Page 1: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

ODOT Structure Project

ManagementSeminar

Bridge Preliminary Design Report

Page 2: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

Project Development

Process (Major)

Step 8

Develop Stage 1 Design

Page 3: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

Step 8: Prepare Environmental Clearance/Develop Stage 1

Design• Submit CE, EA or Draft EIS for approval

– If EIS, develop FEIS and circulate• Request approval (CE/FONSI/ROD)• Develop and submit Stage 1 detailed design• Establish proposed R/W limits• Conduct final (second) Value Engineering

Study• Prepare 404/401 Permit applications and draft

Mitigation plans• Cost Estimates/Schedule

Page 4: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

Step 8- Stage 1 Detailed Design L&D 1403.7

• Design Topics– Survey

– Geometric

– Drainage

– Right of Way

– Traffic Control

– Environmental

– Structures

• Preliminary Structure Design Report (Previously TS&L)

Step 8

Page 5: ODOT Structure Project Management Seminar Bridge Preliminary Design Report
Page 6: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS

A. Final Structure Site Plan Section 202.2.1B. Final Maintenance of Traffic Plan Section

202.2.2C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings

Section 202.2.4

E. Response to Step 7 review comments• Tell the story how the preferred alternative was

decided upon • Compliance with all review comments• Update cost estimate (Provide breakdown of

cost for aesthetic considerations, if applicable)

Page 7: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS

A. Final Structure Site Plan Section 202.2.1• Site plan should be further developed to

contain all the BDM requirements, finalize bridge spans and limits

• Preliminary Design Checklist

B. Final Maintenance of Traffic Plan Section 202.2.2

C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings

Section 202.2.4

Page 8: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS

A. Final Structure Site Plan Section 202.2.1

B. Final Maintenance of Traffic Plan Section 202.2.2In addition to the Preliminary Maintenance of Traffic Plan requirements, the Final Maintenance of Traffic Plan should include the following information:

• Plan views and preliminary working drawings to ensure constructability

• Temporary barrier anchorage details and requirements• Location and type of temporary shoring (See Section

208)• Location of structural members that require

strengthening• Temporary structure design information (See Section

500)• Additional notes and/or details necessary

C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings

Section 202.2.4

Page 9: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS

A. Final Structure Site Plan Section 202.2.1

B. Final Maintenance of Traffic Plan Section 202.2.2

C. Foundation Report Section 202.2.3

D. Supplemental Site Plan for Railway CrossingsSection

202.2.4

Page 10: ODOT Structure Project Management Seminar Bridge Preliminary Design Report

202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS

A. Final Structure Site Plan Section 202.2.1B. Final Maintenance of Traffic Plan Section

202.2.2C. Foundation Report Section 202.2.3

D. Supplemental Site Plan for Railway CrossingsSection

202.2.4• Drainage• Disturbance of railroad operations – fiber optic

lines • Provide ample information so the Railroad

Company can adequately locate crossing• Temporary shoring concerns and how it affects

the railroad operations