be stored separately. With the modification of the liquid waste storing system, we have completed
the united storage of ion-exchange resins. Until 31th
December 2004, 114.1 m3 spent resins were
produced during the operation in both auxiliary buildings, out of which 21.1 m3 were produced in
2004.
There isn't an emergency concerning the processing of ion-exchange resins. If we consider the
reconstruction of the storing containers of spent resins, the available storing capacity – 870 m3 –
will be sufficient for the interim storage of the amount produced through the whole lifetime of the
32
power plant.
6.4.4 Active solvent mixtures
Although their amount is not significant (4 m3 were produced in 2004), they are inflammable so it
was necessary to form a properly installed place which accomplishes the proper interim storage of
both the uncleaned and cleaned liquids.
Contaminated oils and organic solvents are filtered by a kind of silica. This method of filtering
achieves favorable results with quite simple instruments.
6.4.5 Contaminated technological boric acid solutions
There are thousands of m3 boric acid solutions of different concentration which have specific
technological use in the primary coolant system. During the operation, micron-sized or submicron-
sized active contaminations accumulate in these boric acid solutions which cannot be removed
effectively by the traditional method of built-in ion-exchangers. However, there are several reasons
why it is very important to remove them and not to let them increase without restraint. Firstly, their
replacement would become necessary because of the requirements of cleanness, which would result
in a significant increase in liquid waste. These contaminations have a detrimental effect on
transparency and on control. Besides, sediments might be deposited which would spoil heat-
exchange and would generate further processes of corrosion.
In 2004, we carried out the following filtering programs:
We cleaned the primary coolant of both units with the industrial ultra-filtering equipment of
Extension I (on Unit 1 as part of the stoppage and restart, and on Unit 2 as part of the fine
decontamination operation during the stoppage).
We cleaned the coolant of both units with the industrial ultra-filtering equipment installed on
Extension II, as well, during the stoppage and restart. In addition, we accomplished the
cleaning of the cooling pond of Unit 3, and the filtering of the technological boric acid
solution stored in the “contaminated” condensate container (02TC01B002), and the ultra-
filtering of containers 40TH10B001 and 40TR15B001.
We cleaned technological boric acid solutions containing alpha-emitters several times with
the low-performance ultra-filtering equipment installed in No. 1 auxiliary building.
In summary, the measurements (of transparency and the gamma-spectometric analysis) showthat we
completed all the filtering programs with excellent results.
The next chart shows the utilization of liquid waste containing vessels on 31th
December 2004.
(Figure 11)
33
Figure translate:
11. ábra Folyékony hulladéktároló tartályok töltöttsége (2004.12.31-i állapot) = Figure 11 The
utilization of liquid waste containing vessels (31th
December 2004.)
térfogat [m3] = volume [m3]
ioncserélő gyanta és transzportvíz = ion-exchange resin and transport water
technológiai bórsavoldat = technological boric acid solution
evaporátor savazó oldat = evaporator acidifying solution
sűrítmény = concentrate
szabad térfogat = free volume
7 Enviromental Protection Management System
7.1 Enviromental Politics of Paks Nuclear Power Plant
The PNPP’s most important aim is to produce energy in a safe and antipollution way as well as to
provide competitive prices. In order realize its future plans, the PNPP provides the environmental
conditions of the life-time extension and the increase of output of the power plant.
34
One of the PNPP’s duty is to maintain the environmental safety of the power plant, which develops
continually. It proves that the PNPP tries to meet the requirements of the neighbouring population
and the measures.
The PNPP determinates and evaluates the environmental risk factors meaning hazard point to the
environment during the PNPP’s operation. The PNPP decreases the effects of those factors as
efficiently as it can.
To improve environmental protection activity the PNPP is steadily developing the Environment
Centered Controlling System according to the MSZ EN ISO 14001 License. The PNPP’s contracted
partners are required to comply the environmental regulations. The PNPP has made certain of that
their partners’ activity is adequate to the environmental politics and the Environmental Centered
Controlling System of the power plant.
The PNPP applies the measures, regulations concerning and principles of environment protection as
well as:
the principle of precaution, prevention and reconstruction
the principle of responsible utilization of the environment
the principle of co-operation with society, the surrounding country, concerned
organizations and authorities
the principle of direct information,
and realize them consistently.
The PNPP regards the improvement of environmental efficiency and prevention of environment
pollution as its own responsibility. It carefully attends to economic use of natural resources and
utilization of waste generated at the power plant.
The PNPP provides regular courses on environment conscious thinking for its employees.
The environmental politics of the PNPP is under regular control and modified when it is found
necessary.
