ocm jan 2016

20
FF-9218 SN DESCRIPTION OF REPORTS SHEET NO. 1 Previous and Current year - Comparative performance 1 2 Unitwise / Stagewise performance-Statistical data 2 3 Loss of generation details for the month 3 4 Daily unitwise & stagewise generation 4-A 5 Daily coal consumption / receipt/ stock & other coal related data 4-B 6 Fuel oil consumption / stock / receipt etc 5 7 Boiler oerhaul / Steaming validity / Generation Targets 6 8 Tripping Report 7 CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR ( 4 x 210 ) + ( 3 x 500 ) MW = 2340 MW O.C.M. REPORTS FOR THE MONTH OF JAN-2016 INDEX Maharashtra State Power Generation Co.Ltd.

Upload: pravinqns

Post on 09-Jul-2016

232 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Ocm Jan 2016

FF-9218

SN DESCRIPTION OF REPORTS SHEET NO.

1 Previous and Current year - Comparative performance 12 Unitwise / Stagewise performance-Statistical data 23 Loss of generation details for the month 34 Daily unitwise & stagewise generation 4-A5 Daily coal consumption / receipt/ stock & other coal related data 4-B6 Fuel oil consumption / stock / receipt etc 57 Boiler oerhaul / Steaming validity / Generation Targets 68 Tripping Report 7

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

( 4 x 210 ) + ( 3 x 500 ) MW = 2340 MW

O.C.M. REPORTS FOR THE MONTH OF JAN-2016

INDEX

Maharashtra State Power Generation Co.Ltd.

Page 2: Ocm Jan 2016

Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STAGE - I&II In U-1

During During During During Cumulative CumulativeNov-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 383.764 360.358 294.973 316.778 3329.403 3257.0482 PLANT LOAD FACTOR [%] 61.41 57.66 47.20 50.69 53.97 52.80

PLANT LOAD FACTOR [%] (As per MERC) 64.70 67.44 57.06 53.60 54.60 58.303 AVAILABILITY FACTOR [%] 75.00 75.00 59.03 90.41 84.78 68.16

AVAILABILITY FACTOR [%] (As per MERC) 70.26 70.29 57.38 58.12 60.15 62.184 LOADABILITY [%] 81.87 76.88 79.96 56.07 63.66 77.465 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 50 33 56 450 5386 2596 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.130 0.092 0.190 1.421 1.618 0.797 c) TOTAL OIL COST [Rs.CRS] 0.21 0.12 0.20 2.33 27.57 11.00 d) OIL COST [Paise/KWH] 0.56 0.32 0.67 7.36 8.28 3.38

6 FORCED OUTAGE [%] 0.00 0.00 0.00 9.59 9.75 2.74 a) BOILER TUBE LEAKAGE 0.00 0.00 0.00 4.98 5.67 0.65 b) TURBINE AND AUX. 0.00 0.00 0.00 0.00 0.02 0.00 c) OTHERS 0.00 0.00 0.00 4.61 4.06 2.09

7 PLANNED OUTAGE [%] 0.00 0.00 0.00 0.00 5.37 2.34 a) UNIT OVERHAULS 0.00 0.00 0.00 0.00 5.10 2.34 b) OTHERS 0.00 0.00 0.00 0.00 0.27 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 25.00 25.00 40.97 0.00 0.10 26.77 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.00 0.10 0.15 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 15.97 0.00 0.00 1.62 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.00 0.00 h) ECONOMIC SHUTDOWN 25.00 25.00 25.00 0.00 0.00 25.00

9 COAL REALISATION [%] ------ ------ ------ ------ ------ ------10 COAL CONSUMPTION [MT] 332914 300277 223680 273858 3011487 275913511 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.867 0.833 0.758 0.865 0.905 0.84712 GCV OF COAL 3147 3341 3487 3147 2999 320013 GROSS HEAT RATE 2731 2785 2646 2733 2728 271814 TRANSIT LOSS IN COAL (%) ------ ------ ------ ------ ------ ------15 SP. RAW WATER CONSUMPTION [Lt/KWH] 4.82 5.95 6.40 6.39 5.78 5.7016 SP. SOFTENED WATER CONSN [Lt/KWH] 2.49 2.48 2.48 2.42 2.74 2.6417 SP. DM WATER CONSUMPTION [Lt/KWH] 0.076 0.086 0.089 0.128 0.132 0.09718 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0246 0.0291 0.0128 0.0206 0.0247 0.018719 LOSS OF GENERATION [MUs] 241.196 264.602 329.987 151.942 2839.557 2911.912

a) LESS COAL RECEIPT 0.000 0.000 0.000 3.992 126.561 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 49.585 25.622 c) POOR COAL QUALITY 27.246 18.510 7.884 26.281 466.722 215.110 d) LOW SYSTEM DEMAND 17.477 54.245 54.032 19.853 86.086 321.327 e) SYSTEM PROBLEM 0.000 0.000 0.000 0.000 5.581 9.309 f) OTHERS 40.233 35.607 111.831 101.816 2105.023 798.305 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.000 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 0.000 0.000 i) ECONOMIC SHUTDOWN 156.240 156.240 156.240 0.000 0.000 1542.240

20 AUXILIARY CONSUMPTION 0 0 0 0 0 a) AUXILIARY CONSUMPTION [MUs] 32.1233 29.8685 23.4503 30.9754 342.2101 294.9096 b) AUXILIARY CONSUMPTION [%] 8.37 8.29 7.95 9.78 10.28 9.05

SRNO PARTICULARS

Page 3: Ocm Jan 2016

Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STAGE - III In U-1

During During During During Cumulative CumulativeOct-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 760.826 724.013 571.222 795.759 7030.962 7081.8452 PLANT LOAD FACTOR [%] 68.17 64.88 51.18 71.30 63.83 64.290 PLANT LOAD FACTOR [%] (As per MERC) 73.18 77.26 63.11 80.37 66.16 72.883 AVAILABILITY FACTOR [%] 83.58 82.17 65.44 95.00 89.89 85.050 AVAILABILITY FACTOR [%] (As per MERC) 76.99 76.94 62.44 88.44 74.86 76.134 LOADABILITY [%] 81.56 78.96 78.21 75.06 71.00 75.585 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 713 551 354 666 9769 6105 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.94 0.76 0.62 0.84 1.389 0.862 c) TOTAL OIL COST [Rs.CRS] 3.06 1.93 1.25 3.45 50.01 25.86 d) OIL COST [Paise/KWH] 4.03 2.66 2.19 4.34 7.11 3.65

6 FORCED OUTAGE [%] 16.42 13.30 3.28 4.74 4.96 6.62 a) BOILER TUBE LEAKAGE 12.72 0.00 3.28 2.68 3.10 3.17 b) TURBINE AND AUX. 0.00 0.00 0.00 0.29 0.38 0.00 c) OTHERS 3.70 13.30 0.00 1.77 1.48 3.46

7 PLANNED OUTAGE [%] 0.00 4.53 31.28 0.00 4.82 8.22 a) UNIT OVERHAULS 0.00 4.53 31.28 0.00 4.82 8.22 b) OTHERS 0.00 0.00 0.00 0.00 0.00 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 0.00 0.00 0.00 0.25 0.33 0.11 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.25 0.13 0.11 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 0.00 0.00 0.00 0.00 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.20 0.00 h) ECONOMIC SHUTDOWN 0.00 0.00 0.00 0.00 0.00 0.00

9 COAL REALISATION [%] ------ ------ ------ ------ ------ ------10 COAL CONSUMPTION [MT] 686767 601967 477392 659346 6208646 616701111 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.903 0.831 0.836 0.829 0.883 0.87112 GCV OF COAL 2884 3098 3181 3169 2985 301013 GROSS HEAT RATE 2612 2582 2665 2633 2648 262914 TRANSIT LOSS IN COAL (%) ------ ------ ------ ------ ------ ------15 SP. RAW WATER CONSUMPTION [Lt/KWH] 6.50 6.27 6.72 5.64 6.28 6.16

