Oklahoma Capitol Restoration Project 2300 N Lincoln Blvd. Oklahoma City, OK 73105 July 2017 – Monthly Progress Report MONTHLY OVERVIEW Generator Walls Poured, Waterproofed & Backfilled In-wall Rough-in Complete & Drywall Underway for Ground Level South Areas Shaft Wall Construction Underway in SW Elevator Condensing Water Pumps Installed with Bypass Loop Secretary of State – Drywall, Tape & Bed, Prime Paint Complete REPORT CONTENTS Cover Letter Executive Summary Preconstruction Status Construction Schedule Request for Information Submittal Log Construction Photos 2601 NW Expressway, Suite 501W 73107 | t 405.254.1050 f 405.254.1055 | www.manhattanconstruction.com Manhattan Job # 3707 Design/Builder: Project Owner:

Upload: others

Post on 04-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Oklahoma Capitol Restoration Project

2300 N Lincoln Blvd. Oklahoma City, OK 73105

July 2017 – Monthly Progress Report

MONTHLY OVERVIEW

� Generator Walls Poured,

Waterproofed & Backfilled

� In-wall Rough-in Complete &

Drywall Underway for

Ground Level South Areas

� Shaft Wall Construction

Underway in SW Elevator

� Condensing Water Pumps

Installed with Bypass Loop

� Secretary of State – Drywall,

Tape & Bed, Prime Paint

Complete

REPORT CONTENTS

Cover Letter

Executive Summary

Preconstruction Status

Construction Schedule

Request for Information

Submittal Log

Construction Photos

2601 NW Expressway, Suite 501W 73107 | t 405.254.1050 f 405.254.1055 | www.manhattanconstruction.com

Manhattan Job #

3707

Design/Builder:

Project Owner:

Page 2: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Oklahoma Capitol Restoration

2300 N Lincoln Blvd. Oklahoma City, OK 73105

July 2017 - Monthly

Progress Report

Cover Letter

Tab 1 Executive Summary

Tab 2 Preconstruction Status

• Document deliverable status

Tab 3 Construction Schedule

• Schedule narrative

• Critical Items

• Schedule Update

Tab 4 Requests for Information (RFIs)

• RFI Summary Log

Tab 5 Submittal Log

• Submittal Package Summary Log

Tab 6 Construction Photos

• Detailed progress photos – current month

Page 3: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

EXECUTIVE SUMMARY

SECTION 1

Monthly Progress Report – Oklahoma Capitol Restoration

July 2017

1-1

Monthly Progress Report For

Oklahoma Capitol Restoration July 2017

With over 12,000 man-hours worked in the month of July, progress continues throughout the construction areas at a blistering pace. 50% Fire Marshal inspections were conducted and passed in the Secretary of State Offices, Southwest Doghouse, Ground Level West Corridor and Ground Level South tenant spaces. Framing & rough-in activities have also concluded in these three spaces making way for drywall & finish installations to begin. The southwest doghouse made significant progress during July with interior walls being framed, shaftwalls for the elevator going into place, and all utility risers being completed. In the upcoming month, the ground level construction area will transform from rough-in and framing activities throughout to the start of finish applications. Below is a recap of the major construction & design milestones that are upcoming and their completion status:

1. Start Up New Condensing Water Pumps Projected August 14, 2017

2. Sanitary Sewer Main Tie-In Complete Achieved June 26, 2017

3. Framing For Shaftwalls at Elevator Achieved July 28, 2017

4. Ceilings Complete at Ground Level Corridor Projected August 30, 2017

5. Limestone Column Delivery for Ground Level Corridor Project September 11, 2017

6. Elevator Installation Begins Projected September 15, 2017

7. Millwork Installations for Sec. of State & Ground Level Projected October 1, 2017

8. Marble Flooring Installation at Ground Level Corridor Projected October 1, 2017

9. Doors & Hardware Installations for Sec. of State & GL Projected November 1, 2017

Prime Contract Status The prime contract has been updated with Contract Amendment #2 to include funding for the entirety of the Priority 1 scope. Priority 2 funding bill HB 3168 was passed on May 26, 2016. On February 15, 2017, Contract Amendment #3 was executed to incorporate Priority 2 design & the reallocation of construction sequences to seamlessly integrate Priority 1 & 2 scopes of work into the overall project. Design Status Planning & development of the full interior restoration project is ongoing. Programming & Schematic Design efforts are now complete with tenant planning and initial document review complete for all areas of the building. Work is ongoing toward the 65% Design Development documents for the project. All project documents should be 65% complete by year-end. As tenant space planning is ending, work to further define historic displays, art lighting, wayfinding systems, and exhibit design is now commencing. This work will involve several entities including the Arts Council,

Page 4: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

EXECUTIVE SUMMARY

SECTION 1

Monthly Progress Report – Oklahoma Capitol Restoration

July 2017

1-2

Tourism, and the History Center. The focus of these planning efforts will be to enhance the visitor experience in the Capitol and display the many aspects of Oklahoma heritage. Buyout Status Priority 1 buyout efforts are underway and will continue as the drawing packages are completed. The following packages will be bid in August: Ground Level Flooring – Marble Installations, Alternate 1 Ground Level Flooring – Large Format Tile, Alternate 2 Ground Level Flooring – Terrazzo, and Epoxy Flooring. Miscellaneous buyout items such as Toilet Partitions & Accessories, Wood Blinds, and Fire Extinguisher Cabinets were quoted & procured in July. Signage will be the final procurement item for Phase 3.3 and will be completed in late August. Construction Progress & Schedule Status Priority 1 Scope Ground Level – West construction presses on toward a January 2018 turnover date. During July, the generator areaway walls were poured, waterproofed & backfilled; strides were made in the mechanical room with the new condensing water pumps arriving; and all overhead framing for the main corridor began going in to place. Ground Level – South tenant framing was completed along with all MEP rough-in. Several critical activities were completed in southwest doghouse with existing electrical panel decommissioning, new interior wall framing complete, and all vertical risers being installed from ground level up to the 6th floor attic space. Secretary of State construction moves along smoothly with all drywall installed, tape & bed work complete, and prime paint going on the walls this month. Door frames were also installed throughout the interior of the space. Historic replica door frames will arrive in early August to make way for plaster patching & repair where new doors have been installed to the Rotunda and at the existing exterior walls. This area is scheduled for turnover prior to year-end. Request for Information (RFI’s) Current RFI Summary Log attached in Tab 4. Submittals Current Submittal Log attached in Tab 5. Cost Events & Authorization Requests There are currently no open proposals for the project.

Prepared by: Andrea Gossard, Project Manager

Page 5: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PRECONSTRUCTION & DESIGN STATUS

SECTION 2

Monthly Progress Report – Oklahoma Capitol Restoration

July 2017

2-1

Document Deliverables:

• 35% SD Submittal – Group 5 Tenants was submitted for review on July 25, 2017

Design Status Report:

Frankfurt Short Bruza Architects Engineers Planners

Monthly Project Status Report

Date: August 11, 2017 Project: 15151DB – Capitol Interior Restoration

To: Name Kyle Nelson

Company/Position Manhattan Construction Co.

Phone 405.254.1050

Email [email protected]

From: Roger Klein, FSB Project Manager Re: Monthly Project Status Report – July 2017

This project status report is being provided to you to document our status on the current

Capitol Restoration Project, as required by OMES.

DESIGN PROGRESS

In July 2017 the design Build Team continued to coordinate design and construction schedules

for the interior restoration at the Capitol. FSB Architects are currently producing the Design and

Construction documents for Phases 4 and 5. The Phase 6 scope has been developed and the

schematic design effort for the entire project is now complete. Phase 6 schematic design

package was submitted to OMES/AE1 for review on July 25, 2017.

Page 6: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PRECONSTRUCTION & DESIGN STATUS

SECTION 2

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

2-2

The 100% Phase 3.3 Construction Documents were issued in May 2017. The Phase 3.3

Construction documents included The State Election Board, The Ethics Commission, Capitol

Fitness Center, House Print and Storage, and Secretary of State.

The Phase 4 Design includes OMES Facilities, Multi- Purpose/Training, OMES State Finance, LSB

Photographer, Arts Council, and Lt. Governor. Also added to Phase 4, was the Senate 4th and 5th

floors as well as their ground floor storage area. The 95% Construction Documents for Phase 4

are scheduled to be submitted August of 2017. An early material procurement package for the

6th floor Senate was issued June 30, 2017.

Phase 5 Schematic Design was submitted March 2017 and work is currently ongoing toward

the 65% Design Development submission. Phase 5 includes the Governor, the Treasurer,

Judicial, Capitol Press, Tourism, Food Service, the House of Representatives, and all remaining

Senate spaces. Construction documents for Phase 5 are scheduled to be in production until

October 2018, with the 65% Design Development Document submission to be issued in

November 2017.

The Schematic Design effort for Phase 6 began in February 2017, and design meetings

continued through July 2017. These meetings included tours of the existing space, general

discussions, and the generation of Space/Room data based on the approved Capitol Space

Allocation Plans. FSB developed the concept diagrams and space relationships for this

programed space. Follow up meetings included the review of floor plans, project needs, and

required engineering, including mechanical, electrical, and plumbing. The Schematic Design

submission was issued July 24th and included the 2nd Floor Judicial Court Room, the Capitol

Exhibit Space, the Multi-purpose Rooms, the State Auditor Office, and the Sixth Floor Support

Space. Design development and Construction Document production will begin August 7, 2017

and is scheduled to be complete June 2018.

Page 7: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PRECONSTRUCTION & DESIGN STATUS

SECTION 2

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

2-3

In July, the Design Build team has continued their effort on the upcoming submissions, interior

finishes, and the coordination of these submissions with the Construction Sequence Schedule.

A full-scale mockup of a section of the public ground level corridor has been constructed for

review, and has been modified based on the AE1/Owner team’s review

comments. The construction team procured and installed the specified materials and finishes to

be installed throughout the renovated ground floor in the mock-up including; marble flooring,

granite base, limestone columns, millwork trim, fabric walls, historic and art lighting, and

decorative air grills. A mock-up of the art lighting in the North wing of the first floor has also

been installed and was reviewed with Quentin Thomas (art lighting consultant to FSB), OMES,

and the Arts Council. This mock-up helped determine lighting levels and the Color Rendering

Index (CRI) for the display of fine art at the Capitol.

Also in July, FSB continued to collaborate with the historic paint consultant, EverGreene

Architectural Arts, on the interior design and overall paint color palette proposed for historic

spaces. FSB and EverGreene had presented a Schematic Design to OMES, AE1, and MCC on

February 15, at FSB’s office in Oklahoma City. EverGreene had issued a preliminary draft of the

investigation findings, including a color match “historic” color palette with the original

Capitol paint colors and glazes, and several preliminary color schemes based on those original

colors. FSB and EverGreene will issue a 95% Design Development submission that includes the

proposed color palette for the public spaces from the first through fifth floors. That submission

is scheduled to be issued mid-August 2017. Additional selected areas will be studied for color

sampling including the House and Senate Chambers, The Supreme Court, and the Blue Room.

Working mock-ups will be scheduled as the team begins construction at those phased

locations.

Page 8: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PRECONSTRUCTION & DESIGN STATUS

SECTION 2

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

2-4

On July 17, The FSB Design Team met with Russel Baker- Manhattan Construction, Trait

Thompson- OMES, Matt Radcliff- AE1 Mass Architects, and Bob Blackburn with the Oklahoma

Historical Society team to continue to develop the Historical Display scope for the Capitol. The

team discussed an agenda that included steps to establish areas in the Capitol designated for

Historical Display and Art Zones, to identify the creative stakeholders responsible for historic

content, and to identify the parties or individuals responsible for the decision making. Also

discussed were Goals, Objectives and Expectations for the Historic Displays. A timeline was

discussed for scheduling workshops, meetings, and the programing and design effort required

to meet the infrastructure installation required during construction.

End of Report

Page 9: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

CONSTRUCTION SCHEDULE

SECTION 3

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

3-1

Phase 3.2 & 3.3 – Ground Level – West Infrastructure & Finishes

Schedule Status: The Ground Level is quickly transforming from rough construction activities to the final finish-out stages of this phase. Although the Election Board, Ethics Commission and House Print areas cannot be completed until the new west corridor is open, even these spaces have progressed with framing and rough-in up to the temporary dividing wall. The mechanical room is in final stages of completion with the new condensing water pumps arriving late in July. Through mid-August, work will be ongoing in the mechanical room to commission the new pumps and take the old pumps out of service. This equipment changeover will be the last critical activity to complete so that new floor slabs can be placed and enable the wall line for the new corridor to be established. As multiple milestones come and go for the ground level, the same is true for all other areas of construction. Secretary of State now has drywall installations complete and door frames in place. Millwork shop drawings have also been reviewed to put all cabinetry into production, which should arrive in 6 to 8 weeks. The 6th floor Senate re-design is now complete and Construction Documents will be issued in August. New construction in this space should begin September 1st. Critical Schedule Events: Nearly all critical schedule events correlate with material procurement items. Below is a tracking log of all major material delivery items currently on the schedule:

Item Description Estimated Installation Date

Estimated Delivery Date

Actual Delivery Date

Condensing Water Pumps 6/20/17 7/12/17 7/24/17

SW Doghouse Buss Duct 7/21/17 6/20/17 6/30/17

Ground Level West Corridor – Finishes 8/21/17 8/21/17

Rooftop Air Handlers & Condensing Units 8/31/17 7/15/17 7/24/17

DOAS Units 8/31/17 8/30/17

Generator 9/11/17 8/17/17

SW Elevator Rails, Cab & Motor 9/15/17 9/15/17

SW Elevator Doors & Finishes 11/27/17 11/27/17

Milestone Description Baseline Schedule

Last Month’s Update

Current Month Update

Gain or Loss this Month

Tenant Framing – Ground Level W Begins 5/24/17 6/7/17 6/7/17 0 Structure Complete at Generator 6/16/17 7/28/17 7/24/17 -4 Structure Complete at SW Doghouse 5/26/17 7/24/17 8/14/17 +20 Elevator Installation Begins – SW Doghouse 9/14/17 9/15/17 10/3/17 +18 DOAS Rooftop Units Set 8/30/17 10/5/17 8/21/17 -44 SW Riser Installations Complete 8/16/17 9/12/17 9/12/17 0

