offshore wind engineering: constraints and opportunities

18
Offshore Wind Engineering: Constraints and Opportunities Tania Moreira October 2020

Upload: others

Post on 04-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering:Constraints and Opportunities

Tania MoreiraOctober 2020

Page 2: Offshore Wind Engineering: Constraints and Opportunities

Topics

Projects Introduction: Key Facts01

Design: Constraints and Opportunities02

Manufacturing: Local Supply Chain Considerations 03

Construction: “Bumps on the Roads”04

Lessons Learned05Taiwan, a place of abundant offshore wind!

Page 3: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesProjects Introduction - Key Facts: CFXD

Page 3

CFXD

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Page 4: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesProjects Introduction - Key Facts: ZNWF

Page 4

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

ZNWF

Page 5: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesIs it complex or interesting?

Page 5

Is Offshore Wind Farms Development in Taiwan Complex or Interesting?

OpportunitiesRobust Design

InterfacesLearning from

ExperienceQuality

Technology developmentAny others?

Constraints

Page 6: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesChallenges of developing offshore wind farms in Taiwan?

Page 6

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Ø Site Conditions

Ø Technology Maturity / WTG size

Ø Extreme events – earthquakes (liquefaction) & typhoons

Ø Supply Chain Challenges

Ø Construction methodology

Ø Availability/capacity of installation vessels (harsh weather conditions)

Ø Offshore / Onshore Cables Bottlenecks

Ø Any others?

Page 7: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesSite Conditions – Seabed Mobility, the famous “bumps on the roads”

Page 7

The sites are located just offshore of the Zhuoshui river which discharge huge

amounts of sediments into the area. The project conducted a detailed study of the

seabed mobility to predict the future seabed level changes in the wind farm area

before layout selection.

Page 8: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown!

Page 8

CFXD has joined the ACE JIP and it is currently working

with other developers to set up best practice guidance for

an optimized cost effective design for areas prone to

typhoon and earthquakes.

The work is scheduled to be completed in 4Q 2020 – we have the risks of performing the design whilst the JIP is

still on-going.

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Page 9: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesSeismic – a Teamwork exercise!

Page 9

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Page 10: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown!

Page 10

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

ØConsensus reached with DNVGL and external advisory Professor on optimized pin pile design

based on the pile testing. Rambøll has incorporated above conclusions in the pin pile design with

resulting pin pile lengths varying.

ØPile tests have led to significantly shorter piles which optimized manufacturing and installation.

Page 11: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown, R&D exercise!

Page 11

Page 12: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesManufacturing: Local Supply Chain Considerations

Page 12

Ø Steel Grades

Ø Plates lengths (rolling capabilities)

Ø Plates thickness

Ø Section Properties – European vs. Asian

Ø Manufacturing tolerances

Ø Overall Manufacturing/Painting

Capabilities

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Page 13: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”

Page 13

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

ü Early Age Cyclic (EAC): The time-depending grout

strength while hardening during installation is affected by Early Age Cycling (EAC) which may reduce the

fatigue capacity of the grouted connection and hence

only very limited relative movement is allowed during

installation (±0.5mm, total 1mm).

ü Current design does not meet DNV GL requirements

and hence tests are required for relaxation.

DNV GL Tests:

ü The test duration is approximately 7 months.

ü The box specimen to be tested is similar to the used in

the JIP for grouted connections which is representative

of a jacket connection.

ü Horizontal and Vertical testing is carried out.

Page 14: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”

Page 14

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Ø Only one installation vessel can be used at a time for Changfang and Xidao for piling operation. No simultaneous piling is allowed.

Ø For Changfang Offshore Wind Farm, piling operation for a new foundation must not begin one (1) hour prior to sunset until sunrise the next day. For Xidao Offshore Wind Farm, piling operation for a new foundation must not begin two (2) hours prior to sunset until sunrise the next day.

Ø Piling noise takes over a crucial role regarding installation execution planning.

Page 15: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesConstruction: “Bumps on the Roads”

Page 15

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

Ø Complex crossing arrangements on the

onshore cables route.

Ø Changhua developers (CIP, Ørsted, NPI-

Yushan, CSC, and TPC renewable dept.)

agreed to coordinate common technical issues

or liaising with relevant stakeholders (TPC

IDB, and BoE) through the platform of joint

developers’ forum (JDF).

Page 16: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesDesign for the unknown – make sure it is robust to reduce OPEX costs.

Page 16

FEEDDetailed Design

Manufacturing

Transportation Installation

& Commissioning

Operation and Maintenance

.O&M base conceptual design

Ø The project will employ contractors to carry out the operation and maintenance tasks on the BoPassets.

Ø An advanced in-house developed numerical model has been established to determine the project accessibility.

Page 17: Offshore Wind Engineering: Constraints and Opportunities

Offshore Wind Engineering: Constraints and OpportunitiesLessons Learned – top 3

Page 17

1. Invest in Research and Development, the DEVEX costs will be

paid off!

2. Adopt a positive constructive pragmatic co-operative

approach to problem solving. Bring the experts together!

3. Accept the limitations of the contractors in new development

markets. Having some empathy with the local supply chain

being relatively inexperienced and having English as a second

language and accepting that some early assistance in

preparing technical documentation may be a good investment

in the project outcome.

Page 18: Offshore Wind Engineering: Constraints and Opportunities

Page 18

Thank you!

Tania Moreira, Engineering Manager

Email: [email protected]

Phone: +886 925 229 366