objectives, strategy and present status of the prototype tbm program
DESCRIPTION
Objectives, strategy and present status of the prototype TBM program. Review of the TBM lab program Nov. 6 th , 2013 G. Riddone, BE-RF-PM. Important program developed in collaboration with several CERN groups. Content. Introduction CLIC Layout Module layout TBM LAB program - PowerPoint PPT PresentationTRANSCRIPT
Objectives, strategy and present status
of the prototype TBM program
Important program developed in collaboration with several CERN groups.
Review of the TBM lab program
Nov. 6th, 2013
G. Riddone, BE-RF-PM
Nov. 6th, 2013 TBM review G. Riddone
Content
• Introduction – CLIC Layout–Module layout
• TBM LAB program – Objectives– Strategy– Status
Nov. 6th, 2013 TBM review G. Riddone
Introduction
Nov. 6th, 2013 TBM review G. Riddone
CLIC Layout at 3 TeV
Main Beam Generation Complex
Drive Beam Generation Complex
Main LINAC two-beam modules
Nov. 6th, 2013 TBM review G. Riddone
CLIC at 500 GeV (4232 modules)26920 Accelerating structures13460 PETS~ 70000 RF components
CLIC at 3 TeV (21460 modules)142760 Accelerating structures71380 PETS~ 400000 RF components
A. Samoshkin
Two-beam module layout
Nov. 6th, 2013 TBM review G. Riddone
TBM main types
Module Type 1
3 %
Module Type 2
12 %
Module Type 3
9 %
Module Type 4
3 %
1 to 4 pairs of AS replaced by
MB Quadrupoles
CLIC Module Type o
73 %
Standard Module (L = 2010 mm)DB (100 A)4 PETS, 2 Quads with BPMEach PETS feeds 2 AS
MB (1 A)8 acc. structuresMB filling factor: 91%
DB
MB
Nov. 6th, 2013 TBM review G. Riddone
Baseline solutions were defined for each technical system in the CDR
Module design and integration coping with challenging requirements
from different technical systems.SYSTEM REQUIREMENTS
RFAS/PETS shape tolerance ± 2.5/ ±7.5 µmAS/PETS Assembly ± 15/ ± 25 µm
INSTRUMENTATIONBPM resolution: MB - 50 nm, DB – 2 µm, temporal - 10 ns (MB & DB),
SUPPORTINGMax. vertical & lateral deformation of the girders in loaded condition 10 μm
COOLING ~400 W per AS, ~ 7.5 kW per modules
MAGNET & POWERINGDB: 81.2-8.12 T/m, current density: 4.8 A/mm2, MB: 200 T/m
PRE-ALIGNMENT & STABILIZATIONactive pre-alignment ± 14 µm at 1σ, beam axis included in a cylinder of radius 10 µm MB Q stabilization 1 nm > 1 Hz (vertical)
VACUUM 10-9 mbar
ASSEMBLY, TRANSPORT, INSTALLATION
same transverse interconnection plane for DB & MB
Main requirementsMain requirements
Nov. 6th, 2013 TBM review G. Riddone
Objectives and strategy
Nov. 6th, 2013 TBM review G. Riddone
Demonstration of novel scheme of two beam acceleration in compact modules integrating all technical systems for RF production, beam measurement and acceleration including alignment, stabilisation and vacuum at their nominal parameters.