Limestone Column Installations 10/6/17 10/6/17 10/13/17 +7 Marble Flooring Installations 11/3/17 11/3/17 10/27/17 -7

Page 10: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

DesignDesign1219 1153 21-Apr-17 A 01-Feb-22

Master PlanMaster Plan1219 1153 21-Apr-17 A 01-Feb-22

Construction DocumentsConstruction Documents437 371 21-Apr-17 A 03-Jan-19

Package 3 - First Floor N, E, SPackage 3 - First Floor N, E, S80 39 18-May-17 A 11-Sep-17

D-M01-1620 CD's 100% 65 24 18-May-17 A 18-Aug-17

D-M01-1630 Owner 100% Review 15 15 21-Aug-17 11-Sep-17

Package 4 - Floors 2 through 5Package 4 - Floors 2 through 5437 371 21-Apr-17 A 03-Jan-19

D-M01-1560 DD (65% CD's) 220 160 21-Apr-17 A 05-Mar-18

D-M01-1680 Owner 65% Review 15 15 06-Mar-18 26-Mar-18

D-M01-1690 CD's 100% 181 181 27-Mar-18 11-Dec-18

D-M01-1720 Owner 100% Review 15 15 12-Dec-18 03-Jan-19

Package 5 - Ground N, E, SPackage 5 - Ground N, E, S246 246 18-Jul-17 05-Jul-18

D-M01-1570 SD Submission Documentation 10 10 18-Jul-17 31-Jul-17

D-M01-1580 Owner Review 20 20 01-Aug-17 28-Aug-17

D-M01-1640 DD (65% CD's) 43 43 29-Aug-17 27-Oct-17

D-M01-1660 Owner 65% Review 15 15 30-Oct-17 17-Nov-17

D-M01-1670 CD's 100% 143 143 20-Nov-17 13-Jun-18

D-M01-1700 Owner 100% Review 15 15 14-Jun-18 05-Jul-18

Fire Marshall PermitsFire Marshall Permits36 36 18-Jul-17 06-Sep-17

6th Floor Senate6th Floor Senate36 36 18-Jul-17 06-Sep-17

D-M01-1750 MCC Submit FM Set 1 1 18-Jul-17 18-Jul-17

D-M01-1755 FM Review / Approve Building Permit 15 15 19-Jul-17 08-Aug-17

D-M01-1760 Release FA / FS Design Drawings 10 10 09-Aug-17 22-Aug-17

D-M01-1765 FM Review / Approve FS 10 10 23-Aug-17 06-Sep-17

D-M01-1770 FM Review / Approve FA 10 10 23-Aug-17 06-Sep-17

Master Plan MilestonesMaster Plan Milestones1015 1015 01-Feb-18 01-Feb-22

Legislative Session MilestonesLegislative Session Milestones1015 1015 01-Feb-18 01-Feb-22

M-M01-1005 2018 Session Begins (Construction Ends) 0 0 01-Feb-18

M-M01-1010 2018 Session Ends (Construction Starts) 0 0 01-Jun-18

M-M01-1015 2019 Session Begins (Construction Ends) 0 0 01-Feb-19

M-M01-1020 2019 Session Ends (Construction Starts) 0 0 31-May-19

M-M01-1025 2020 Session Starts (Construction Ends) 0 0 03-Feb-20

M-M01-1030 2020 Session Ends (Construction Starts) 0 0 01-Jun-20

M-M01-1035 2021 Session Starts (Construction Ends) 0 0 01-Feb-21

M-M01-1040 2021 Session Ends (Construction Starts) 0 0 01-Jun-21

M-M01-1045 2022 Session Begins (Construction Ends) 0 0 01-Feb-22

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

CD's 100%

Owner 100% Review

DD (65% CD's)

Owner 65% Review

CD's 100%

Owner 100% Review

SD Submission Documentation

Owner Review

DD (65% CD's)

Owner 65% Review

CD's 100%

Owner 100% Review

MCC Submit FM Set

FM Review / Approve Building Permit

Release FA / FS Design Drawings

FM Review / Approve FS

FM Review / Approve FA

2018 Session Begins (Construction Ends)

2018 Session Ends (Construction Starts)

2019 Session Begins (Construction Ends)

2019 Session Ends (Construction Starts)

2020 Session Starts (Construction Ends)

2020 Session Ends (Construction Starts)

2021 Session Starts (Construction Ends)

2021 Session Ends (Construction Starts)

2022 Session Begins (Construction En

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 1 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 11: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

SequencesSequences1232 1029 28-Sep-16 A 04-Aug-21

Prerequisite Phase 3 - Basement Prep & Long Lead ProcurementPrerequisite Phase 3 - Basement Prep & Long Lead Procurement275 42 28-Sep-16 A 14-Sep-17

Material ProcurementMaterial Procurement275 42 28-Sep-16 A 14-Sep-17

Procurement Phase SummariesProcurement Phase Summaries171 59 28-Sep-16 A 14-Sep-17

PROC3-LEAD Procurement - Prerequisite Phase 3 171 59 28-Sep-16 A 14-Sep-17

ElevatorsElevators80 42 06-Jun-17 A 14-Sep-17

PROC3-1400 Fab & Deliver - Elevators 80 42 06-Jun-17 A 14-Sep-17

PROC3-1530 Price & Produce Shop Drawings Mach Rm Steel 15 4 30-Jun-17 A 21-Jul-17

PROC3-1535 Fab & Deliver Mach Rm Steel 10 10 24-Jul-17 04-Aug-17

Buss DuctBuss Duct80 30 03-Mar-17 A 28-Aug-17

PROC3-1430 Fab & Deliver - Buss Duct 80 30 03-Mar-17 A 28-Aug-17

GeneratorGenerator130 42 04-Jan-17 A 14-Sep-17

PROC3-1440 Fab & Deliver - Generator 130 42 04-Jan-17 A 14-Sep-17

RTURTU30 24 02-Jun-17 A 18-Aug-17

PROC3-1450 Fab & Deliver - DOAS 30 24 02-Jun-17 A 18-Aug-17

AHUAHU50 9 21-Mar-17 A 28-Jul-17

PROC3-1470 Fab & Deliver - AHU 50 9 21-Mar-17 A 28-Jul-17

Sequence 1Sequence 1528 345 03-Oct-16 A 26-Nov-18

Material ProcurementMaterial Procurement523 340 24-Oct-16 A 15-Nov-18

Procurement Phase SummariesProcurement Phase Summaries519 486 24-Oct-16 A 15-Nov-18

S-S01-1070 Procurement - Sequence 1 519 486 24-Oct-16 A 15-Nov-18

MockupMockup21 4 17-May-17 A 21-Jul-17

P-S01-2235 Owner/AE1 Review Paint Colors 21 4 17-May-17 A 21-Jul-17

Mechanical RoomMechanical Room119 24 02-Mar-17 A 18-Aug-17

P-S01-1170 Fab & Deliver - Condensing Units (Rooftop) 60 9 02-Mar-17 A 28-Jul-17

P-S01-1440 Fab & Deliver - DOAS Units (Rooftop) 80 24 02-Jun-17 A 18-Aug-17

Public CorridorPublic Corridor379 340 08-Mar-17 A 15-Nov-18

P-S01-1560 Fab & Deliver - Security Devices 30 19 30-May-17 A 11-Aug-17

P-S01-1600 Fab & Deliver - H1 Light Fixture 120 84 08-Mar-17 A 13-Nov-17

P-S01-2240 Order On Hold Per Final Count - H8 Light Fixture 120 100 05-Jun-17 A 07-Dec-17

P-S01-1640 Fab & Deliver - H8 Light Fixture 240 240 08-Dec-17 15-Nov-18

P-S01-2245 Order On Hold Per Final Count - H3 Light Fixture 120 100 05-Jun-17 A 07-Dec-17

P-S01-1680 Fab & Deliver - H3 Light Fixture 120 120 08-Dec-17 29-May-18

P-S01-2250 Select Custom Colorl - KArt Light Fixture 15 5 02-Jun-17 A 24-Jul-17

P-S01-1720 Fab & Deliver - KArt Light Fixture 120 40 25-Jul-17 19-Sep-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Procurement - Prerequisite Phase 3

Fab & Deliver - Elevators

Price & Produce Shop Drawings Mach Rm Steel

Fab & Deliver Mach Rm Steel

Fab & Deliver - Buss Duct

Fab & Deliver - Generator

Fab & Deliver - DOAS

Fab & Deliver - AHU

Procurement - Sequence 1

Owner/AE1 Review Paint Colors

Fab & Deliver - Condensing Units (Rooftop)

Fab & Deliver - DOAS Units (Rooftop)

Fab & Deliver - Security Devices

Fab & Deliver - H1 Light Fixture

Order On Hold Per Final Count - H8 Light Fixture

Fab & Deliver - H8 Light Fixture

Order On Hold Per Final Count - H3 Light Fixture

Fab & Deliver - H3 Light Fixture

Select Custom Colorl - KArt Light Fixture

Fab & Deliver - KArt Light Fixture

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 2 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 12: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

P-S01-1770 MCC Receive / Review Submittal - Acoustic Plaster 5 5 18-Jul-17 24-Jul-17

P-S01-1780 AE2 (FSB) Receive / Review Submittal - Acoustic Plaster 10 10 25-Jul-17 07-Aug-17

P-S01-1790 AE1 (Mass) Receive / Review Submittal - Acoustic Plaster 15 15 08-Aug-17 28-Aug-17

P-S01-1800 Fab & Deliver - Acoustic Plaster 30 15 29-Aug-17 19-Sep-17

P-S01-2255 Value Engineer - Marble Flooring 27 9 21-Jun-17 A 28-Jul-17

P-S01-2180 Contracting & Submittal Prep - Marble Flooring 5 5 31-Jul-17 04-Aug-17

P-S01-1810 MCC Receive / Review Submittal - Marble Flooring 5 5 07-Aug-17 11-Aug-17

P-S01-1820 AE2 (FSB) Receive / Review Submittal - Marble Flooring 10 10 14-Aug-17 25-Aug-17

P-S01-1830 AE1 (Mass) Receive / Review Submittal - Marble Flooring 15 15 28-Aug-17 18-Sep-17

P-S01-1840 Fab & Deliver - Marble Flooring 30 40 19-Sep-17 13-Nov-17

P-S01-1850 MCC Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 5 5 18-Jul-17 24-Jul-17

P-S01-1860 AE2 (FSB) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 10 10 25-Jul-17 07-Aug-17

P-S01-1870 AE1 (Mass) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 15 15 08-Aug-17 28-Aug-17

P-S01-1880 Fab & Deliver - Acoustic Wall Fabric/ Assembly 30 30 29-Aug-17 10-Oct-17

P-S01-1890 MCC Receive / Review Submittal - Limestone Veneer Columns 5 4 17-Jul-17 A 21-Jul-17

P-S01-1900 AE2 (FSB) Receive / Review Submittal - Limestone Veneer Columns 10 10 24-Jul-17 04-Aug-17

P-S01-1910 AE1 (Mass) Receive / Review Submittal - Limestone Veneer Columns 15 15 07-Aug-17 25-Aug-17

P-S01-1920 Fab & Deliver - Limestone Veneer Columns 30 30 28-Aug-17 09-Oct-17

P-S01-2260 Value Engineer - Granite Base 27 9 21-Jun-17 A 28-Jul-17

P-S01-2200 Contracting & Submittal Prep - Granite Base 10 10 31-Jul-17 11-Aug-17

P-S01-1930 MCC Receive / Review Submittal - Granite Base 5 5 14-Aug-17 18-Aug-17

P-S01-1940 AE2 (FSB) Receive / Review Submittal - Granite Base 10 10 21-Aug-17 01-Sep-17

P-S01-1950 AE1 (Mass) Receive / Review Submittal - Granite Base 15 15 05-Sep-17 25-Sep-17

P-S01-1960 Fab & Deliver - Granite Base 30 30 26-Sep-17 06-Nov-17

P-S01-2010 MCC Receive / Review Submittal - Wood Trim 5 5 18-Jul-17 24-Jul-17

P-S01-2020 AE2 (FSB) Receive / Review Submittal - Wood Trim 10 10 25-Jul-17 07-Aug-17

P-S01-2030 AE1 (Mass) Receive / Review Submittal - Wood Trim 15 15 08-Aug-17 28-Aug-17

P-S01-2040 Fab & Deliver - Wood Trim 30 30 29-Aug-17 10-Oct-17

P-S01-2230 Fab & Deliver - Door Frames 40 3 02-Jun-17 A 20-Jul-17

ConstructionConstruction503 345 03-Oct-16 A 26-Nov-18

Schedule Driven MilestonesSchedule Driven Milestones323 323 16-Aug-17 26-Nov-18

M-S01-1080 Interim Substantial Completion - Sanitary / Grease 0 0 16-Aug-17

M-S01-1010 Interim Substantial Completion - House S. / Fitness / Public Corridor / Generator 0 0 12-Feb-18

M-S01-1050 Interim Substantial Completion - Mechanical Room 0 0 12-Feb-18

M-S01-1020 Interim Substantial Completion - House Print 0 0 27-Jun-18*

M-S01-1030 Interim Substantial Completion - Election 0 0 27-Jun-18*

M-S01-1040 Interim Substantial Completion - Ethics 0 0 27-Jun-18*

M-S01-1060 Interim Substantial Completion - SW Dog House 0 0 27-Jun-18*

M-S01-1090 Sequence 1 New Construction Ends 0 0 26-Nov-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

