TRANSCRIPT
ODOT Structure Project
ManagementSeminar
Bridge Preliminary Design Report
Project Development
Process (Major)
Step 8
Develop Stage 1 Design
Step 8: Prepare Environmental Clearance/Develop Stage 1
Design• Submit CE, EA or Draft EIS for approval
– If EIS, develop FEIS and circulate• Request approval (CE/FONSI/ROD)• Develop and submit Stage 1 detailed design• Establish proposed R/W limits• Conduct final (second) Value Engineering
Study• Prepare 404/401 Permit applications and draft
Mitigation plans• Cost Estimates/Schedule
Step 8- Stage 1 Detailed Design L&D 1403.7
• Design Topics– Survey
– Geometric
– Drainage
– Right of Way
– Traffic Control
– Environmental
– Structures
• Preliminary Structure Design Report (Previously TS&L)
Step 8
202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS
A. Final Structure Site Plan Section 202.2.1B. Final Maintenance of Traffic Plan Section
202.2.2C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings
Section 202.2.4
E. Response to Step 7 review comments• Tell the story how the preferred alternative was
decided upon • Compliance with all review comments• Update cost estimate (Provide breakdown of
cost for aesthetic considerations, if applicable)
202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS
A. Final Structure Site Plan Section 202.2.1• Site plan should be further developed to
contain all the BDM requirements, finalize bridge spans and limits
• Preliminary Design Checklist
B. Final Maintenance of Traffic Plan Section 202.2.2
C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings
Section 202.2.4
202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS
A. Final Structure Site Plan Section 202.2.1
B. Final Maintenance of Traffic Plan Section 202.2.2In addition to the Preliminary Maintenance of Traffic Plan requirements, the Final Maintenance of Traffic Plan should include the following information:
• Plan views and preliminary working drawings to ensure constructability
• Temporary barrier anchorage details and requirements• Location and type of temporary shoring (See Section
208)• Location of structural members that require
strengthening• Temporary structure design information (See Section
500)• Additional notes and/or details necessary
C. Foundation Report Section 202.2.3D. Supplemental Site Plan for Railway Crossings
Section 202.2.4
202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS
A. Final Structure Site Plan Section 202.2.1
B. Final Maintenance of Traffic Plan Section 202.2.2
C. Foundation Report Section 202.2.3
D. Supplemental Site Plan for Railway CrossingsSection
202.2.4
202.2 BRIDGE PRELIMINARY DESIGN REPORT SUBMISSION REQUIREMENTS
A. Final Structure Site Plan Section 202.2.1B. Final Maintenance of Traffic Plan Section
202.2.2C. Foundation Report Section 202.2.3
D. Supplemental Site Plan for Railway CrossingsSection
202.2.4• Drainage• Disturbance of railroad operations – fiber optic
lines • Provide ample information so the Railroad
Company can adequately locate crossing• Temporary shoring concerns and how it affects
the railroad operations