october 1, 1987
TRANSCRIPT
n o 0 1 9 1*
TECHNICAL PROGRESS SUMMARY FOR DPO GW7956
SPIEGELBERG AND RASMUSSEN DUMP SITES
OCTOBER 1, 1987
IMUS Suite 56920 South Cedar StreetLansing- Micht«in 4891 °517-694-1304
C-34-8-7-22M
October 1, 1987
NUS Project Numbers 8842 and 8843
Ms. Amy Carter, Project Manager
Michigan Department of Natural Resources
StevensT. Mason Building
Post Office Box 30028
Lansing, Michigan 48909
Subject: Technical Progress Summary for DPO GW7956
Spiegelberg and Rasmussen Dump Sites
Dear Ms. Carter:
This summary of technical progress was prepared in response to your letter dated January 12, 1987,
where you defined those items you needed from NUS to close DPO GW7956 and release the 20%
retention. DPO GW79S6 was discontinued on June 30, 1986, after discussions between you, your
colleagues, and I in July, 1986. At that time, we determined that a sufficient number of expansions
had occurred to the scope and schedule of the project that the original DPO GW7956 no longer was
applicable and should be terminated; and that a new DPO/CR should be initiated to complete the
project- Work Plan Modification No. 5, dated July 30, 1986, addressed the termination of the work
for DPO GW7956 and the projected requirements to complete as understood at that time. A
summary of the technical progress, documents generated, and percent of tasks completed (with
respect to entire Rl) with respect to the entire RI/FS is provided below. NUS Invoices for Service
Period July, 1987, indicated that they were the final billings for DPO GW7956. Subsequent to that
billing, your review of invoices (letter dated September 14, 1987) stated that charges eligible for
DPOGW7956 were incorrectly charged to a different DPO, and that these charges should be
1
^5 A Halliburton Company
transferred to DPO 7956. We are presently transferring these charges to DPO GW7956 and you will»
receive an additional invoice for these charges in the near future.
The approved Work Plan, dated December, 1984, contained the following thirteen technical tasksfortheRI/FS:
TASK 1.0 Initial ActivitiesTASK 1.1 Work Plan PreparationTASK 1 .2 Description of Current Situation
TASK 1 .3 Project Management
TASK 2.0 Pre-lnvestigation Support ActivitiesTASK 2.1 Topographic Mapping, Ground Surveying, and Warning Signs
TASK 2.2 Health, Safety and General Site ReconnaissanceTASK 2.3 Site Health and Safety PlanTASK 2.4 Quality Assurance and Quality Control
TASK 2.5 Site Operations PlanTASK 2.6 Mobilization of Field Equipment
TASK 2. 7 Subcontractor ManagementTASK 2.8 Preliminary Identification of Remedial Technologies
TASK 3.0 Site InvestigationTASK 3.1 Air Quality AnalysisTASK 3.2 Geophysical InvestigationsTASK 3.3 Hydrogeological Investigation
TASK 3.4 Environmental SamplingTASK 3.5 Field Monitoring
TASK 4.0 Site Data EvaluationTASK 4.1 Data Validation, Reduction, and Evaluation
TASK 4.2 Public Health and Environmental Risk Assessment
5.0 Remedial Investigation
TASK 6.0 Description of Current Situation and Scope Refinement
NUS CORPORATION
TASK 7.0 Development of Alternatives
TASK 8.0 Initial Screening of AlternativesTASK 9.0 Laboratory Work Plan Preparation
TASK 10.0 Remedial Alternatives Evaluation and Preliminary Feasibility Study ReportPreparation
TASK 11.0 Selection of Cost Effective Alternative
TASK 12.0 Conceptual Design Development
TASK 13.0 Final Report
The following paragraphs describe the general technical progress for each of these tasks at the timeof termination of DPO GW7956.
TASK 1.0 INITIAL ACTIVITIES
TASK 1.1 WORK PLAN PREPARATION
e Summary of Activities
The request for Work Plan was issued by the DNR Project Manager on June 18, 1984; andthe final (approved) Work Plan was issued to DNR on December 5, 1984. Preparation of
the Work Plan required several meetings with DNR at the DNR Lansing office. One
peculiarity of the project schedule was that the drilling for the R! was planned to bephased around a drum removal, Initial Remedial Measure (IRM) to be performed by U.S.
EPA on the Rasmussen Dump Site.
Expansions in the scope of work defined in the final Work Plan required preparation of
five work plan modifications for work performed under DPO GW7956. in addition, several
additions and deletions to approved staff for the project were made m writing, to DNR.Numerous minor adjustments to the scope of work were required that were not
significant enough to cost-effectively prepare formal Work Plan modifications but
collectively contributed to increased level of effort, cost, and schedule. The small
NUS COPPORATICN
modifications were always performed with the knowledge and concurrence of the DNRproject manager; and, Work Plan modifications were prepared at appropriate times to
accommodate the changes.
•• Documents Prepared
- First Draft Work Plan, July 20,1984
Revisions to Work Plan (letter), August 9 and 17, 1984
- Second Draft Work Plan, September 19,1984
- Final Work Plan, Decembers, 1984 -
Work Plan Modification No. 1, Test Pit investigation for Waste Characterization,
June, 1985
Work Plan Modification No. 2, Phase 2 Drilling - Additional Drilling for Plume
Identification in the Upper Aquifer, June 10, 1985
Work Plan Modification No. 3, Phase 3, Drilling and Monitoring Well Installations,
August 16, 1985/Rev. August 28, 1985
- Work Plan Modification No. 4, Phased Feasibility Study, October 21, 1985/Rev.
January 29, 1986
- Work Plan Modification No. 5, Revision to Scope, Schedule and Budgets for the RI/F5,
July 30,1986 (This modification established end date of DPO GW7956 work as June 30,
1986.)
• Percent Complete - 60% (additional Work Plan Modifications 6, 7, 7a, and 8 required to
completeRI/FS)
NUS CORPCRATiaiM
TASK t .2 DESCRIPTION OF CURRENT SITUATION
• Summary of Activities
The primary activity involved reviewing the site data in detail after approval of the Work
Plan. The Work Plan stated that a brief report would be prepared describing the current
situation at the site; however, after the Work Plan was approved, the ONR determinedthat the description in Section 2.0 of the approved Work Plan was sufficient for the sitedescription. Subsequent to that decision, a significantly more detailed description of thecurrent site conditions was prepared and was incorporated into the second version of theQuality Assurance Project Plan, dated August 1985, (Section 3.0, Project Description). Mostof the Level of Effort for preparation of that Section was charged to task 1.2.
TASK 1.3 PROJECT MANAGEMENT
• Summary of Activities
Project management was an ongoing task throughout the RI/FS work for DPO GW7956.
• Documents Prepared
• Weekly Reports completed through the end of Ju^e, 1986
• Percent Complete - 60%
TASK 2.0 PRE-INVESTIGATION SUPPORT ACTIVITIES
TASK 2.1 TOPOGRAPHIC MAPPING, GROUND SURVEYING, AND WARNING SIGNS
• Summary of Activities
The Work Plan slated three separate surveying events would be conducted by DNRsurveyors, The first survey was to establish ground control for aerial photography and
property lines for site access requirements. The remaining two surveys were to locate
monitoring wells and sampling points during the Rl. DNR performed the three surveys, as
well as additional surveys for other phases of the project.
NUS
Warning signs were obtained for placement at areas designated by the DNR project
manager. The locations described in the Work Plan were not totally utilized because theland owners requested alternative locations.
• Documents Prepared
Topographic map at 1" a 200' scale and 2' contour interval. The map was updated asadditional wells were installed, (prepared by DNR)
- Warning signs were obtained by the prime subcontractor
• Percent Complete - 80% (Phase 4 drilling locations remained after June, 1986)
TASK 2.2 HEALTH, SAFETY AND GENERAL SITE RECONNAISSANCE
• Summary of Activities
The Work Plan states that the initial site reconnaissance objectives were to: inspect the site
for health and safety, geologic and hydrologic conditions; locate surface sampling points;and conduct air sampling. All objectives were met with the site reconnaissance task except
the air sampling. Continuous monitoring of the air was made using organic vapor meters;however, air sampling was deferred because the Quality Assurance Project Plan (QAPP)had to be prepared and approved by U.S. ERA prior to any sampling. Preparation and
approval of the QAPP for Region 5 requirements was a long and arduous process thatwould have significantly delayed the start-up of the project. (Although the Superfundprogram was five years old and Region 5 was using a QAPP guidance developed in 1980,
Region 5 had only one approved QAPP for their entire remedial program, as of summer,
1985, according to an individual in the Region 5 Central Regional Laboratory who was
involved with the Superfund program.)
• Documents Prepared - None Required
• Percent Complete- 100%
NUS
TASK 2.3 SITE HEALTH AND SAFETY PLAN
• Summary of Activities
The Site Health and Safety Plan was developed as specified in the approved Work Plan,
using the Health and Safety Plan developed by the State. The Plan was updated forvarious major field activities as those activities were identified and implemented.
• Documents Prepared
e Percent Complete - 95% (Updated task plans for Phase 4 drilling and drilling fluid drumssampling/removal were required after June, 1986.)
TASK 2.4 QUALITY ASSURANCE AND QUALITY CONTROL PLAN
e Summary of Activities
The Quality Assurance and Quality Control Plan (QA/QC Plan) was prepared under a
different DPO and was not a task under DPO GW7956. The first QA/QC Plan prepared
under a different DPO was in accordance to the format successfully used by NUS forSuperfund RI/FS projects in EPA Zone 1 (NUS was the REM/FIT contractor to U.S. EPA for all
of Zone 1 from October, 1982, through October, 1986). The format was acceptable to theState, but rejected by U. S. EPA Region 5. This resulted in extensive revisions and additionsto the Plan that added considerable time and expense to the effort (the original QA/QCPlan was prepared for about $5400, and the final QAPP cost about $30,000).
A significant amount of the work for preparing the revised QAPP was considered actualimplementation of quality procedures, particularly since the preparation of the document
was contemporaneous with much of the work being performed for the RI/FS. Therefore,QAPP implerrenta*iop was incorporated into the task under DPO GW7956, as explained
and documented in a letter to the State entitled "Summary of the Scope and Costs for
QAPP Development and Implementation", dated December 4, 1985. In addition, several
amendments to the QAPP were performed, primarily to modify field analyt ical
procedures.
NUS COPPGPATIGN
• Documents Prepared
Quality Assurance Project Plan, dated July, 1984
Quality Assurance Project Plan, dated August, 1985QAPP Amendments
• Percent Complete - 90% (Update on sampling numbers, matricies and analysis needed forPhase 4 drilling and PRP oversight activities, complete the RI/FS.)
TASK 2.5 SITE OPERATIONS PLAN
• Summary of Activities
The Site Operations Plan (SOP) was defined as a reference guide in the field that wouldconsist of the Health and Saftty, Quality Assurance, and Work Plans. The documents weremaintained in the field office trailer during the field operations.
• Documents Prepared
The SOP was a compended group of Ptans and maps prepared under other various tasks.