19 August, 2003 Paks
Dr. Kocsis István
Chief executive
7.2 Enviromental Centered Goals and Programs
One of the main characteristics of the Environment Centered Controlling System is the
improvement of the environmental protection activity, whose most important task is to determine
environmental goals and achieve them.
35
The environmental protection activity does not appear in every field of the corporation profile. The
aims of environmental protection are changing dynamically. While new goals are determined
annually, others get achieved.
The realization of programs for achieving the PNPP’s goals is continually evaluated by managerial
inspections.
Detailed programs belong to all of the PNPP’s goals.
New goals are determined every year. Some of the goals are short-term ones, so a few goals
determined earlier have already achieved (such as making the Environmental Reports 2001 and
2002); while others are long-term ones, whose realization is in progress according to the programs.
New goals are to be determined in 2004, too.
Present environmental goals of the PNPP and their evaluations are summarized below.
36
Enviromental Centered Goal
Enviromental Centered Goal Evaluation
We are accomplishing the full-scope
reconstruction of radiation protection and
environment control systems of the power plant.
The reconstruction of the radiation protection
and environment control systems is carried out
within the frames of an investment. The most
important task of the year 2004 was to finish the
establishment of the radiation protection and
environment control systems, and according to
this to guarantee the operation of the new, higher
technological quality monitoring system. Putting
the new system into operation was carried out
gradually, in parallel with the operation of the
old system. The execution of this work was
carried out continuously according to the action
program and it is expected to be finished in the
first half of the year 2005.
We are executing a complex program of
environmental protection in order to check the
direct and indirect environmental effects of the
nuclear power plant.
On the basis of the schedule discussed with the
authorities the so-called company site
characterization program, consisting of 13 sub-
programs, the goal of which is to carry out the
preparations for the environmental protection
licensing of the extension of the operating time
has been in progress since the year 2001. The
program was going on in 2004 as well, using the
basic concept, the technological content of
which is checked every year. The tasks were
carried out according to the schedule during the
year. The program is going to be finished on 31
December 2005.
Rebuilding subsurface oil tanks using cutting-
edge technologies.
According to the 33/2000. (III.17.) decree, in its
decision the Environmental Authority obligated
the PNPP to inspect the oil tanks partially. The
PNPP performed the obligation and in its report
it advanced the plans for the reconstruction of
the tanks on the basis of the measures given.
In order to rebuild the underground oil
containers, a development plan was accepted on
7 September 2004; according to the accepted
schedule the rebuilding of the containers
(making them double-walled) is going to be
carried out between 2005 and 2007. To do the
task, the selection of the entrepreneur has
started – within the frames of a public
procurement process.
Enviromental Centered Goal Evaluation
Complete reconstruction of catchment basin
system of extra water.
The development proposal considering the
reconstruction of the supplementary water
preparing wastewater system was accepted in
37
the year 2004. On the basis of the prepared plans
the reconstruction was supported by the
environmental authority. The deadline for
finishing the reconstruction is 2006.
Getting the environmental influence test and
operation license for over the planned lifetime of
the power plant
The Paks Nuclear Power Plant handed in the
preliminary environmental study (PES) of the
extension of the operating time to the
environmental authority in April 2004, and the
supplement of the missing things prescribed by
the authorities in September 2004.
The environmental authority informed the
neighboring local governments about the request
of the Paks Nuclear Power Plant on 31
December 2004.
Windup of the oil-contaminated wastewater tank The development proposal connected to the
liquidation of the pool for oil-containing sewage
was accepted in September 2004. The plans
connected to the liquidation were accepted by
the authorities.
According to the accepted schedule the pool for
oil-containing sewage is going to be replaced by
an oil-separating construction works in 2005,
and it will have been liquidated by December
2006.
Enviromental Centered Goal Evaluation
Recultivation of the building-rubble dump The Environmental Authority obligated the
PNPP to close down the building-rubble dump.
One of the tasks was to carry out the placing
2300 m3 of concrete units and rubble in an
ordinate way and mulching in accordance with
the local circumstances (recultivation).
On the basis of the plans accepted by the
environmental authority the restoration of the
tip for building rubble was finished. The
required closing documentation was prepared
and handed in before the deadline, and it was
accepted by the environmental authority in its
resolution.
In the resolution the five-year aftercare of the
territory and the regular checking of the
groundwater were prescribed.
Extension of the selective collection of office
and wrapping paper produced by the PNPP
The collection of paper waste was recorded in
the internal regulation. From the beginning of
this year the waste store receives packaging and
“crushed” paper waste without documentation,
in case the organizational units transport them
there.
38
The type of the collecting container used for
selective collection was chosen; the places
where the containers should be put were
determined, and after their procurement the
containers were transported to the given places.