16 SP. SOFTENED WATER CONSN [Lt/KWH] 2.66 2.67 2.77 2.71 2.81 2.8317 SP. DM WATER CONSUMPTION [Lt/KWH] 0.102 0.124 0.112 0.111 0.110 0.11218 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0177 0.0143 0.0304 0.01 0.0224 0.017819 LOSS OF GENERATION [MUs] 355.174 391.987 544.778 320.241 3963.447 3934.155

a) LESS COAL RECEIPT 0.000 0.000 0.000 46.274 664.123 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 58.147 120.546 c) POOR COAL QUALITY 61.095 49.301 31.635 57.076 802.791 602.616 d) LOW SYSTEM DEMAND 43.133 122.120 116.166 85.904 223.938 821.589 e) SYSTEM PROBLEM 0.000 0.000 0.000 2.842 14.858 12.127 f) OTHERS 250.946 220.566 396.977 128.146 2199.590 2377.277 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.000 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 21.591 0.000 i) ECONOMIC SHUTDOWN 0.000 0.000 0.000 0.000 0.000 0.000

20 AUXILIARY CONSUMPTION 0 0 0 0 0 a) AUXILIARY CONSUMPTION [MUs] 58.376 59.026 44.419 63.236 604.176 574.277 b) AUXILIARY CONSUMPTION [%] 7.67 8.15 7.78 7.95 8.59 8.11

PARTICULARSSRNO

Page 4: Ocm Jan 2016

---- Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STATION In U-1

During During During During Cumulative CumulativeOct-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 1144.590 1084.371 866.195 1112.537 10360.365 10338.8932 PLANT LOAD FACTOR [%] 65.74 62.29 49.75 63.90 60.29 60.16

PLANT LOAD FACTOR [%] (As per MERC) 70.14 73.73 60.94 70.76 62.01 67.653 AVAILABILITY FACTOR [%] 80.50 79.59 63.14 93.35 88.06 78.99

AVAILABILITY FACTOR [%] (As per MERC) 74.58 74.55 60.62 77.56 69.58 71.124 LOADABILITY [%] 81.67 78.25 78.80 68.45 68.46 76.175 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 763 584 410 1116 15155 8701 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.667 0.539 0.473 1.003 1.463 0.842 c) TOTAL OIL COST [Rs.CRS] 3.28 2.04 1.45 5.78 77.59 36.86 d) OIL COST [Paise/KWH] 2.86 1.88 1.67 5.20 7.49 3.57

6 FORCED OUTAGE [%] 10.52 8.53 2.10 6.48 6.68 5.23 a) BOILER TUBE LEAKAGE 8.15 0.00 2.10 3.51 4.02 2.26 b) TURBINE AND AUX. 0.00 0.00 0.00 0.19 0.25 0.00 c) OTHERS 2.37 8.53 0.00 2.79 2.41 2.96

7 PLANNED OUTAGE [%] 0.00 2.91 20.05 0.00 5.02 6.11 a) UNIT OVERHAULS 0.00 2.91 20.05 0.00 4.92 6.11 b) OTHERS 0.00 0.00 0.00 0.00 0.10 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 8.97 8.97 14.71 0.16 0.25 9.68 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.16 0.12 0.12 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 5.73 0.00 0.00 0.58 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.13 0.00 h) ECONOMIC SHUTDOWN 8.97 8.97 8.97 0.00 0.00 8.97

9 COAL REALISATION [%] 93.08 88.47 64.66 77.25 77.70 87.8210 COAL CONSUMPTION [MT] 1019681 902244 701072 933204 9220133 8926146

11 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.891 0.832 0.809 0.839 0.890 0.86312 GCV OF COAL 2962 3175 3281 3163 2985 306913 GROSS HEAT RATE 2645 2647 2660 2662 2670 265714 TRANSIT LOSS IN COAL (%) 0.539 1.661 1.172 0.359 0.528 0.799

15 SP. RAW WATER CONSUMPTION [Lt/KWH] 5.94 6.16 6.62 5.85 6.12 6.02

16 SP. SOFTENED WATER CONSN [Lt/KWH] 2.60 2.61 2.67 2.63 2.79 2.7717 SP. DM WATER CONSUMPTION [Lt/KWH] 0.093 0.112 0.104 0.116 0.117 0.10718 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0200 0.0193 0.0244 0.0159 0.0231 0.018119 LOSS OF GENERATION [MUs] 596.370 656.589 874.765 472.183 6824.595 6846.067

a) LESS COAL RECEIPT 0.000 0.000 0.000 50.266 790.684 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 107.732 146.168 c) POOR COAL QUALITY 88.341 67.811 39.519 83.357 1269.512 817.726 d) LOW SYSTEM DEMAND 60.610 176.365 170.198 105.757 310.024 1142.916 e) SYSTEM PROBLEM 0.000 0.000 0.000 2.842 20.439 21.436 f) OTHERS 291.179 256.173 508.808 229.962 4304.613 3175.582 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.00 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 21.59 0.000 i) ECONOMIC SHUTDOWN 156.240 156.240 156.240 0.000 0.00 1542.240

20 AUXILIARY CONSUMPTION

a) AUXILIARY CONSUMPTION [MUs] 90.4991 88.8945 67.8697 94.2109 946.3859 869.1862 b) AUXILIARY CONSUMPTION [%] 7.91 8.20 7.84 8.47 9.13 8.41

Remark:

1) Forced OUTAGE

2) Planned OUTAGE1) U-1 Under Reserved Shutdown2) U-2 Withdrawn due to no MPCB Consent.

1) U-7 Withdrawn due to BTL (Zone - WW)

SRNO PARTICULARS

Page 5: Ocm Jan 2016

Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STAGE - I&II Ex. U-1

During During During During Cumulative CumulativeNov-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 383.764 360.358 294.973 316.778 3329.403 3257.0482 PLANT LOAD FACTOR [%] 81.87 76.88 62.93 67.58 61.89 70.40

PLANT LOAD FACTOR [%] (As per MERC) 86.26 89.91 76.08 71.46 62.61 77.743 AVAILABILITY FACTOR [%] 100.00 100.00 78.71 90.41 84.78 90.88

AVAILABILITY FACTOR [%] (As per MERC) 93.68 93.72 76.50 77.49 68.99 82.904 LOADABILITY [%] 81.87 76.88 79.96 74.75 73.01 77.465 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 50 33 56 450 5386 2596 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.130 0.092 0.190 1.421 1.618 0.797 c) TOTAL OIL COST [Rs.CRS] 0.21 0.12 0.20 2.33 27.57 11.00 d) OIL COST [Paise/KWH] 0.56 0.32 0.67 7.36 8.28 3.38

6 FORCED OUTAGE [%] 0.00 0.00 0.00 9.59 9.75 3.65 a) BOILER TUBE LEAKAGE 0.00 0.00 0.00 4.98 5.67 0.87 b) TURBINE AND AUX. 0.00 0.00 0.00 0.00 0.02 0.00 c) OTHERS 0.00 0.00 0.00 4.61 4.06 2.78

7 PLANNED OUTAGE [%] 0.00 0.00 0.00 0.00 5.37 3.12 a) UNIT OVERHAULS 0.00 0.00 0.00 0.00 5.10 3.12 b) OTHERS 0.00 0.00 0.00 0.00 0.27 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 0.00 0.00 21.29 0.00 0.10 2.35 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.00 0.10 0.20 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 21.29 0.00 0.00 2.16 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.00 0.00

9 COAL REALISATION [%] ------ ------ ------ ------ ------ ------10 COAL CONSUMPTION [MT] 332914 300277 223680 273858 3011487 275913511 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.867 0.833 0.758 0.865 0.905 0.84712 GCV OF COAL 3147 3341 3487 3147 2999 320013 GROSS HEAT RATE 2731 2785 2646 2733 2728 271814 TRANSIT LOSS IN COAL (%) ------ ------ ------ ------ ------ ------15 SP. RAW WATER CONSUMPTION [Lt/KWH] 4.82 5.95 6.40 6.39 5.78 5.7016 SP. SOFTENED WATER CONSN [Lt/KWH] 2.49 2.48 2.48 2.42 2.74 2.6417 SP. DM WATER CONSUMPTION [Lt/KWH] 0.076 0.086 0.089 0.128 0.132 0.09718 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0246 0.0291 0.0128 0.0206 0.0247 0.018719 LOSS OF GENERATION [MUs] 84.956 108.362 173.747 151.942 2839.557 1369.672

a) LESS COAL RECEIPT 0.000 0.000 0.000 3.992 126.561 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 49.585 25.622 c) POOR COAL QUALITY 27.246 18.510 7.884 26.281 466.722 215.110 d) LOW SYSTEM DEMAND 17.477 54.245 54.032 19.853 86.086 321.327 e) SYSTEM PROBLEM 0.000 0.000 0.000 0.000 5.581 9.309 f) OTHERS 40.233 35.607 111.831 101.816 2105.023 798.305 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.000 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 0.000 0.000

