offshore wind engineering: constraints and opportunities
TRANSCRIPT
Offshore Wind Engineering:Constraints and Opportunities
Tania MoreiraOctober 2020
Topics
Projects Introduction: Key Facts01
Design: Constraints and Opportunities02
Manufacturing: Local Supply Chain Considerations 03
Construction: “Bumps on the Roads”04
Lessons Learned05Taiwan, a place of abundant offshore wind!
Offshore Wind Engineering: Constraints and OpportunitiesProjects Introduction - Key Facts: CFXD
Page 3
CFXD
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Offshore Wind Engineering: Constraints and OpportunitiesProjects Introduction - Key Facts: ZNWF
Page 4
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
ZNWF
Offshore Wind Engineering: Constraints and OpportunitiesIs it complex or interesting?
Page 5
Is Offshore Wind Farms Development in Taiwan Complex or Interesting?
OpportunitiesRobust Design
InterfacesLearning from
ExperienceQuality
Technology developmentAny others?
Constraints
Offshore Wind Engineering: Constraints and OpportunitiesChallenges of developing offshore wind farms in Taiwan?
Page 6
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Ø Site Conditions
Ø Technology Maturity / WTG size
Ø Extreme events – earthquakes (liquefaction) & typhoons
Ø Supply Chain Challenges
Ø Construction methodology
Ø Availability/capacity of installation vessels (harsh weather conditions)
Ø Offshore / Onshore Cables Bottlenecks
Ø Any others?
Offshore Wind Engineering: Constraints and OpportunitiesSite Conditions – Seabed Mobility, the famous “bumps on the roads”
Page 7
The sites are located just offshore of the Zhuoshui river which discharge huge
amounts of sediments into the area. The project conducted a detailed study of the
seabed mobility to predict the future seabed level changes in the wind farm area
before layout selection.
Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown!
Page 8
CFXD has joined the ACE JIP and it is currently working
with other developers to set up best practice guidance for
an optimized cost effective design for areas prone to
typhoon and earthquakes.
The work is scheduled to be completed in 4Q 2020 – we have the risks of performing the design whilst the JIP is
still on-going.
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Offshore Wind Engineering: Constraints and OpportunitiesSeismic – a Teamwork exercise!
Page 9
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown!
Page 10
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
ØConsensus reached with DNVGL and external advisory Professor on optimized pin pile design
based on the pile testing. Rambøll has incorporated above conclusions in the pin pile design with
resulting pin pile lengths varying.
ØPile tests have led to significantly shorter piles which optimized manufacturing and installation.
Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown, R&D exercise!
Page 11
Offshore Wind Engineering: Constraints and OpportunitiesManufacturing: Local Supply Chain Considerations
Page 12
Ø Steel Grades
Ø Plates lengths (rolling capabilities)
Ø Plates thickness
Ø Section Properties – European vs. Asian
Ø Manufacturing tolerances
Ø Overall Manufacturing/Painting
Capabilities
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”
Page 13
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
ü Early Age Cyclic (EAC): The time-depending grout
strength while hardening during installation is affected by Early Age Cycling (EAC) which may reduce the
fatigue capacity of the grouted connection and hence
only very limited relative movement is allowed during
installation (±0.5mm, total 1mm).
ü Current design does not meet DNV GL requirements
and hence tests are required for relaxation.
DNV GL Tests:
ü The test duration is approximately 7 months.
ü The box specimen to be tested is similar to the used in
the JIP for grouted connections which is representative
of a jacket connection.
ü Horizontal and Vertical testing is carried out.
Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”
Page 14
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Ø Only one installation vessel can be used at a time for Changfang and Xidao for piling operation. No simultaneous piling is allowed.
Ø For Changfang Offshore Wind Farm, piling operation for a new foundation must not begin one (1) hour prior to sunset until sunrise the next day. For Xidao Offshore Wind Farm, piling operation for a new foundation must not begin two (2) hours prior to sunset until sunrise the next day.
Ø Piling noise takes over a crucial role regarding installation execution planning.
Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”
Page 15
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
Ø Complex crossing arrangements on the
onshore cables route.
Ø Changhua developers (CIP, Ørsted, NPI-
Yushan, CSC, and TPC renewable dept.)
agreed to coordinate common technical issues
or liaising with relevant stakeholders (TPC
IDB, and BoE) through the platform of joint
developers’ forum (JDF).
Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown – make sure it is robust to reduce OPEX costs.
Page 16
FEEDDetailed Design
Manufacturing
Transportation Installation
& Commissioning
Operation and Maintenance
.O&M base conceptual design
Ø The project will employ contractors to carry out the operation and maintenance tasks on the BoPassets.
Ø An advanced in-house developed numerical model has been established to determine the project accessibility.
Offshore Wind Engineering: Constraints and OpportunitiesLessons Learned – top 3
Page 17
1. Invest in Research and Development, the DEVEX costs will be
paid off!
2. Adopt a positive constructive pragmatic co-operative
approach to problem solving. Bring the experts together!
3. Accept the limitations of the contractors in new development
markets. Having some empathy with the local supply chain
being relatively inexperienced and having English as a second
language and accepting that some early assistance in
preparing technical documentation may be a good investment
in the project outcome.
Page 18
Thank you!
Tania Moreira, Engineering Manager
Email: [email protected]
Phone: +886 925 229 366