objective-oriented project planning (zopp) dr anthony wemakor dept of community nutrition smhs uds
TRANSCRIPT
Objective-Oriented Project Planning (ZOPP)
Dr Anthony WemakorDept of Community Nutrition
SMHS UDS
Project and Programme
• A project can be described as the process of using inputs to carry out activities in order to achieve previously defined objectives.
• A programme is a series of projects in a sector, sub-sector or region that are linked together by a clearly defined concept.
3
Project Cycle Management
Plan (Idea)
Implementation (Do)
Evaluation (See)
PDM
4
Why Project Planning
Objective-oriented – not activity-driven Consistency Logical - Logically sets objectives and actions Participatory Transparency and accountability Monitoring and evaluation Framework for assessing relevance, feasibility and
sustainability Describes external factors that influence the project’s
success: assumptions and risks
5
Project planning instruments
• Methods to facilitate the planning and implementation of projects and programmes
• Late 1960s Logical Framework Approach (LFA) (USAID)
• Early 1980s Objective-Oriented Project Planning (ZOPP) (GTZ)
European countries adapted the ZOPP
Objective-oriented project planning (ZOPP)
Goal-oriented project planning
“Zeroing on People and Processes”
ZOPP
ZOPP is a systematic structure for identification, planning, and management of projects
Applied through iterative workshops with project authorities, beneficiaries and stakeholders
Utilizes problem analysis and stakeholder analysis to create a project planning matrix similar to logical project framework
Zopp Workshops
Lasts from 1 day to 2 weeks (avg. 1 week) Participants selected to represent all interest
groups Basic premise: main interest groups must be
represented from all levels Exercise requires a facilitator with a high
degree of experience and skill
Methods and Tools
ZOPP
ZOPP has 2 phases:A. Analysis Analysis phase comprises 5 sub-types
1. Stakeholder analysis2. Problem analysis3. Objective analysis4. Alternative analysis5. Assumptions
B. Project planning
A. Analysis Participant analysis: (interests, motives, attitudes and
implications for project) Problem analysis: major problems grouped into a
problem-tree with cause and effect and identification of the core problem
Objectives analysis: a restatement of the problems into realistically achievable goals;
Alternatives analysis: assessment of alternative objectives according to resources, feasibility, cost-benefit ratio, social risks, sustainability and other factors as decided by group. Prepared on charts.
Assumptions: These conditions are necessary for successful transformation of problems into secured objectives.
1. Participant/stakeholder
Any group within or outside a project that has a stake in the project’s activities and/or outcomes.
Examples Government Local Authorities Vulnerable
groups Employers Workers NGOs
1. Participant/stakeholder Analysis
Purpose: To identify those groups who, directly or indirectly,
will affect or be affected by a project. To determine, through consultation, the issues,
concerns and information needs of different stakeholders
To estimate the probable impact which various stakeholders will have on the project
To identify measures to enhance stakeholder support for the sustainable development objectives of the project.
Importance of Stakeholder Analysis
Stakeholder Analysis promotes the three necessary conditions for the effective implementation of a project.
1. Awareness/Commitment: that stakeholders
understand and believe in the objectives and implementation strategy of the project.
2. Capability: that stakeholders believe they can cope with and benefit from the changes which the project is intended to bring
3. Inclusion: that stakeholders feel they are valued, consulted and part of the change process which the project represents
Methods and Tools
Step 3
Identify the Strengths, Weaknesses, Opportunities and Threats of the Stakeholders to the Project (SWOT) What are the strengths and weaknesses of
the stakeholders? As a consequence, what are the
opportunities and threats of the external environment?
Step 4
Identify the main individuals/groups of Stakeholders who need special attention and propose specific measures in a summary table:
Stakeholder Stakeholder
Interest(s) in the Project
Assessment of Impact
Potential Strategies for Obtaining Support or Reducing Obstacles
Methods and Tools
2. Problem Analysis
Purpose: To identify major problems and their main causal relationships.
Output: ‘Problem tree’: a graphical arrangement of problems differentiated according to ‘causes’ and ‘effects’
Core Problem Approach
1. Identify a “core” or central problem
2. List all the problems related to or stemming from the core problem
3. Determine which related problems are causes and which are effects of the core problem
4. Arrange the problems in a cause-effect heirarchy around the core problem
Methods and Tools
Example: Problem Tree of Infant Malnutrition, Iquitos, Peru, 2005
Problem Tree Analysis
Relies on:• Group-based interaction e.g. Workshop format
• Participation of key stakeholders• Process facilitation • Achieving consensus on problems, causes and
effects
Methods and Tools
3. Objective analysis
The Problem Tree provides the basis for the objective analysis:
a) the identification of specific project objectives – by converting problems or constraints into specific
objectives
b) the definition of project activities and outputs – by substituting cause-effect relationships with means-end
relationships
B. Project Planning
• The output of the Analysis Phase of the ZOPP process feeds into the planning phase.