CLIC feasibility issuesCLIC feasibility issues
Nov. 6th, 2013 TBM review G. Riddone
Two-beam acceleration validation
Two-beam test stand (PETS and ac. structures)
TBM Lab
TBM CLEX
Demonstration of the two-beam acceleration with one PETS and one accelerating structure at nominal parameters in CLEX
Demonstration of the two-beam module designThis implies: - the assembly and integration of all
components and technical systems, such as RF, magnet, vacuum, alignment and stabilization, in the very compact 2-m long two-beam module
- validation of the thermal and mechanical module behaviorDemonstration of the two-beam
acceleration with two-beam modules in CLEXAddress other feasibility issues in an integrated approach
2011-2015
2009-2013
Nov. 6th, 2013 TBM review G. Riddone
TBM Lab objectives
• Integration of all technical systems • Validation of different types of girders and movers• Pre-alignment of girders/quadrupoles in the module environment, • Full metrology of the module components• Validation of interconnections and vacuum systems under different
thermal loads • Stabilization of main beam quad in the module environment• Vibration study of all systems and identification of vibration sources• Measurement of resonant frequencies • Simulation of several thermal cycles and alignment verification• Transport of the module and alignment verification
CLIC Two-Beam Module Type 0 in B169
Nov. 6th, 2013 TBM review G. Riddone
Status
Nov. 6th, 2013 TBM review G. Riddone
TBM Lab overall status
3) Components under procurement and
assembly
TM1
4) Last module – few components under
procurements
TM4TM0#1
1) Under test
TM0#2
2) Under assembly and installation
Nov. 6th, 2013 TBM review G. Riddone
TBM T0#2 in LAB
Component Design Production Status Expected
3D %
2D %
Parts % Assembly Date
SAS 100 100 100 Brazing Dec’13
PETS 100 100 100 Brazing Nov’13
RF Network waveguides 100 100 100 Brazing Nov’13
DB BPM 100 100 100 100 -
Vacuum tank 100 100 100 100 -
Vacuum network 100 100 100 100 -
Compact Loads mock-ups 100 100 100 100 -
Cooling tubes/fittings 100 100 100 100 -
Supporting system 100 100 100 100 -
U-clamps 100 100 100 100 -
TBM ASSEMBLY Dec’13
Nov. 6th, 2013 TBM review G. Riddone
TBM T1 in LABComponent Design Production Status Expected
3D % 2D % Parts % Assembly Date
SAS* 50 50 0 Process optiimisation
Jul’14
PETS 100 100 100 pending May’14
RF Network waveguides 100 100 30 0 Jul’14
DB BPM vacuum chambers 100 100 60 20 May’14
Vacuum tank 100 100 100 100 done
Compact Loads mock-ups 100 100 100 pending May’14
Cooling tubes/fittings 100 100 0 0 May’14
Supporting system** 100 100 90 60 May’14
MBQ + stabilization unit 100 100 100 100 tests
U-clamps 75 50 0 0 -
TBM ASSEMBLY Aug’14
*possibility to integrate a real SAS**DB and MB girders + V-shaped supports are fabricated; cradles fabrication is under way.
Nov. 6th, 2013 TBM review G. Riddone
TBM T4 in LAB
Component Design Production Status Expected
3D % 2D % Parts % Assembly Date
DB BPM vacuum chambers + BPM 100 80 0 0 -
DBQ mock-up/real 100 100 100 100 ready
MBQ 100 100 100 100 ready
MB Vacuum drift tube + BPM 100 100 0 0 -
MBQ stabilization unit started 0 0 0 -
Supporting system* 100 80 50 50 Ready DB
U-clamps 0 0 0 0 -
TBM ASSEMBLY April 2015
*DB girder + V-shaped supports are fabricated.
Nov. 6th, 2013 TBM review G. Riddone
Test objectives TM01
o Understanding geometrical tolerances of assembled modules
o Geometrical stability o Temperature • map in the module • variations with operating modes
and environmental conditions (simulation of the real tunnel environment - air flow, ambient T)
• time constants o Functionality of the technical
systems: • cooling system • vacuum system• active alignment system• stabilisation system
See next talks
Dmitry
Fabrizio
Hélène
Cédric
Detailed reports available in EDMS:https://edms.cern.ch/nav/P:AB-011534:V0/P:AB-001829:V0/TAB3
Nov. 6th, 2013 TBM review G. Riddone
Requirements for AS and PETS
Dictated by beam physics and RF ultra high precision machining
Turning – milling Several annealing
steps (no burrs, no
scratches)AS Disk
PETS bar