• Percent Complete - 90% (Phas« IV fieldwork remained after June, 1986.)
TASK 2.6 MOBILIZATION OF FIELD EQUIPMENT
• Summary of Activities
The initial field mobilization began on November 11, 1984, and continued for severalweeks as field work was initiated. Items included in the mobilization included installation
of the field gas chromatograph in the DNR office trailer, procurement of a storage trailer,
construction of the decontamination pad and appurtenant facilities, construction of the
Spiegelberg Site access ramp and cable-gate. The initial mobilization was conducted
concurrently with the U.S. EPA drum removal IRM, and the EPA contractor (OH Materials,
Inc.) used the decontamination facility as pan of their operation.
NUS CORPCSATIGN
The Work Plan stated that a fence with gates would be installed around the control area,
and around the area designated for drum storage. NUS and the State decided that
installation of the fence enclosure during EPA IRM activities would be impractical, andthat only a fence and gate across the Rasmussen access road to the o f f i cetrailer/decontamination area was installed. After completion of the IRM, NUS and the
State reassessed the necessity for tht fence enclosure as defined in the Work Plan, and thedecision was made that the fence installed at the entrance of the access road, and thecable-gate on the access ramp bttwten the Spiegetberg and Rasmussen properties wouldbe sufficient for site security.
The site was demobilized in May 23, 1986, with the removal of the DNR office trailer. TheRl had experienced several expansions in scope that caused several more mobilizations offield equipment and drillers than anticipated in the Work Plan. For example, the soil gasand surface/shallow subsurface soil sampling tasks were initiated in December, 1984, at atime when the ground had frozen and could not be penetrated using hand operateddrilling tools. NUS and the State decided to mobilize the drilling subcontractor to drill
through the frozen ground so that the soil sampling could proceed without furtherdelaying the Rl.
• Percent Complete - 90% (Phase 4 drilling; Final Drum Removal)
TASK 2.7 SUBCONTRACTOR MANAGEMENT
* Summary of Activities
Subcontractor management of prime subcontractor, EDI Science and Engineering until" • ' " / •
June 15, 1986, when they discontinued work on the project. Subcontractor management
of A 4 B Industrial Services occurred for the test pit operations.
Percent Complete-80% (Phase 4 drilling and drum removal remained after June, 1986.)
NUS CORPORATION
TASK 2.8 PRELIMINARY IDENTIFICATION OF REMEDIAL TECHNOLOGIES
• Summary of Activities
The purpose of this task, as defined in the Work Plan, was to maintain the focus of the Rl
on the objectives of the FS. This focus was maintained throughout the Rl, and was the
primary reason that the numerous Work Plan Modifications were required, since most ofthe modifications increased the scope of various tasks to assure sufficient information was
obtained for the Risk Assessment or the FS. For example, Work Plan Modification No. 1 fortest pits in waste areas was recommended to evaluate the exact character wastes in areas
detected by geophysics and soil gas so that excavation and disposal alternatives could bebetter addressed in the FS. Likewise, Work Plan Modification Nos. 2 and 3 were to expand
the drilling program so that groundwater contamination could be better defined for
remediation considerations.
The length of the project spanned a period of time when new guidance, and
implementation of new guidance for Feasibility Studies were occurring, changing the data
requirements for the M. Where possible, adjustments and modifications were made to
address the guidance for FS Studies.
TASK 3.0 SITE INVESTIGATIONS
TASK 3.1 AIR QUALITY ANALYSIS
• Summary of Activities
The air quality analysis was scheduled to be conducted during the initial site
reconnaissance, but was delayed because the QAPP had to be approved by U.S. EPA prior
to sampling, and Region 5 normally required several months (or longer) to process these
documents. The air quality investigation was performed on July 1-2, 1985. The results
indicated that air quality is not a serious problem at these sites, under the site conditions
that existed the days of the sampling.
10NUS
• Documents Prepared»
Technical Memorandum on Air Sampling at Spiegelberg and Rasmussen Dump Sites,dated January 28, 1986
• Percent Complete - 100%
TASK 3.2 GEOPHYSICAL INVESTIGATIONS
• Summary of Activities
The Work Plan identified use of electrical resistivity and EM conductivity, magneticgradiometer, and borehole (gamma and resistivity) geophysics. Each of these techniques
were used at the site, as well as a radar survey conducted by the State on the SpiegelbergSite. The electrical resistivity was the least used method since the EM conductivity proved
to be more valuable and is quicker and less costly to operate. The most useful techniqueswere the gradiometer and borehole geophysics.
The initial geophysical surveys were conducted during the week of November 27, 1984,
with electrical resistivity and EM conductivity. The surveys were initiated to test the
methods abilities to delineate wastes, geology, and contaminant plumes. The resultsindicated that the EM. conductivity and magnetometer should be used to delineate
wastes, and possibly assist with defining the geology.
The Work Plan stated that the geophysical surveys would be conducted in two phases, one
before and one after the EPA IRM operations. Since the IRM was conducted before any
geophysical surveys, both phases were conducted at the same time. The Work Planspecified that magnetometer surveys would only be performed on the Rasmussen Dump
Site; however, the resistivity and conductivity survey conducted on the Spiegelberg Site
indicated that buried metal may occur in the paint sludge disposal area, so the
magnetometer task was expanded to incorporate the Spiegelberg Site paint sludge area.The Work Plan also specified that only the top of the Rasmussen landfill area would be
-yj.rveyed with resistivity, conductivity, and magnetometer; however, visual site
reconnaissance indicated that buried materials may occur in the pit area df the Rasmussen
Dump Site, and the geophysical surveys were extended into this area.
11NUS
The geophysical surveys conducted on both sites indicated the presence of buried wastes,
possibly metal, in the Spiegelberg paint sludge area; selected areas of the top of the
Rasmussen landfill; small portions of the Rasmussen gravel pit; and isolated areas in theberm on the Rasmussen property that parallels the west property line adjacent to theSpiegelberg gravel pit.
The gradiometer was also used later in the investigation to check drilling locations where
the possibility of buried materials could occur that could be dangerous if encountered bythe drill.
The State conducted a radar survey on January 3^-31, 1985, on several areas on theSpiegelberg Site. The radar surveys were made near the 'pole barn' to check for buriedtrenches; at the 'wood pile' area to check for buried materials; and the 'paint sludge'
disposal area to check the depth and for buried drums. The radar survey concluded thatno buried trenches were discernable near the pole barn; several potential areas occur inthe wood pile area where trenching or natural erosion and backfilling with 'structureless'material occurred, or areas where electrolyte leached into the subsoil occur. The radarsurvey in the paint sludge area was not successful because of the high conductivity of thesurface materials, and no conclusions were made by the State geophysicist
e Documents Prepared
Technical Memorandum - Surface Geophysical Surveys, submission date,
August 23, 1985
- Memo - Radar Survey, dated February 13, 1985 (prepared by State)
• Percent Complete -100%
TASK 3.3 HYPROG^O'OGICAL INVESTIGATION
• Summary of Activities
The approved Work Plan, and Quality Assurance Project Plan provided for a step-wise
approach for locating sources and pathways of groundwater contamination, with efforts
concentrated mainly in the gravel pit areas on both sites. The step-wise approach included
12NLJS CORPORATION
thirty hand-auger soil samplings, soil gas testing, subsurface soil sampling from tenhollow-stem auger borings, and installing ten to thirteen monitoring wells about ten feet
below the water table. In addition to locating source of groundwater contamination,
about six deep monitoring wells were to be drilled across both sites to characterize thesubsurface geology and hydrogeology that may effect groundwater flow beneath thesite.
The Remedial Investigation required three phases of drilling and well installations prior tothe end of June, 1986. A fourth phase of drilling and well installations was requiredsubsequent to June, 1986, but was not part of the DPO GW7956 activities.
The hydrogeological investigation was initiated in late November, 1984. The
hydrogeologic investigation was initiated at about the same time as the U.S. ERAImmediate Removal operations of waste drums on the Rasmussen Dump Site. Sitemobilization involved installation of the office, storage and decontamination trailers; and
the electrical and phone services on the Rasmussen Dump Site. A decontamination padand facility were constructed on the Rasmussen Dump Site. The facilities on theRasmussen Dump Site wert used for field operations on both sites throughout theduration of the first three phases of field work.
The first phase of field work immediately encountered problems due to the weather. An
intense rain followed by freezing temperatures caused the ground to freeze excessivelydeep, and hard. The ground was impenetrable by hand-auger or hand-held drills and thedriller had to be mobilized to provide the shallow soil samples and the soil gas holes.
Phase 1 soil gas testing occurred in January and February, 1985. Approximately 78 soil gas
testing locations were tested; with 30 on the Rasmussen Dump Site and 48 on theSpiegelberg Site during Phase 1. In addition, thirty soil gas samples were obtained in a
concentrated area around monitoring well RA-MW-22 in September, 1985.
Surface water and sediment samples were also obtained during Phase 1 field operations,
with four samples of each obtained from the Spiegelberg Site.
Phase 1 surface and shallow subsurface (hand augered) soil samples were obtained forchemical testing for contamination after difficulties with frozen ground were overcome inFebruary, 1985. Surface soils and subsurface soils were obtained on the Rasmussen Dump
13NUS CORPORATION
Site and Spicgelberg Site during these field operations. In addition four samples of gravel
from two gravel stockpiles were obtained for analysis; two from a stockpile on the
Rasmussen Dump Site and two from a stockpile on the Spiegelberg Site.
As the hydrogcological investigation progressed, the complexity of the subsurfacegeology became apparent, and tht need for additional borings and wells was recognizedand accommodated through adjustments to the number, location, and depths ofmonitoring wells as the investigation progressed. These adjustments were documented inWork Plan Modifications.
Phase 1 of the drilling and wtll installations occurred from January, 1985, through March1985. A total of 21 wells wtre installed, with five wells installed using auger/cable-toolmethods; two wells installed using cable-tool methods only; and 14 wells installed withhollow-stem augers. Nine welts were installed on the Rasmussen Dump Site and twelve
wells were installed on the Spiegelberg Site. Phase I well drilling and installation data aresummarized on Table la.
Phase 1 also involved drilling sixteen borings, with no wells, to depths of approximatelyten feet, to obtain soil samples for chemical analyses in areas where contamination wasdetected or suspected by surface soil sampling, or soil gas testing, or geophysics. Nineborings were installed on the Spiegelberg Site and seven borings on the Rasmussen DumpSite for these purposes. Tablt 2 summarizes the soil boring information.
Phase 2 drilling and well installations were performed in June and July, 1985, based on theresults of Phase 1 that indicated two distinct aquifers existed beneath both sites, and that
several contaminated plumes may exist within the upper and lower aquifers. The purpose
of Phase 2 was to better define the plume or plumes in the upper aquifer, and to betterdelineate the dip on the surface of the aquitard (clay layer) separating the aquifers sincethe dtp may have controlled, in part, migration of heavy liquid contaminates along thebase of the upper aquifer. The possibility of additional drilling into the lower aquifer wasrecognized at this time, but determination of conditions in the upper aquifer was required
before further recommendations for the lower aquifer could be made. Phase 2 drillingand well installations consisted of nine wells using hollow-stem augers. Seven wells were
installed on the Rasmussen Dump Site and two wells were installed on the Spiegelberg
Site. Phase II drilling and well installation data are summarized on Table ib.