MCC Receive / Review Submittal - Acoustic Plaster

AE2 (FSB) Receive / Review Submittal - Acoustic Plaster

AE1 (Mass) Receive / Review Submittal - Acoustic Plaster

Fab & Deliver - Acoustic Plaster

Value Engineer - Marble Flooring

Contracting & Submittal Prep - Marble Flooring

MCC Receive / Review Submittal - Marble Flooring

AE2 (FSB) Receive / Review Submittal - Marble Flooring

AE1 (Mass) Receive / Review Submittal - Marble Flooring

Fab & Deliver - Marble Flooring

MCC Receive / Review Submittal - Acoustic Wall Fabric/ Assembly

AE2 (FSB) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly

AE1 (Mass) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly

Fab & Deliver - Acoustic Wall Fabric/ Assembly

MCC Receive / Review Submittal - Limestone Veneer Columns

AE2 (FSB) Receive / Review Submittal - Limestone Veneer Columns

AE1 (Mass) Receive / Review Submittal - Limestone Veneer Columns

Fab & Deliver - Limestone Veneer Columns

Value Engineer - Granite Base

Contracting & Submittal Prep - Granite Base

MCC Receive / Review Submittal - Granite Base

AE2 (FSB) Receive / Review Submittal - Granite Base

AE1 (Mass) Receive / Review Submittal - Granite Base

Fab & Deliver - Granite Base

MCC Receive / Review Submittal - Wood Trim

AE2 (FSB) Receive / Review Submittal - Wood Trim

AE1 (Mass) Receive / Review Submittal - Wood Trim

Fab & Deliver - Wood Trim

Fab & Deliver - Door Frames

Interim Substantial Completion - Sanitary / Grease

Interim Substantial Completion - House S. / Fitness / Public Corridor / Generator

Interim Substantial Completion - Mechanical Room

Interim Substantial Completion - House Print

Interim Substantial Completion - Election

Interim Substantial Completion - Ethics

Interim Substantial Completion - SW Dog House

Sequence 1 New Construction Ends

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 3 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 13: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

Construction Phase SummariesConstruction Phase Summaries510 345 03-Oct-16 A 27-Jun-18

S-S01-1000 Construction - Sequence 1 510 345 03-Oct-16 A 27-Jun-18

SW Dog House (Elevator)SW Dog House (Elevator)207 219 17-Jul-17 A 25-May-18

C-S01-7170 Procure Lintel 6 4 17-Jul-17 A 21-Jul-17

C-S01-7175 Install Lintel 10 10 24-Jul-17 04-Aug-17

C-S01-7085 Demo Elevator Lobby Fronts 6 6 01-Aug-17 08-Aug-17

C-S01-6680 Install Temp Deck at 6th Flr Penthouse 5 5 07-Aug-17 11-Aug-17

C-S01-1440 Install New Structure @ Elevator Penthouse 20 20 14-Aug-17 11-Sep-17

C-S01-1460 Install Hoistway Walls Flrs B-6 15 15 12-Sep-17 02-Oct-17

C-S01-1530 Install Hoistway Smoke / Heat Detection 2 2 03-Oct-17 04-Oct-17

C-S01-1020 Install Elevator Rails 15 15 03-Oct-17 23-Oct-17

C-S01-1540 Install Hoistway Fire Suppression 3 3 05-Oct-17 09-Oct-17

C-S01-1550 Install Hoistway Lighting 2 2 10-Oct-17 11-Oct-17

C-S01-1570 Remove Elevator Hoistway Scaffold 5 5 24-Oct-17 30-Oct-17

C-S01-1560 Install Elevator Cab & Motor 80 80 31-Oct-17 23-Feb-18

C-S01-1110 Install Elevator Door Fronts 25 25 05-Feb-18 09-Mar-18

C-S01-1120 Install Elevator Cab Finishes 20 20 12-Mar-18 06-Apr-18

C-S01-1130 Elevator Test & Balance 5 5 09-Apr-18 13-Apr-18

C-S01-4290 Complete MCC / FSB Punch List 10 15 09-Apr-18 27-Apr-18

C-S01-1140 DOL Final Inspection on Elevator 1 1 16-Apr-18 16-Apr-18

C-S01-4300 Complete AE1 / Owner Punch List 10 30 16-Apr-18 25-May-18

C-S01-3920 Fire Marshal Final - SW Dog House 1 1 17-Apr-18 17-Apr-18

C-S01-7180 Layout & Core Vertical Risers 17 17 18-Jul-17 09-Aug-17

C-S01-1480 Frame Interior Walls 15 15 20-Jul-17 09-Aug-17

C-S01-1490 In Wall Rough In 15 15 25-Jul-17 14-Aug-17

C-S01-7190 Install Stone Hard Flooring 4 4 04-Aug-17 09-Aug-17

C-S01-1500 Hang, Tape & Finish 25 9 15-Aug-17 25-Aug-17

C-S01-1510 Prime & 1st Coat 15 15 28-Aug-17 18-Sep-17

C-S01-1520 Surface Mount All Electrical / MEP 15 15 19-Sep-17 09-Oct-17

C-S01-1590 Install HVAC Flrs G-6 45 45 18-Jul-17 19-Sep-17

C-S01-1610 Install Vertical IT / Low Voltage Pathways 30 30 25-Jul-17 05-Sep-17

C-S01-6995 Install Hose Cabinets Flrs G-6 15 15 01-Aug-17 21-Aug-17

C-S01-1035 Install SW Dog House Plumbing 20 20 18-Jul-17 14-Aug-17

PlumbingPlumbing66 22 01-Jun-17 A 16-Aug-17

C-S01-6050 OMES - Shut Down Loading Dock/ Turn Around Drive/ West Entry 66 22 01-Jun-17 A 16-Aug-17

C-S01-7185 Cure Site Paving 25 10 26-Jun-17 A 31-Jul-17

C-S01-6150 Complete MCC / FSB Punch List 5 5 18-Jul-17 24-Jul-17

C-S01-6170 Stripe Paving - Sanitary 2 2 01-Aug-17 02-Aug-17

C-S01-6140 Final Clean & Remove Temp Fence 5 5 03-Aug-17 09-Aug-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - Sequence 1

Procure Lintel

Install Lintel

Demo Elevator Lobby Fronts

Install Temp Deck at 6th Flr Penthouse

Install New Structure @ Elevator Penthouse

Install Hoistway Walls Flrs B-6

Install Hoistway Smoke / Heat Detection

Install Elevator Rails

Install Hoistway Fire Suppression

Install Hoistway Lighting

Remove Elevator Hoistway Scaffold

Install Elevator Cab & Motor

Install Elevator Door Fronts

Install Elevator Cab Finishes

Elevator Test & Balance

Complete MCC / FSB Punch List

DOL Final Inspection on Elevator

Complete AE1 / Owner Punch List

Fire Marshal Final - SW Dog House

Layout & Core Vertical Risers

Frame Interior Walls

In Wall Rough In

Install Stone Hard Flooring

Hang, Tape & Finish

Prime & 1st Coat

Surface Mount All Electrical / MEP

Install HVAC Flrs G-6

Install Vertical IT / Low Voltage Pathways

Install Hose Cabinets Flrs G-6

Install SW Dog House Plumbing

OMES - Shut Down Loading Dock/ Turn Around Drive/ West Entry

Cure Site Paving

Complete MCC / FSB Punch List

Stripe Paving - Sanitary

Final Clean & Remove Temp Fence

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 4 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 14: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-6160 Complete AE1 / Owner Punch List 5 5 10-Aug-17 16-Aug-17

C-S01-2010 ONG Set Meter 0 0 18-Jul-17

ElectricalElectrical111 71 19-Apr-17 A 25-Oct-17

C-S01-1115 SW DH Build Out 42 42 28-Aug-17 25-Oct-17

C-S01-1435 Install Buss Duct Tap Box - SW DH Elec Build Out 3 3 28-Aug-17 30-Aug-17

C-S01-1425 Install Branch Panels - SW DH Elec Build Out 7 7 28-Aug-17 06-Sep-17

C-S01-1445 Install Buss Duct - SW DH Elec Build Out 2 3 31-Aug-17 05-Sep-17

C-S01-1455 Install Buss Duct Disconnet - SW DH Elec Build Out 2 2 06-Sep-17 07-Sep-17

C-S01-1465 Run Overhead Piping - SW DH Elec Build Out 14 14 07-Sep-17 26-Sep-17

C-S01-1475 Pull Feeders to Branch Panels - SW DH Elec Build Out 7 7 27-Sep-17 05-Oct-17

C-S01-1485 Terminate Wiring at Tapbox - SW DH Elec Build Out 3 3 06-Oct-17 10-Oct-17

C-S01-1495 Terminate Panel Boards and Main Switch - SW DH Elec Build Out 4 4 11-Oct-17 16-Oct-17

C-S01-1505 Install Grounding - SW DH Elec Build Out 7 7 17-Oct-17 25-Oct-17

C-S01-1105 Main Electric Room Build Out 111 52 19-Apr-17 A 28-Sep-17

C-S01-1375 Pull Overhead Feeders from Genset - Main Elec Rm Build Out 4 4 18-Jul-17 21-Jul-17

C-S01-1235 Set EM Panel Boards - Main Elec Rm Build Out 7 5 18-Jul-17 24-Jul-17

C-S01-1295 Run Overhead Piping for EM - Main Elec Rm Build Out 19 19 25-Jul-17 18-Aug-17

C-S01-1305 Run Overhead Piping for Normal - Main Elec Rm Build Out 18 18 08-Aug-17 31-Aug-17

C-S01-1385 Pull Wire and Terminate EM Gear - Main Elec Rm Build Out 5 5 21-Aug-17 25-Aug-17

C-S01-1145 Install for Fire Pump Feeder 8 8 28-Aug-17 07-Sep-17

C-S01-1395 Pull Wire and Terminate Normal Gear - Main Elec Rm Build Out 5 5 01-Sep-17 08-Sep-17

C-S01-1405 Terminate Main Gear - Main Elec Rm Build Out 14 14 11-Sep-17 28-Sep-17

C-S01-6480 Demo Overhead Bus Duct 2 2 11-Oct-17 12-Oct-17

C-S01-6500 Install Bus Duct to OG&E Vault 1 1 13-Oct-17 13-Oct-17

C-S01-6460 OMES - Power Shut Down 7 7 13-Oct-17 19-Oct-17

C-S01-6470 OG&E Disconnect Power to Building 1 1 13-Oct-17* 13-Oct-17

C-S01-6490 Terminate Existing Main Gear 2 2 14-Oct-17 15-Oct-17

C-S01-6510 Terminate Tap Boxes 1 1 16-Oct-17 16-Oct-17

C-S01-6520 OG&E Terminate at Vault 3 3 16-Oct-17 18-Oct-17

C-S01-1185 OG&E Restore Permanent Power 0 0 19-Oct-17

C-S01-6530 OMES / MCC Restore Building Services 2 2 20-Oct-17 21-Oct-17

C-S01-1195 Commissioning of New Gear 3 3 20-Oct-17 24-Oct-17

Mechanical RoomMechanical Room159 145 27-Jun-17 A 12-Feb-18

C-S01-4140 Overhead Electrical Rough In 5 1 27-Jun-17 A 18-Jul-17

C-S01-4230 MEP Device Out 5 5 18-Jul-17 24-Jul-17

C-S01-4150 Overhead Sprinkler Rough In 5 10 18-Jul-17 31-Jul-17

C-S01-4310 Complete MCC / FSB Punch List 10 10 18-Jul-17 31-Jul-17

C-S01-4100 Install Chilled Water Pumps 3 15 18-Jul-17 07-Aug-17

C-S01-4200 Install Door Frames 2 2 21-Jul-17 24-Jul-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Complete AE1 / Owner Punch List

ONG Set Meter

SW DH Build Out

Install Buss Duct Tap Box - SW DH Elec Build Out

Install Branch Panels - SW DH Elec Build Out

Install Buss Duct - SW DH Elec Build Out

Install Buss Duct Disconnet - SW DH Elec Build Out

Run Overhead Piping - SW DH Elec Build Out

Pull Feeders to Branch Panels - SW DH Elec Build Out

Terminate Wiring at Tapbox - SW DH Elec Build Out

Terminate Panel Boards and Main Switch - SW DH Elec Build Out

Install Grounding - SW DH Elec Build Out

Main Electric Room Build Out

Pull Overhead Feeders from Genset - Main Elec Rm Build Out

Set EM Panel Boards - Main Elec Rm Build Out

Run Overhead Piping for EM - Main Elec Rm Build Out

Run Overhead Piping for Normal - Main Elec Rm Build Out

Pull Wire and Terminate EM Gear - Main Elec Rm Build Out

Install for Fire Pump Feeder

Pull Wire and Terminate Normal Gear - Main Elec Rm Build Out

Terminate Main Gear - Main Elec Rm Build Out

Demo Overhead Bus Duct

Install Bus Duct to OG&E Vault

OMES - Power Shut Down

OG&E Disconnect Power to Building

Terminate Existing Main Gear

Terminate Tap Boxes

OG&E Terminate at Vault

OG&E Restore Permanent Power

OMES / MCC Restore Building Services

Commissioning of New Gear

Overhead Electrical Rough In

MEP Device Out

Overhead Sprinkler Rough In

Complete MCC / FSB Punch List

Install Chilled Water Pumps

Install Door Frames

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 5 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 15: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-4170 Install Hand Sink 2 2 25-Jul-17 26-Jul-17

C-S01-4250 Install Access Controll / Security 5 5 25-Jul-17 31-Jul-17

C-S01-4220 Install Light Fixtures 5 5 08-Aug-17 14-Aug-17

C-S01-4240 Seal Concrete Floor 3 10 15-Aug-17 28-Aug-17

C-S01-4210 Install Doors & Hardware 2 2 29-Aug-17 30-Aug-17

C-S01-4320 Complete AE1 / Owner Punch List 10 10 31-Aug-17 14-Sep-17

C-S01-2960 Fire Marshal Final - Mechanical Room 1 1 12-Feb-18 12-Feb-18

C-S01-3930 Turnover Mechanical Room (Awaiting Public Corridor Open) 0 0 12-Feb-18