• The output of the project planning phase is the Project Planning Matrix (PPM).
• The PPM is a 4 x 4 matrix.• The PPM is a one-page summary of:
why the project is carried out, what the project is expected to achieve, how the project is going to achieve these results, factors crucial for the success of the project, how the success of the project can be measured, which data are needed to assess project success, what the project will cost.
Methods and Tools
The Project Planning MatrixSummary of objectives/ activities
Objectively Verifiable Indicators
Means/Sources of Verification
Important Assumptions
Overall Goal (OG) Indicators that the OG has been achieved
Document/database available to prove that the OG has been achieved
For sustaining objectives in the long term
Project Purpose (PP)
Indicators proving that the PP has been achieved
Document/database available to prove that the PP has been achieved
For achieving the overall goal
Results/Outputs Indicators proving that the results/outputs have been achieved
Document/database available to prove that the results/outputs have been achieved
For achieving the project purpose
Activities Specification of inputs/costs of each activity
Records of cost involved e.g. voucher, personnel emolument
For achieving the results/outputs
Summary of objectives/activities• Overall Goal to which the contributes• Project Purpose: which project purpose needs
to be achieved for a significant contribution to be made to the project goal?
• Results/Outputs: which results/outputs will have to be obtained in order to achieve anticipated impact?
• Activities: which activities will the project have to carry out in order for the results/outputs to be obtained?
Important Assumptions• For sustaining objectives in the long term: Which external factors will
have to occur in order to assure sustained continuity of the achieved contribution to the OG in the longer term?
• For achieving the overall goal: Which external factors will have to occur for the anticipated contribution to the overall goal to actually take place?
• For achieving the project purpose? Which important assumptions in relation to the results/outputs 1-..., that cannot be influenced by the project or has been consciously defined as external factors, that must occur for the project purpose to be achieved?
• For achieving the results/outputs? Which important assumptions in relation to the activities 1-..., that cannot be influenced by the project or have been consciously defined as external factors, that must occur in order for the results/outputs to be obtained?
Stages in the ZOPP Process
Pre-ZOPP: in-house exercise by agencies in preparation for a project. Appraisal ZOPP: in-house appraisal for preparing Project TORs
Partner ZOPP: in-country; presentation and discussion of previous phase conclusions and recommendations with staff of project country
Take-off ZOPP: in-country; preparation of the plan of operations with
personnel responsible for project execution and counterpart authorities. Re-planning ZOPP: prepared in-country; adjustments during project
implementation.
Methods and Tools
ZOPP’s Iterative Workshops
• ZOPP is not a oneshot exercise; • Each plannng phase has a specific goal• Each goal is the subject of a workshop• Each workshop comprised of different
stakeholders• Participants analyse key issues throughout the
project cycle.• No set formula for successful workshop. • All need to create common language and
understand one another divergent views
ZOPP’s Iterative ProcessMethods and Tools
Conclusion
Collaboration is not "automatically" part of the ZOPP process. The project team, borrower/donor, and stakeholders must commit to adopting a participatory stance for the overall project; otherwise, the ZOPP process is merely an organizing tool.
ConclusionMethods and Tools
Logical Framework Analysis
3. Logical Framework Analysis
Q:What is Logical Framework Analysis?A: An analytical tool to assist project specialists
and stakeholders in conceptualising:
the objectives of a project; the means whereby these objectives will be
achieved how progress towards achieving objectives
will be measured and, the underlying assumptions and risks which
will be faced
Methods and Tools
Objectives (Narrative Summary)
Verifiable Indicators Means of Verification Important Assumptions
Goal: (Development Objective)
What are the quantitative ways of measuring, or qualitative ways of judging, whether these broad objectives are being achieved? (estimated time)
What sources of information exists, or can be provided cost-effectively?
What external factors are necessary for sustaining objectives in the long run?
Purpose: (Immediate Objectives)
What are the quantitative measures or qualitative evidence by which achievement and distribution of impacts and benefits can be judged (estimated time)
What sources of information exists or can be provided cost-effectively? Does provision for collection need to be made under inputs-outputs?
(Purpose to Goal): What conditions external to the project are necessary if achievements of the project’s purpose is to contribute to reaching the project goal?
Outputs: Indicate each of the outputs that are to be produced by the project in order to achieve project purpose
What kind and quantity of outputs, and by when will they be produced? (quantity, quality, time)
What sources of information?
(Output of Purpose): What are the factors not within the control of the project which, if not present, are liable to restrict progress from outputs to achievements of project purpose?
Activities: Indicate each of the activities that must be undertaken in order to accomplish the outputs.
VI’s should be included against all activities. This is essential for projects reporting and monitoring against the Logical Framework.
What are sources of information?
(Activity to Output): 1) What external factors must be realised to obtain planned outputs on schedule? 2) What kind of decisions or actions outside the control of the project are necessary for inception of the project?
Contents of the LogFrame Matrix