PAVER INSTALLATION
grade lines are set with string and controlled with pipe
PAVER INSTALLATION
material is roughly moved into place with a skid-loader…
PAVER INSTALLATION
…and then carefully spread into final location by hand
PAVER INSTALLATION
2x4 boards are used to smooth the setting bed
PAVER INSTALLATION
long boards with laborers at each end set precise elevations
PAVER INSTALLATION
a vibratory plate compactor is used on the setting bed and pavers
PAVER INSTALLATION
paver placement can begin in areas while bedding work continues elsewhere
PAVER INSTALLATION
notice base course, setting bed, and pavers coming together
PAVER INSTALLATION
pavers are individually placed by hand
PAVER INSTALLATION
a cart can be used to help move pavers once a bearing surface is established
PAVER INSTALLATION
the amount of manual labor required is a matter of perspective
PAVER INSTALLATION
laying the pavers in a herringbone pattern provides maximum durability
PAVER INSTALLATION
the leading edge can be moved forward in a straight line, until…
PAVER INSTALLATION
…a curb line or other perimeter edge restraint is encountered
PAVER INSTALLATION
curved surfaces also require custom cutting to create flush edge
PAVER INSTALLATION
Aqua-Bric® joint spacing… void filler same as bedding