ojvggoldprojectfstechreport-mar2013-plant & infrastucture capex

Upload: roberto-veas

Post on 04-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    1/55

    20.4.4 Ancillary Equipment

    20.4.5 Electricity

    20.4.6 Labour

    20.4.7 Mine Dewatering

    20.4.8 Mine Miscellaneous Costs

    20.5 Plant and Infrastructure Capital Cost Estimate (CAPEX)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    2/55

    Table 20.10: Total Plant and Infrastructure Capital Cost Summary by Area

    WBS Cost Element Total Cost Estimate ($M)

    02 PROCESS PLANT 70.6

    03 ON-SITE INFRASTRUCTURE 40.1

    05 OFF-SITE INFRASTRUCTURE 19.4

    06 INDIRECTS 36.3

    07 MINE 9.2

    08 MISCELLANEOUS 7.0

    TOTAL CAPITAL COST 182.6

    Estimate Contributors

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    3/55

    Estimate Organisation

    Scope of Estimate

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    4/55

    Estimating Design Allowances

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    5/55

    Table 20.11: Total Cost Breakdown

    WBS Cost ElementTotal Bare Cost

    ($M)Estimating Design

    AllowanceTotal Cost Estimate

    ($)

    02 PROCESS PLANT 65.4 70.8

    03 ON-SITE INFRASTRUCTURE 37.2 40.1

    05 OFF-SITE INFRASTRUCTURE 17.5 19.4

    06 INDIRECTS 33.5 36.2

    07 MINE 8.4 9.2

    08 MISCELLANEOUS 6.4 7.0

    TOTAL CAPITAL COST 168.4 8.4% 182.6

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    6/55

    Table 20.12: Table Cost Report by Pricing Type

    PRICING TYPE % OF DIRECT COST

    Direct Cost Development

    Earthworks

    Concrete

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    7/55

    Structural steelwork

    Platework and Tankage

    Mechanical Equipment Supply

    Mechanical Equipment Installation

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    8/55

    Piping Supply and Installation

    Electrical and Instrumentation

    Buildings

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    9/55

    Freight

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    10/55

    Labour

    General Cost Development

    First-fill Reagents, Grinding Media, and Lubricants

    Workshop Tools and Equipment

    Warehouse Racking and Shelving

    Mobile Plant and Equipment

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    11/55

    Table 20.13: Summary of Mobile Equipment

    Vehicle Type Quantity

    Spares

    Temporary Construction Facilities Cost Development

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    12/55

    Indirect Cost Development

    Engineering Procurement & Construction Management (EPCM) Labour

    EPCM Expenses

    Commissioning

    Vendor Representatives

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    13/55

    Project Fee

    20.5.1 Escalation

    20.5.2 Owners Costs

    20.5.3 Taxes and Duties

    20.5.4 Contingency

    20.6 Process Plant Operating Cost Estimate (OPEX)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    14/55

    Table 20.14: Estimated Average Operating Costs ($/t)

    Cost CategoryPrimary Hard Ore

    (4,541 t/d)Weathered Soft Ore

    (7,392 t/d)

    Process Operating Cost

    Subtotal Process Operating Cost 21.93 12.85G&A Costs

    Subtotal G&A Cost 6.16 3.78

    TOTAL Cost $28.09 /t or $46.6M /y $16.63 /t or $44.9M /y

    20.6.1 Basis of Process and G&A Operating Cost Estimate

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    15/55

    Table 20.15: Derivation of Plant Operating Costs

    Cost Category Source Of Cost Data

    OJVG

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    16/55

    20.6.2 Plant Operating Cost Estimate Inclusions

    Labour

    Table 20.16: Summary of Process Plant Labour

    Area National Expat

    Total 87 18

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    17/55

    Table 20.17: Process Plant Labour rates

    Process Plant Labour

    Description US$/month Comment

    Admin and Technical

    Maintenance

    Operations

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    18/55

    Table 20.18: Process Plant Labour Cost Summary

    Area $/a (0 - 2 years) $/a (>2 Years)

