Installation of Ormonde and Other Offshore Wind Farms
Mike Hulton- Project Manager
ode
1. Ormonde – Foundations
2. Ormonde – Cables
3. Ormonde – Making It Fit
4. Other UK Wind projects
5. Experience and Knowledge Transfer
6. America
Installation of Ormonde and Other Offshore Wind Projects
ode Overall Project Timeline: Ormonde UK
ode 1. Ormonde: Foundations
Finish it. Lift it. Barge it.
ode 1. Ormonde: Foundations
Design for Transportation and Installation
ode 1. Ormonde : Foundations
Design the Installation
ode
Safety. Engineering. Environment. Consents. Stakeholders. Contractors.
2. Ormonde: Export Cable
ode
Safety. Design. Logistics. Installation.
2. Ormonde: Inter Array Cables
ode
Safety. Neighbours. Switch On.
3. Ormonde: Integration
ode 3. Ormonde : Integration
A triumph of Integration
ode 3. Ormonde : Integration
Electrical Topsides Foundatn
Specify
Design
Supply
Install
Commissn
od
e
= By Project Manager ode
= By Electrical Contractor
= By Fabrication Contractor
= By Installation Contractor
N/A
od
e
od
e
od
e
od
e
od
e
od
e
od
e
od
e
od
e
N/A
N/A
N/A N/A
od
e
od
e
It starts with the procurement strategy.
ode
3. Ormonde: Integration
Design the Transportation…
ode 3. Ormonde: Integration
And then do it…
ode
3. Ormonde: Integration
3 major contractor interfaces…
ode 3. Ormonde: Integration
Wind and Weight Interfaces…
ode 4. Other UK Wind Projects
Southern North Sea
30 x 2MW Turbines
Project Management Contract
ode 4. Other UK Wind Projects
Solway Firth
60 x 3MW Turbines
Project Management
ode 5. Benefit of Experience
0
20
40
60
80
1 2 3 4 5 6 7 8
Cycle
Tim
e
Cost of learning new operation
Cost Saving on Next Project
ode
• 40 years experience in the Energy Sector.
• Head Office in London
• Hands-on experience
• Lessons Learned.
• Assign experienced engineers to American projects.
5. Knowledge Transfer
ode 5. Knowledge Transfer
Region Number of Wind Farms
UK
55
Europe 3
North America 2
ode
FEED
• Wind farm layout
• Export cable route
• HVDC link
• Turbine structures
• O & M Philosophy
• Support for Permits
& Consents
• CAPEX cost estimate
• OPEX cost estimate
6. North America: Naikun Wind - Canada
ode 6. North America: Baryonyx - Texas
• Layouts
• Power Export
• Schedule
• Cost Estimate
• Structure types
ode Who to contact
Mike Hulton [ode UK]
Tel : +44 (0) 208 481 4275
Cell: +44 (0)7795 074 813
Email : [email protected]
Daniel Woodman [ode USA]
Tel : 1 720 542 9955
Cell : 1 303 330 6902
Email : [email protected]
www.ode-ltd.co.uk