ofon 2 project mca performance july meeting 5th august 2015 – napims, ikoyi

9
OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

Upload: roy-rogers

Post on 19-Jan-2016

237 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

OFON 2 PROJECT

MCA Performance July Meeting5th August 2015 – NAPIMS, Ikoyi

Page 2: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

2

OFON2 Project

OFQ Living quarter by EIFFAGE

Installed December 13

OFD5 drilling pltfby NIGERDOCK

Jacket installed May 14

OFP2 Process pltfInstalled January 14 by HHI – TECHNIP

SAIPEM

Existings revampingby PONTICELLI

OFD3 drilling pltfby NIGERDOCK

Jacket installed June14

Sealinesby SUBSEA 7

Installed April 147 EPCs with 19 interfaces

Bridges installed April 14by NIGERDOCK

FLARE OUT Achieved

15th Dec 2014

Page 3: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

3

Page 4: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

OFON PHASE 2 – Physical Progress Excluding Drilling

Milestones: Drilling OFD1: July 2015 First Oil OFD1: November 2015 RFLO of OFD3/OFD5: October 2015 Drilling OFD5: Q1 2016

Page 5: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

5

MCA 2008 – Cost breakdown

MOD M$

COST ESTIMATED MCA2008

NNPC APPROVED CONTRACT

VAR.

EPC2 225 490 265

EPCI3 227 487 260

EPC4 173 437 264

EPCI5 155 180 25

EPCI8 116 232 116

TOTAL 930

MCA 2008 - appendix 1: TABLE TO BE USED FOR THE APPLICATION OF THE ARTICLE 4.1 (as it is mentioned in the MCA 2008):

3807 M$

NDDC associated to NNPC Contract award not yet approved (930M$ x 3% = 27.9M$).

Page 6: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

Ofon Phase 2 – Status per Contract

6

Optimised development scheme

OFQ OFP2

OFD5

OFD3

OFD1

OFP1

OFD2

1- EPCC1 (HHI - OFP2): HHI Demobilised, Discussions on remaining change orders, Contract Closure

2- EPCC2 (NIGERDOCK – OFD 3 & 5 plus Bridges): Construction of Decks (D3/D5) to continue to be completed by October 2015.

3- EPCI3 (GLOBSTAR – Sealines and Wellhead Decks install.): Early Termination of contractor. Remedial works in 3Q 2015 to be performed by another contractor. Fabrication of Spools on-going. OFD 3/5 topsides installation to bend of Q4 2015. Hook Up completion Q1 2016.

4- EPCI5 (PONTICELLI – Integration works): SOW limited to phase 2a (OFD2 gas lift by Sep-15).

5- EPCC4 (EIFAGGE – Living Quarters), EPCI8 (SAIPEM) and T&I7 (TECHNIP) close out

Page 7: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

MCA 2008 – PERFORMANCE – NAPIMS RECOMENDATIONFOLLOW UP

7

ISSUES / WAY FORWARD:

Previous Years LS / PS Recommended to TECOM but subject to OPCOM Approval / Follow-up on the sign-off.

2015 Performance recommendation is constraint due to non-approved budget. Performance recommendation is still being

based in 2014 Budget. / Approval of 2015 Initial Budget to have a clear basis in performance recommendations.

NAPIMS recommended CO $219M pending approval from NNPC / Request NAPIMS for follow-up on the approval process.

CO Review meetings to be continued for other EPC’s / TEPNG requests fair and objective assessment of the CORs

Page 8: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

CASH CALL – PERFORMANCE – NAPIMS RECOMENDATION FOLLOW UP

8

ISSUES / WAY FORWARD:

2014 Full Year Performance not yet reviewed as per new directive that Cash Call will be reviewed by various

department within NAPIMS / NAPIMS to advise date and proper channel of reviewing Cash Call.

2015 Performance jointly recommended were not accepted by Planning Division as per the new directive. /

NAPIMS to advise date and proper channel of reviewing Cash Call.

Page 9: OFON 2 PROJECT MCA Performance July Meeting 5th August 2015 – NAPIMS, Ikoyi

Approvals Going Foward; Provisional Sums

ISSUES / WAY FORWARD:

Some WO not yet approved by NNPC after more than a year / NNPC to advise status and if further

information is required kindly advise.