14NUS CORPORATION
Phase 3 drilling and well installations occurred from September to October, 1985.. Thepurpose of Phase 3 was to determine the groundwater flow and contamination conditions
in the lower aquifer, beneath the aquitard (clay layer). Nine wells were installed usingrotary and/or cable-tool drilling methods, into the lower aquifer. Four wells were installed
on the Rasmussen Dump Site and five wells were installed on the Spiegelberg Site. Table1c summarizes the-drilling and monitoring well data for Phase III.
In summary, a total of 39 borings, of which 34 had permanent wells, were installed for thethree phases of drilling. In addition, 16 soil borings were installed to test for soilcontamination (seven on Rasmussen Dump Site; and nine on the Spiegelberg Site.)
During the well drilling operations, subsurface soil samples were taken at 5 to 10 footintervals in the borings for classification purposes and visual evaluation of relativepermeability; and, groundwater samples were taken using temporary wells at about 10foot intervals in the borings for field screening analysis to assist in determining the depth
that the well screens should be set Borehole geophysical logs (natural gamma) weretaken in most wells to assist in classifying the soil types in vertical profile. In addition, insitu permeability tests were conducted in each well to determine the hydraulicconductivity characteristics of the aquifers. Weds which were gamma logged and testedfor permeability are indicated on Tables la, 1b, and 1c.
In addition to the Work Plan items originally scheduled for this task, a Test Pit investigation wasundertaken when the geophysical data indicated potentially buried wastes at locations on both the
Rasmussen and Spiegelberg sites. A total of 17 test pits were excavated using a large, tread-mounted backhoe. Two test pits were excavated in the paint sludge disposal area on the
Spiegelberg site. Additional test pits were planned on the site, however, the landowner forced
discontinuance of the test pit operation prior to completion. Fifteen test pits were excavated on the
Rasmussen sitt: two in the berm between the properties; one in the disposal area discovered in thebase of the gravel pit; one at the north boundary of the gravel pit; three in the buried drum area onthe northeast part of the municipal landfill; seven on the top of the municipal landfill; and, one in
the south facing slope below the municipal landfill.
Surveying locations and elevations of monitoring welts was provided by Michigan DNR surveyors.
Borings without wells, test pits, and surface/shallow subsurface soil sampling locations were notsurveyed, but were approximated on the topographic base map of the site by sampling personnel.
15NUS CORPORATION
• Documents prepared
hBoring Logs (prepared by EDI and NUS)
Gamma ray (Geophysical) logs (prepared by EDI)In situ permeability logs (prepared by EDI)
Phase 1,2, and 3 Technical Memorandum (prepared by EDI)
Test Pit Memorandum
Soil Gas Testing Around Well RA-MW-22 Memorandum, May 22,1986In situ Permeability Testing Memorandum (prepared by EDI)
Workman Mod. No. 1, Test Pit Investigation for Waste Characterization, June, 1985
Work Plan Mod. NO. 3, Phase 3 Drilling and Monitoring Well Installations, August, 1985Letter - Drilling Modifications for Boring 43, October, 1985
• Percent Complete -75% (Phase IV drilling and PRP oversight remained after June, 1985.)
TASK 3.4 ENVIRONMENTAL SAMPLING
e Summary of Activities
The Environmental Sampling task included the sampling of soils, sediment, surface water,and groundwater. Soil samples included those collected from the surface and shallow
subsurface using hand augers; those collected from split-barrel (spoon) sampling ofsubsurface soils during drilling; and those collected as surface 'grab' samples in areas ofsuspected contamination on both sites. Sediment and surface water samples werecollected from the ponds and wet areas on both sites. Groundwater samples werecollected from existing DNR wells; temporary monitoring wells installed as drilling
proceeded; and, permanent monitoring wells installed on both sites.
Th« number of samples, and types of analysis increased as the investigation proceeded
because of the complexity of both sites. Table 3 presents the summary of the totalestimated number of samples for each media (soil gas, soil, sediment, surface water, andgroundwater) with respect to type of analysis, as estimated in the approved Work Plan
__ (jOecember, 1984), the approved QAPP (August, 1986) and the actual amounts through the
end of June, 1986. Table 3 demonstrates the required increase in number of samples and
types of analysis required to achieve the goals of the investigation. Tables 4a through 4h
(Spiegelberg Site Samples) and Tables 5a through 5h (Rasmussen Dump Site Samples)
16NUS CORPORATION
provide a detailed breakdown of the samples by media, fiefcTnumber, type of analysis, and
date sampled.
e Documents Prepared
Air Sampling Technical Memorandum, January 28, 1986
QA/QC required tracking forms (traffic reports, chain-of-custody)
Field notebook documentation of sample numbers for samples analyzed by field of otherlaboratories ^
Boring logs for documentation of soils and temporary well samples obtained during
drilling but not analyzed by field or other laboratory
• Percent Compfete - 75% (Phase IV drilling and oversight of PRP test trenching remainedafter June, 1985.)
TASK 3.5 FIELD MONITORING
Field monitoring involved tht monitoring of the breathing space during filed operationsto ensure that the health and safety requirements of the project were maintained.
e Documents Prepared
>!
No formal documents required.
e Percent Complete -75% (Phase IV drilling remained to be completed after June, 1985.)
TASK 4.0 SITE DATA EVALUATION (Subtasks 4.1 and 4.2)
e Summary of Activities
The site data evaluation task is subdivided into two major subtasks: Subtask 4.1 - Data
Validation, Reduction and Evaluation; and, Subtask 4.2 - Public Health and RiskAssessment. Data validation was completed for laboratory analysis of samples collected
17NLJS CORPORATION
prior to June, 1986. Data validation reports have been transmitted to the DNR projectmanager.
Subtask 4.2 (Public Health and Risk Assessment) was not completed under OPO GW7956
because changes in the scope and schedule of the project necessarily delayed the initiationof the risk assessment beyond the end of June, 1986. The scope of work for the Remedial
Investigation, which requires completion prior to initiating the Risk Assessment,significantly increased to obtain the basic information necessary to perform a Risk
Assessment and Feasibility Study. (A Risk Assessment was performed of the Spiegelberg
Site Paint Sludge Area Operable Unit under a different DPO/CR number when NUS, DNRand EPA identified the area an as operable unit.)
Subtask 4.1 (Data Validation. Reduction, and Evaluation) the Work Pfan lists a number of
methods and techniques that are to be incorporated into the Remedial Investigation. Theincreases in the scope and schedule of the investigation did not allow the completion ofmost of these listed items; however, many of them were in progress. A number of field
activities were anticipated beyond the end of June, 1986, (e.g. Phase 4 Drilling) so dataevaluations and products (e.g. maps, tables, geological cross-sections) were not complete,and in preliminary draft stages. A status for each of the listed items is as follows:
Chemical data validation was partially complete for samples collected prior to the endof June, 1986.
Chemical data from the field screening, CLP laboratories and NUS laboratory were
entered into computer data bases (field screening, DNR data, NUS laboratory data are
on Lotus 1-2-3; CLP laboratory data and several groundwater samples run by NUS
laboratory are on R base 5000 data base).
The location, relative thickness, and general character of the waste areas on both sites
had been identified, and divided into preliminary operable units, under this DPO. Theoperable units were described in the November, 1986, Draft Phased Feasibility Study
which was prepared under a different DPO/CR.
Preliminary draft "topographic maps were prepared showing the sample locations,
sample number, sample date, and organic compounds that passed validation for
surface soils, sediments, and subsurface soils for both sites.
18NUS CORPORATION
Worksheets for geological cross-sections were prepared, but not completed, pendingthe results of Phase 4 drilling.
Worksheets for ground water flow in both the upper and lower aquifers wereprepared but not complete pending the results of Phase 4 Drilling.
Isoconcentration maps of groundwater contamination were not prepared as of theend of June, 1986, because the field investigation was not complete; however,
preliminary draft topographic maps showing well locations, and analytical results fororganic constituents, passing validation were prepared, and utilized for dataevaluation.
The quantity of groundwater recharge through the waste materials was analytically
estimated under this DPO, and provided in the November, 1985, Phased FeasibilityStudy that was prepared under a different OPO/CR.
Air quality data obtained at both sites was summarized in tables, and locationsprovided on maps in the technical memorandum for the air sapling investigation.
Potential receptors wert tentatively identified, although final identification waspending the results of additional drilling. No formal documents were preparedregarding the potential groundwater receptors; however, the areas of concern wereidentified during the investigation, and formally defined in a letter to the ONRmanager, dated September, 11,1986.
The data evaluation task, as defined in the Work Plan, was also to identify 'gaps' in thedata-for potential further investigation. Identification of data gaps upon completion of
the Remedial Investigation was a formal element of the Remedial Investigation/FeasibilityStudy process because of the way in which Superfund projects were implemented at thattime in the program. In practice, the data gaps were identified as the data was acquired
and reviewed during the investigation, and adjustments were made through Work Plan
Modifications 1 through 5.
19NUS CORPORATION
• Documents Prepared
No formal documents were required for this task; however, numerous technicalworksheets, maps, tables, and other 'internal use' documents were prepared and utilizedin meetings with the ONR and EPA.
e Percent complete - 75% (Phase IV drilling and PRP oversight activities remained afterJune, 1985.)
TASK 5.0 REMEDIAL INVESTIGATION REPORT
e Summary of Activities
No Remedial Investigation report was initiated prior to June, 1986, because increases in
scope and schedule of the project left a significant amount of field work to be performedafter that date.
• Percent Complete - 0%
TASKS 6THROUGH13 (FEASIBILITY STUDY)
The Feasibility Study was initiated under this ^PO \vhan the operable units were identifiedfor both sites. DNR and EPA requested that NUS prepare a Phased Feasibility Study (PFS)for the operable units on both sites in October, 1985. The scope of the PFS was modified inJanuary, 1986, to only include an area on the Spiegelberg Site since the presence ofdioxins/dibenzofurans was discovered on the Rasmussen site, delaying the evaluation ofthe operable units pending further field sampling and analysis. Most of the workperformed for the PFS was conducted under a different DPO/CR; however, it was
recognized that certain elements of work for the PFS would be the same for the FeasibilityStudy, so a part of the I evel-of -effort approved for the Feasibility Study in DPO GW7956was used for the PFS, as explained in Work Plan Modification No. 4. A general increase inthe scope of the feasibility studies for both sites was recognized as the complexity of thesites was learned during the course of the investigation, and general requirements forfeasibility studies changed in the Superfund Program. Additional level of effort and
budget allocations for completing a feasibility study were requested and approved in
Work Plan Modifications Nos. 5 and 8.
20NUS
e Documents Prepared
No formal Feasibility Study documents were submitted under DPO GW7956; however, a
portion of the work for the two PFS reports that were submitted (November, 1985; May,1986) was performed under tht level-of-effort and budget of DPO GW7956.
