nyu hospital center pim alerts demo – 1.28.2013. nyu pim alerts 10/29/2015confidential please do...

13
NYU Hospital Center PIM Alerts Demo – 1.28.2013

Upload: sarah-quinn

Post on 03-Jan-2016

215 views

Category:

Documents


2 download

TRANSCRIPT

NYU Hospital Center

PIM Alerts Demo – 1.28.2013

NYU PIM Alerts

04/20/23 Confidential please do not copy or redistribute 2

Alert # 1 - Project Phase Mismatch

04/20/23 Confidential please do not copy or redistribute 3

Priority High

Description Validates project phase against completed schedule milestone actual dates Project Phase Mismatch alert will show up if the project is past the move in date but does not have the phase updated as completed.

Notes 1. If either Feasibility Sign-Off or Schematic Design Sign-Off have been entered, the project should be in the Design phase

2. If Construction Documents Sign-Off or Bid Award have been entered, the project should be in the Bidding phase

3. If Bid Award has been entered, the project should be in the Construction phase4. If Move-In or First Patient/User has been entered, the project should be in the Punch list

phase5. If Project Close-Out has been entered, the project should be in the Completed phase

Alert # 2 - Expired Forecast Date

04/20/23 Confidential please do not copy or redistribute 4

Priority MediumDescription

Forecast milestone date is in the past, and actual date for the same activity is null. Only applies during and after the design phase.

Alert # 3 - Missing Project Document

04/20/23 Confidential please do not copy or redistribute 5

Priority High

Description Project document is missing and project phase is Design or later. This alert applies only to projects with budgets in fiscal year 2014 or later.

Sample Issue Phase is Design, and project doc has not been uploaded.

Sample Output Missing Project Document

Alert # 4 - Cash Flow Budget Allocation

04/20/23 Confidential please do not copy or redistribute 6

Priority High

Description If the project has passed the Schematic Design Sign-Off milestone, the budget fact sheet should be entered in FTS. (Which manifests on the PIM Cash Flow page)

Sample Issue Construction milestone has an actual date, but the budget is not spread in FTS.

Sample Output Project budget is not spread in FTS.

Notes If no budget, or under a certain dollar amount (500k), or if a subproject then no alert.

Alert # 5 Missing Milestone Date

04/20/23 Confidential please do not copy or redistribute 7

Priority High

Description Start date is missing for baseline, forecast, or actual for important milestones.

Sample Issue Move-In milestone has no forecast date.

Sample Output Missing Est Start Date for activity “Move-In”

Alert # 6 and #7 Missing Architect or Contractor

04/20/23 Confidential please do not copy or redistribute 8

Priority MediumDescription Project phase is Design or later, and no architect has been assigned in PIM.Sample Issue Phase is Construction, and a consultant that is flagged as a Design Consultant has not been

added to the project.Sample Output Missing Design Consultant.

Notes Users can choose “No Architect” option if the project does not require an architect.

Priority MediumDescription Project phase is Construction or later, and no contractor has been assigned in PIM.

Sample Issue Phase is Move-In, and a consultant that is flagged as a contractor has not been added to the project.

Sample Output Missing contractor.

Notes Users can choose “No Contractor” option if the project does not require a contractor

Alert # 8 and #9 Missing Location and Square Footage

04/20/23 Confidential please do not copy or redistribute 9

Priority Low

Description If the project has passed the Project Document Sign-Off milestone, project location should be filled out.

Sample Issue Location is empty, and Project Document Sign-Off milestone has an actual date.

Sample Output Missing location.

Priority LowDescription If the project is in or past the construction phase, square footage should be filled out.

Sample Issue Square footage is empty, and project phase is construction.

Sample Output Missing square footage.

Notes At least one, not necessarily all, SQFT box needs to be filled.

Alert # 10 Missing Anticipated Final Cost

04/20/23 Confidential please do not copy or redistribute 10

Priority Medium

Description If project has an approved budget, anticipated final cost should be filled out.

Sample Issue Project has approved budget, but AFC is blank.

Sample Output

Project has approved budget, but no anticipated final cost.

Alert # 11 Empty Role Assignments

04/20/23 Confidential please do not copy or redistribute 11

Priority MediumDescription Checks each role assignment to see that they have been filled

out. Missing EPIC Contact alerts will only trigger on clinical projects, and missing EH&S PM alerts will only trigger on construction projects.

Sample Issue Design PM is null.Sample Output Missing Design PM assignment.Notes This alert module checks:

1.Program Director2.Construction PM3.Design PM4.IT PM5.EPIC Contact – only for Clinical projects6.Key Contact These should show up to the PD

Alert # 12 Empty, Incomplete or Overbooked Timesheets

04/20/23 Confidential please do not copy or redistribute 12

Priority Low

Description Checks for empty, incomplete, or overbooked weeks in the last 4 weeks.

Sample Issue Timesheet completion for last week is 90%

Sample Output Timesheet incomplete, week of [Date of week]

Alert # 13 Project and Person Specific Alert

Priority High

Description Notifies user of pending action items issued from asbestos tab.

04/20/23 Confidential please do not copy or redistribute 13