    Total 4,044,000 2,569,000

    Power

    Table 20.19: Power generation cost inputs

    Description Unit Criteria

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    19/55

    Table 20.20: Plant and Site Power Cost Summary

    Power Cost ($/t)Primary Hard Ore (1,657,392

    t/a)Weathered Soft Ore (2,698,080

    t/a)

    TOTAL $/t 11.37 5.59

    TOTAL $M/y 18.85 15.09

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    20/55

    Table 20.21: Process Plant Vehicle Maintenance Cost Summary

    Number of Vehicles Hours of OperationMaintenance and

    Consumables Cost($/h)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    21/55

    Table 20.22: Reagent Consumption Rates

    Item UnitPrimary Ore

    Consumption Per Tonneof Feed @ 1.66 Mt/a

    Weathered OreConsumption Per Tonne

    of Feed @ 2.70 Mt/a

    Table 20.23: Reagent Costs

    Item Unit price ($/kg)

    Primary Ore [email protected] Mt/a

    ($M/a)

    Weathered Ore Cost @2.70 Mt/a

    ($M/a)

    Total 5.935 9.634

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    22/55

    Table 20.24: Crusher and Mill Liner Consumption

    ItemUnit Cost

    ($M per set)

    Primary and WeatheredOre Consumption Cost ($M/a)

    TOTAL $M/y 3.16

    Table 20.25: Grinding Media Details Usage and Pricing

    Mill Diameter TypeCost Primary Ore Consumption

    Rate @1.66 Mt/a (kg/t)

    Weathered Ore ConsumptionRate @ 2.70 Mt/a

    Consumption Rate (kg/t)$/kg

    Table 20.26: Grinding Media Costs

    ItemPrimary Ore @1.66 Mt/a Cost

    ($M)Weathered Ore @2.70 Mt/a

    Cost ($M)

    TOTAL $M/y 2.97 2.17TOTAL $/t 1.79 0.81

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    23/55

    General and Administrative (G&A) Costs

    Table 20.27: G&A Costs

    Item Type Annual Cost ($M)

    TOTAL Fixed 10.202

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    24/55

    Process Plant and G&A Operating Variable Cost Modelling

    Table 20.28: Primary and Weathered Ore OPEX Variances

    Criteria Primary Hard Ore Weathered Soft Ore

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    25/55

    Figure 20.1: Plant throughput vs. Processing Costs

    Table 20.29: Example of Process Cost Modelling

    Criteria Units80% Hard Ore

    Case43% Hard Ore

    Case

    Total Process and G&A $/t milled 24.7 18.4

    y = 430.31x-0.5497

    y = 543.86x-0.6427

    Processing

    Cost($/

    t)

    Total Plant Throughput (t/h)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    26/55

    21 Economic Analysis

    21.1 Summary

    Table 21.1: Summary Economics.

    Gold Price ($/oz)

    Parameter Unit $1,350 $1,550 $1,750

    1261

    740

    961

    558

    21.2 Modelling Practice

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    27/55

    21.3 Construction Schedule

    21.4 Production Schedule

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    28/55

    Table 21.2: Modelled base production schedule.

    PERIOD

    Parameter Unit Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

    OPEN PIT MINING

    10.4

    17.1

    27.5

    0.6

    2.10

    2.3

    2.37

    212

    0.8

    0.1

    0.9

    0.0

    5.61

    0.0

    12.11

    7

    29.3

    126.8

    156.0

    6.2

    1.46

    12.8

    2.26

    1,224

    O/P MINING ALL DEPOSITS 40.6

    143.9

    184.4

    6.8

    1.53

    15.1

    2.28

    Total ore mined O/P Mt 21.9 0.3 0.8 1.3 1.8 1.8 1.8 1.6 1.5 1.5 1.3 1.3 1.3 1.2 1.2 1.4 1.6 0.2