• Percent Complete-10%
TASK 14.0 ADDITIONAL REQUIREMENTS
(No additional requirements attributable to this task were made.)
TASK 15.0 COMMUNITY RELATIONS SUPPORT
• Summary of Activities
DNR conducted all community relations for the project. NUS provided limited support toDNR and EPA for Community Meetings held at various times. The support was mainlyattending the meetings and being available to answer questions when directed to do soby the DNR.
• Documents Prepared
No formal documents required for this task. ~
TASK 16.0 DEVELOPMENT OF PHASE II COOPERATIVE AGREEMENT APPLICATION
e Summary of Activities
NUS did not assist DNR with a Phase II Cooperative Agreement; however, NUS did assist
DNR at various times in meetings with the EPA, and with providing information for DNRs
preparation of various administrative documents and requests.
21NUS CORPORATION
This concludes the summary of activities for DPO GW7956. Work for the Spiegelberg and Rasmussen
Dump Sites Rl/FS continues under DPO/CR GA-7885. If you have any questions, please contact me.
Very truly yours,
George D. GardnerProject Manager
cc: A. BombergerC. Nieland
G. SgroD. Snyder
22NUS CdRPQRATlQN
TABLE 1a
SUMMARY OF MONITORING WELL DATA FOR PHASES I. II. AND III
SPIEGELBERG AND RASMUSSEN DUMP SITES
PHASE I
WellNo
SP-5D
SP-12
SP-13
SP-14
SP-15
RA-16
RA-17
RA-18D
SP-19
SP-20D
RA-21
RA-22
Month/YearDrilling
Completed
3/85
2/85
2/85
2/85
3/85
3/85
3/85
3/85
3/85
4/85
3/85
3/85
SurfaceElevation
(feet MSL)
914
930.4
9376
9336
887.9
903.1
9223
9346
8956
917.2
920.6
9356
TotalDepth
Drilled (ft)
79
75
76.5
72
19
37
51.5
112
20
183.5
50
61.5
Final Screen Depth(ft)
57-61
72-75
73,5-765
69-72
15-18
34-37
47-50
101-105
15-18
72-76
44-47
57-60
DrillingMethod
HSA/CT
HSA
H5A
HSA
HSA
HSA
HSA
HSA/CT
HSA
HSA/CT
HSA
HSA
IntervalBetween
SoilSamples
(ft)
-
10
10
10
5
5
S
-
5
5 (to 50)
5
5
Insitu (1)Permeability
X
X
X
X
X
X
X
X
X
X
X
X
Gamma(2)Log
X
X
X
X
X
X
X
X
X
X
X
(1) Insitu permeability tests also performed on existing DNR wells Nos 81-2,3,4,5,6,7,8,9,10(2) Gamma Logs also performed on nine existing DNR wells Nos 81-2,3,4,5,6,7,8,9,10
PAGE 1 OF 2
TABLE la
SUMMARY OF MONITORING WELL DATA FOR PHASES I, II. AND III
SPIEGELBERG AND RASMUSSEN DUMP SITES
PHASE 1
WellNo
RA-23D
SP-24
SP-25D
SP-26
RA-27
RA-28
SP-29D
SP-30D
RA-31D
Month/YearDrilling
Completed
4/85
3/85
4/85
3/85
3/85
3/85
3/85
4/85
5/85
SurfaceElevation
(feet MSL)
9330
9229
9273
911.4
911 5
9187
9360
8989
900(2)
TotalDepth
Drilled (ft)
100
66
187
40
41.5
50
40
143
150
Final Screen Depth(ft)
No wellScreen Collasped
63-66
160-163
35-38
32.5-35.5
44-47
--
130-134
69.5-73.5
DrillingMethod
HSA/CT
HSA
HSA/CT
HSA
HSA
HSA
HSA
CT
CT
IntervalBetween
SoilSamples
(ft)
5 (to 60)
5
5 (to 45)
5
5
5
5
-
-
Insitu (1)Permeability
--
X
X
X
X
X
-X
X
Gamma(2)Log
X
X
X
X
X
X
--X
X
(1) Insitu permeability tests also performed on existing DNR wells Nos. 81-2,3.4,5,6,7,8,9,10(2) Gamma Logs also performed on nine existing DNR wells Nos 81-2,3,4,5,6,7.8,9.10
PAGE 2 OF 2
TABLE 1b
SUMMARY OF MONITORING WELL DATA FOR PHASES I, II, AND III
SPIEGELBERG AND RASMUSSEN DUMP SITES
PHASE II .
WellNo
RA 32
RA-33
RA-34
RA-35
RA-36
SP 37
RA-38
RA 39
SP-40
Monti i/YearDrilling
Completed
6/85
6/85
6/85
6/85
6/85
7/85
7/85
7/85
7/85
SurfaceElevation
(feet MSL)
9135
892.7
9220
9058
905.0
927.2
8866
887.1
9140
TotalDepth
Drilled (It)
101
855
102
85
75
100
77
94.4
80
FinalScreen
Depth (ft)
45-47
67-70
97-101
72-75
30-33
54-57
58-61
57-60
72-75
DrillingMethod
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
Temporary Well Sample
IntervalBetween
Well Samples(ft)
10
10
10
10
10
10
10
10
--
Depth (ft)
(40-90)
(20-70)
(60-100)
(30-70)
'(35-60)
(58-68)
(20-80)
(20-60)
--
InsituPermeability
X
X
X
X
--
X
X
X
GammaLog
X
X
X
X
X
X
X
X
X
PAGE 1 OF 1
TABLE 1c
SUMMARY OF MONITORING WELL DATA FOR PHASES I, II, AND III
SPIEGELBERG AND RASMUSSEN DUMP SITES
PHASE III
WenNo
i
RA-41
RA-42
RA-43*
SP-44
SP-45
SP-46
RA-47
SP-48
SP-49
Month/YearDrilling
Completed
9/85
10/85
10/85
10/65
9/85
10/85
10/85
10/85
10/85
SurfaceElevation
(feet MSL)
919
934
930
918
931
952
935
912
913.1
TotalDepth
Drilled (ft)
153
190
110
169
182
199
190
24
161
FinalScreen
Depth (ft)
144-147
163-167
-
158-162
159-163
174-177
149-153
HoleCollaspe
140-144
DrillingMethod
R(to100)/CT
R(to95)/CT
R(TollO)
R (to 50)/CT
CT
CT
R(to 100)/CT
R(to24)
R(to95)/CT
Temporary Well Sample
IntervalBetween
Well Samples(ft)
--
10
-
10
10
10
10
"
10
Depth (ft)
--
(145-185)
-
(80-160)
(80-170)
(100.110,120.145.165.175.
185)
(150-170)
--
(136,147)
InsituPermeability
--
X
--
X
X
--
--
-
Gamma(1)Log
X
X
--
X
X
X
X
»X
R - Rotary Drilling CT = Cable Tool DrillingHSA = Hollow Steel Auger Drilling MSL = Mean Sea LevelY = Yes, Borehole/well was tested or logged N = No, borehole/well was not tested or logged* -- Landowner demanded abandonment of well - no well installed( 1 ) ~ Resistivity loops also performed for wells RA-MW-41,42,44 and SP-MW-44
PAGE 1 OF 1
TABLE 2
SUMMARY OF SOIL BORING DATA(BORINGS WITH NO WELLS)
SPIEGELBERG AND RASMUSSEN DUMP SITES
BORINGNO.
RA-B1
RA-B2
SP-B3
SP-B4
SP-B5
RA-B6
RA-B7
RA-B8
RA-B9
SP-B10
SP-B11
RA-812
5P-B13
SP-B14
SP-B15
SP-B16
MONTH/YEARDRILLED
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
3/85
APPROXIMATESURFACE
ELEVATION(FEETMSU_
920
917
915.2 '
892
923
932
933
910
913
90S
910
938
917
910
890
931
TOTALDEPTH
(FT)
10
10
45
20
10
10
10
10
10
10
9.0
10
10
2.5
to10
DRILLINGMETHOD^)
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
HSA
NUMBER OFSPLIT-BARREL
SOIL SAMPLES'"
4
4
9*
5
4
5*
4
4
4
4
4
4
4
4
4
4
( 1 ) HSA = Hollow stem auger, samples obtained using a split-barrel (spoon) sampler(2) Sampling interval generally 0, 2.5, 5, 10, 15... feet below ground surface* Includes one duplicate sample
PAGE 1 OF 1
TABLE 3
SUMMARY OF TOTAL NUMBER OF SAMPLES VERSUS MEDIA(THROUGH JUNE, 1986)
SPIEGELBERG AND RASMUSSEN DUMP SITE
MEDIA
SOILS RA
SP
SOIL GAS RA
SP
SEDIMENTS RA
SP
SURFACE WATER RA
SP
GROUNDWATER RA
SP
GRAVEL RA
SP
WASTES RA
SP
TOTALS
HSLVOAs
1180)
55<»
6
6
65
67
2
2
12
8
341
HSLSNA
1181')
55«t
6
6
65
67
2
2
12
8
341
HSLPCBs
145«'>
55(»
6
6
65
67
2
2
12
a368
HSLINORG.
1070
55<»
6
6
65
65
2
2
12
8
328
DIOXINS
7
7
NUS LABANALYSIS
FOR TARGETMETALS
12
4
16
FIELDSCREENING
65<»
68w
60
48
78
103
422
DNRGEN
CHEMISTRY
18
19
37
(1) Includes 34 soil samples collected with waste samples during test pitting operations(2) Includes 2 soil samples collected with waste samples during test pitting operations(3) Includes 31 soil samples collected from borings(4) Includes 41 soil samples collected from borings
* r 4 r\r
TABLE 4a
SOIL GAS ANALYSIS*
SPIEGELBERG SITE
SAMPLENUMBER
SP-SG01
SP-SG-02
SP-SG-03
SP-SG-04
SP-SG-05
SPSG-06
SP-SG-07
SPSG-08
SP-SG-09
SP-SG-10
SP-SG-11
SP-SG-12
SPSG 13
SP-SG-14
SP-SG-15
SPSG- 16
DATESAMPLED
2/14/85
2/14/85
'--
2/13/85
2/13/85
2/13/85
2/13/85
2/13/85
2/13/85
2/13/85
2/13/85
2/14/85
2/14/85
2/12/85
2/12/85
2/12/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG.
OIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
NR
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
NR = Not Run* = Does not include prep runs or blanks
PAGE 1 OF 4
TABLE 4a
SOIL GAS ANALYSIS*
SPIEGELBERG SITE
SAMPLENUMBER
SP-SG-17
SP-SG-1B
SP-SG-19
SP-SG 20
SP-SG-21
SPSG-22
SP-SG-23A
SP-SG-23B
SPSG-24
SP-SG-25
SP-SG 26
SP-SG 27
SP-SG-28
SP-SG 29
SP-SG-30
SP-SG-31
DATESAMPLED
2/12/Bf
2/12/85
2/21/85
2/12/85
2/12/85
2/21/85
2/28/B5
2/12/85
--
2/25/85
2/27/85
2/27/85
2/27/85
2/21/85
2/21/85
2/22/85
HSLVOAs
•
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITY
—— 1-
NUS LABSCREENING
>
FIELDSCREENING
X
X
X
X
X
X
X
X
NR
X
X
X
X
X
X
X
ONRGEN
CHEMISTRY
NR = Not Run* = Does not include prep runs or blanks
PAGE 2 OF 4
TABLE 4a
SOIL GAS ANALYSIS*
SPIEGELBERG SITE
SAMP' ENUMBFR
SP-SG i2
SPSG-33
SP-SG -34
SP-SG- 34A
SP-SG-35
SP-SG-36
SP-SG-37
SP-SG 38
SP-SG-39
SP-SG -40
SP-SG-41
SP-SG 42
SP-SG 43
SP-SG-44
SP-SG 45
SP-SG-46
DATESAMPLED
2/22/85
2/25/85
2/25/85
2/25/85
2/25/85
2/21/85
2/22/85
2/26/85
2/26/85
2/26/85
3/1/85
3/1/85
3/1/85
3/1/85
3/6/85
3/6/85
HSLVOAs
HSLBNA
i
HSLPCBs
•
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
r
NR - Not Run* = Does not include prep runs or blanks
PAGE 3 OF 4
TABLE 4a
SOIL GAS ANALYSIS*
SPIEGELBERG SITE
SAMPLENUMBER
SP-SG-47
SP-SG-48
DATESAMPLED
3/6/85
3/26/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
DNRGEN
CHEMISTRY
NR - Not Run* - Does not include prep runs or blanks
PAGE 4 OF 4
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
24 (MW30D PP)
25 (MW25D PP)
26 (MW30D PP)
27 (MW26 PP)
28 (MW19 PP)
MW5D 344 -374 '
MW5D 394-42.4'
MW5D 40-43'
MW5D 51 5-53.5'
MW5D 61 64'
MW5D 67-70'
MW5D PP
MW12 PP
MW13 PP
MW14 PP
MW15 DIS
DATEANALYZED
5/14/85
5/14/85
5/ 14/85
5/14/85
5/15/85
3/12/85
3/13/85
3/18/85
3/19/85
3/19/85
3/20/85
4/9/85
4/3/85
4/3/85
4/3/85
3/12/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
- Does nol include prep runs or blanksPP = Post Production SampleDIS - Dischaiye Sample
PAGE 1 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPtEGELBERG SITE
SAMPLEIDENTIFICATION
MW.15 PP
MW19 DIS
MW19 PP
MW19 PP
MW20D 43-45 5'
MW20D 62-65'
MW20D 67-70'
MW20D 72-76'
MW20D 73 5-76'
MW20D 73 5-76'dup
MW20D 83 85 5'
MW20D 93 94 5'
MW20D 100-102 5'
MW20D 108-1105'
MW20D 119-120'
MW20D 130-131 5'
DATEANALYZED
4/3/85
3/14/85
4/9/86
5/13/85
3/19/85
3/27/85
3/27/85
4/3/85
3/28/85
3/28/85
3/28/85
3/29/85
4/1/85
4/1/85
4/2/85
4/3/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG DIOXINS
EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
= Does not include prep runs or blanksPP = Post Production SampleDIS = Discharge Sample
PAGE 2 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
MW20D 140-142'
MW20D 150-152'
MW20D 160-162.5'
MW20D 170-1725'
MW20D 171-173 5'
MW24 DIS
MW24 PP
MW24 PPdup
MW25D 47 .5-50 5'
MW25D 62-64 5'
MW25D 72-75 5'
MW25D 100 102'
MW25D 110 112'
MW25D 120-122'
MW25D 130-132'
MW25D 140-142'
DATEANALYZED
4/3/85
3/28/85
4/8/85
4/9/85
4/10/85
3/21/85
4/9/85
4/9/85
3/27/85
4/12/85
4/15/85
4/16/85
4/17/85
4/17/85
4/18/85
4/18/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
|TOXICITYi
NUSLABSCREENING
>
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
* = Does not include prep runs or blanksPP = Post Production SampleDIS = Discharge Sample
PAGE 3 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
MW25D 1515-154'
MW25D 162-164'
MW25D 172-174'
MW25D 176-178'
MW26 DIS
MW26 PP
MW26 PP
MW30D 30-33'
MW30D 63-66'
MW30D 108-110'
MW30D 118-120'
MW30D 128-120'
MW30D 130-134'
MW37 54-57'
MW37 58'
MW37 58' dup
DATEANALYZED
4/19/85
4/22/85
4/22/85
4/22/85
3/22/85
4/3/85
4/9/B5
4/30/85
5/2/85
5/2/85
5/3/85
5/6/85
5/7/85
7/2/85
7/1/85
7/1/85
HSLVOAs
HSLBNA
1
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
* = Does not include prep runs or blanksPP = Post Production SampleDIS - Discharge Sample
PAGE 4 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBER6 SITESAMPLE
IDENTIFICATION
MW44 80-83'
MW44 88 -91'
MW44 98-10V
MW44 108- 11 1'
MW44 119-121'
MW44 129-132'
MW44 139-140'
MW44 149-150'
MW44 156-160'
MW45 90'
MW45 100'
MW45 110'
MW45 118 120'
MW45 130'
MW45 140'
MW45 148-151'
DATEANALYZED
10/9/85
10/10/85
10/10/85
10/14/85
10/14/85
10/15/85
10/15/85
10/17/85
10/22/85
9/12/85
9/12/85
9/13/85
9/19/85
9/20/85
9/20/85
9/23/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXIGTYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
= Does not include prep runs or blanksPP = Post Production SampleDIS = Discharge Sample
PAGE 5 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
MW4S 158-160'
MW45 159 163'
MW45 168-171'
MW46 102-105'
MW46 112-115'
MW46 122 5-125.5*
MW46 132 5-135 5'
MW46 142 145'
MW46 152-155'
MW46 158-160'
MW46 162-165'
MW46 162-165'dup
MW46 172-175'
MW46 177'
MW46 182-185'
MW49 125-126'
DATEANALYZED
9/24/85
9/26/85
9/24/85
10/7/85
10/8/85
10/8/65
10/8/85
10/9/85
10/9/85
10/17/85
10/10/85
10/10/85
10/10/85
10/17/85
10/11/85
10/25/85
H5LVOAs
H5LBNA
HSLPCBs
HSLINORG.
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
* = Does not include prep runs or blanksPP = Post Production SampleDIS = Discharge Sample
PAGE 6 OF 7
TABLE 4b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
*
MW49 146 149'
MW49 PP
81-5 PP
81-6 PP
SPB3 45'
SPB3 45' dup
SPB4 DIS
DATEANALYZED
10/28/85
10/28/85
4/3/85
4/3/85
3/25/85
3/25/85
3/26/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG.
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
* = r ^es not include prep runs or blanksPP Production Sampler rge Sample
PAGF 7 OF 7
TABLE 4c
FIELD SCREENING - SOIL BORINGS*
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
SPB3 1-2.5'
SPB3 3 5 5 '
SPB3 8.5-10'
SPB3 13.5-15'
SPB3 18.5-20'
SPB3 23.5-25'
SPB3 28.5-30'
SPB4 2.5'
SPB4 5'
SPB4 10'
SPB4 15'
SPB4 20'
SPB5 0'
SPB5 2.5'
SPB5 5'
SPB5 10'
SPB10 0'
DATEANALYZED
3/25/85
3/25/85
3/25/85
3/25/85
3/25/85
3/25/85
3/25/85
3/26/85
3/26/85
3/26/85
3/26/85
3/26/85
3/27/85
3/27/85
3/27/85
3/27/85
3/28/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG DIOXINS EP
TOXICITY
i
NUSLABSCREENING
>
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
———————— \
= Does not include prep runs or blanks
PAGE 1 OF 3
TABLE 4c
FIELD SCREENING - SOIL BORINGS*
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
SPB10 2 r'
SPB10 5'
SPB10 10k
SPB11 0'
SPB11 2.5'
SPB11 5'
SPBII 10'SPB13 0'
SPB13 2.5'
SPB13 5'
SPB13 10'
SPB14 0'
SPBH 2.5'
SPB14 5'
SPB14 10'
SPB15 0'
SPB15 2.5'
DATEANALYZED
3/28/85
3/28/85
3/28/85
3/28/85
3/28/65
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
= Does not include prep runs or blanks
PAGE 2 OF 3
TABLE 4c
FIELD SCREENING - SOIL BORINGS*
SPIEGELBERG SITE
SAMPLEIDENTIFICATION
SPB15 5'
SPB15 10'
SPB16 0'
SPB16 2 5'
SPB16 5'
SPB16 10'
SPMW20D 39.5-41'
DATEANALYZED
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/19/85
HSLVOAs
HSLSNA
HSLPCBs
HSLINORG. DtOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
= Doesnot include prep runs or blanks
PAGE 3 OF 3
TABLE 4d
NUS LABORATORY ANALYSIS FOR INORGANIC TARGET COMPOUNDS - SOILS
SPIEGELBERG SITE
SAMPLENUMBER
SP-SOS-001
SP-SOS-002
SP-SOS-003
SP-SOS-004
DATESAMPLED
1/12/85
1/12/85
1/12/85
1/12/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUS LAB
SCREENING
X
X
X
X
FIELDSCREENING
DNRGEN
CHEMISTRY
PAGE 1 OF 1
TABLE 4e
HSL ANALYSIS - GRAVEL, SURFACE WATER, SEDIMENT
SPIEGELBERG SITE
SAMPLENUMBER
SP-GR-001
SP-GR-002
SP-SW-000
SP-SW-001
SPSW-001A
SP-SW-002
SP-SW-003
SP-SW-004
SP-SD-000
SP-SD-001
SP-SD-001A
SP-SD-002
SPSD-003
SP-SD-004
DATESAMPLED
1/16/85
1/16/85
12/4/84
12/4/84
12/4/84
12/4/84
12/4/84
12/4/84
12/6/84
12/6/84
12/6/84
12/6/84
12/6/84
12/6/84
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
PAGE 1 OF 1
TABLE 4f
HSL ANALYSIS - TEST PIT SAMPLES
SPIEGELBERG SITE
SAMPLENUMBER
SP-TP-001
SP-TP-002
SP-TP-003
SP-TP-004
SP-TP-005
SP-TP-006
SP-TP-007
SP-TP-008
DATESAMPLED
6/1 1/85
6/1 1/85
6/1 1/85
6/1 1/85
6/11/85
6/1 1/85
6/1 1/85
6/1 1/85
HSLVOAs
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITYr
NUSLABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
PAGE 1 OF 1
TABLE 4g
HSL AND FIELD SCREENING ANALYSIS") - SURFACE AND SHALLOW SUBSURFACE SOILS
SPIEGELBERG SITE
SAMPLENUMdER
sp-so-oorSP-SOFS-GJ1
SP-SOFS-Ob2
SP-SOFS-003
SP-SOFS-004
SP-SOFS-005
SP-SOFS 006
SP-SO-006
SP-SOFS-007
SP-SO-007
SP-SO-007A
SP-SOFS-008
SP-SOFS-009
SP-SO-009
SP-SOFS-010
SPSOFS-011
DATESAMPLED
1/3/85
12/11/84
12/11/84
12/12/84
12/12/84
12/12/84
12/12/84
1/3/85
12/12/84
1/3/85
1/3/85
12/12/84
12/12/84
1/3/85
1/5/85
1/15/85
HSLVOAs
X
X
X
X
X
HSLBNA
X
X
I
X
X
X
HSLPCBs
X
X
X
X
X
HSLINORG.