Public CorridorPublic Corridor371 345 08-May-17 A 26-Nov-18

C-S01-1980 Construction - Public Corridor 156 145 08-May-17 A 12-Feb-18

C-S01-3090 Frame Ceilings 5 36 19-Jun-17 A 06-Sep-17

C-S01-3020 Overhead Mechanical Rough In 10 5 11-Jul-17 A 24-Jul-17

C-S01-3240 Install Door Frames 5 5 21-Jul-17 27-Jul-17

C-S01-3135 Complete Floor Demolition (Slab) @ West Entry 5 5 08-Aug-17 14-Aug-17

C-S01-3145 F/R/P Floor @ West Entry 3 3 15-Aug-17 17-Aug-17

C-S01-3155 Frame Walls @ West Entry 5 5 18-Aug-17 24-Aug-17

C-S01-7050 Electrical In Wall Rough In @ West Entry 3 3 25-Aug-17 29-Aug-17

C-S01-7055 Hang Sheetrock & Plywood @ West Entry 2 2 30-Aug-17 31-Aug-17

C-S01-7060 Tape, Bed & 1st Coat @ West Entry 3 3 01-Sep-17 06-Sep-17

C-S01-3100 Rough In Lights 5 5 07-Sep-17 13-Sep-17

C-S01-3030 Overhead Electrical Rough In 10 10 07-Sep-17 20-Sep-17

C-S01-3040 Overhead Sprinkler Rough In 10 10 07-Sep-17 20-Sep-17

C-S01-3115 Install K1 Lights 4 4 20-Sep-17 25-Sep-17

C-S01-7155 50% Fire Marshal Inspection 1 1 21-Sep-17 21-Sep-17

C-S01-7160 Hang Sheetrock Ceiling 5 5 22-Sep-17 28-Sep-17

C-S01-3110 Acoustical Plaster Ceiling 5 20 26-Sep-17 23-Oct-17

C-S01-3130 Level Five Finish Walls & Ceilings With Paint 5 20 29-Sep-17 26-Oct-17

C-S01-3120 Crown Moulding 5 10 13-Oct-17 26-Oct-17

C-S01-7065 Install Limestone Columns 26 26 13-Oct-17 17-Nov-17

C-S01-4010 MEP Trim Outs 5 5 19-Oct-17 25-Oct-17

C-S01-4020 Install Temp Lights 5 5 19-Oct-17 25-Oct-17

C-S01-4030 Fire Alarm Device Out 5 5 26-Oct-17 01-Nov-17

C-S01-3140 Install Mud Bed for Marble Floor 5 20 27-Oct-17 27-Nov-17

C-S01-3150 Install Marble Floors 5 30 14-Nov-17 28-Dec-17

C-S01-7045 Grout & Grind Marble Floors 15 15 29-Dec-17 19-Jan-18

C-S01-4040 Final Paint 5 15 08-Jan-18 26-Jan-18

C-S01-4270 Complete MCC / FSB Punch List 10 10 15-Jan-18 26-Jan-18

C-S01-3160 Install Granite Base 5 5 22-Jan-18 26-Jan-18

C-S01-4000 Install Doors & Hardware 5 5 22-Jan-18 26-Jan-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Hand Sink

Install Access Controll / Security

Install Light Fixtures

Seal Concrete Floor

Install Doors & Hardware

Complete AE1 / Owner Punch List

Fire Marshal Final - Mechanical Room

Turnover Mechanical Room (Awaiting Public Corridor Open)

Construction - Public Corridor

Frame Ceilings

Overhead Mechanical Rough In

Install Door Frames

Complete Floor Demolition (Slab) @ West Entry

F/R/P Floor @ West Entry

Frame Walls @ West Entry

Electrical In Wall Rough In @ West Entry

Hang Sheetrock & Plywood @ West Entry

Tape, Bed & 1st Coat @ West Entry

Rough In Lights

Overhead Electrical Rough In

Overhead Sprinkler Rough In

Install K1 Lights

50% Fire Marshal Inspection

Hang Sheetrock Ceiling

Acoustical Plaster Ceiling

Level Five Finish Walls & Ceilings With Paint

Crown Moulding

Install Limestone Columns

MEP Trim Outs

Install Temp Lights

Fire Alarm Device Out

Install Mud Bed for Marble Floor

Install Marble Floors

Grout & Grind Marble Floors

Final Paint

Complete MCC / FSB Punch List

Install Granite Base

Install Doors & Hardware

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 6 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 16: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-4050 Install Wall Panels 5 5 29-Jan-18 02-Feb-18

C-S01-4060 Install Access Controll / Security 5 5 05-Feb-18 09-Feb-18

C-S01-4280 Complete AE1 / Owner Punch List 10 10 05-Feb-18 16-Feb-18

C-S01-1990 Open Corridor 1A (Main Corridor) & Close Corridor 1B 0 0 12-Feb-18

C-S01-2910 Fire Marshal Final - House S. / Fitness / Public Corridor / Generator 1 1 12-Feb-18 12-Feb-18

C-S01-4360 Install Historic Lights 5 5 16-Nov-18 26-Nov-18

House StorageHouse Storage89 89 18-Jul-17 20-Nov-17

C-S01-1680 Hang Sheetrock 5 5 18-Jul-17 24-Jul-17

C-S01-1690 Install Door Frames 1 1 25-Jul-17 25-Jul-17

C-S01-1700 Tape / Bed / Paint Sheetrock 10 10 25-Jul-17 07-Aug-17

C-S01-1720 Install Ceiling Grid / Border 3 3 08-Aug-17 10-Aug-17

C-S01-1940 Tile Break Room & Res troom 3 3 08-Aug-17 10-Aug-17

C-S01-1730 Install Lighting 3 3 11-Aug-17 15-Aug-17

C-S01-1740 Install Diffusers 3 3 11-Aug-17 15-Aug-17

C-S01-1750 Trim Sprinklers 3 3 11-Aug-17 15-Aug-17

C-S01-1760 Install Speakers (By Owner) 3 3 11-Aug-17 15-Aug-17

C-S01-1770 Trim Out Fire Alarm Devices 3 3 11-Aug-17 15-Aug-17

C-S01-1780 Install Base & Casing 5 5 15-Aug-17 21-Aug-17

C-S01-1710 LV / FA / IT Complete 0 0 16-Aug-17

C-S01-1790 Drop Ceiling Tile 1 1 16-Aug-17 16-Aug-17

C-S01-1810 Test & Balance 7 7 16-Aug-17 24-Aug-17

C-S01-1850 Final Paint 5 5 17-Aug-17 23-Aug-17

C-S01-1820 Install Floor Finish 3 3 22-Aug-17 24-Aug-17

C-S01-1880 Trim Out Security Devices 2 2 24-Aug-17 25-Aug-17

C-S01-1870 Hang Doors & Install Hardware 2 2 25-Aug-17 28-Aug-17

C-S01-1830 Install Cabinets / Millwork 5 5 25-Aug-17 31-Aug-17

C-S01-1900 Install Glazing / Stops 1 1 29-Aug-17 29-Aug-17

C-S01-1840 Set Countertops 5 5 01-Sep-17 08-Sep-17

C-S01-1860 Install Plumbing Fixtures 3 3 11-Sep-17 13-Sep-17

C-S01-1800 Conditioned Air Available 0 0 19-Oct-17

C-S01-1890 Complete MCC / FSB Punch List 10 10 20-Oct-17 02-Nov-17

C-S01-1920 Touch Up Paint 1 1 03-Nov-17 03-Nov-17

C-S01-1910 Final Clean 1 1 06-Nov-17 06-Nov-17

C-S01-1930 Complete AE1 / Owner Punch List 10 10 07-Nov-17 20-Nov-17

FitnessFitness91 89 14-Jul-17 A 20-Nov-17

C-S01-2130 Rough In In Walls 5 3 14-Jul-17 A 20-Jul-17

C-S01-2140 Frame Hard Lids 2 2 21-Jul-17 24-Jul-17

C-S01-2150 Hang Sheetrock 5 5 25-Jul-17 31-Jul-17

C-S01-2160 Install Door Frames 1 1 01-Aug-17 01-Aug-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Wall Panels

Install Access Controll / Security

Complete AE1 / Owner Punch List

Open Corridor 1A (Main Corridor) & Close Corridor 1B

Fire Marshal Final - House S. / Fitness / Public Corridor / Generator

Install Historic Lights

Hang Sheetrock

Install Door Frames

Tape / Bed / Paint Sheetrock

Install Ceiling Grid / Border

Tile Break Room & Res troom

Install Lighting

Install Diffusers

Trim Sprinklers

Install Speakers (By Owner)

Trim Out Fire Alarm Devices

Install Base & Casing

LV / FA / IT Complete

Drop Ceiling Tile

Test & Balance

Final Paint

Install Floor Finish

Trim Out Security Devices

Hang Doors & Install Hardware

Install Cabinets / Millwork

Install Glazing / Stops

Set Countertops

Install Plumbing Fixtures

Conditioned Air Available

Complete MCC / FSB Punch List

Touch Up Paint

Final Clean

Complete AE1 / Owner Punch List

Rough In In Walls

Frame Hard Lids

Hang Sheetrock

Install Door Frames

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 7 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 17: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-2170 Tape / Bed / Paint Sheetrock 10 10 01-Aug-17 14-Aug-17

C-S01-2180 Install Ceiling Grid / Border 3 3 15-Aug-17 17-Aug-17

C-S01-2200 Install Lighting 3 3 15-Aug-17 17-Aug-17

C-S01-2250 Install Floor Finish 3 3 15-Aug-17 17-Aug-17

C-S01-2330 Hang Doors & Install Hardware 2 2 18-Aug-17 21-Aug-17

C-S01-2210 Install Diffusers 3 3 18-Aug-17 22-Aug-17

C-S01-2220 Trim Sprinklers 3 3 18-Aug-17 22-Aug-17

C-S01-2230 Install Speakers (By Owner) 3 3 18-Aug-17 22-Aug-17

C-S01-2240 Trim Out Fire Alarm Devices 3 3 18-Aug-17 22-Aug-17

C-S01-2320 Install Lockers 5 5 18-Aug-17 24-Aug-17

C-S01-2190 Tile Res trooms 15 15 18-Aug-17 08-Sep-17

C-S01-2340 Install Glazing / Stops 1 1 22-Aug-17 22-Aug-17

C-S01-2260 LV / FA / IT Complete 0 0 23-Aug-17

C-S01-2270 Drop Ceiling Tile 1 1 23-Aug-17 23-Aug-17

C-S01-2280 Test & Balance 7 7 23-Aug-17 31-Aug-17

C-S01-2300 Final Paint 5 5 24-Aug-17 30-Aug-17

C-S01-2350 Trim Out Security Devices 2 2 31-Aug-17 01-Sep-17

C-S01-2360 Set Countertops 5 5 11-Sep-17 15-Sep-17

C-S01-2370 Install Plumbing Fixtures 3 3 18-Sep-17 20-Sep-17

C-S01-2290 Conditioned Air Available 0 0 19-Oct-17

C-S01-2310 Complete MCC / FSB Punch List 10 10 20-Oct-17 02-Nov-17

C-S01-2380 Touch Up Paint 1 1 03-Nov-17 03-Nov-17

C-S01-2390 Final Clean 1 1 06-Nov-17 06-Nov-17

C-S01-2400 Complete AE1 / Owner Punch List 10 10 07-Nov-17 20-Nov-17

C-S01-2040 Install Hot Water Heater 2 2 15-Aug-17 16-Aug-17

C-S01-2420 Install Bathroom Partitions & Accessories 3 3 21-Sep-17 25-Sep-17

ElectionElection97 97 12-Feb-18 27-Jun-18

C-S01-2430 Lay Out Walls 1 1 12-Feb-18 12-Feb-18

C-S01-2460 Rough In Sprinklers 5 5 13-Feb-18 19-Feb-18

C-S01-2470 Rough In Mechanicial Pipe 5 5 13-Feb-18 19-Feb-18

C-S01-2480 Install U/G Plumbing 5 5 13-Feb-18 19-Feb-18

C-S01-2440 Rough In O/H Electric 10 10 13-Feb-18 26-Feb-18

C-S01-2450 Rough In O/H Mechanical w/ HP 15 15 13-Feb-18 05-Mar-18

C-S01-2490 Frame Walls 7 7 20-Feb-18 28-Feb-18

C-S01-2510 Rough In In Walls 10 10 01-Mar-18 14-Mar-18

C-S01-2520 Frame Hard Lids 5 5 15-Mar-18 21-Mar-18

C-S01-2530 Hang Sheetrock 10 10 22-Mar-18 04-Apr-18

C-S01-2540 Install Door Frames 3 3 05-Apr-18 09-Apr-18

C-S01-2550 Tape / Bed / Paint Sheetrock 10 10 05-Apr-18 18-Apr-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Tape / Bed / Paint Sheetrock

Install Ceiling Grid / Border

Install Lighting

Install Floor Finish

Hang Doors & Install Hardware

Install Diffusers

Trim Sprinklers

Install Speakers (By Owner)

Trim Out Fire Alarm Devices

Install Lockers

Tile Res trooms

Install Glazing / Stops

LV / FA / IT Complete

Drop Ceiling Tile

Test & Balance

Final Paint

Trim Out Security Devices

Set Countertops

Install Plumbing Fixtures

Conditioned Air Available

Complete MCC / FSB Punch List

Touch Up Paint

Final Clean

Complete AE1 / Owner Punch List

Install Hot Water Heater

Install Bathroom Partitions & Accessories

Lay Out Walls

Rough In Sprinklers

Rough In Mechanicial Pipe

Install U/G Plumbing

Rough In O/H Electric

Rough In O/H Mechanical w/ HP

Frame Walls

Rough In In Walls

Frame Hard Lids

Hang Sheetrock

Install Door Frames

Tape / Bed / Paint Sheetrock

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 8 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 18: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-2560 Install Ceiling Grid / Border 3 3 19-Apr-18 23-Apr-18