    Total Mined ounces O/P oz Au 1,443 33 68 92 80 85 101 90 89 114 83 86 81 85 93 117 124 23

    t:t 8.4

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    29/55

    Table 21.3: Underground Production Schedule

    PERIOD

    Parameter Unit Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

    UNDERGROUND MINING

    4.60

    4.19

    6209

    1.3

    5.15

    221

    0.2

    8.16

    50

    Total ore mined U/G Mt 6.1

    Total Mined ounces U/G oz Au 890

    Table 21.4: Total Production Schedule

    PERIOD

    Parameter Unit Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

    TOTAL ALL DEPOSITS

    40.6

    143.9

    184.4

    6.8

    1.53

    21.2

    2.93

    337

    1997 Total ore mined Mt 28.03

    Total mined grade Au g/t 2.59

    Total mined ounces oz Au 2334

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    30/55

    21.5 Commodity Pricing

    21.6 Capital Costs

    Table 21.5: High Level Capital Cost Summary

    CAPITAL EXPENDITURE ($M USD) Total Initial Sustaining

    TOTAL CAPITAL COST 504.74 297.08 207.66

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    31/55

    21.7 Operating Costs

    Table 21.6: Unit Operating Costs Summary

    Summary Unit Operating Costs Unit Cost

    Total Unit OPEX $/t milled $49.44

    Total Unit OPEX $/oz $653.98

    Table 21.7: Unit Operating Costs per Tonne of Ore (Underground)

    Underground Unit Operating Costs Unit Cost

    All Underground Mining Opex $/t ore mined $41.51

    Table 21.8: Unit Operating Costs per Tonne (Open Pit)

    Open Pit Unit Operating Costs Unit Cost

    LOM Strip Ratio (Waste:Ore) (Waste : Ore) 8.4 : 1

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    32/55

    Table 21.9: Unit Operating Costs per Tonne of Ore (Processing)

    Processing Unit Cost

    Processing Total $/t ore milled $19.30

    Table 21.10: Unit Operating Costs per Tonne of Ore (G&A)

    General and Administration Unit Cost

    G&A Total $/t ore milled $5.50

    Table 21.11: Summary Unit Costs per Ounce of Gold

    Unit Costs per Ounce Unit Cost

    Total Unit OPEX M$ $653.98

    21.8 Taxes and Royalties21.8.1 Government Royalty

    21.8.2 Corporate Income Tax

    21.8.3 Customs Duties

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    33/55

    21.8.4 Value Added Tax

    21.8.5 Withholding Tax

    21.9 Working Capital

    21.10Life-of-Mine summary Cashflows

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    34/55

    Table 21.12: LOM Summary Cashflow at $1250 per Ounce

    Category UNIT NPV TOTAL

    28.0

    Recoverable Grade gpt 2.4 0.0 3.1 3.1 2.8 2.2 2.0 2.3 2.3 2.4 2.6 2.4 2.0 1.9 2.4 2.5 2.6 2.3 3.0 0.0 0.0