Our goal is to enhance the amount of the re-
collected office- and wrapping paper waste.
Enviromental Centered Goal Evaluation
The execution of the program concerning the
examination of the conditions of the systems
belonging to the class ABOS 4, steel and other
pipelines that can be found in the territory of the
Paks Nuclear Power Plant and that endanger the
environment in case of being damaged and do
not belong to the group of cyclic revision.
The condition-examining program had been
prepared by 31 December 2003, and most of its
tasks were carried out in 2004.
It was not possible to carry out the examination
of the station for drawing off oil and the
emergency oil-removing system in 2004 because
of operational problems; these parts of the
program are going to be re-scheduled to the
main reparations of the year 2005.
Paks Nuclear Power Plant carries out an open
and efficient policy of giving information, in
order to enhance the social acceptance of
nuclear energetics and the awareness of
environmental protection.
The events determined in the program connected
to this goal were carried out (Open Day, Angling
Family Day); the Paks Nuclear Power Plant took
part in the exhibition of ÖKOTECH, and
according to the signed contracts the Paks
Nuclear Power Plant appeared in the regional
media.
8 Transport of Hazardous Products and the Safety Advisory System
The safe transport of hazardous products including tasks such as sending, delivery, storage,
packaging and forwarding has a very important role in the life of the PNPP and its neighbourhoods.
The consolidation and operation of the hazardous product transport advisory system of the PNPP
started with the appointment of advisors in December 2002.
The hazardous product safety transport advisors’ tasks are determined by the measures.
Their main tasks are: - consultative assistance
- controlling
- giving reports.
39
The power plant has carried out many tasks in order to fulfill the regulations connected to the
hazardous products since the system was introduced in 2003. The most important events of the year
2004 are going to be discussed below:
In the year 2003 the system of regulations connected to the transport of hazardous products was
established in the power station, the revision of which is going to be carried out in 2004 – on the
basis of the experiences of its one-year operation.
The exaction of fulfilling the regulations connected to the transport of hazardous products from
the haulers has been started.
In 2004 the complex ADR training of the new employees and property guards of the Atomix
Security Service was going on. Some of our staff members also did the course “Administrator of
hazardous products”. The training and the examinations were recorded in the educational
database.
The ADR equipment of the motor vehicles used for transporting hazardous products were
purchased in 2004. The drivers involved in the transport of hazardous products gained ADR
educational certificates, as well as certificates of the aptitude test “PÁV II”.
The hazardous products were recorded in the information system.
Paks Nuclear Power Plant has got a license of transport concerning Tolna County, the whole
country, as well as international license of transport in connection with radioactive and nuclear
materials belonging to the seven classes of the ADR, with the exception of the nuclear fuel
elements of the seven classes. In order to carry out the transport the nuclear power station
operates two motor vehicles that have got official certificates. The equipment required by the
Traffic Regulations and the ADR are available in the cases of both motor vehicles.
We have met our engagements towards the Hungarian Central Statistical Office, as far as the
supplying of statistical data connected to the transport of hazardous products is concerned, at the
end of each quarter.
The transport of the spent fuel elements between the Paks Nuclear Power Plant and the
PURAM3 is considered on-site transport so the ADR/RID regulations do not pertain to it.
The spent fuel elements were not transported outside the company seat in 2004; in connection
with the nuclear fuel most of the advisory tasks connected to the transport of nuclear fuel
elements of the seven classes as hazardous products were determined by keeping tabs on the
transport of the new fuel elements.
Paks Nuclear Power Plant becomes responsible for the shipment of new fuel elements regarded
as hazardous products after the reception of Csap.
The regulations connected to the transport of hazardous products are going to be extended with
a chapter entitled “Prescriptions of Public Security” from 1 January 2005. The reason for the
extension is the demand for taking the recent terrorist threats into consideration on the level of
the legislative regulations, and the position of the UN and the EU that the protection against
3
PURAM = Public Agency for Radioactive Waste Management
40
terrorism plays the primary, most important role in the field of transport/traffic as well. After the
ADR of 2005 comes into force the Paks Nuclear Power Plant has to look at the tasks connected
to this.
41
9 Abbreviations and concepts
TPH = Total Paraffin Hydrocarbons, oil content
PAH = Polycyclic Aromatic Hydrocarbons
SZOE = szerves oldószer extrakt (olaj-zsír) = organic solvent extract (oil, fat)
KOICr = dichromate oxygen consumption
NH3 - NH4+ = total amount of ammonia and ammonium ions per 10-3
kg/m3 of nitrogen
PCB = Polychlorine Biphenils
UNSCEAR = United Nations Scientific Committee on Effects of Atomic Radiation