20 AUXILIARY CONSUMPTION a) AUXILIARY CONSUMPTION [MUs] 32.1233 29.8685 23.4503 30.9754 342.2101 294.9096 b) AUXILIARY CONSUMPTION [%] 8.37 8.29 7.95 9.78 10.28 9.05

100.00 100.00 100.00 100.00 100.00 100.00

SRNO PARTICULARS

Page 6: Ocm Jan 2016

Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STAGE - III PREVIOUDuring During During During Cumulative CumulativeOct-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 760.826 724.013 571.222 795.759 7030.962 7081.8452 PLANT LOAD FACTOR [%] 68.17 64.88 51.18 71.30 63.83 64.29

PLANT LOAD FACTOR [%] (As per MERC) 73.18 77.26 63.11 80.37 66.16 72.883 AVAILABILITY FACTOR [%] 83.58 82.17 65.44 95.00 89.89 85.05

AVAILABILITY FACTOR [%] (As per MERC) 76.99 76.94 62.44 88.44 74.86 76.134 LOADABILITY [%] 81.56 78.96 78.21 75.06 71.00 75.585 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 713 551 354 666 9769 6105 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.94 0.76 0.62 0.84 1.389 0.862 c) TOTAL OIL COST [Rs.CRS] 3.06 1.93 1.25 3.45 50.01 25.86 d) OIL COST [Paise/KWH] 4.03 2.66 2.19 4.34 7.11 3.65

6 FORCED OUTAGE [%] 16.42 13.30 3.28 4.74 4.96 6.62 a) BOILER TUBE LEAKAGE 12.72 0.00 3.28 2.68 3.10 3.17 b) TURBINE AND AUX. 0.00 0.00 0.00 0.29 0.38 0.00 c) OTHERS 3.70 13.30 0.00 1.77 1.48 3.46

7 PLANNED OUTAGE [%] 0.00 4.53 31.28 0.00 4.82 8.22 a) UNIT OVERHAULS 0.00 4.53 31.28 0.00 4.82 8.22 b) OTHERS 0.00 0.00 0.00 0.00 0.00 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 0.00 0.00 0.00 0.25 0.33 0.11 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.25 0.13 0.11 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 0.00 0.00 0.00 0.00 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.20 0.00

9 COAL REALISATION [%] ------ ------ ------ ------ ------ ------10 COAL CONSUMPTION [MT] 686767 601967 477392 659346 6208646 616701111 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.903 0.831 0.836 0.829 0.883 0.871

12 GCV OF COAL 2884 3098 3181 3169 2985 301013 GROSS HEAT RATE 2612 2582 2665 2633 2648 262914 TRANSIT LOSS IN COAL (%) ------ ------ ------ ------ ------ ------15 SP. RAW WATER CONSUMPTION [Lt/KWH] 6.50 6.27 6.72 5.64 6.28 6.1616 SP. SOFTENED WATER CONSN [Lt/KWH] 2.66 2.67 2.77 2.71 2.81 2.83

17 SP. DM WATER CONSUMPTION [Lt/KWH] 0.102 0.124 0.112 0.11 0.110 0.11218 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0177 0.0143 0.0304 0.01 0.0224 0.017819 LOSS OF GENERATION [MUs] 355.174 391.987 544.778 320.241 3963.447 3934.155

a) LESS COAL RECEIPT 0.000 0.000 0.000 46.274 664.123 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 58.147 120.546 c) POOR COAL QUALITY 61.095 49.301 31.635 57.076 802.791 602.616 d) LOW SYSTEM DEMAND 43.133 122.120 116.166 85.904 223.938 821.589 e) SYSTEM PROBLEM 0.000 0.000 0.000 2.842 14.858 12.127 f) OTHERS 250.946 220.566 396.977 128.146 2199.590 2377.277 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.000 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 21.591 0.000

20 AUXILIARY CONSUMPTION a) AUXILIARY CONSUMPTION [MUs] 58.376 59.026 44.419 63.236 604.176 574.277 b) AUXILIARY CONSUMPTION [%] 7.67 8.15 7.78 7.95 8.59 8.11

100.00 100.00 100.00 100.00 100.00 100.00

SRNO PARTICULARS

Page 7: Ocm Jan 2016

---- Chandrapur Super Thermal Power Station OCM-1 FF-9218

PREVIOUS & CURRENT YEAR COMPARATIVE PERFORMANCE - STATION Ex. U-1

During During During During Cumulative CumulativeOct-15 Dec-15 Jan-16 Jan-15 2014 - 15 2015 - 16

1 GENERATION [MUs] 1144.590 1084.371 866.195 1112.537 10360.365 10338.8932 PLANT LOAD FACTOR [%] 72.23 68.43 54.66 70.20 63.19 66.09

PLANT LOAD FACTOR [%] (As per MERC) 77.05 81.00 66.95 77.73 65.00 74.323 AVAILABILITY FACTOR [%] 88.44 87.44 69.37 93.35 88.06 86.78

AVAILABILITY FACTOR [%] (As per MERC) 81.93 81.90 66.60 85.20 72.94 78.144 LOADABILITY [%] 81.67 78.25 78.80 75.20 71.76 76.175 OIL CONSUMPTION

a) OIL CONSUMPTION [KL] 763 584 410 1116 15155 8701 b) SPECIFIC OIL CONSUMPTION [ml/kwh] 0.667 0.539 0.473 1.003 1.463 0.842 c) TOTAL OIL COST [Rs.CRS] 3.28 2.04 1.45 5.78 77.59 36.86 d) OIL COST [Paise/KWH] 2.86 1.88 1.67 5.20 7.49 3.57

6 FORCED OUTAGE [%] 11.56 9.37 2.31 6.48 6.68 5.74 a) BOILER TUBE LEAKAGE 8.96 0.00 2.31 3.51 4.02 2.49 b) TURBINE AND AUX. 0.00 0.00 0.00 0.19 0.25 0.00 c) OTHERS 2.60 9.37 0.00 2.79 2.41 3.26

7 PLANNED OUTAGE [%] 0.00 3.19 22.03 0.00 5.02 6.71 a) UNIT OVERHAULS 0.00 3.19 22.03 0.00 4.92 6.71 b) OTHERS 0.00 0.00 0.00 0.00 0.10 0.00

8 OUTAGE DUE TO EXTERNAL FACTOR [%] 0.00 0.00 6.30 0.16 0.25 0.77 a) LOW SYSTEM DEMAND 0.00 0.00 0.00 0.00 0.00 0.00 b) LESS COAL RECEIPT 0.00 0.00 0.00 0.00 0.00 0.00 c) SYSTEM PROBLEM 0.00 0.00 0.00 0.16 0.12 0.13 d) WET COAL PROBLEMS 0.00 0.00 0.00 0.00 0.00 0.00 e) OTHERS 0.00 0.00 6.30 0.00 0.00 0.64 f) WATER SHORTAGE PROBLEM 0.00 0.00 0.00 0.00 0.00 0.00 g) EXCESSIVE RAIN 0.00 0.00 0.00 0.00 0.13 0.00

9 COAL REALISATION [%] 93.08 88.47 64.66 77.25 77.70 87.8210 COAL CONSUMPTION [MT] 1019681 902244 701072 933204 9220133 8926146

11 SPECIFIC COAL CONSUMPTION [Kg/Kwh] 0.891 0.832 0.809 0.839 0.890 0.863

12 GCV OF COAL 2962 3175 3281 3163 2985 306913 GROSS HEAT RATE 2645 2647 2660 2662 2670 265714 TRANSIT LOSS IN COAL (%) 0.539 1.661 1.172 0.359 0.528 0.79915 SP. RAW WATER CONSUMPTION [Lt/KWH] 5.94 6.16 6.62 5.85 6.12 6.02