    2119

    $1250/oz

    14.8

    Gross Income pre-royalties M$ 2641.3

    79.2

    NET INCOME FROM MINING M$ 2562.0

    OPERATING COST SUMMARY

    254.1

    376.0

    540.8

    154.1

    60.8

    TOTAL OPEX M$ 1385.8

    PRE-TAX NET OPERATING INCOME M$ 1156.4

    NET FEDERAL TAXABLE INCOME M$ 709.1

    NET PROFIT AFTER TAXES M$ 554.9

    OPERATING CASH FLOW M$ 671 1002.2

    CAPITAL COST SUMMARY

    Underground

    29.6 1.0

    59.6

    4.4

    Open Pit

    62.7

    10.4

    3.9

    3.0

    Process Plant and Infrastructure

    70.6

    40.1

    19.3

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    35/55

    Category UNIT NPV TOTAL

    36.3

    9.2

    7.1

    14.0

    TSF, Water, Roads and Closure

    7.1

    5.9

    28.2

    3.5

    17.5

    Owners Costs

    20.0

    51.3

    TOTAL CAPITAL COST M$ 504.7

    NET ANNUAL CASH FLOW M$ 497.5

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    36/55

    Table 21.13: LOM Summary Cashflow at $1350 per Ounce

    Category UNIT NPV TOTAL

    28.0

    Recoverable Grade gpt 2.4 0.0 3.1 3.1 2.8 2.2 2.0 2.3 2.3 2.4 2.6 2.4 2.0 1.9 2.4 2.5 2.6 2.3 3.0 0.0 0.0

    2119

    $1350/oz

    14.8

    Gross Income pre-royalties M$ 2849.4

    85.5

    NET INCOME FROM MINING M$ 2764.0

    OPERATING COST SUMMARY

    254.1

    376.0

    540.8

    154.1

    60.8

    TOTAL OPEX M$ 1385.8

    PRE-TAX NET OPERATING INCOME M$ 1358.3

    NET FEDERAL TAXABLE INCOME M$ 911.1

    NET PROFIT AFTER TAXES M$ 708.9

    OPERATING CASH FLOW M$ 772 1156.1

    CAPITAL COST SUMMARY

    Underground

    29.6 1.0

    59.6

    4.4

    Open Pit

    62.7

    10.4

    3.9

    3.0

    Process Plant and Infrastructure

    70.6

    40.1

    19.3

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    37/55

    Category UNIT NPV TOTAL

    36.3

    9.2

    7.1

    14.0

    TSF, Water, Roads and Closure

    7.1

    5.9

    28.2

    3.5

    17.5

    Owners Costs

    20.0

    51.3

    TOTAL CAPITAL COST M$ 504.7

    NET ANNUAL CASH FLOW M$ 651.4

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    38/55

    Table 21.14: LOM Summary Cashflow at $1550 per Ounce

    Category UNIT NPV TOTAL

    28.0

    Recoverable Grade gpt 2.4 0.0 3.1 3.1 2.8 2.2 2.0 2.3 2.3 2.4 2.6 2.4 2.0 1.9 2.4 2.5 2.6 2.3 3.0 0.0 0.0

    2119

    $1550/oz

    14.8

    Gross Income pre-royalties M$ 3269.5

    98.1

    NET INCOME FROM MINING M$ 3171.4

    OPERATING COST SUMMARY

    254.1

    376.0

    540.8

    154.1

    60.8

    TOTAL OPEX M$ 1385.8

    PRE-TAX NET OPERATING INCOME M$ 1765.8

    NET FEDERAL TAXABLE INCOME M$ 1318.5

    NET PROFIT AFTER TAXES M$ 1017.7

    OPERATING CASH FLOW M$ 976 1465.0

    CAPITAL COST SUMMARY

    Underground

    29.6 1.0

    59.6

    4.4

    Open Pit

    62.7

    10.4

    3.9

    3.0

    Process Plant and Infrastructure

    70.6

    40.1

    19.3

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    39/55

    Category UNIT NPV TOTAL

    36.3

    9.2

    7.1

    14.0

    TSF, Water, Roads and Closure

    7.1

    5.9

    28.2

    3.5

    17.5

    Owners Costs

    20.0

    51.3

    TOTAL CAPITAL COST M$ 504.7

    NET ANNUAL CASH FLOW M$ 960.2

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    40/55

    Table 21.15: LOM Summary Cashflow at $1750 per Ounce

    Category UNIT NPV TOTAL

    28.0

    Recoverable Grade gpt 2.4 0.0 3.1 3.1 2.8 2.2 2.0 2.3 2.3 2.4 2.6 2.4 2.0 1.9 2.4 2.5 2.6 2.3 3.0 0.0 0.0