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
RE = Sample re-extracted(U =
PAGE 1 OF 6
TABLE 4g
HSL AND FIELD SCREENING ANALYSISO) - SURFACE AND SHALLOW SUBSURFACE SOILS
SPIE6ELBERG SITE
SAMPLENUMBER
SPSOFS012
SPSOFS-013
5P-SOFS-014
5P-SOFS-015
SP-SOFS-016
SP-SO-016
SP-SO-016A
SPSOFS-017
SP-SOFS-018
SP-SOFS 019
SP-SOFS020
SP-SO-020
SPSOFS-021
SP-SOFS-022
SPSO-022
SP-SOFS-023
DATESAMPLED
1/6/85
1/6/85
1/6/85
1/6/86
1/6/85
1/10/85
1/10/85
1/6/85
1/6/85
1/6/85
1/6/85
1/10/85
5/29/85
5/29/85
1/10/85
5/29/85
HSLVOAs
X
X
*
X
X
HSL8NA
X
X
X
X
HSLPCBs
X
X
X
X
HSLINORG.
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
RE = Sample re extracted0) =
PAGE 2 OF 6
TABLE 4g
HSL AND FIELD SCREENING ANALYSIS") - SURFACE AND SHALLOW SUBSURFACE SOILS
SPIEGELBERG SITE
SAMPLENUMBER
SP-SO023
SP-SOFS-024
SP-SO-024"'
SP-SO-025
SP-SO-026
SP-SO-026A
SP-SO-027
SP-SO-028
SP-SO-029
SP-SO 030
SP-SO-031
SP-SO-032
SP-SOQ33
SP-SO-034
SP-SO-034A
SPSO-035
DATESAMPLED
1/10/85
5/29/85
2/1/85
2/1/85
2/1/85
2/1/85
2/7/85
2/7/85
2/7/85
2/7/85
2/22/85
2/22/85
2/22/85
2/22/85
2/22/85
2/22/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
X
DNRGEN
CHEMISTRY
RE = Sample re-extracted(D =
PAGE 3 OF 6
TABLE 4g
HSL AND FIELD SCREENING ANALYSIS") - SURFACE AND SHALLOW SUBSURFACE SOILS
SPIEGELBERG SITE————————— V —————
SAMPLENUMBER
SPSO 036
SP-SO-037
SP-SO 038
SP-SO- 039
SP-SO040
SP-SO 041
SP-SO 042
SP-SO-043
SP-SO-044
SP-SO 04 5
SP-SO-046
SP-SO-047
SP-SO048
SP-SO-049
SP-SO-050
SP-SO-051
DATESAMPLED
2/22/85
2/22/85
2/28/85
2/28/85
2/28/85
3/20/85
3/21/85
3/21/85
3/21/85
3/27/85
3/27/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
RE = Sample re-extracted(1) =
PAGE 4 OF 6
TABLE 4g
HSL AND FIELD SCREENING ANALYSIS*') • SURFACE AND SHALLOW SUBSURFACE SOILS
SPIEGELBERG SITE
SAMPLENUMBER
SP-SO-052
SP-SO-053
SP-SO-054
SP-SOFS-055
SP-SO-055
SP-SOFS-056
SP-SO-056
SPSOFS-057
SP-SO-057
SPSO-058
SP-SO-058A
SP-SO-059
SP-SO-060
SP-SO-061
SP-SO-062
SP-SO-062A
DATESAMPLED
3/28/85
3/28/85
3/28/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
5/8/85
5/8/85
5/8/85
5/14/86
5/14/86
5/14/86
5/14/86
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X,
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
DtOXINS EPTOXICITY
i
NUSLABSCREENING
>
•
FIELDSCREENING
X
X
X
DNRGEN.
CHEMISTRY
RE = Sample re-extracted(1) =
PAGE 5 OF 6
TABLE 4g
HSL AND FIELD SCREENING ANALYSIS") - SURFACE AND SHALLOW SUBSURFACE SOILS
SPIE6ELBERG SITE
SAMPLENUMBER
AFTERJUNE, 1986
SP-SO-063 ,
SP-SO-064
SP-SO-065
DATESAMPLED
6/21/86
8/21/86
8/21/86
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG.
DIOXINS EPTOXICITY
X
X
X
NUSLABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
RE = Sample re-extracted(D =
PAGE 6 OF 6
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-000
SP-GW-000
SP-GW-000"
SP-GW-000
SP-GW-000
SP-GW-000
SP-GW-000
SP-GW-002
SP-GW-003
SP-GW-004
SP-GW-005
SP-GW-005A
SP-GW-006
SP-GW-007
SP-GW-008
DATESAMPLED
3/27/85
4/10/85
4/23/85
5/8/85
10/16/85
10/30/85
5/14/86
1/31/85
1/31/85
1/30/85
1/30/85
1/30/85
1/30/85
1/30/85
3/27/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
*X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
OIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
X
X
X
X
X
X
X
MDPH
RE = Sample re-extractedN = NUS Laboratory-quick turnaround
PAGE 1 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW009
SP-GW-010
SP-GW-010A
SP-GW-011
SP-GW-012
SP-GW-013
SP-GW-014
SP-GW-015N
SP-GW-015
SP-GW-016
SP-GW-016A
SP-GW-017
SP-GW-01B
SP-GW-019
SP-GW-020N
DATESAMPLED
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/1 1/85
4/9/85
4/9/85
4/9/85
4/9/85
4/9/85
4/10/85
4/1 1/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
X
X
X
X
X
X
X
MDPH
RE = Sample re-extractedN = NUS Laboratory-quick turnaround
PAGE 2 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-021
SP-GW-021A
SP-GW-022
SP-GW-022A
SP GW-023
SP-GW-024
SP-GW-025
SP-GW-026
SP-GW-026A
SP-GW-027
SP-GW-028
SP-GW-029
SP-GW-029A
SP-GW-030
SP-GW-031
DATESAMPLED
4/23/85
4/23/85
5/7/85
5/7/85
5/14/85
5/14/85
5/14/85
5/14/85
5/14/85
5/15/85
5/15/85
7/30/85
7/30/85
7/30/85
10/15/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
H5LBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
X
X
X
MDPH
RE = Sample re-extractedN = NUS Laboratory-qukk turnaround
PAGE 3 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-032
SP-GW-032A
SP-GW-033
SP-GW-034
SP-GW-035
SP-GW-036
SP-GW-037
SP-GW-038
SP-GW-039
SP-GW-040
SP-GW-041
SP-GW 042
SP-GW-043
SP-GW-043A
SP-GW 044
DATESAMPLED
10/15/85
10/15/85
10/29/85
10/29/85
10/29/85
10/30/85
10/29/85
10/29/85
10/31/85
10/30/85
10/31/85
10/31/85
11/18/85
11/18/85
5/14/86
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
s*
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBS
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXIQTY
NUS LABSCREENING
*
FIELDSCREENING
DNRGEN
CHEMISTRYMDPH
1
RE = Sample re-extractedN = NUS Laboratory-quick turnaround
PAGE 4 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-045
SP-GW-046
SP-GW-047
SP-GW-048
SP-GW-049
SP-GW-050
SP-GW-051
AFTER JUNE, 1986
SP-GW-000
SP-GW-000
SP-GW-000
SP-GW-000
SP-GW-052
SP-GW-053
SP-GW-054
DATESAMPLED
5/14/86
S/ 14/86
5/14/86
5/14/86
5/13/86
5/13/86
5/14/86
3/18/87
3/20/87
3/24/87
7/24/87
3/17/87
3/18/87
3/17/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBS
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
X
X
X
X
MDPH
RE = Sample re-extractedN - NUS Laboratory-quick turnaround
PAGE 5 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNOWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-055
SP-GW-055A
SP-GW-056
SP-GW-057
SP-GW-058
SP-GW 059
SP-GW-060
SP-GW-061
SP-GW-062
SP-GW-063
SP-GW-064
SP-GW-065
SP-GW-065A
5P-GW-066
SPGW067
DATESAMPLED
3/18/67
3/18/67
3/18/87
3/23/87
3/18/87
3/1 B/87
3/18/87
3/18/87
3/19/87
3/19/87
3/18/87
3/19/87
3/19/87
3/19/87
3/19/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
*X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
MDPH
RE = Sample re-extractedN = NUS Laboratory - quick turnaround
PAGE 6 OF 8
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-068
SP-GW-069
5P-GW-070
SP-GW-071
SP-GW-072
SP-GW-073
SP-GW-074
SP-GW-075
SP-GW-075A
SP-GW-076
5P-GW-077
SP-GW-078
SP-GW-079
SP-GW-080
SP-GW-081
DATESAMPLED
3/19/87
3/23/87
3/18/87
3/24/87
3/24/87
3/23/87
3/19/87
3/18/87
3/18/87
3/20/87
3/23/87
3/20/87
3/23/87
3/24/87
3/24/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
MDPH
RE = Sample re-extractedN = NUS Laboratory-quick turnaround
PAGE 7 OF 8jft
TABLE 4h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
SPIEGELBERG SITE
SAMPLENUMBER
SP-GW-082
SP-GW-083
SP-GW-084
SP-GW-085
SP-GW-085A
SP-GW-086
SP-GW-087
SP-GW-OB8
SP-GW-089
SP-GW-090
SP-GW-091
SP-GW-091A
DATESAMPLED
3/24/87
3/24/B7
3/24/87
3/23/87
3/23/87
6/26/87
6/26/87
6/26/87
6/26/87
6/26/87
7/24/87
7/24/87
HSLVOAs
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
HSLPCBs
X
X "
X
X
X
X
X
HSLINORG.
X
X
X
X
X
DIOXINS EPTOXtCITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN.
CHEMISTRY
X
X
X
X
X
MDPH
X
X
X
X
X
RE = Sample re-extractedN = NUS Laboratory - quick turnaround
PAGE 8 OF 6
TABLE 5a
SOIL GAS ANALYSIS*
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SG-01
RA-SG-02
RA-SG-03
RA-SG-04
RA-SG-05
RA-SG-06
RA-SG-07
RA-SG-08
RA-SG-09
RA-SG-10
RA-SG-11
RA-SG-12
RA-SG-13
RA-SG-14
RA-SG-15
RASG-16
DATESAMPLED
1/:0/85
1/30/85
1/LO/85
1/30/85
2/27/85
2/14/85
2/14/85
2/1 1/85
2/1 1/85
2/1 1/85
2/1 1/85
2/11/85
2/5/85
2/1 1/85
2/14/85
2/14/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITY
1
NUS LABSCREENING
>
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
NR = Not Run* = Does not include preparation runs or blanks
PAGE 1 OF 4
TABLE 5a
SOIL GAS ANALYSIS*
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SG-17
RA-SG-19
RA-SG-19
RA-5G-20
RA-SG-21
RA-SG-22
RA-SG-23
RA-SG-24
RA-SG-25
RA-SG-26
RA-SG-27
RA-SG-28
RA-SG-29
RA-SG-30
RA-SG-31
RA-SG-32
DATESAMPLED
2/27/85
2/27/85
2/27/85
2/27/85
--
3/1/85
3/6/85
3/6/85
--
--
3/19/85
3/19/85
3/19/85
3/19/85
9/24-25/85
9/24-25/85
HSLVOAs
HSLBNA
I
HSLPCBs
HSLINORG.