C-S01-2580 Tile Break Room 5 5 19-Apr-18 25-Apr-18

C-S01-2570 Install Base & Casing 10 10 19-Apr-18 02-May-18

C-S01-2590 Install Lighting 3 3 24-Apr-18 26-Apr-18

C-S01-2600 Install Diffusers 3 3 24-Apr-18 26-Apr-18

C-S01-2610 Trim Sprinklers 3 3 24-Apr-18 26-Apr-18

C-S01-2620 Install Speakers (By Owner) 3 3 24-Apr-18 26-Apr-18

C-S01-2630 Trim Out Fire Alarm Devices 3 3 24-Apr-18 26-Apr-18

C-S01-2650 LV / FA / IT Complete 0 0 27-Apr-18

C-S01-2660 Drop Ceiling Tile 1 1 27-Apr-18 27-Apr-18

C-S01-2670 Test & Balance 5 5 27-Apr-18 03-May-18

C-S01-2680 Conditioned Air Available 0 0 27-Apr-18

C-S01-2690 Final Paint 3 3 30-Apr-18 02-May-18

C-S01-2700 Complete MCC / FSB Punch List 10 10 30-Apr-18 11-May-18

C-S01-2740 Trim Out Security Devices 2 2 03-May-18 04-May-18

C-S01-2640 Install Floor Finish 10 10 14-May-18 25-May-18

C-S01-2720 Hang Doors & Install Hardware 2 2 29-May-18 30-May-18

C-S01-2710 Install Cabinets 5 5 29-May-18 04-Jun-18

C-S01-2730 Install Glazing / Stops 1 1 31-May-18 31-May-18

C-S01-2750 Set Countertops 1 1 05-Jun-18 05-Jun-18

C-S01-2760 Install Plumbing Fixtures 3 3 06-Jun-18 08-Jun-18

C-S01-2770 Touch Up Paint 1 1 11-Jun-18 11-Jun-18

C-S01-2780 Final Clean 1 1 12-Jun-18 12-Jun-18

C-S01-2790 Complete AE1 / Owner Punch List 10 10 13-Jun-18 26-Jun-18

C-S01-2800 Install Built Ins 10 10 30-Apr-18 11-May-18

C-S01-2950 Fire Marshal Final - Election 1 1 27-Jun-18 27-Jun-18

EthicsEthics97 97 12-Feb-18 27-Jun-18

C-S01-3540 Lay Out Walls 1 1 12-Feb-18 12-Feb-18

C-S01-3570 Rough In Sprinklers 5 5 13-Feb-18 19-Feb-18

C-S01-3580 Rough In Mechanicial Pipe 5 5 13-Feb-18 19-Feb-18

C-S01-3590 Install U/G Plumbing 5 5 13-Feb-18 19-Feb-18

C-S01-3550 Rough In O/H Electric 10 10 13-Feb-18 26-Feb-18

C-S01-3560 Rough In O/H Mechanical w/ HP 15 15 13-Feb-18 05-Mar-18

C-S01-3600 Frame Walls 3 3 20-Feb-18 22-Feb-18

C-S01-3610 Rough In In Walls 10 10 23-Feb-18 08-Mar-18

C-S01-3620 Frame Hard Lids 2 2 09-Mar-18 12-Mar-18

C-S01-3630 Hang Sheetrock 5 5 13-Mar-18 19-Mar-18

C-S01-3640 Install Door Frames 2 2 20-Mar-18 21-Mar-18

C-S01-3650 Tape / Bed / Paint Sheetrock 10 10 20-Mar-18 02-Apr-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Ceiling Grid / Border

Tile Break Room

Install Base & Casing

Install Lighting

Install Diffusers

Trim Sprinklers

Install Speakers (By Owner)

Trim Out Fire Alarm Devices

LV / FA / IT Complete

Drop Ceiling Tile

Test & Balance

Conditioned Air Available

Final Paint

Complete MCC / FSB Punch List

Trim Out Security Devices

Install Floor Finish

Hang Doors & Install Hardware

Install Cabinets

Install Glazing / Stops

Set Countertops

Install Plumbing Fixtures

Touch Up Paint

Final Clean

Complete AE1 / Owner Punch List

Install Built Ins

Fire Marshal Final - Election

Lay Out Walls

Rough In Sprinklers

Rough In Mechanicial Pipe

Install U/G Plumbing

Rough In O/H Electric

Rough In O/H Mechanical w/ HP

Frame Walls

Rough In In Walls

Frame Hard Lids

Hang Sheetrock

Install Door Frames

Tape / Bed / Paint Sheetrock

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 9 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 19: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-3660 Install Ceiling Grid / Border 3 3 03-Apr-18 05-Apr-18

C-S01-3680 Tile Break Room 5 5 03-Apr-18 09-Apr-18

C-S01-3670 Install Base & Casing 7 7 03-Apr-18 11-Apr-18

C-S01-3690 Install Lighting 3 3 06-Apr-18 10-Apr-18

C-S01-3700 Install Diffusers 3 3 06-Apr-18 10-Apr-18

C-S01-3710 Trim Sprinklers 3 3 06-Apr-18 10-Apr-18

C-S01-3720 Install Speakers (By Owner) 3 3 06-Apr-18 10-Apr-18

C-S01-3730 Trim Out Fire Alarm Devices 3 3 06-Apr-18 10-Apr-18

C-S01-3740 LV / FA / IT Complete 0 0 11-Apr-18

C-S01-3750 Drop Ceiling Tile 1 1 11-Apr-18 11-Apr-18

C-S01-3760 Test & Balance 5 5 11-Apr-18 17-Apr-18

C-S01-3770 Conditioned Air Available 0 0 11-Apr-18

C-S01-3790 Final Paint 3 3 12-Apr-18 16-Apr-18

C-S01-3780 Install Floor Finish 10 10 12-Apr-18 25-Apr-18

C-S01-3800 Complete MCC / FSB Punch List 10 10 12-Apr-18 25-Apr-18

C-S01-3810 Trim Out Security Devices 2 2 17-Apr-18 18-Apr-18

C-S01-3830 Hang Doors & Install Hardware 2 2 26-Apr-18 27-Apr-18

C-S01-3820 Install Cabinets 5 5 26-Apr-18 02-May-18

C-S01-3840 Install Glazing / Stops 1 1 30-Apr-18 30-Apr-18

C-S01-3850 Set Countertops 1 1 03-May-18 03-May-18

C-S01-3860 Install Plumbing Fixtures 3 3 04-May-18 08-May-18

C-S01-3870 Touch Up Paint 1 1 09-May-18 09-May-18

C-S01-3880 Final Clean 1 1 10-May-18 10-May-18

C-S01-3890 Complete AE1 / Owner Punch List 10 10 11-May-18 24-May-18

C-S01-3910 Fire Marshal Final - Ethics 1 1 27-Jun-18 27-Jun-18

House PrintHouse Print97 97 12-Feb-18 27-Jun-18

C-S01-3170 Lay Out Walls 1 1 12-Feb-18 12-Feb-18

C-S01-3180 Rough In O/H Electric 5 5 13-Feb-18 19-Feb-18

C-S01-3200 Rough In Sprinklers 5 5 13-Feb-18 19-Feb-18

C-S01-3210 Rough In Mechanicial Pipe 5 5 13-Feb-18 19-Feb-18

C-S01-3220 Install U/G Plumbing 5 5 13-Feb-18 19-Feb-18

C-S01-3190 Rough In O/H Mechanical w/ HP 10 10 13-Feb-18 26-Feb-18

C-S01-3230 Frame Walls 1 1 20-Feb-18 20-Feb-18

C-S01-3250 Rough In In Walls 2 2 21-Feb-18 22-Feb-18

C-S01-3260 Frame Hard Lids 1 1 23-Feb-18 23-Feb-18

C-S01-3270 Hang Sheetrock 1 1 26-Feb-18 26-Feb-18

C-S01-3280 Install Door Frames 1 1 27-Feb-18 27-Feb-18

C-S01-3290 Tape / Bed / Paint Sheetrock 3 3 27-Feb-18 01-Mar-18

C-S01-3300 Install Ceiling Grid / Border 3 3 02-Mar-18 06-Mar-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Ceiling Grid / Border

Tile Break Room

Install Base & Casing

Install Lighting

Install Diffusers

Trim Sprinklers

Install Speakers (By Owner)

Trim Out Fire Alarm Devices

LV / FA / IT Complete

Drop Ceiling Tile

Test & Balance

Conditioned Air Available

Final Paint

Install Floor Finish

Complete MCC / FSB Punch List

Trim Out Security Devices

Hang Doors & Install Hardware

Install Cabinets

Install Glazing / Stops

Set Countertops

Install Plumbing Fixtures

Touch Up Paint

Final Clean

Complete AE1 / Owner Punch List

Fire Marshal Final - Ethics

Lay Out Walls

Rough In O/H Electric

Rough In Sprinklers

Rough In Mechanicial Pipe

Install U/G Plumbing

Rough In O/H Mechanical w/ HP

Frame Walls

Rough In In Walls

Frame Hard Lids

Hang Sheetrock

Install Door Frames

Tape / Bed / Paint Sheetrock

Install Ceiling Grid / Border

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 10 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 20: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-3310 Install Base & Casing 3 3 02-Mar-18 06-Mar-18

C-S01-3320 Tile Break Room 3 3 02-Mar-18 06-Mar-18

C-S01-3340 Install Diffusers 1 1 07-Mar-18 07-Mar-18

C-S01-3350 Trim Sprinklers 1 1 07-Mar-18 07-Mar-18

C-S01-3360 Install Speakers (By Owner) 1 1 07-Mar-18 07-Mar-18

C-S01-3370 Trim Out Fire Alarm Devices 1 1 07-Mar-18 07-Mar-18

C-S01-3330 Install Lighting 3 3 07-Mar-18 09-Mar-18

C-S01-3380 Install Floor Finish 3 3 07-Mar-18 09-Mar-18

C-S01-3410 Test & Balance 3 3 08-Mar-18 12-Mar-18

C-S01-3390 LV / FA / IT Complete 0 0 12-Mar-18

C-S01-3400 Drop Ceiling Tile 1 1 12-Mar-18 12-Mar-18

C-S01-3450 Install Cabinets 1 1 12-Mar-18 12-Mar-18

C-S01-3460 Hang Doors & Install Hardware 1 1 12-Mar-18 12-Mar-18

C-S01-3420 Conditioned Air Available 0 0 12-Mar-18

C-S01-3490 Set Countertops 1 1 13-Mar-18 13-Mar-18

C-S01-3470 Install Glazing / Stops 1 1 13-Mar-18 13-Mar-18

C-S01-3430 Final Paint 3 3 13-Mar-18 15-Mar-18

C-S01-3440 Complete MCC / FSB Punch List 5 5 13-Mar-18 19-Mar-18

C-S01-3500 Install Plumbing Fixtures 1 1 14-Mar-18 14-Mar-18

C-S01-3480 Trim Out Security Devices 1 1 16-Mar-18 16-Mar-18

C-S01-3510 Touch Up Paint 2 2 20-Mar-18 21-Mar-18

C-S01-3520 Final Clean 1 1 22-Mar-18 22-Mar-18

C-S01-3530 Complete AE1 / Owner Punch List 10 10 23-Mar-18 05-Apr-18

C-S01-3900 Fire Marshal Final - House Print 1 1 27-Jun-18 27-Jun-18

GeneratorGenerator148 137 30-Jun-17 A 31-Jan-18

C-S01-2860 FRP Exterior Walls w/ Additional 15' of Wall 15 2 30-Jun-17 A 19-Jul-17

C-S01-2870 Strip Forms & Clean 3 3 20-Jul-17 24-Jul-17

C-S01-2880 Install Waterproofing 10 10 25-Jul-17 07-Aug-17

C-S01-2980 Install Grate 5 10 25-Jul-17 07-Aug-17

C-S01-2875 JE Dunn - Demo West Plaza Deck 10 10 25-Jul-17 07-Aug-17

C-S01-2970 Backfill 5 15 28-Jul-17 17-Aug-17

C-S01-2890 Install Subsurface Drainage 5 5 08-Aug-17 14-Aug-17

C-S01-2885 JE Dunn - Waterproof West Plaza 5 5 08-Aug-17 14-Aug-17

C-S01-2900 Shot Blast Existing Decking 5 5 08-Aug-17 14-Aug-17

C-S01-2895 JE Dunn - FRP West Plaza Deck 3 3 15-Aug-17 17-Aug-17

C-S01-2905 Paint Metal Decking & Existing Structure 5 5 15-Aug-17 21-Aug-17

C-S01-2990 Set Generator 0 0 14-Sep-17

C-S01-1000 Install Duct to Generator 15 15 15-Sep-17 05-Oct-17

C-S01-1080 Install Mechanical Piping to Generator 15 15 06-Oct-17 26-Oct-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Base & Casing

Tile Break Room

Install Diffusers

Trim Sprinklers

Install Speakers (By Owner)

Trim Out Fire Alarm Devices

Install Lighting

Install Floor Finish

Test & Balance

LV / FA / IT Complete

Drop Ceiling Tile

Install Cabinets

Hang Doors & Install Hardware

Conditioned Air Available

Set Countertops

Install Glazing / Stops

Final Paint

Complete MCC / FSB Punch List

Install Plumbing Fixtures

Trim Out Security Devices

Touch Up Paint

Final Clean

Complete AE1 / Owner Punch List

Fire Marshal Final - House Print

FRP Exterior Walls w/ Additional 15' of Wall

Strip Forms & Clean

Install Waterproofing

Install Grate

JE Dunn - Demo West Plaza Deck

Backfill

Install Subsurface Drainage

JE Dunn - Waterproof West Plaza

Shot Blast Existing Decking

JE Dunn - FRP West Plaza Deck

Paint Metal Decking & Existing Structure

Set Generator

Install Duct to Generator

Install Mechanical Piping to Generator

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 11 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 21: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-S01-3010 Install Electical Piping to Generator 20 20 27-Oct-17 27-Nov-17

C-S01-1135 Feeder Install for Generator Feeds 7 7 28-Nov-17 06-Dec-17

C-S01-1175 Final Tie into Generator 35 35 28-Nov-17 17-Jan-18

C-S01-3000 Install Electrical to Generator 3 3 07-Dec-17 11-Dec-17

C-S01-4330 Complete MCC / FSB Punch List 10 10 07-Dec-17 20-Dec-17

C-S01-1205 Commissioning of New Generator 3 3 18-Jan-18 22-Jan-18

C-S01-4340 Complete AE1 / Owner Punch List 10 10 18-Jan-18 31-Jan-18

Sequence 2Sequence 2454 454 08-Sep-17 21-Jun-19

ConstructionConstruction454 454 08-Sep-17 21-Jun-19

Construction Phase SummariesConstruction Phase Summaries454 454 08-Sep-17 21-Jun-19

C-S02-1010 Install Fire Pump 1 1 08-Sep-17 08-Sep-17

C-S02-1020 OMES / JEDUNN to Complete Water Proofing at Loading Dock 0 0 26-Jun-18

S-S02-1000 Construction - Sequence 2 360 360 27-Jun-18 21-Jun-19

Sequence 3Sequence 3285 285 22-Jun-19 01-Apr-20

ConstructionConstruction285 285 22-Jun-19 01-Apr-20

Construction Phase SummariesConstruction Phase Summaries285 285 22-Jun-19 01-Apr-20