16 SP. SOFTENED WATER CONSN [Lt/KWH] 2.60 2.61 2.67 2.63 2.79 2.77

17 SP. DM WATER CONSUMPTION [Lt/KWH] 0.093 0.112 0.104 0.116 0.117 0.10718 SP. LUB OIL CONSUMPTION [ml/KWH] 0.0200 0.0193 0.0244 0.0159 0.0231 0.018119 LOSS OF GENERATION [MUs] 440.130 500.349 718.525 472.183 6824.595 5303.827

a) LESS COAL RECEIPT 0.000 0.000 0.000 50.266 790.684 0.000 b) WET COAL PROBLEM 0.000 0.000 0.000 0.000 107.732 146.168 c) POOR COAL QUALITY 88.341 67.811 39.519 83.357 1269.512 817.726 d) LOW SYSTEM DEMAND 60.610 176.365 170.198 105.757 310.024 1142.916 e) SYSTEM PROBLEM 0.000 0.000 0.000 2.842 20.439 21.436 f) OTHERS 291.179 256.173 508.808 229.962 4304.613 3175.582 g) WATER SHORTAGE PROBLEM 0.000 0.000 0.000 0.000 0.00 0.000 h) EXCESSIVE RAIN 0.000 0.000 0.000 0.000 21.59 0.000

20 AUXILIARY CONSUMPTION a) AUXILIARY CONSUMPTION [MUs] 90.4991 88.8945 67.8697 94.2109 946.3859 869.1862 b) AUXILIARY CONSUMPTION [%] 7.91 8.198 7.835 8.47 9.13 8.41

Remark:1) Forced OUTAGE 100.00 100.00 100.00 100.00 100.00 100.00

SRNO PARTICULARS

1) U-7 Withdrawn due to BTL (Zone - WW)

Page 8: Ocm Jan 2016

OCM-2In U-1

MONTH :

SN PARTICULARS UNIT-1 UNIT-2 UNIT-3 UNIT-4 STG-I&II UNIT-5 UNIT-6 UNIT-7 STG-III STATION

1 Capacity (MW) 210 210 210 210 840 500 500 500 1500 2340

2 Max.possible Gen.(Mus) 156.240 156.240 156.240 156.240 624.960 372.000 372.000 372.000 1116.000 1740.960

3 Actual Generation (Mus) 0.000 33.884 128.727 132.362 294.973 12.555 291.279 267.388 571.222 866.195

4 Plant load factor (%) 0.00 21.69 82.39 84.72 62.93 3.38 78.30 71.88 51.18 49.75

5 Running hours 0.00 268.45 744.00 744.00 45.53 744.00 670.50 0 0

6 Availability factor 0.00 36.12 100.00 100.00 59.03 6.17 100.00 90.17 65.44 63.14

7 a) Planned outage hours 744.00 475.15 0.00 0.00 698.07 0.00 0.00 0.00 0.00

b) Planned outage (%) 100.00 63.88 0.00 0.00 40.97 93.83 0.00 0.00 31.28 34.76

C) Mus loss 156.240 99.803 0.000 0.000 256.043 349.058 0.000 0.000 349.058 605.101

8 a) Forced outage hours 0.00 0.00 0.00 0.00 0.00 0.00 0.00 73.10 0.00 0.00

0 b) Forced outage (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.83 3.28 2.10

0 C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 36.583 36.583 36.583

9 a) Reserve S/D (LD) hrs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0 b) Reserve S/D (LD) (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0 C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

10 a) Reserve S/D(Less coal) hr 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0 0

0 a) Reserve S/D(Less coal) % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0 C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

11 Partial outage (Mus) 0.000 22.553 27.513 23.878 73.944 10.387 80.721 68.029 159.136 233.081

0 Partial outage (%) 0.00 14.44 17.61 15.28 15.78 2.79 21.70 18.29 14.26 13.39

12 Auxiliary consn (Mus) 0.1372 3.4202 9.5006 10.3923 23.4503 2.8380 22.6488 18.9326 44.4194 67.8697

13 Auxiliary consn (%) #DIV/0! 10.09 7.38 7.85 7.95 22.60 7.78 7.08 7.78 7.84

14 Average load (MW) 0 126 173 178 274 392 399

15 Peak load (MW) 0 137 205 200 530 405 450 447 885 1386

16 Peak hours Gen. (Mus) 0.000 22.204 85.858 87.830 195.892 8.870 193.920 177.814 380.604 576.496

17 Peak hours PLF (%) #DIV/0! 42.63 164.86 168.64 125.38 7.15 156.39 143.40 102.31 99.34

18 Coal linkage (MT) 1192000

19 Coal Received (MT) 770717

20 Coal Recd as % of linkage 64.66

21 Coal consumption (MT) 0 25689 97323 100668 223680 10295 243272 223825 477392 701072

22 Specific coal cons (Kg/kwh) #DIV/0! 0.758 0.756 0.761 0.758 0.820 0.835 0.837 0.836 0.809

23 Fuel oil consumption (KL) 0 4 0 52 56 308 21 25 354 410

24 Sp.fuel oil cons (ml/kwh) #DIV/0! 0.118 0.000 0.393 0.190 24.53 0.07 0.09 0.620 0.473

25 DM water consumption(M3) 229 9881 8574 7670 26354 11307 27087 25455 63849 90203

26 Sp.DM consn (Lit/kwh) #DIV/0! 0.292 0.067 0.058 0.089 0.901 0.093 0.095 0.112 0.104

27 Soften water consn(M3) 0 131533 299500 299513 730546 108157 767201 704396 1579754 2310300

28 Sp.Soften consn (Lit/kwh) #DIV/0! 3.882 2.327 2.263 2.477 8.615 2.634 2.634 2.766 2.667

29 Raw water(Ash disposal)(M3) 423014 1653849 2076863

30 Domestic water (M3) 293082

31 Loadability (%) #DIV/0! 60.04 82.39 84.72 79.96 54.73 78.30 79.72 78.21 78.80

32 Availability factor Yearly (%) 0.00 88.53 95.32 88.79 68.16 78.90 79.31 96.96 85.05 78.99

UNITWISE & STAGEWISE PERFORMANCE Jan-2016

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

Page 9: Ocm Jan 2016

OCM-2Ex. U-1

MONTH :

SN PARTICULARS UNIT-1 UNIT-2 UNIT-3 UNIT-4 STG-I&II UNIT-5 UNIT-6 UNIT-7 STG-III STATION

1 Capacity (MW) 0 210 210 210 630 500 500 500 1500 2130

2 Max.possible Gen.(Mus) 0.000 156.240 156.240 156.240 468.720 372.000 372.000 372.000 1116.000 1584.720

3 Actual Generation (Mus) 0.000 33.884 128.727 132.362 294.973 12.555 291.279 267.388 571.222 866.195

4 Plant load factor (%) 0.00 21.69 82.39 84.72 62.93 3.38 78.30 71.88 51.18 54.66

5 Running hours 268.45 744.00 744.00 45.53 744.00 670.50

6 Availability factor 0.00 36.12 100.00 100.00 78.71 6.17 100.00 90.17 65.44 69.37

7 a) Planned outage hours 744.00 475.15 0.00 0.00 698.07 0.00 0.00

b) Planned outage (%) 100.00 63.88 0.00 0.00 21.29 93.83 0.00 0.00 31.28 28.32

C) Mus loss 0.000 99.803 0.000 0.000 99.803 349.058 0.000 0.000 349.058 448.861

8 a) Forced outage hours 0.00 0.00 0.00 0.00 0.00 0.00 73.10

b) Forced outage (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.83 3.28 2.31

C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 36.583 36.583 36.583

9 a) Reserve S/D (LD) hrs 0.00 0.00 0.00 0.00 0.00 0.00 0.00

b) Reserve S/D (LD) (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

10 a) Reserve S/D(Less coal) hr 0.00 0.00 0.00 0.00 0.00 0.00 0.00

a) Reserve S/D(Less coal) % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C) Mus loss 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