DIOXINS EP.TOXICITY
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
NR
X
X
X
NR
NR
X
X
X
X
X
X
DNRGEN.
CHEMISTRY
NR = Not Run* = Does not include preparation runs or blanks
PAGE 2 OF 4
TABLE 5a
SOIL GAS ANALYSIS*
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SG-33
RA-SG-34
RA-SG-35
RA-SG-36
RA-SG-37
RA-SG-38
RA-SG-39
RA-SG-40
RA-SG-41
RA-SG-42
RA-SG-43
RA-SG-44
RA-SG-45
RA-SG-46
RA-SG-47
RA-SG-48
DATESAMPLED
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24*25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
HSLVOAs
V
HStBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
NR a Not Run* = Does not include preparation runs or blanks
PAGE 3 OF 4
TABLE 5a
SOIL GAS ANALYSIS*
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SG-49
RA-SG-50
RA-SG-51
RA-SG-52
RA-SG-53
RA-SG-54
RA-SG-55
RA-SG-56
RA-SG-57
RA-SG-58
RA-SG-59
RA-SG-60
DATESAMPLED
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
9/24-25/85
HSLVOAs
HSLBNA
HSLPCBs
-
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENING
"
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
NR = Not Run* = Does not include preparation runs or blanks
PAGE 4 OF 4
TABLE 5b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
MW16 DIS
MW16 PP
MW16 PP dup
MW17 DIS
MW17 PP
MW17 PP
MW17 PP dup
MW18 100'
MW18 100' dup
MW18 56.5-59 5'
MW18 60.5-63.5'
MW18 70.5-72'
MW18 80-83'
MW18 90'
MW18 PP
MW18 PP
DATEANALYZED
3/3/85
4/3/85
4/3/85
3/4/85
4/9/85
5/14/85
5/14/85
3/25/85
3/25/85
3/14/65
3/15/85
3/21/85
3/22/85
3/25/85
4/9/85
5/15/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNOS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
PP = Post ProductionDIS = Discharge* ~ Does not include prep runs or blanks
PAGE 1 OF 5
TABLE 5b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
MW21 PP
MW21 DIS
MW21 PP
MW22 PP
MW23 55.5-58.5'
MW23 59 5-62.5'
MW23 PP
MW23 PP
MW23 PP dup
MW27 DIS
MW27 PP
MW28 DIS
MW28 PP
MW28 PP dup
MW31D 26-29'
MW31D 30-32'
DATEANALYZED
9/9/85
3/19/85
4/9/85
4/10/85
3/21/85
3/21/85
4/26/85
5/14/85
5/14/85
3/26/85
4/9/85
3/29/85
4/10/85
4/10/85
5/8/85
5/8/85
HSLVOAs
HSLBNA
-
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUSLAB
SCREENING
t
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
«
PP = Post ProductionDIS = Discharge* = Does not include prep runs or blanks
PAGE 2 OF 5
TABLE 5b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
MW31D 40-43'
MW31D 50-53'iMW31D 64-67'
MW31D 72-75'
MW31D PP
MW32 39-42'
MW32 52 5'
MW32 52 5' dup
MW32 58'
MW32 61.5'
MW32 69-70'
MW32 78'
MW32 88-89'
MW33 18'
MW33 28'
MW33 38'
DATEANALYZED
5/8/85
5/8/85
5/8/85
5/8/85
5/14/85
6/13/85
6/13/85
6/13/85
6/19/85
6/14/85
6/14/85
6/17/85
6/17/85
6/19/85
6/19/85
6/19/85
HSLVOAs
•
HSLBNA
1 —————
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
PP = Post ProductionDIS = Discharge* - Does not include prep runs or blanks
PAGE 3 OF 5
TABLE 5b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
MW33 70'
MW33 71-73'
MW34 58-60'
MW34 66-67'
MW34 78'
MW34 89'
MW35 29'
MW3S 50'
MW3S 60'
MW35 70'
MW36 35'
MW36 55-58'
MW36 55-58' dup
MW36 PP
MW38 38'
MW3B 48'
DATEANALYZED
6/19/85
6/20/85
6/21/85
6/20785
6/24/85
6/24/85
6/25/85
6/25/85
6/25/85
6/25/85
6/26/85
6/27/86
6/27/85
6/28/85
7/8/85
7/9/85
HSLVOAs
t*.
HSLBNA
HSLPCBs
HSLINORG OIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
PP = Post ProductionDIS = Discharge* = Does not include prep runs or blanks
PAGE 4 OF 5
TABLE 5b
FIELD SCREENING - GROUNDWATER*(TEMPORARY WELLS)
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
MW39 12'
MW41 141'
MW41 141' dup
MW41 PP
MW42 146'
MW42 155'
MW42 166'
MW42 166' dup
MW42 174-177'
MW42 184'
MW42 PP
MW47 147-150'
MW47 157'
MW47 167'
DATEANALYZED
7/10/85
9/18/85
9/17/85
9/19/85
9/30/85
9/30/85
10/1/85
10/1/85
10/1/85
10/2/85
10/3/85
10/22/85
10/22/85
10/22/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
PP = Post ProductionDIS = Discharge* = Does not include prep runs or blanks
PAGE 5 OF 5
TABLE 5c
FIELD SCREENING - SOIL BORINGS*
RASMUSSEN DUMP SITE¥
SAMPLEIDENTIFICATION
RAB1 0'
RAB1 2.5'
RAB1 5'
RAB1 10'
RAB2 0'
RAB2 2 5'
RAB2 5'
RAB2 10'
RAB6 0'
RAB6 25'
RAB6 5'
RAB6 5' dup
RAB6 10'
RAB7 0'
RAB7 2.V
RAB7 5'
RAB7 10'
RAB8 0'
DATEANALYZED
3/14/B5
3/14/85
3/14/85
3/14/85
3/14/85
3/14/85
3/14/85
3/14/85
3/27/85
3/27/85
3/27/85
3/27/85
3/27/85
3/28/87
3/27/85
3/27/85
3/27/85
3/27/85
HSLVOAs
HSLBNA
HSLPCBs
HSLINORG. DIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
t
- Does not include prep runs or blanks
PAGE 1 OF 2
TABLE 5c
FIELD SCREENING - SOIL BORINGS*
RASMUSSEN DUMP SITE
SAMPLEIDENTIFICATION
RAB8 2.5'
RAB8 5'
RAB8 10'
RAB9 0'
RAB9 2.5'
RAB9 5'
RAB9 10'
RAB12 0'
RAB12 2.5'
RAB12 5'
RAB12 10'
MW18 41'
MW22 15-30'
DATEANALYZED
3/27/85
3/27/85
3/27/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/28/85
3/14/85
3/20/85
HSLVOAs
HSLBNA
HSLPCB$
HSLINORG DIOXINS TOX
E,PC|TY
n
NUSLABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
——————— *-
= Does not include prep runs or blanks
PAGE 2 OF 2
TABLE 5d
NUS LABORATORY ANALYSIS FOR INORGANIC TARGET COMPOUNDS - SOILS
RASMUSSEN DUMP SITE
SAMPLENUM3ER
RA-SOS-001
RA-SOS-Op2
RA-SOS-003
RA-SOS 004
RA-SOS-005
RA-SOS-006
RA-SOS-007
RA-SOS-008
RA- SOS-009
RA-SOS-010
RA-SOS-011
RA-SOS-012
DATESAMPLED
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
1/12/85
HSLVOAs
HSLBNA
j
HSLPCBs
HSLINORG.
DIOXINS EPTOXICITY
NUS LABSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
FIELDSCREENING
DNRGEN.
CHEMISTRY
PAGE 1 OF 1
TABLE 5e
HSL ANALYSIS - GRAVEL
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GR-001
RA-GR-002
DATESAMPLED
1/16/85
2/1/85
HSLVOAs
X
X
HSLBNA
X
X
HSLPCBs
X
X
HSLINORG.