S-S03-1000 Construction - Sequence 3 285 285 22-Jun-19 01-Apr-20

Sequence 4Sequence 4285 285 24-Oct-20 04-Aug-21

ConstructionConstruction285 285 24-Oct-20 04-Aug-21

Construction Phase SummariesConstruction Phase Summaries285 285 24-Oct-20 04-Aug-21

S-S04-1000 Construction - Sequence 4 285 285 24-Oct-20 04-Aug-21

CoreCore1417 1385 05-Jun-17 A 30-Dec-22

Risers / Fresh AirRisers / Fresh Air509 338 05-Jun-17 A 13-Nov-18

ConstructionConstruction509 338 05-Jun-17 A 13-Nov-18

Schedule Driven MilestonesSchedule Driven Milestones281 281 05-Oct-17 13-Nov-18

M-C01-1025 Risers Complete - SW 0 0 05-Oct-17

M-C01-1000 Risers Complete - NW 0 0 16-Nov-17

M-C01-1005 Risers Complete - North 0 0 20-Dec-17

M-C01-1010 Risers Complete - South 0 0 05-Mar-18

M-C01-1020 Risers Complete - NE 0 0 18-Sep-18

M-C01-1015 Risers Complete - SE 0 0 13-Nov-18

Construction Phase SummariesConstruction Phase Summaries733 484 05-Jun-17 A 13-Nov-18

S-C01-1000 Construction - Risers / Fresh Air 729 484 05-Jun-17 A 13-Nov-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Electical Piping to Generator

Feeder Install for Generator Feeds

Final Tie into Generator

Install Electrical to Generator

Complete MCC / FSB Punch List

Commissioning of New Generator

Complete AE1 / Owner Punch List

Install Fire Pump

OMES / JEDUNN to Complete Water Proofing at Loading Dock

Construction - Sequence 2

Construction - Sequence 3

Construction - Sequence 4

Risers Complete - SW

Risers Complete - NW

Risers Complete - North

Risers Complete - South

Risers Complete - NE

Risers Complete - SE

Construction - Risers / Fresh Air

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 12 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 22: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

S-C01-1015 Construction - SW Risers 139 80 05-Jun-17 A 05-Oct-17

S-C01-1025 Construction - NW Risers 183 122 07-Jun-17 A 16-Nov-17

S-C01-1040 Construction - North Risers 115 114 29-Aug-17 20-Dec-17

S-C01-1045 Construction - South Risers 120 120 06-Nov-17 05-Mar-18

S-C01-1035 Construction - NE Risers 233 245 17-Jan-18 18-Sep-18

S-C01-1030 Construction - SE Risers 289 301 17-Jan-18 13-Nov-18

SW - Offices 508 and 510 Outside AirSW - Offices 508 and 510 Outside Air8 8 18-Jul-17 27-Jul-17

C-C01-1170 OMES Move In 3 3 18-Jul-17 20-Jul-17

C-C01-3770 Install Smoke / Fire Damper 4 4 18-Jul-17 21-Jul-17

C-C01-3755 Install Outside Air Riser 5 5 18-Jul-17 24-Jul-17

C-C01-1175 OMES (House Employees) Move In 1 1 21-Jul-17 21-Jul-17

C-C01-3760 Install Shaft Walls / Access Panels 4 4 24-Jul-17 27-Jul-17

SW - Room 112.12 Outside AirSW - Room 112.12 Outside Air11 11 17-Jul-17 A 01-Aug-17

C-C01-1305 Tape, Bed, Paint 5 4 17-Jul-17 A 21-Jul-17

C-C01-1315 Re-Install Floor Finishes 2 2 24-Jul-17 25-Jul-17

C-C01-1320 Test Smoke / Fire Damper 1 1 26-Jul-17 26-Jul-17

C-C01-1325 Remove Temp Walls 2 2 27-Jul-17 28-Jul-17

C-C01-1330 Final Clean 2 2 31-Jul-17 01-Aug-17

SW - Rooms 200, 206 & Stairwell Restroom Outside AirSW - Rooms 200, 206 & Stairwell Restroom Outside Air29 27 14-Jul-17 A 23-Aug-17

C-C01-1640 Fire Caulk / Seal Floor Penetration @ Riser 3 1 14-Jul-17 A 18-Jul-17

C-C01-1355 Install Smoke / Fire Damper 5 5 19-Jul-17 25-Jul-17

C-C01-1360 Install Shaft Walls / Access Panels 5 5 26-Jul-17 01-Aug-17

C-C01-1365 Tape, Bed, Paint 5 5 02-Aug-17 08-Aug-17

C-C01-1370 Re-Install Ceiling Grid & Tile 3 3 09-Aug-17 11-Aug-17

C-C01-1375 Re-Install Floor Finishes 3 3 14-Aug-17 16-Aug-17

C-C01-1380 Test Smoke / Fire Damper 1 1 17-Aug-17 17-Aug-17

C-C01-1385 Remove Temp Walls 2 2 18-Aug-17 21-Aug-17

C-C01-1390 Final Clean 2 2 22-Aug-17 23-Aug-17

SW - Room 205 Outside AirSW - Room 205 Outside Air21 21 18-Jul-17 15-Aug-17

C-C01-3710 Install Shaft Walls / Access Panels 5 5 18-Jul-17 24-Jul-17

C-C01-3715 Tape, Bed, Paint 5 5 25-Jul-17 31-Jul-17

C-C01-3720 Re-Install Ceiling Grid & Tile 3 3 01-Aug-17 03-Aug-17

C-C01-3725 Re-Install Floor Finishes 3 3 04-Aug-17 08-Aug-17

C-C01-3730 Test Smoke / Fire Damper 1 1 09-Aug-17 09-Aug-17

C-C01-3735 Remove Temp Walls 2 2 10-Aug-17 11-Aug-17

C-C01-3740 Final Clean 2 2 14-Aug-17 15-Aug-17

SW - Rooms 301 & 305A Outside AirSW - Rooms 301 & 305A Outside Air28 26 14-Jul-17 A 22-Aug-17

C-C01-1410 Install Outside Air Riser 5 3 14-Jul-17 A 20-Jul-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - SW Risers

Construction - NW Risers

Construction - North Risers

Construction - South Risers

Construction - NE Risers

Construction - SE Risers

OMES Move In

Install Smoke / Fire Damper

Install Outside Air Riser

OMES (House Employees) Move In

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Outside Air Riser

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 13 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 23: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-1645 Fire Caulk / Seal Floor Penetration @ Riser 2 2 21-Jul-17 24-Jul-17

C-C01-1415 Install Smoke / Fire Damper 4 4 25-Jul-17 28-Jul-17

C-C01-1420 Install Shaft Walls / Access Panels 4 4 31-Jul-17 03-Aug-17

C-C01-1425 Tape, Bed, Paint 4 4 04-Aug-17 09-Aug-17

C-C01-1430 Re-Install Ceiling Grid & Tile 2 2 10-Aug-17 11-Aug-17

C-C01-1435 Re-Install Floor Finishes 2 2 14-Aug-17 15-Aug-17

C-C01-1440 Test Smoke / Fire Damper 1 1 16-Aug-17 16-Aug-17

C-C01-1445 Remove Temp Walls 2 2 17-Aug-17 18-Aug-17

C-C01-1450 Final Clean 2 2 21-Aug-17 22-Aug-17

SW - Rooms 401, 411 & Womens Restroom Outside AirSW - Rooms 401, 411 & Womens Restroom Outside Air33 33 18-Jul-17 31-Aug-17

C-C01-1460 Demo Walls & Ceilings 4 4 18-Jul-17 21-Jul-17

C-C01-1465 Saw Cut Floor 1 1 24-Jul-17 24-Jul-17

C-C01-1470 Install Outside Air Riser 5 5 25-Jul-17 31-Jul-17

C-C01-1650 Fire Caulk / Seal Floor Penetration @ Riser 2 2 01-Aug-17 02-Aug-17

C-C01-1475 Install Smoke / Fire Damper 4 4 03-Aug-17 08-Aug-17

C-C01-1480 Install Shaft Walls / Access Panels 4 4 09-Aug-17 14-Aug-17

C-C01-1485 Tape, Bed, Paint 4 4 15-Aug-17 18-Aug-17

C-C01-1490 Re-Install Ceiling Grid & Tile 2 2 21-Aug-17 22-Aug-17

C-C01-1495 Re-Install Floor Finishes 2 2 23-Aug-17 24-Aug-17

C-C01-1500 Test Smoke / Fire Damper 1 1 25-Aug-17 25-Aug-17

C-C01-1505 Remove Temp Walls 2 2 28-Aug-17 29-Aug-17

C-C01-1510 Final Clean 2 2 30-Aug-17 31-Aug-17

SW - Rooms 500A & 500 Outside AirSW - Rooms 500A & 500 Outside Air35 35 25-Jul-17 12-Sep-17

C-C01-1515 Install Temp Walls 2 2 25-Jul-17 26-Jul-17

C-C01-1520 Demo Walls & Ceilings 4 4 27-Jul-17 01-Aug-17

C-C01-1525 Saw Cut Floor 1 1 02-Aug-17 02-Aug-17

C-C01-1530 Install Outside Air Riser 5 5 03-Aug-17 09-Aug-17

C-C01-1655 Fire Caulk / Seal Floor Penetration @ Riser 2 2 10-Aug-17 11-Aug-17

C-C01-1535 Install Smoke / Fire Damper 4 4 14-Aug-17 17-Aug-17

C-C01-1540 Install Shaft Walls / Access Panels 4 4 18-Aug-17 23-Aug-17

C-C01-1545 Tape, Bed, Paint 4 4 24-Aug-17 29-Aug-17

C-C01-1550 Re-Install Ceiling Grid & Tile 2 2 30-Aug-17 31-Aug-17

C-C01-1555 Re-Install Floor Finishes 2 2 01-Sep-17 05-Sep-17

C-C01-1560 Test Smoke / Fire Damper 1 1 06-Sep-17 06-Sep-17

C-C01-1565 Remove Temp Walls 2 2 07-Sep-17 08-Sep-17

C-C01-1570 Final Clean 2 2 11-Sep-17 12-Sep-17

SW - 6th FloorSW - 6th Floor20 20 03-Aug-17 30-Aug-17

C-C01-1585 Saw Cut Floor 5 5 03-Aug-17 09-Aug-17

C-C01-1590 Install Outside Air Riser 5 5 10-Aug-17 16-Aug-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Saw Cut Floor

Install Outside Air Riser

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 14 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 24: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-1660 Fire Caulk / Seal Floor Penetration @ Riser 5 5 17-Aug-17 23-Aug-17

C-C01-1595 Install Smoke / Fire Damper 5 5 24-Aug-17 30-Aug-17

SW - RooftopSW - Rooftop67 57 10-Jul-17 A 05-Oct-17

C-C01-4530 Procure & Receive Roof Top Curb 15 9 10-Jul-17 A 28-Jul-17

C-C01-1005 Set Roof Top Curb 5 5 31-Jul-17 04-Aug-17

C-C01-1000 Set Roof Top Equipment (SW) 3 3 21-Aug-17 23-Aug-17

C-C01-1010 Install SW Roof Top Equipment 40 20 24-Aug-17 21-Sep-17

C-C01-1020 Start Up SW Roof Top Equipment 10 10 22-Sep-17 05-Oct-17

NW - Offices 548, 540A, 539 Outside AirNW - Offices 548, 540A, 539 Outside Air36 15 17-Jul-17 A 07-Aug-17

C-C01-1245 Tape / Bed and Paint 5 1 17-Jul-17 A 18-Jul-17

C-C01-1250 Install Ceiling Grid 6 1 17-Jul-17 A 18-Jul-17

C-C01-1255 OVHD MEP Trim Out 5 1 17-Jul-17 A 18-Jul-17

C-C01-1260 Final Clean 2 4 18-Jul-17 21-Jul-17

C-C01-3780 Install Outside Air Riser 5 5 18-Jul-17 24-Jul-17

C-C01-1265 OMES Move In 6 6 24-Jul-17 31-Jul-17

C-C01-3785 Fire Caulk / Seal Floor Penetration @ Riser 2 2 25-Jul-17 26-Jul-17

C-C01-3790 Install Smoke / Fire Damper 3 3 27-Jul-17 31-Jul-17

C-C01-1270 OMES (House Employees) Move In 4 4 01-Aug-17 04-Aug-17

C-C01-3795 Install Shaft Walls / Access Panels 5 5 01-Aug-17 07-Aug-17

NW - Room 109.37 Outside AirNW - Room 109.37 Outside Air15 15 18-Jul-17 07-Aug-17

C-C01-1765 Tape, Bed, Paint 5 5 18-Jul-17 24-Jul-17

C-C01-1770 Re-Install Ceiling Grid & Tile 3 3 25-Jul-17 27-Jul-17

C-C01-1775 Re-Install Floor Finishes 2 2 28-Jul-17 31-Jul-17

C-C01-1780 Test Smoke / Fire Damper 1 1 01-Aug-17 01-Aug-17

C-C01-1785 Remove Temp Walls 2 2 02-Aug-17 03-Aug-17

C-C01-1790 Final Clean 2 2 04-Aug-17 07-Aug-17

NW - Rooms 240, 242, 250, Mech Rm, Supreme Court Outside AirNW - Rooms 240, 242, 250, Mech Rm, Supreme Court Outside Air26 23 13-Jul-17 A 17-Aug-17

C-C01-1820 Install Smoke / Fire Damper 5 2 13-Jul-17 A 19-Jul-17

C-C01-1825 Install Shaft Walls / Access Panels 5 5 20-Jul-17 26-Jul-17

C-C01-1830 Tape, Bed, Paint 5 5 27-Jul-17 02-Aug-17

C-C01-1835 Re-Install Ceiling Grid & Tile 3 3 03-Aug-17 07-Aug-17

C-C01-1840 Re-Install Floor Finishes 3 3 08-Aug-17 10-Aug-17

C-C01-1845 Test Smoke / Fire Damper 1 1 11-Aug-17 11-Aug-17

C-C01-1850 Remove Temp Walls 2 2 14-Aug-17 15-Aug-17

C-C01-1855 Final Clean 2 2 16-Aug-17 17-Aug-17

NW - Rooms 328 & 338 Outside AirNW - Rooms 328 & 338 Outside Air23 22 17-Jul-17 A 16-Aug-17