11 Partial outage (Mus) 0.000 22.553 27.513 23.878 73.944 10.387 80.721 68.029 159.136 233.081

Partial outage (%) 0.00 14.44 17.61 15.28 15.78 2.79 21.70 18.29 14.26 14.71

12 Auxiliary consn (Mus) 0.1372 3.4202 9.5006 10.3923 23.4503 2.8380 22.6488 18.9326 44.4194 67.8697

13 Auxiliary consn (%) #DIV/0! 10.09 7.38 7.85 7.95 22.60 7.78 7.08 7.78 7.84

14 Average load (MW) 0 126 173 178 274 392 399

15 Peak load (MW) 0 137 205 200 530 405 450 447 885 1386

16 Peak hours Gen. (Mus) 0.000 22.204 85.858 87.830 195.892 8.870 193.920 177.814 380.604 576.496

17 Peak hours PLF (%) #DIV/0! 42.63 164.86 168.64 125.38 7.15 156.39 143.40 102.31 109.14

18 Coal linkage (MT) 1192000

19 Coal Received (MT) 770717

20 Coal Recd as % of linkage 64.66

21 Coal consumption (MT) 0 25689 97323 100668 223680 10295 243272 223825 477392 701072

22 Specific coal cons (Kg/kwh) #DIV/0! 0.758 0.756 0.761 0.758 0.820 0.835 0.837 0.836 0.809

23 Fuel oil consumption (KL) 0 4 0 52 56 308 21 25 354 410

24 Sp.fuel oil cons (ml/kwh) #DIV/0! 0.118 0.000 0.393 0.190 24.53 0.07 0.09 0.620 0.473

25 DM water consumption(M3) 229 9881 8574 7670 26354 11307 27087 25455 63849 90203

26 Sp.DM consn (Lit/kwh) #DIV/0! 0.292 0.067 0.058 0.089 0.901 0.093 0.095 0.112 0.104

27 Soften water consn(M3) 0 131533 299500 299513 730546 108157 767201 704396 1579754 2310300

28 Sp.Soften consn (Lit/kwh) #DIV/0! 3.882 2.327 2.263 2.477 8.615 2.634 2.634 2.766 2.667

29 Raw water(Ash disposal)(M3) 423014 1653849 2076863

30 Domestic water (M3) 293082

31 Loadability (%) #DIV/0! 60.04 82.39 84.72 79.96 54.73 78.30 79.72 78.21 78.80

32 Availability factor Yearly (%) 0.00 88.53 95.32 88.79 90.88 78.90 79.31 96.96 85.05 86.78

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

Jan-2016UNITWISE & STAGEWISE PERFORMANCE

Page 10: Ocm Jan 2016

Mus % Mus % Mus % Mus % Mus % Mus % Mus % Mus %

A Possible generation 156.240 ### 156.240 100.0 156.240 100.0 156.240 100.0 372.000 100.0 372.000 100.0 372.000 100.0 1740.960 100.0B Actual generation 0.000 ### 33.884 21.69 128.727 82.4 132.362 84.72 12.555 3.38 291.279 78.30 267.388 71.88 866.195 49.75C Loss of generation 156.240 ### 122.356 78.31 27.513 17.61 23.878 15.28 359.445 96.6 80.721 21.70 104.612 28.12 874.764 50.25I Unit overhauls 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 349.058 93.83 0.000 0.00 0.000 0.0 349.058 20.05II Low system demand 0.000 ### 4.975 3.18 26.493 16.96 22.564 14.44 1.804 0.48 62.326 16.75 52.036 13.99 170.198 9.78III Poor coal receipt 156.240 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 156.240 8.97IV Poor coal quality 0.000 ### 5.649 3.62 0.995 0.64 1.240 0.79 0.620 0.17 16.570 4.45 14.445 3.88 39.519 2.27V Wet coal problems 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00VI System problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00VII Water shortage 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00VIII Excessive Rains 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00IX Op. & Mt factors 0.000 ### 111.732 71.51 0.025 0.02 0.074 0.05 7.963 2.1 1.825 0.49 38.131 10.25 159.749 9.18

Details of O&M factors1 Boiler tube leakage 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 36.583 9.83 36.583 2.102 Pr.parts/pipes/valves 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.003 Coal mills 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 2.375 0.64 0.000 0.00 0.000 0.00 2.375 0.14

4 ID/FD/PA fan 0.000 ### 4.175 2.67 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 4.175 0.24

5 Flame fail / Furnace pr 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.006 Drum level 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.007 Governing problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.008 Turbine Brg./CV/rotor/bal 0.000 ### 2.680 1.72 0.000 0.00 0.000 0.00 0.000 0.0 0.000 0.00 0.000 0.00 2.680 0.159 HP heaters 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0010 BFP problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0011 Condenser Vacuum 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 1.230 0.33 0.838 0.23 2.068 0.1212 Condenser tube lkg/ clng 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0 0.000 0.00 0.000 0.00 0.000 0.0013 Gen.hydrogen leakage 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0014 Electrical problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0015 T&IC problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0016 CHP/ poor bunkering 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.0017 Turbine startup/ Withdrawl 0.000 ### 0.048 0.03 0.000 0.00 0.000 0.00 4.983 1.34 0.000 0.00 0.037 0.01 5.067 0.2918 Any other problems 0.000 ### 104.829 67.09 0.025 0.02 0.074 0.05 0.605 0.16 0.595 0.16 0.673 0.18 106.801 6.130 a) Drum pr.rest/Silica 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.605 0.16 0.000 0.00 0.000 0.00 0.605 0.030 b) MS,RH metal/steam temp 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 c) ESP/chimney emission 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 d) Ash handling system 0.000 ### 0.000 0.00 0.000 0.00 0.074 0.05 0.000 0.00 0.000 0.00 0.000 0.00 0.074 0.000 e) Boiler ageing problems 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 f) Clinker formation 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 g) Duct lkg/modification 0.000 ### 2.680 1.72 0.000 0.00 0.000 0.00 0.000 0.00 0.595 0.16 0.331 0.09 3.606 0.210 h) Generator brg./problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 i) Boiler misc/others 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 j) Turbine misc/others 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.000 k) Air Heaters problem 0.000 ### 2.347 1.50 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.342 0.09 2.689 0.150 l) others 0.000 ### 99.802 63.88 0.025 0.02 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 99.827 5.730 m) critical coal problem 0.000 ### 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00

Sr ReasonII Low system demand

1 Boiler tube leakage

3 Coal Mill4 ID/FD/PA fan

8 Turbine Brg./CV/rotor/bal

11 Condenser Vacuum

18 d) Ash Handling System

18 g) Duct lkg/modification

18 k) Air Heaters problem

18 i) Others

U-2 10 MW, U-5 10-15 MW, U-7 10-15 MW.

U-2 30 MW, U-5 10 MW, U-7 10-15 MW.

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR OCM-3UNITWISE LOSS OF GENERATION IN MUS & % Jan-2016

SN

In. U-1

P A R T I C U L A R SUNIT-1 UNIT-2 UNIT-3 UNIT-4 UNIT-5 UNIT-6 UNIT-7 STATION

U-5 Coal Mill LOP problemsU-2 ID-2A Vibration

RemarksLoss as per DC-SG=195.337 Mus & DC-AG=170.198 Mus.

U-7 withdrawn due to BTL (Zone - Water Wall)

U-2 HPCV-1 steam broken

U-2 withdrawn due to no MPCB consent to operate

U-5 10 MW loss, U-6 20 MW loss, U-7 15-20 MW loss

U-4 Bottom Ash system problem (Peep hole chokeup hence ground unloading done)

Page 11: Ocm Jan 2016

OCM-4A

Month:

Date Unit-1 Unit-2 Unit-3 Unit-4 Stg-I&II Unit-5 Unit-6 Unit-7 Stg-III Station

01-Jan 0.000 3.071 4.132 4.292 11.495 0.000 9.061 9.751 18.812 30.307

02-Jan 0.000 3.077 4.293 4.297 11.667 0.000 9.419 9.883 19.302 30.969

03-Jan 0.000 2.961 4.185 4.283 11.429 0.000 9.352 9.895 19.247 30.676

04-Jan 0.000 2.966 4.221 4.228 11.415 0.000 9.164 9.886 19.050 30.465

05-Jan 0.000 3.106 4.256 4.305 11.667 0.000 9.334 9.882 19.216 30.883

06-Jan 0.000 3.040 4.194 4.318 11.552 0.000 9.277 9.400 18.677 30.229

07-Jan 0.000 3.035 4.099 4.317 11.451 0.000 9.123 9.857 18.980 30.431

08-Jan 0.000 3.000 4.183 4.314 11.497 0.000 9.078 9.489 18.567 30.064

09-Jan 0.000 2.925 4.198 4.339 11.462 0.000 9.261 9.728 18.989 30.451

10-Jan 0.000 3.005 4.120 4.290 11.415 0.000 9.229 9.716 18.945 30.360

11-Jan 0.000 3.091 4.102 4.335 11.528 0.000 9.160 9.618 18.778 30.306

12-Jan 0.000 0.607 4.142 4.286 9.035 0.000 9.325 9.840 19.165 28.200

13-Jan 0.000 0.000 4.127 4.311 8.438 0.000 9.204 9.775 18.979 27.417

14-Jan 0.000 0.000 4.133 4.301 8.434 0.000 9.095 9.638 18.733 27.167

15-Jan 0.000 0.000 4.155 4.403 8.558 0.000 9.419 9.453 18.872 27.430

16-Jan 0.000 0.000 4.107 4.352 8.459 0.000 9.438 9.817 19.255 27.714

17-Jan 0.000 0.000 4.202 4.350 8.552 0.000 9.353 9.817 19.170 27.722

18-Jan 0.000 0.000 4.099 4.302 8.401 0.000 9.229 9.737 18.966 27.367

19-Jan 0.000 0.000 4.226 4.321 8.547 0.000 9.555 9.868 19.423 27.970

20-Jan 0.000 0.000 4.065 4.195 8.260 0.000 9.353 9.220 18.573 26.833

21-Jan 0.000 0.000 3.969 4.218 8.187 0.000 9.497 9.030 18.527 26.714

22-Jan 0.000 0.000 4.082 4.150 8.232 0.000 9.624 9.180 18.804 27.036

23-Jan 0.000 0.000 4.150 4.169 8.319 0.000 9.622 9.395 19.017 27.336

24-Jan 0.000 0.000 4.142 4.325 8.467 0.000 9.671 9.551 19.222 27.689

25-Jan 0.000 0.000 4.248 4.280 8.528 0.000 9.688 9.469 19.157 27.685

26-Jan 0.000 0.000 4.098 4.214 8.312 0.000 9.525 8.979 18.504 26.816

27-Jan 0.000 0.000 4.089 4.137 8.226 0.000 9.620 8.853 18.473 26.699

28-Jan 0.000 0.000 4.140 4.161 8.301 0.000 9.679 8.661 18.340 26.641

29-Jan 0.000 0.000 4.161 4.185 8.346 0.000 9.641 0.000 9.641 17.987

30-Jan 0.000 0.000 4.286 4.274 8.560 3.851 9.899 0.000 13.750 22.310

31-Jan 0.000 0.000 4.123 4.110 8.233 8.704 9.384 0.000 18.088 26.321

Total 0.000 33.884 128.727 132.362 294.973 12.555 291.279 267.388 571.222 866.195

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

Jan-2016UNITWISE & STAGEWISE DAILY GENERATION

Page 12: Ocm Jan 2016

OCM-4B

Month: Jan-2016644670.76

Coal Road Total Closing CoalDate consn Receipt Receipt 252 Receipt Wgns Receipt Coal Receipt Stock

(MT) (MT) MSEB WCL (MT) Rcvd ULD-I&II ULD-III C.B. (MT) Uld (MT) (MT) (MT)01-Jan 24543 800 18.00 0.00 29055.76 388 118 354 168 620.52 11 1417.060 31893.340 652021.10

02-Jan 25089 1200 17.00 0.00 27025.81 345 126 307 80 673.30 11 2288.170 31187.280 658119.38

03-Jan 24864 2200 16.00 0.00 29215.08 518 115 352 131 1264.14 22 2377.630 35056.850 668312.23

04-Jan 24685 3600 11.00 0.00 20037.50 334 85 245 135 674.90 11 2375.150 26687.550 670314.78

05-Jan 25016 4500 9.30 0.00 19422.24 463 72 245 281 0.00 0 2433.910 26356.150 671654.93

06-Jan 24475 4300 10.45 0.00 21422.05 288 76 277 216 0.00 0 2294.090 28016.140 675196.07

07-Jan 24654 3800 10.30 0.00 17001.32 288 68 211 225 0.00 0 2538.640 23339.960 673882.03

08-Jan 24337 3800 11.00 0.00 24979.09 332 91 314 152 1304.54 23 2320.620 32404.250 681949.28

09-Jan 24669 4100 9.45 0.00 19393.50 280 74 241 117 1694.32 30 2894.960 28082.780 685363.06

10-Jan 24598 3400 11.30 0.00 23452.52 405 93 285 144 0.00 0 2698.260 29550.780 690315.84

11-Jan 24540 2500 13.45 0.00 22388.54 352 92 268 136 0.00 0 2286.960 27175.500 692951.34

12-Jan 22980 1200 17.00 0.00 24743.57 464 77 315 208 0.00 0 2583.700 28527.270 698498.61

13-Jan 22370 2500 13.30 0.15 18199.55 292 62 219 219 889.14 15 2527.160 24115.850 700244.46

14-Jan 22157 1200 17.15 0.00 19859.11 288 78 237 192 1712.38 30 2934.050 25705.540 703793.00

15-Jan 22371 1000 17.30 0.00 14963.65 350 71 167 304 0.00 0 925.610 16889.260 698311.26

16-Jan 22621 1300 16.45 0.00 22251.39 176 69 300 111 847.02 15 2371.250 26769.660 702459.92

17-Jan 22617 2600 13.30 0.00 18869.97 348 63 266 130 0.00 0 2267.600 23737.570 703580.49

18-Jan 22332 3500 11.00 0.00 16874.46 177 49 229 29 1670.38 30 2730.820 24775.660 706024.15

19-Jan 22828 1100 17.15 0.00 18716.79 463 73 227 192 763.26 15 2527.410 23107.460 706303.61

20-Jan 21897 1100 17.15 0.00 19743.96 347 76 240 223 0.00 0 1809.190 22653.150 707059.76

21-Jan 21476 0 20.00 0.00 22779.75 295 117 235 166 0.00 0 1649.000 24428.750 710012.51

22-Jan 21736 0 20.00 0.00 18995.85 345 97 201 213 796.10 15 0.000 19791.950 708068.46

23-Jan 21980 0 19.30 0.00 19772.63 231 99 201 144 886.76 15 0.000 20659.390 706747.85

24-Jan 22264 1000 19.30 0.00 16946.20 172 77 185 54 814.92 15 0.000 18761.120 703244.97

25-Jan 22260 2000 15.00 0.00 18227.95 401 67 228 160 0.00 0 659.850 20887.800 701872.77

26-Jan 21556 500 18.45 0.00 20247.59 236 83 238 75 2335.24 45 1236.500 24319.330 704636.10

27-Jan 21460 0 20.00 0.00 18010.29 397 80 208 184 0.00 0 1236.810 19247.100 702423.20

28-Jan 21410 400 19.00 0.00 23016.74 346 96 275 159 0.00 0 1055.530 24472.270 705485.47

29-Jan 14304 0 20.00 0.00 15738.30 291 99 151 200 0.00 0 1028.540 16766.84 707948.31

30-Jan 17837 0 20.00 0.00 18050.10 348 100 195 253 766.68 15 966.050 19782.83 709894.14

31-Jan 21146 0 20.00 0.00 23855.80 290 106 270 167 842.46 15 869.430 25567.69 714315.83

Total 701072 53600 0.00 0.00 643257.06 10250 2649 7686 18556.06 333 55303.950 770717.07

COAL RECEIPT AGAINST LINKAGE DURING THE MONTH MAX & MIN STOCK DURING MONTH

Total DATE STOCK No.of days1192000.00 31-Jan 714315.83 18.58770717.07 01-Jan 652021.10 16.96

64.66136056.52

Imported coal 0.00 0Wash coal 0.00 WCL 2.237E+09

701072.00 SECL

UTSWagons

COAL CONSUMPTION , RECEIPT & STOCK POSITION

Ropeway

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

Break down time

Railway

Particulars Ropeway Railway (excl wash) UTS RoadLinkage (MT) 210000.00 842000.00 50000.00 90000.00Receipt (MT) 53600.00 643257.06 18556.06 55303.95

Realisation (%) 25.52 76.40 37.11 61.45

Wash coal WCL SECL total washLinkage (MT) 0.00 0.00 0.00Receipt (MT) 0.00 0.00 0.00

Realisation (%) #DIV/0! #DIV/0! #DIV/0!