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
PAGE 1 OF 1
TABLE 5f
HSL ANALYSIS - TEST PIT SAMPLES
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-TP-009
RA-TP-010
RA-TP-011
RA-TP-012
RA-TP-013
RA-TP-014
RA-TP-015
RA-TP-016
RA-TP-017
RA-TP-018
RA-TP-019
RA-TP-020
RA-TP-021
RA-TP-022
RA-TP-023
RA-TP-024
DATESAMPLED
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
t xX
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINSEP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
DNRGEN
CHEMISTRY
PAGE 1 OF 3
TABLE 5f
HSL ANALYSIS • TEST PIT SAMPLES
RASMUSSEN DUMP SITEV
SAMPLENUMBER
RA-TP-025
RA-TP-026
RA-TP-027
RA-TP-028
RA-TP-029
RA-TP-030
RA-TP-031
RA-TP-032
RA-TP-033
RA-TP-034
RA-TP-035
RA-TP036
RA-TP-037
RA-TP-038
RA-TP-039
RA-TP-040
DATESAMPLED
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
r
PAGE 2 OF 3
TABLE 5f
HSL ANALYSIS - TEST PIT SAMPLES
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-TP-041
RA-TP-042
RA-TP-043
RA-TP-044
RA-TP-045
RA-TP-046
RA-TP-047
RA-TP-048
RA-TP-049
RA-TP-050
RA-TP-051
RA-TP-052
RA-TP-052A
RA-TP-053
DATESAMPLED
0/13/85
ft/ 13/85
W13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
6/13/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOX1CITY
1
NUSLABSCREENING
>
FIELDSCREENING
DNRGEN
CHEMISTRY
PAGE 3 OF 3
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SOFS-01
RA-SOFS-O'M 2'
RA-SOFS-002
RA-SOFS-002 2'
RA-SOFS-003
RA-SO-003
RA-SOFS-003 2'
RA-SO-003 2'
RA-SOFS-004
RA-SO-004
RA-SOFS-005
RA-SOFS 006
RA-SOFS-007
RA-SOFS-008
RA-SOFS-009
RASOFS-010
DATESAMPLED
12/11/84
12/19/84
12/19/84
12/19/84
12/11/84
1/10/85
12/19/84
1/10/85
12/12/85
. 1/3/85
12/12/84
12/12/84
12/19/84
. 12/19/84
1/5/85
1/5/85
HSLVOAs
X
X
X
HSLBNA
X
X
I
X
HSLPCBs
X
X
X
HSLINORG
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
X
X
X
X
DNRGEN
CHEMISTRY
R = Blank for PCB samplesRE = Re-extraction
PAGE 1 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SOFS-011
RA-SQFS-012
RA-SOFS-013
RA-SO-013"'
RA SOFS-014
RA-SO-014
RA-SOFS-015
RA-SO-015
RA-SOFS-016
RA-SO-016
RA-SO-017
RASOFS-018
RA-SOFS-019
RA-SO-019
RA-SO-019A
RA-SOFS-020
DATESAMPLED
1/5/85
1/6/85
1/9/85
1/15/85
1/9/85
1/15/85
1/9/85
1/16/85
1/9/85
1/16/85
1/16/85
5/29/85
5/29/85
1/15/85
1/15/85
5/29/85
HSLVOAs
X
X
X
X
\x
"
X
X
HSLBNA
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
X
X
X
X
X
X
X
X
X
• DNRGEN
CHEMISTRY
R - Blank for PCB samplesRE - Re-extraction
PAGE 2 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS * SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-020
RA-SOFS-021
RA-SO-021
RA-SOFS-022
RA-SO-022
RA-SO-023
RA-SO-024
RA-SO-025
RA-SO-026
RA-SO-026A
RA-SO-027
RA-SO-028
RA-SO-029
RA-SO-030
RA-SO-031
RA-SO-032
DATESAMPLED
1/15/85
5/29/85
1/16/85
5/29/85
2/1/85
2/1/85
2/1/85
2/1/85
2/7/85
' 2/7/85
2/7/85
2/7/85
2/7/85
2/7/85
2/7/85
2/7/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
, X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
N US LABSCREENING
FIELDSCREENING
X
X
DNRGEN
CHEMISTRY
R = Blank for PCB samplesRE = Re-extraction
PAGE 3 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE>
SAMPLENUMBER
RA-SO-033
RA-SO-034
RA-SO-035
RA-SO-036
RA-SO037
RA SO-037A
RA SO-038
RA-SO-039
RA-SO-040
RA-SO-041
RA SO-042
RA SO 043
RA-SO-044
RA-SO-045
RA-SO-046
RA SO 046A
DATESAMPLED
2/22/85
2/22/85
2/28/85
2/28/85
2/28/85
2/28/85
2/28/85
2/28/85
2/28/85
3/13/85
3/15/85
3/14/85
3/14/85
3/14/85
3/14/85
3/14/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
' X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINSEP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
DNRGEN
CHEMISTRY
r
R - Blank for PCB samplesRE = Re-extraction
PAGE 4 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-047
RA-SO-048
RA-SO049
RA-SO-050
RA-SO-051
RA-SO-052
RA-SO-053
RA-SO-054
RA-SO-055
RA-SO-056
RA-SO-057
RA-SO-058
RA-SO059
RA-SO-060
RA-SO-061
RA-SO-061A
DATESAMPLED
3/14/85
3/14/85
3/14/85
3/14/85
3/20/85
3/20/85
3/20/85
3/20/85
3/20/85
3/20/85
3/27/85
3/27/85
3/27/85
3/27/85
3/28/85
3/28/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
>
FIELDSCREENING
DNRGEN
CHEMISTRY
——————— \
R = Blank for PCB samplesRE = Re-extraction
PAGE 5 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-062
RA-SO-063
RA-SOFS-064
RA-SO-064
RA-SO-064A
RASOFS-065
RA-SO-065
RA-SOFS-066
RA-SOFS-066D
RA-SO-066
RA-SO-067
RA-SO-068
RA-SOFS-069
RA-SO-069
RA-SOFS-070
RA-SO070
DATESAMPLED
3/28/85
3/28/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
4/3/85
3/28/85
3/28/85
4/17/85
4/17/85
4/ 17/85
4/17/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
1X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
X
X
X
X
X
X
DNRGEN
CHEMISTRY
R = Blank for PCB samplesRE = Re-extraction
PAGE 6 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-070A
RA-SOFS-071
RA-SO-071
RASOFS-072
RASO-072
RA-SOFS-073
RA-SO-073
RA-SOFS-074
RA-SO-074
RA-SO-075
RA-SO076
RA-SO-077
RA-SO-078
RA-SO-079
RA-SO-080
RA-SO-081
DATESAMPLED
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
4/17/85
5/8/85
5/8/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
HSLVOAs
X
X
X
X
X
X
,x'• •
HSLBNA
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
DIOXINSEP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
X
X
X
X
DNRGEN
CHEMISTRY
R = Blank for PCS samplesRE = Re-extraction
PAGE 7 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-082
RA-SO-083
RA-SO-084
RA-SO-085
RA-SO-085A
RA-SO-086
RA-SO-087
RA-SO-08B
RA-SO-089
RA-SO-090
RA-SO-091
RA-SO-092
RA-SO-093
RA-SO-094
RA-SO-095
RA-SO-096
DATESAMPLED
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
HSLVOAs
HSLBNA
HSLPCBs
X
X
X
X
X
X
X
X
X
. X
X
X
X
X
X
X
HSLINORG DIOXINS EP
TOXICITYNUS LAB
SCREENINGFIELD
SCREENING
DNRGEN
CHEMISTRY
R - Blank for PCB samplesRE = Re-extraction
PAGE 8 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITEr
SAMPLENUMBER
RASO-097
RA-SO-098
RA-SO-099
RA-SO-100
RA-SO-101
RA-SO-000"
RA SO- 102
RA-SO-103
RA-SO-104
RA-SO-105
RA-SO-106
RA-SO-106A
RA-SO-107
RA-SO-108
RA-SO-109
RA-SO-110
DATESAMPLED
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/5/85
9/18/85
9/18/85
9/18/85
9/18/85
9/18/85
9/18/85
9/18/85
10/9/85
10/9/85
10/9/85
HSLVOAs
X
X
X
HSLBNA
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
HSLINORG DIOXINS
X
X
X
X
X
X
X
EPTOX1CITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
*
R = Blank for PCB samplesRE = Re-e'xtraction
PAGE 9 OF 10
TABLE 5g
HSL AND FIELD SCREENING ANALYSIS - SURFACE AND SHALLOW SUBSURFACE SOILS
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-SO-111
RA-SO-112
RA-SO-113
RA-SO-114
RA-SO-115
RA-SO-116
RA-SO-117
RA-SO-117A
DATESAMPLED
10/9/85
10/9/85
10/9/85
10/10/85
10/10/85
10/10/85
. 10/10/85
10/10/85
HSLVOAs
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
HSLPCBS
X
X
X
X
X
X
X
X
HSLINORG. DIOXINS
—— f
EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
R = Blank for PCB samplesRE = Re-extraction
PAGE 10 OF 10
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GW-000
RA-GW-OQO
RA-GW-000
RA-GW-000
RA-GW-000
RA-GW-000
RA-GW-001
RA-GW-002
RA-GW-003
RA-GW-004
RA-GW-004A
RA-GW-005
RA-GW-006
RA-GW-007
RA-GW-008
RA GW-009
RA-GW-010
DATESAMPLED
1/31/85
4/3/85
5/14/85
7/30/85
9/10/85
11/18/85
1/30/85
1/30/85
1/31/85
3/26/85
3/26/85
4/3/85
4/9/85
4/9/85
4/10/85
4/9/85
4/9/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
Xj
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
X
X
X
X
X
X
X
PAGE 1 OF 6
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GW-011
RA-GW-016
RA-GW-017
RA-GW-018
RA-GW-019
RA-GW-020
RA-GW-021
RA-GW-022
RA-GW-023
RA-GW-024
RA-GW-025
RA-GW-026
RA-GW-027
RA-GW-028
RA-GW-029
RA-GW-029A
RA-GW-030
DATESAMPLED
4/10/85
4/1 1/85
5/14/85
5/15/85
5/13/85
5/14/85
7/30/85
7/30/85
7/30/85
7/30/85
7/30/85
7/30/85
7/30/85
7/30/85
9/9/85
9/9/85
10/14/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
-X
xX
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOX1CITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
X
X
X
X
X
X
X
PAGE 2 OF 6
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GW-031
RA-GW-032
RA-GW-033
RA-GW-034
RA-GW-035
RA-GW-036
RA-GW-037
RA-GW-038
RA-GW-039
RA-GW-039A
RA-GW-040
RA-GW-041
RA-GW-042
RA-GW 043
RA-GW-044
RA-GW-045
RA-GW-046
DATESAMPLED
10/15/85
10/15/85
10/15/85
10/15/85
10/14/85
10/15/85
10/15/85
10/15/85
10/30/85
10/30/85
10/31/85
10/31/85
10/31/85
10/31/85
10/30/85
11/18/85
11/18/85
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOX1CITY
NUSLABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
PAGE 3 OF 6
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GW-047
RA-GW-049
RA-GW-050
RA GW 051
RA-GW-052
RA-GW-053
RA-GW-054
RA-GW-055
RA-GW-056
RA-GW-057
RA-GW-058
RA-GW-059
RA-GW-059A
RA-GW-Q60
After June, 1986
RA-GW-061
RA-GW-06)
DATESAMPLED
11/18/85
S/ 13/86
5/13/86
5/13/86
5/14/86
5/13/86
5/13/86
5/14/86
5/13/86
5/14/86
5/13/86
5/13/86
5/13/86
5/13/86
3/16/87
3/17/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
-X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUS LABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
PAGE 4 OF 6
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
ORA-GW-63
RA-GW-064
RA-GW-065
RA-GW-066
RA-GW-067
RA-GW-068
RA-GW-069
RA-GW-070
RA-GW-070A
RA-GW-071
RA-GW-072
RA-GW-073
RA-GW-074
RA-GW-075
RA-GW-076
RA-GW-077
RA-GW-078
DATESAMPLED
J/17/87
3/17/87
3/17/87
3/17/87
3/17/87
3/19/87
3/17/87
3/17/87
3/17/87
3/17/87
3/17/87
3/19/87
3/19/87
3/23/87
3/19/87
3/20/87
3/20/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
»
FIELDSCREENING
ONRGEN
CHEMISTRY
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
PAGE 5 OF 6
TABLE 5h
HSL AND OTHER LAB ANALYSIS - GROUNDWATER(MONITORING WELLS)
RASMUSSEN DUMP SITE
SAMPLENUMBER
RA-GW-079
RA-GW-080
RA-GW-081
RA-GW-082
RA-GW-083
RA-GW-084
RA-GW-084A
RA-GW-000
RA-GW-000
RA-GW-085
RA-GW-086
RA-GW-087
DATESAMPLED
3/20/87
3/20/87
3/20/87
3/20/87
3/20/87
3/20/87
3/20/87
3/16/87
3/18/87
7/23/87
7/23/87
7/23/87
HSLVOAs
X
X
X
X
X
X
X
X
X
X
X
X
HSLBNA
X
X
X
X
X
X
X
X
X
X
X
X
HSLPCBs
X
X
X
X
X
X
X
X
X
HSLINORG.
X
X
X
X
X
X
X
X
X
DIOXINS EPTOXICITY
NUSLABSCREENING
FIELDSCREENING
DNRGEN
CHEMISTRY
X
X
X
X
X
X
X
X
X
PAGE 6 OF 6