C-C01-1880 Fire Caulk / Seal Floor Penetration @ Riser 2 1 17-Jul-17 A 18-Jul-17

C-C01-1885 Install Smoke / Fire Damper 4 4 19-Jul-17 24-Jul-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Procure & Receive Roof Top Curb

Set Roof Top Curb

Set Roof Top Equipment (SW)

Install SW Roof Top Equipment

Start Up SW Roof Top Equipment

Tape / Bed and Paint

Install Ceiling Grid

OVHD MEP Trim Out

Final Clean

Install Outside Air Riser

OMES Move In

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

OMES (House Employees) Move In

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 15 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 25: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-1890 Install Shaft Walls / Access Panels 4 4 25-Jul-17 28-Jul-17

C-C01-1895 Tape, Bed, Paint 4 4 31-Jul-17 03-Aug-17

C-C01-1900 Re-Install Ceiling Grid & Tile 2 2 04-Aug-17 07-Aug-17

C-C01-1905 Re-Install Floor Finishes 2 2 08-Aug-17 09-Aug-17

C-C01-1910 Test Smoke / Fire Damper 1 1 10-Aug-17 10-Aug-17

C-C01-1915 Remove Temp Walls 2 2 11-Aug-17 14-Aug-17

C-C01-1920 Final Clean 2 2 15-Aug-17 16-Aug-17

NW - Rooms 433, 442 & Mens Restroom Outside AirNW - Rooms 433, 442 & Mens Restroom Outside Air29 29 18-Jul-17 25-Aug-17

C-C01-1935 Saw Cut Floor 1 1 18-Jul-17 18-Jul-17

C-C01-1940 Install Outside Air Riser 5 5 19-Jul-17 25-Jul-17

C-C01-1945 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Jul-17 27-Jul-17

C-C01-1950 Install Smoke / Fire Damper 4 4 28-Jul-17 02-Aug-17

C-C01-1955 Install Shaft Walls / Access Panels 4 4 03-Aug-17 08-Aug-17

C-C01-1960 Tape, Bed, Paint 4 4 09-Aug-17 14-Aug-17

C-C01-1965 Re-Install Ceiling Grid & Tile 2 2 15-Aug-17 16-Aug-17

C-C01-1970 Re-Install Floor Finishes 2 2 17-Aug-17 18-Aug-17

C-C01-1975 Test Smoke / Fire Damper 1 1 21-Aug-17 21-Aug-17

C-C01-1980 Remove Temp Walls 2 2 22-Aug-17 23-Aug-17

C-C01-1985 Final Clean 2 2 24-Aug-17 25-Aug-17

NW - Room 549 Outside AirNW - Room 549 Outside Air33 33 19-Jul-17 01-Sep-17

C-C01-1990 Install Temp Walls 2 2 19-Jul-17 20-Jul-17

C-C01-1995 Demo Walls & Ceilings 3 3 21-Jul-17 25-Jul-17

C-C01-2000 Saw Cut Floor 1 1 26-Jul-17 26-Jul-17

C-C01-2005 Install Outside Air Riser 5 5 27-Jul-17 02-Aug-17

C-C01-2010 Fire Caulk / Seal Floor Penetration @ Riser 2 2 03-Aug-17 04-Aug-17

C-C01-2015 Install Smoke / Fire Damper 3 3 07-Aug-17 09-Aug-17

C-C01-2020 Install Shaft Walls / Access Panels 4 4 10-Aug-17 15-Aug-17

C-C01-2025 Tape, Bed, Paint 4 4 16-Aug-17 21-Aug-17

C-C01-2030 Re-Install Ceiling Grid & Tile 2 2 22-Aug-17 23-Aug-17

C-C01-2035 Re-Install Floor Finishes 2 2 24-Aug-17 25-Aug-17

C-C01-2040 Test Smoke / Fire Damper 1 1 28-Aug-17 28-Aug-17

C-C01-2045 Remove Temp Walls 2 2 29-Aug-17 30-Aug-17

C-C01-2050 Final Clean 2 2 31-Aug-17 01-Sep-17

NW - 6th FloorNW - 6th Floor20 20 27-Jul-17 23-Aug-17

C-C01-2065 Saw Cut Floor 5 5 27-Jul-17 02-Aug-17

C-C01-2070 Install Outside Air Riser 5 5 03-Aug-17 09-Aug-17

C-C01-2075 Fire Caulk / Seal Floor Penetration @ Riser 5 5 10-Aug-17 16-Aug-17

C-C01-2080 Install Smoke / Fire Damper 5 5 17-Aug-17 23-Aug-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 16 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 26: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

NW - RooftopNW - Rooftop87 87 18-Jul-17 16-Nov-17

C-C01-3835 Set Roof Top Curb 7 7 18-Jul-17 26-Jul-17

C-C01-1275 Set Roof Top Equipment (NW) 3 3 24-Aug-17 28-Aug-17

C-C01-1060 Install NW Roof Top Equipment 40 30 22-Sep-17 02-Nov-17

C-C01-1070 Start Up NW Roof Top Equipment 10 10 03-Nov-17 16-Nov-17

North - Rooms 104, 107 & 106 Outside AirNorth - Rooms 104, 107 & 106 Outside Air35 35 29-Aug-17 17-Oct-17

C-C01-2640 Install Temp Walls 2 2 29-Aug-17 30-Aug-17

C-C01-2645 Demo Walls & Ceilings 4 4 31-Aug-17 06-Sep-17

C-C01-2650 Saw Cut Floor 1 1 07-Sep-17 07-Sep-17

C-C01-2655 Install Outside Air Riser 5 5 08-Sep-17 14-Sep-17

C-C01-2660 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Sep-17 18-Sep-17

C-C01-2665 Install Smoke / Fire Damper 4 4 19-Sep-17 22-Sep-17

C-C01-2670 Install Shaft Walls / Access Panels 4 4 25-Sep-17 28-Sep-17

C-C01-2675 Tape, Bed, Paint 4 4 29-Sep-17 04-Oct-17

C-C01-2680 Re-Install Ceiling Grid & Tile 2 2 05-Oct-17 06-Oct-17

C-C01-2685 Re-Install Floor Finishes 2 2 09-Oct-17 10-Oct-17

C-C01-2690 Test Smoke / Fire Damper 1 1 11-Oct-17 11-Oct-17

C-C01-2695 Remove Temp Walls 2 2 12-Oct-17 13-Oct-17

C-C01-2700 Final Clean 2 2 16-Oct-17 17-Oct-17

North - Rooms 230, 237 & 238 Outside AirNorth - Rooms 230, 237 & 238 Outside Air35 35 08-Sep-17 26-Oct-17

C-C01-2705 Install Temp Walls 2 2 08-Sep-17 11-Sep-17

C-C01-2710 Demo Walls & Ceilings 4 4 12-Sep-17 15-Sep-17

C-C01-2715 Saw Cut Floor 1 1 18-Sep-17 18-Sep-17

C-C01-2720 Install Outside Air Riser 5 5 19-Sep-17 25-Sep-17

C-C01-2725 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Sep-17 27-Sep-17

C-C01-2730 Install Smoke / Fire Damper 4 4 28-Sep-17 03-Oct-17

C-C01-2735 Install Shaft Walls / Access Panels 4 4 04-Oct-17 09-Oct-17

C-C01-2740 Tape, Bed, Paint 4 4 10-Oct-17 13-Oct-17

C-C01-2745 Re-Install Ceiling Grid & Tile 2 2 16-Oct-17 17-Oct-17

C-C01-2750 Re-Install Floor Finishes 2 2 18-Oct-17 19-Oct-17

C-C01-2755 Test Smoke / Fire Damper 1 1 20-Oct-17 20-Oct-17

C-C01-2760 Remove Temp Walls 2 2 23-Oct-17 24-Oct-17

C-C01-2765 Final Clean 2 2 25-Oct-17 26-Oct-17

North - Rooms 312, 314 & 312 Corridor Outside AirNorth - Rooms 312, 314 & 312 Corridor Outside Air35 35 19-Sep-17 06-Nov-17

C-C01-2770 Install Temp Walls 2 2 19-Sep-17 20-Sep-17

C-C01-2775 Demo Walls & Ceilings 4 4 21-Sep-17 26-Sep-17

C-C01-2780 Saw Cut Floor 1 1 27-Sep-17 27-Sep-17

C-C01-2785 Install Outside Air Riser 5 5 28-Sep-17 04-Oct-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Set Roof Top Curb

Set Roof Top Equipment (NW)

Install NW Roof Top Equipment

Start Up NW Roof Top Equipment

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 17 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 27: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-2790 Fire Caulk / Seal Floor Penetration @ Riser 2 2 05-Oct-17 06-Oct-17

C-C01-2795 Install Smoke / Fire Damper 4 4 09-Oct-17 12-Oct-17

C-C01-2800 Install Shaft Walls / Access Panels 4 4 13-Oct-17 18-Oct-17

C-C01-2805 Tape, Bed, Paint 4 4 19-Oct-17 24-Oct-17

C-C01-2810 Re-Install Ceiling Grid & Tile 2 2 25-Oct-17 26-Oct-17

C-C01-2815 Re-Install Floor Finishes 2 2 27-Oct-17 30-Oct-17

C-C01-2820 Test Smoke / Fire Damper 1 1 31-Oct-17 31-Oct-17

C-C01-2825 Remove Temp Walls 2 2 01-Nov-17 02-Nov-17

C-C01-2830 Final Clean 2 2 03-Nov-17 06-Nov-17

North - Rooms 432A, 432B, 429 & Snackbar Outside AirNorth - Rooms 432A, 432B, 429 & Snackbar Outside Air47 47 28-Sep-17 05-Dec-17

C-C01-2835 Install Temp Walls 4 4 28-Sep-17 03-Oct-17

C-C01-2840 Demo Walls & Ceilings 5 5 04-Oct-17 10-Oct-17

C-C01-2845 Saw Cut Floor 2 2 11-Oct-17 12-Oct-17

C-C01-2850 Install Outside Air Riser 7 7 13-Oct-17 23-Oct-17

C-C01-2855 Fire Caulk / Seal Floor Penetration @ Riser 3 3 24-Oct-17 26-Oct-17

C-C01-2860 Install Smoke / Fire Damper 5 5 27-Oct-17 02-Nov-17

C-C01-2865 Install Shaft Walls / Access Panels 5 5 03-Nov-17 09-Nov-17

C-C01-2870 Tape, Bed, Paint 5 5 10-Nov-17 16-Nov-17

C-C01-2875 Re-Install Ceiling Grid & Tile 3 3 17-Nov-17 21-Nov-17

C-C01-2880 Re-Install Floor Finishes 3 3 22-Nov-17 28-Nov-17

C-C01-2885 Test Smoke / Fire Damper 1 1 29-Nov-17 29-Nov-17

C-C01-2890 Remove Temp Walls 2 2 30-Nov-17 01-Dec-17

C-C01-2895 Final Clean 2 2 04-Dec-17 05-Dec-17

North - Rooms 533, 535A, 536 & 537 Outside AirNorth - Rooms 533, 535A, 536 & 537 Outside Air47 47 13-Oct-17 20-Dec-17

C-C01-2900 Install Temp Walls 4 4 13-Oct-17 18-Oct-17

C-C01-2905 Demo Walls & Ceilings 5 5 19-Oct-17 25-Oct-17

C-C01-2910 Saw Cut Floor 2 2 26-Oct-17 27-Oct-17

C-C01-2915 Install Outside Air Riser 7 7 30-Oct-17 07-Nov-17

C-C01-2920 Fire Caulk / Seal Floor Penetration @ Riser 3 3 08-Nov-17 10-Nov-17

C-C01-2925 Install Smoke / Fire Damper 5 5 13-Nov-17 17-Nov-17

C-C01-2930 Install Shaft Walls / Access Panels 5 5 20-Nov-17 28-Nov-17

C-C01-2935 Tape, Bed, Paint 5 5 29-Nov-17 05-Dec-17

C-C01-2940 Re-Install Ceiling Grid & Tile 3 3 06-Dec-17 08-Dec-17

C-C01-2945 Re-Install Floor Finishes 3 3 11-Dec-17 13-Dec-17

C-C01-2950 Test Smoke / Fire Damper 1 1 14-Dec-17 14-Dec-17

C-C01-2955 Remove Temp Walls 2 2 15-Dec-17 18-Dec-17

C-C01-2960 Final Clean 2 2 19-Dec-17 20-Dec-17

North - 6th FloorNorth - 6th Floor20 20 30-Oct-17 28-Nov-17

C-C01-2975 Saw Cut Floor 5 5 30-Oct-17 03-Nov-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Saw Cut Floor

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 18 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 28: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-2980 Install Outside Air Riser 5 5 06-Nov-17 10-Nov-17

C-C01-2985 Fire Caulk / Seal Floor Penetration @ Riser 5 5 13-Nov-17 17-Nov-17

C-C01-2990 Install Smoke / Fire Damper 5 5 20-Nov-17 28-Nov-17

South - OMES Storage & Photographer Temp Storage Outside AirSouth - OMES Storage & Photographer Temp Storage Outside Air65 65 06-Nov-17 08-Feb-18

C-C01-3030 Install Temp Walls 5 5 06-Nov-17 10-Nov-17

C-C01-3035 Demo Walls & Ceilings 5 5 13-Nov-17 17-Nov-17

C-C01-3040 Saw Cut Floor 5 5 20-Nov-17 28-Nov-17

C-C01-3045 Install Outside Air Riser 5 5 29-Nov-17 05-Dec-17

C-C01-3050 Fire Caulk / Seal Floor Penetration @ Riser 5 5 06-Dec-17 12-Dec-17

C-C01-3055 Install Smoke / Fire Damper 5 5 13-Dec-17 19-Dec-17

C-C01-3060 Install Shaft Walls / Access Panels 5 5 20-Dec-17 27-Dec-17

C-C01-3065 Tape, Bed, Paint 5 5 28-Dec-17 04-Jan-18

C-C01-3070 Re-Install Ceiling Grid & Tile 5 5 05-Jan-18 11-Jan-18

C-C01-3075 Re-Install Floor Finishes 5 5 12-Jan-18 18-Jan-18

C-C01-3080 Test Smoke / Fire Damper 5 5 19-Jan-18 25-Jan-18

C-C01-3085 Remove Temp Walls 5 5 26-Jan-18 01-Feb-18

C-C01-3090 Final Clean 5 5 02-Feb-18 08-Feb-18

South - Hall of Gov & Lt Governor Reception Outside AirSouth - Hall of Gov & Lt Governor Reception Outside Air42 42 29-Nov-17 29-Jan-18