CoalConsum

ption0.00

Raw coal 0.00

Page 13: Ocm Jan 2016

OCM-5

Month:

SN PARTICULARS UNIT-1 UNIT-2 UNIT-3 UNIT-4 STG-I&II UNIT-5 UNIT-6 UNIT-7 STG-III STATION

1 FURNACE OIL (KL)

a) Opening Balance 2869.93 388.16 3258.09b) Receipt 0 538 0c) Consumption 0 4 0 52 56 209 21 25 255 311d) Closing balance 2275.93 671.16 2947.09

2 L.D.O.(KL)

a) Opening Balance 710.75 1165.69 1876.45b) Receipt 0 0.00 0.00c) Consumption 0 0 0 0 0 99 0 0 99 99d) Closing balance 710.75 1066.69 1777.45

3 L.S.H.S (KL)

a) Opening Balance 0 0 0b) Receipt 0 0 0c) Consumption 0 0 0 0 0 0 0 0 0 0d) Closing balance 0 0 0

4 Total oil consumption (KL) 0 4 0 52 56 308 21 25 354 410

5 Sp.oil consumption (ml/kwh) #### 0.118 0.00 0.393 0.190 24.532 0.072 0.093 0.620 0.473

Reasonwise Oil consn :- U-1 U-2 U-3 U-4 Stg-I&II U-5 U-6 U-7 Stg-III StationCoal mills 0 0 0Pr. Parts 0 0 0Turbine CV/Brg. Problem 0 0 0CHP/ poor bunkering 0 0 0Flame stablility 2 32 34 21 25 46 80Wet Coal 0 0 0Governing Problem 0 0 0Overhaul 0 74 74 74TIC problem 0 0 0System problem 0 0 0Electrical problem 0 0 0Clinker Formation 20 20 0 20Lightup /withdrawl 2 2 234 234 236Low System Demand 0 0 0BTL 0 0 0ID / FD fan problem 0 0 0 Total 0 4 0 52 56 308 21 25 354 410

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPUR

FUEL OIL DATA Jan-2016

Page 14: Ocm Jan 2016

OCM-6

A) BOILER STEAMING VALIDITY & LAST OVERHAULS MONTH:

Unit Boiler No. Hydraulic SteamingTo test date validity 1st 2nd 3rd 4th

Unit-1 MR-11088 11-03-2012 to 26-04-2012 20-04-2014 16-10-2014

Unit-2 MR-11103 14-01-2014 to 23-02-2014 16-02-2014 15-02-2015 17-08-2015 16-02-2016

Unit-3 MR-11207 12-11-2014 to 29-12-2014 21-12-2014 20-12-2015 04-05-2016

Unit-4 MR-11211 29-08-2015 to 27-09-2015 22-09-2015 21-09-2016

Unit-5 MR-11729 27-12-2015 to 30-01-2016 24-01-2016 23-01-2017

Unit-6 MR-11842 09-06-2015 to 22-07-2015 12-07-2015 11-07-2016

Unit-7 MR-12705 19-06-2014 to 02-08-2014 13-07-2014 12-07-2015 11-07-2016

B) CEA / PLANNING COMMISSION / MERC TARGETS :Proportional Actual

SN Particulars TARGET Target till Gen. tillJan-2016 Jan-2016

1. CEA target for the year 2015-2016 (Mus) 16000 13413.70 10338.8932. MERC target for the year 2015-2016 (Mus) 16400 13749.04 10338.8933. Planning commssn target for 2015-2016 (Mus) Not received

3. OCM target for the current month Jan-2016 1040 Mus

Unit-1 Unit-3 Unit-4 Unit-5 Unit-6 Unit-7 Station0 135 135 25 325 325 1040

4. Actual Gen. for the current month Jan-2016 866.195 Mus

Unit-1 Unit-3 Unit-4 Unit-5 Unit-6 Unit-7 Station0.000 128.727 132.362 12.555 291.279 267.388 866.195

5. Loss of gen.due to backing down (Mus) Jan-2016 170.198 Mus

6. Proposed target for next month (Mus) Feb-2016 1190 Mus

Unit-1 Unit-3 Unit-4 Unit-5 Unit-6 Unit-7 Station0 130 130 310 310 310 1190

70.63

77.0875.20

CHANDRAPUR SUPER THERMAL POWER STATION CHANDARPUR

Jan-2016

Performance%

Last overhaul carried out EXTENSIONFrom

0Unit-2

Unit-2

Unit-233.884

95

Page 15: Ocm Jan 2016

OCM-7 FF - 9218

CHANDRAPUR SUPER THERMAL POWER STATION CHANDRAPURTRIPPINGS / OUTAGES (planned / Forced) details Month: Jan-2016

SN Tripping Synchronisation Outage Outage

Date Time Date Time Hours Type

UNIT-1 …….Continued Continued……. 744.00 Planned

Unit outage was under Economic shutdown since 28-08-2014 to 31-03-2015 (as per MERC order no 74 of 2014) &From 01-04-2015 Unit is under Reserved Shutdown (as perMERC order no 28 of 2015)

156.240

UNIT-2 1 12/01/2016 04:45 Continued……. 475.15 Planned Unit withdrawn due to no MPCB consent to operate 99.803

UNIT-3 ----- ----- No outage during the month 0.000

UNIT-4 ----- ----- No outage during the month 0.000

UNIT-5 …….Continued 30/01/2016 02:07 698.07 Planned Unit withdrawn for Capital Overhaul 349.058

UNIT-6 ----- ----- No outage during the month 0.000

UNIT-7 2 28/01/2016 22:50 Continued……. 73.10 Forced Unit withdrawn due to BTL (Zone - Water Wall) 36.583

Generationloss (Mus)

REASONS / REMARKSUNIT

Page 16: Ocm Jan 2016

AOH /COH /

Any otherPlannedmaint.

Due toForcedoutages

Due toPartialloading

1 0.000 0.00 0.00 100.00 0.00 0 0 #DIV/0! #DIV/0! #DIV/0! Unit under Reserved Shutdown #DIV/0! 156.240 0.000 0.000

2 33.884 21.69 36.12 63.88 0.00 137 2656 10.09 0.118 0.758 1Unit withdrawn due to no MPCB consentto operate

0.00 99.803 0.000 22.553

3 128.727 82.39 100.00 0.00 0.00 205 2632 7.38 0.000 0.756 0.00 0.000 0.000 27.513

4 132.362 84.72 100.00 0.00 0.00 200 2654 7.85 0.393 0.761 0.00 0.000 0.000 23.878

5 12.555 3.38 6.17 93.83 0.00 405 2785 22.60 24.532 0.820 Unit Under COH. 0.00 349.058 0.000 10.387

6 291.279 78.30 100.00 0.00 0.00 450 2672 7.78 0.072 0.835 0.00 0.000 0.000 80.721

7 267.388 71.88 90.17 0.00 9.83 447 2668 7.08 0.093 0.837 1 Unit withdrawn due to BTL (WW) 1 9.83 0.000 36.583 68.029

Total 866.195 49.75 63.14 34.76 2.10 1386 2660 7.84 0.473 0.809 2 1 2.10 605.101 36.583 233.081

Generation(Mus)

Reasonsin brief

for forcedoutages

Sp.Coal

Cons.(Kg /Kwh)

PL F(%)

AVF(%)

Max.Load

duringYear(MW)

HeatRate(Kcal/Kwh)

Aux.Cons.(%)

ForcedOutage

(%)

No.of

tripp-ings

Chandrapur Super Thermal Power Station, Chandrapur - Unitwise Performance during January -2016

Sp.Oil

Cons.(ml /Kwh)

Downtimeof

BTLin %

Loss of Generation (Mus)

No.of

BTL

PlannedOutage

(%)

Gen.Records

if any(Mus)

UnitNo.