    2119

    $1750/oz

    14.8

    Gross Income pre-royalties M$ 3693.3

    110.8

    NET INCOME FROM MINING M$ 3582.5

    OPERATING COST SUMMARY

    254.1

    376.0

    540.8

    154.1

    60.8

    TOTAL OPEX M$ 1385.8

    PRE-TAX NET OPERATING INCOME M$ 2176.8

    NET FEDERAL TAXABLE INCOME M$ 1729.6

    NET PROFIT AFTER TAXES M$ 1330.2

    OPERATING CASH FLOW M$ 1,184 1777.4

    CAPITAL COST SUMMARY

    Underground

    29.6

    1.0

    59.6

    4.4

    Open Pit

    62.7

    10.4

    3.9

    3.0

    Process Plant and Infrastructure

    70.6

    40.1

    19.3

    36.3

    9.2

    7.1

    14.0

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    41/55

    Category UNIT NPV TOTAL

    TSF, Water, Roads and Closure

    7.1

    5.9

    28.2

    3.5

    17.5

    Owners Costs

    20.0

    51.3

    TOTAL CAPITAL COST M$ 504.7

    NET ANNUAL CASH FLOW M$ 1272.7

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    42/55

    21.11Sensitivities

    Table 21.16: Effect of Variation of Gold Price and Operating Costs on NPV5 ($1,550 base price).

    LOM Capital Costs ($M)

    OperatingCost($/oz)

    558

    Table 21.17: Effect of Variation of Capital and Operating Costs on NPV5 ($1,550 base price)

    Price ($/oz)

    OperatingCost($/oz)

    558

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    43/55

    Table 21.18: Effect of variation in Price and All Costs on NPV5 ($1,550 base price).

    Price ($/oz)

    AllCosts

    (CapexandOpex)

    558

    Figure 21.1: Sensitivity Graph at $1350 Price Base

    Post-taxNPV5%

    (M$)

    Percent Change from Base Case

    Sensitivity of $1350 Case Economics(Post-tax NPV5%)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    44/55

    Figure 21.2: Sensitivity Graph at $1550 Price Base

    Figure 21.3: Sensitivity Graph at $1750 Price Base

    Post-taxNPV5%

    (M$)

    Percent Change from Base Case

    Sensitivity of $1550 Case Economics(Post-tax NPV5%)

    Post-taxNPV5%

    (M$)

    Percent Change from Base Case

    Sensitivity of $1750 Case Economics(Post-tax NPV5%)

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    45/55

    21.12Payback Period

    Table 21.19:Payback Period from Commencement of Production

    Price ($/oz)

    AllCosts(CapexandOpex)

    23

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    46/55

    22 Adjacent Properties

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    47/55

    Figure 22.1: Adjacent Properties

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    48/55

    22.1 Teranga Sabodala

    Table 22.1: Teranga Exploration Concessions

    Exploration Permit Teranga interest Area km Anniversary Date

    Sabodala Mine Lease

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    49/55

    Regional Exploration

    Bransan

    Dembala Berola

    Massakounda

    Makana

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    50/55

    Sounkounkou

    Sabodala Northwest

    22.2 Randgold Resources Ltd.

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    51/55

    23 Other Relevant Data and Information

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    52/55

    24 Interpretation and Conclusions

    24.1 Conclusions

    24.2 Upside Risks

    24.3 Downside Risks

    Golouma Gold

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    53/55

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    54/55

    25 Recommendations

    25.1 Project Mining and Processing Strategy

    25.2 Exploration

    25.3 Hydrogeology

  • 8/13/2019 OJVGGoldProjectFSTechReport-Mar2013-Plant & Infrastucture Capex

    55/55

    25.4 Metallurgical and Mineral Processing Recommendations

    25.4.1 Further Comminution Test Work

    25.4.2 General Plant Design Test Work

    25.4.3 Mill Power

    G