Page 17: Ocm Jan 2016

FF 7956

ETP-1, 2, 3, Ash Bund, Erai Bridge & Waste Hold water recovery during January-16

ETP - 1, 2 & 3 water recovery

ETP - 1 ETP - 2 ETP - 3TotalETP

water1 25920 3841 1720 31481 19200 0 3900 545812 31590 3958 1800 37348 19200 0 2400 589483 29780 4651 1800 36231 19200 0 1200 566314 34560 4984 1720 41264 16920 0 3900 620845 32940 4447 1800 39187 17600 0 5100 618876 35100 6140 1800 43040 19200 0 5400 676407 31860 4993 1800 38653 17320 0 2400 583738 32400 4215 1800 38415 11720 0 4500 546359 30780 3323 1800 35903 15380 0 3600 5488310 33480 2549 1800 37829 19200 0 2400 5942911 30780 2574 1800 35154 17380 0 3900 5643412 25110 3054 1800 29964 19200 0 4500 5366413 38070 1499 1800 41369 11380 0 3300 5604914 37800 3091 1800 42691 8000 0 3000 5369115 37260 2773 1760 41793 19200 0 4800 6579316 33480 2542 1760 37782 19200 0 0 5698217 37530 2198 1760 41488 16520 0 2400 6040818 38880 2945 1760 43585 19200 0 3600 6638519 37800 2767 1800 42367 19200 0 1200 6276720 37800 4850 1840 44490 19200 0 1800 6549021 38880 5399 1760 46039 19200 0 2700 6793922 38880 5861 1800 46541 17380 0 3600 6752123 38880 3782 1840 44502 9600 0 2100 5620224 38880 0 1800 40680 9600 0 0 5028025 38880 2356 1760 42996 10120 0 3900 5701626 38880 3857 1800 44537 9600 0 3300 5743727 38880 3210 1760 43850 9600 0 3000 5645028 38880 2770 1800 43450 7780 0 3600 5483029 38880 3605 1920 44405 9600 0 2400 5640530 29970 2830 1800 34600 9600 0 0 4420031 32400 3235 1800 37435 9600 0 4800 51835

Total 1085210 108299 55560 1249069 465100 0 92700 1806869

1653849 M3* Stage-III Raw water consumption for ashdisposal =

All figures are in Cu.M.

Date

AshBundwater

recovery

EraiBridgewater

recovery

WasteHold

waterrecovery

Totalwater

recovery

Page 18: Ocm Jan 2016

ETP - 1, 2 & 3 water recovery

ETP - 1 ETP - 2 ETP - 3TotalETP

water

Apr-15 771666 177885 6741 956292 442620 0 304800 1703712

May-15 828850 172550 8473 1009873 493960 0 192796 1696629

Jun-15 575653 163434 9704 748791 345320 0 172400 1266511

Jul-15 324805 186663 9522 520990 322940 0 0 843930

Aug-15 315780 170660 6955 493395 61160 0 142200 696755

Sep-15 743768 58781 9449 811998 219800 0 74400 1106198

Oct-15 765758 152830 50843 969431 120320 0 92850 1182601

Nov-15 459121 147649 54540 661310 557840 0 109050 1328200

Dec-15 888140 130049 48516 1066705 518020 0 94200 1678925

Jan-16 1085210 108299 55560 1249069 465100 0 92700 1806869

Feb-16

Mar-16

2015-16 6758751 1468800 260303 8487854 3547080 0 1275396 13310330

Currentmonth 1085210 108299 55560 1249069 465100 0 92700 1806869

Apr-15 1171200 4800 548960 34320 2268560 1824620 5852460May-15 1187200 1600 585920 62240 2308600 1848240 5993800Jun-15 1136520 40400 403040 109920 1713030 1716540 5119450Jul-15 1151360 83760 594960 202640 1922340 2019660 5974720Aug-15 1203200 91600 365280 237778 2151520 2815980 6865358Sep-15 1128000 4000 298080 40160 2492460 2361660 6324360Oct-15 1189280 0 546560 113120 2399180 2547000 6795140Nov-15 1150880 43360 356800 453840 2546460 2331260 6882600Dec-15 1190400 0 357600 595200 2496340 2040900 6680440Jan-16 1198400 10640 263200 416560 2039100 1802040 5729940Feb-16Mar-162015-16 11706440 280160 4320400 2265778 22337590 21307900 62218268

ASHWATER 3 in

M3

Waterdrawn fromErai dam in

M3

MonthRAW -1 in

M3

ASHWATER 1 in

M3RAW -2 in

M3

ASHWATER 2 in

M3Non DM in

M3

Water recycled quanitity during FY 2015-16 at CSTPS, Chandrapur.

Month

AshBundwater

recovery

EraiBridgewater

recovery

WasteHold

waterrecovery

Totalwater

recovery

Page 19: Ocm Jan 2016

Month: Jan-16*/-

Normative Heat Rate: 2683.63 Kcal/KwhSp. Oil Consumption: 2 ml/KwhAuxiliary Cons.: 8.71 %Transit Loss: 0.80 %PLF 80 %Fixed Cost 83075 RsPerformance Summery Profit / Loss SummeryNo. of days Nos. 31 ParametersPerticular Unit Value Perticular Allowed (Lakhs) Disallowed (Lakhs) Cost AllowedGeneration Mus 866.195 Coal Consumption 18722.95 -59.57 18663.38 DisAllow - Coal Cons.AVF (MERC) % 60.62 Oil Consumption 612.28 -467.38 144.91 DisAllow - Oil Cons.Aux Cons Mus 67.86972 Aux. Cons. 1684.10 -169.11 1514.99 DisAllow - Aux Cons.Coal Consumption MT 701072 Transit Loss 149.31 69.38 218.68 DisAllow - Tans. LossOil consumption KL 410 AVF 5346.71 1708.97 7055.68 DisAllow - PLFCoal Price Rs/Ton 2662 * Total 26515.35 1082.29 27597.64Oil Price Rs/KL 35343 *Coal GCV Kcal/Kg 3281 REC 2.23 -0.06 2.17Oil GCV Kcal/KL 9351Transit Loss % 1.172

Sp. Oil Cons. ml/Kwh 0.473Heat Rate Kcal/Kwh 2660Coal Rate Kg/Kwh 0.809Aux. Cons. % 7.84

599040

1819

18722.95

612.28 1684.10149.31 5346.71

-367.34-271.39

114.75

-118.37

1003.44

-5000

0

5000

10000

15000

20000

Cos

ts (L

akhs

)Cost Allowed / Disallowed (Apr-2015)

Disallowed (Lakhs) Allowed (Lakhs)

Page 20: Ocm Jan 2016

Month: 2015-16

Normative Heat Rate: 2683.63 Kcal/KwhSp. Oil Consumption: 2 ml/KwhAuxiliary Cons.: 8.71 %Transit Loss: 0.80 %PLF 80 %Fixed Cost 83075 RsPerformance Summery Profit / Loss SummeryNo. of days Nos. 306 ParametersPerticular Unit Value Perticular Allowed (Lakhs) Disallowed (Lakhs) Cost AllowedGeneration Mus 10338.89 Coal Consumption 255039.05 -1343.12 253695.93 DisAllow - Coal Cons.AVF(MERC) % 71.12 Oil Consumption 8215.17 -4758.31 3456.86 DisAllow - Oil Cons.Aux Cons Mus 869.186 Aux. Cons. 22929.44 -797.78 22131.67 DisAllow - Aux Cons.Coal Consumption MT 8926146 Transit Loss 2029.57 -1.50 2028.07 DisAllow - Tans. LossOil consumption KL 8701 AVF 61918.97 7727.47 69646.44 DisAllow - PLFCoal Price Rs/Ton 2842 * Total 350132.20 826.76 350958.96Oil Price Rs/KL 39729 *Coal GCV Kcal/Kg 3069 REC 2.55 -0.06 2.49Oil GCV Kcal/KL 9137Transit Loss % 0.799

Sp. Oil Cons. ml/Kwh 0.842Heat Rate Kcal/Kwh 2657Coal Rate Kg/Kwh 0.863Aux. Cons. % 8.41

599040

181920

2125100

255039.05

8215.17 22929.442029.57 61918.97

-1343.12-4758.31 -797.78 -1.50

7727.47

-50000

0

50000

100000

150000

200000

250000

300000

Cos

ts (L

akhs

)Cost Allowed / Disallowed (2015-16 up to May-2015)

Disallowed (Lakhs) Allowed (Lakhs)