C-C01-3850 Install Scaffold 5 5 29-Nov-17 05-Dec-17

C-C01-3095 Install Temp Walls 2 2 06-Dec-17 07-Dec-17

C-C01-3100 Demo Walls & Ceilings 4 4 08-Dec-17 13-Dec-17

C-C01-3105 Saw Cut Floor 1 1 14-Dec-17 14-Dec-17

C-C01-3110 Install Outside Air Riser 5 5 15-Dec-17 21-Dec-17

C-C01-3115 Fire Caulk / Seal Floor Penetration @ Riser 2 2 22-Dec-17 26-Dec-17

C-C01-3120 Install Smoke / Fire Damper 4 4 27-Dec-17 02-Jan-18

C-C01-3125 Install Shaft Walls / Access Panels 4 4 03-Jan-18 08-Jan-18

C-C01-3130 Tape, Bed, Paint 4 4 09-Jan-18 12-Jan-18

C-C01-3135 Re-Install Ceiling Grid & Tile 2 2 15-Jan-18 16-Jan-18

C-C01-3140 Re-Install Floor Finishes 2 2 17-Jan-18 18-Jan-18

C-C01-3145 Test Smoke / Fire Damper 1 1 19-Jan-18 19-Jan-18

C-C01-3150 Remove Temp Walls 2 2 22-Jan-18 23-Jan-18

C-C01-3855 Remove Scaffold 2 2 24-Jan-18 25-Jan-18

C-C01-3155 Final Clean 2 2 26-Jan-18 29-Jan-18

South - Rotunda 4th & 5th FloorOutside AirSouth - Rotunda 4th & 5th FloorOutside Air55 55 15-Dec-17 05-Mar-18

C-C01-3860 Install Scaffold 5 5 15-Dec-17 21-Dec-17

C-C01-3160 Install Temp Walls 4 4 22-Dec-17 28-Dec-17

C-C01-3165 Demo Walls & Ceilings 5 5 29-Dec-17 05-Jan-18

C-C01-3170 Saw Cut Floor 2 2 08-Jan-18 09-Jan-18

C-C01-3175 Install Outside Air Riser 7 7 10-Jan-18 18-Jan-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Scaffold

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Remove Scaffold

Final Clean

Install Scaffold

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 19 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 29: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-3180 Fire Caulk / Seal Floor Penetration @ Riser 3 3 19-Jan-18 23-Jan-18

C-C01-3185 Install Smoke / Fire Damper 5 5 24-Jan-18 30-Jan-18

C-C01-3190 Install Shaft Walls / Access Panels 5 5 31-Jan-18 06-Feb-18

C-C01-3195 Tape, Bed, Paint 5 5 07-Feb-18 13-Feb-18

C-C01-3200 Re-Install Ceiling Grid & Tile 3 3 14-Feb-18 16-Feb-18

C-C01-3205 Re-Install Floor Finishes 3 3 19-Feb-18 21-Feb-18

C-C01-3210 Test Smoke / Fire Damper 1 1 22-Feb-18 22-Feb-18

C-C01-3215 Remove Temp Walls 2 2 23-Feb-18 26-Feb-18

C-C01-3225 Remove Scaffold 3 3 27-Feb-18 01-Mar-18

C-C01-3220 Final Clean 2 2 02-Mar-18 05-Mar-18

South - 6th Floor Outside AirSouth - 6th Floor Outside Air20 20 10-Jan-18 06-Feb-18

C-C01-3235 Saw Cut Floor 5 5 10-Jan-18 16-Jan-18

C-C01-3240 Install Outside Air Riser 5 5 17-Jan-18 23-Jan-18

C-C01-3245 Fire Caulk / Seal Floor Penetration @ Riser 5 5 24-Jan-18 30-Jan-18

C-C01-3250 Install Smoke / Fire Damper 5 5 31-Jan-18 06-Feb-18

NE - Secretary of State - (Copy Room & Reception) Outside AirNE - Secretary of State - (Copy Room & Reception) Outside Air36 36 17-Jan-18 07-Mar-18

C-C01-3290 Install Temp Walls 2 2 17-Jan-18 18-Jan-18

C-C01-3295 Demo Walls & Ceilings 3 3 19-Jan-18 23-Jan-18

C-C01-3300 Saw Cut Floor 1 1 24-Jan-18 24-Jan-18

C-C01-3305 Install Outside Air Riser 5 5 25-Jan-18 31-Jan-18

C-C01-3310 Fire Caulk / Seal Floor Penetration @ Riser 2 2 01-Feb-18 02-Feb-18

C-C01-3315 Install Smoke / Fire Damper 3 3 05-Feb-18 07-Feb-18

C-C01-3320 Install Shaft Walls / Access Panels 5 5 08-Feb-18 14-Feb-18

C-C01-3325 Tape, Bed, Paint 5 5 15-Feb-18 21-Feb-18

C-C01-3330 Re-Install Ceiling Grid & Tile 3 3 22-Feb-18 26-Feb-18

C-C01-3335 Re-Install Floor Finishes 2 2 27-Feb-18 28-Feb-18

C-C01-3340 Test Smoke / Fire Damper 1 1 01-Mar-18 01-Mar-18

C-C01-3345 Remove Temp Walls 2 2 02-Mar-18 05-Mar-18

C-C01-3350 Final Clean 2 2 06-Mar-18 07-Mar-18

NE - Treasurers Office (Charlie Hover) Outside AirNE - Treasurers Office (Charlie Hover) Outside Air40 40 25-Jan-18 21-Mar-18

C-C01-3355 Install Temp Walls 2 2 25-Jan-18 26-Jan-18

C-C01-3360 Demo Walls & Ceilings 3 3 29-Jan-18 31-Jan-18

C-C01-3365 Saw Cut Floor 1 1 01-Feb-18 01-Feb-18

C-C01-3370 Install Outside Air Riser 5 5 02-Feb-18 08-Feb-18

C-C01-3375 Fire Caulk / Seal Floor Penetration @ Riser 2 2 09-Feb-18 12-Feb-18

C-C01-3380 Install Smoke / Fire Damper 3 3 13-Feb-18 15-Feb-18

C-C01-3385 Install Shaft Walls / Access Panels 5 5 16-Feb-18 22-Feb-18

C-C01-3390 Tape, Bed, Paint 5 5 23-Feb-18 01-Mar-18

C-C01-3395 Re-Install Ceiling Grid & Tile 3 3 02-Mar-18 06-Mar-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Remove Scaffold

Final Clean

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 20 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 30: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-3400 Re-Install Floor Finishes 2 2 07-Mar-18 08-Mar-18

C-C01-3405 Test Smoke / Fire Damper 1 5 09-Mar-18 15-Mar-18

C-C01-3410 Remove Temp Walls 2 2 16-Mar-18 19-Mar-18

C-C01-3415 Final Clean 2 2 20-Mar-18 21-Mar-18

NE - Room 309.1B Outside AirNE - Room 309.1B Outside Air36 36 02-Feb-18 23-Mar-18

C-C01-3420 Install Temp Walls 2 2 02-Feb-18 05-Feb-18

C-C01-3425 Demo Walls & Ceilings 3 3 06-Feb-18 08-Feb-18

C-C01-3430 Saw Cut Floor 1 1 09-Feb-18 09-Feb-18

C-C01-3435 Install Outside Air Riser 5 5 12-Feb-18 16-Feb-18

C-C01-3440 Fire Caulk / Seal Floor Penetration @ Riser 2 2 19-Feb-18 20-Feb-18

C-C01-3445 Install Smoke / Fire Damper 3 3 21-Feb-18 23-Feb-18

C-C01-3450 Install Shaft Walls / Access Panels 5 5 26-Feb-18 02-Mar-18

C-C01-3455 Tape, Bed, Paint 5 5 05-Mar-18 09-Mar-18

C-C01-3460 Re-Install Ceiling Grid & Tile 3 3 12-Mar-18 14-Mar-18

C-C01-3465 Re-Install Floor Finishes 2 2 15-Mar-18 16-Mar-18

C-C01-3470 Test Smoke / Fire Damper 1 1 19-Mar-18 19-Mar-18

C-C01-3475 Remove Temp Walls 2 2 20-Mar-18 21-Mar-18

C-C01-3480 Final Clean 2 2 22-Mar-18 23-Mar-18

NE - 4th Floor Outside AirNE - 4th Floor Outside Air21 21 01-Jun-18 29-Jun-18

C-C01-3490 Demo Walls & Ceilings 4 4 01-Jun-18 06-Jun-18

C-C01-3495 Saw Cut Floor 1 1 07-Jun-18 07-Jun-18

C-C01-3500 Install Outside Air Riser 5 5 08-Jun-18 14-Jun-18

C-C01-3505 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Jun-18 18-Jun-18

C-C01-3510 Install Smoke / Fire Damper 4 4 19-Jun-18 22-Jun-18

C-C01-3515 Install Shaft Walls / Access Panels 4 4 25-Jun-18 28-Jun-18

C-C01-3535 Test Smoke / Fire Damper 1 1 29-Jun-18 29-Jun-18

NE - 5th Floor Outside AirNE - 5th Floor Outside Air35 35 08-Jun-18 27-Jul-18

C-C01-3550 Install Temp Walls 2 2 08-Jun-18 11-Jun-18

C-C01-3555 Demo Walls & Ceilings 4 4 12-Jun-18 15-Jun-18

C-C01-3560 Saw Cut Floor 1 1 18-Jun-18 18-Jun-18

C-C01-3800 Lay Out Steel 1 1 18-Jun-18 18-Jun-18

C-C01-3805 Install Steel 5 5 18-Jun-18 22-Jun-18

C-C01-3565 Install Outside Air Riser 5 5 19-Jun-18 25-Jun-18

C-C01-3570 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Jun-18 27-Jun-18

C-C01-3575 Install Smoke / Fire Damper 4 4 28-Jun-18 03-Jul-18

C-C01-3580 Install Shaft Walls / Access Panels 4 4 05-Jul-18 10-Jul-18

C-C01-3585 Tape, Bed, Paint 4 4 11-Jul-18 16-Jul-18

C-C01-3590 Re-Install Ceiling Grid & Tile 2 2 17-Jul-18 18-Jul-18

C-C01-3595 Re-Install Floor Finishes 2 2 19-Jul-18 20-Jul-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Test Smoke / Fire Damper

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Lay Out Steel

Install Steel

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 21 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 31: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-3600 Test Smoke / Fire Damper 1 1 23-Jul-18 23-Jul-18

C-C01-3605 Remove Temp Walls 2 2 24-Jul-18 25-Jul-18

C-C01-3610 Final Clean 2 2 26-Jul-18 27-Jul-18

NE - 6th FloorNE - 6th Floor20 20 19-Jun-18 17-Jul-18

C-C01-3625 Saw Cut Floor 5 5 19-Jun-18 25-Jun-18

C-C01-3630 Install Outside Air Riser 5 5 26-Jun-18 02-Jul-18

C-C01-3635 Fire Caulk / Seal Floor Penetration @ Riser 5 5 03-Jul-18 10-Jul-18

C-C01-3640 Install Smoke / Fire Damper 5 5 11-Jul-18 17-Jul-18

NE - RooftopNE - Rooftop60 60 25-Jun-18 18-Sep-18

C-C01-3840 Set Roof Top Curb 7 7 25-Jun-18 03-Jul-18

C-C01-3825 Set Roof Top Equipment (NE) 3 3 05-Jul-18 09-Jul-18

C-C01-1090 Install NE Roof Top Equipment 40 40 10-Jul-18 04-Sep-18

C-C01-1100 Start Up NE Roof Top Equipment 10 10 05-Sep-18 18-Sep-18

SE - 122 Break Room & 121 Cubicles North Outside AirSE - 122 Break Room & 121 Cubicles North Outside Air35 35 17-Jan-18 06-Mar-18

C-C01-2120 Install Temp Walls 2 2 17-Jan-18 18-Jan-18

C-C01-2125 Demo Walls & Ceilings 4 4 19-Jan-18 24-Jan-18

C-C01-2130 Saw Cut Floor 1 1 25-Jan-18 25-Jan-18

C-C01-2135 Install Outside Air Riser 5 5 26-Jan-18 01-Feb-18

C-C01-2140 Fire Caulk / Seal Floor Penetration @ Riser 2 2 02-Feb-18 05-Feb-18

C-C01-2145 Install Smoke / Fire Damper 4 4 06-Feb-18 09-Feb-18

C-C01-2150 Install Shaft Walls / Access Panels 4 4 12-Feb-18 15-Feb-18

C-C01-2155 Tape, Bed, Paint 4 4 16-Feb-18 21-Feb-18

C-C01-2160 Re-Install Ceiling Grid & Tile 2 2 22-Feb-18 23-Feb-18

C-C01-2165 Re-Install Floor Finishes 2 2 26-Feb-18 27-Feb-18

C-C01-2170 Test Smoke / Fire Damper 1 1 28-Feb-18 28-Feb-18

C-C01-2175 Remove Temp Walls 2 2 01-Mar-18 02-Mar-18

C-C01-2180 Final Clean 2 2 05-Mar-18 06-Mar-18

SE - Governors Waiting, Travis & Gary, Blue Room Outside AirSE - Governors Waiting, Travis & Gary, Blue Room Outside Air47 47 26-Jan-18 02-Apr-18

C-C01-2185 Install Temp Walls 4 4 26-Jan-18 31-Jan-18

C-C01-2190 Demo Walls & Ceilings 5 5 01-Feb-18 07-Feb-18

C-C01-2195 Saw Cut Floor 2 2 08-Feb-18 09-Feb-18

C-C01-2200 Install Outside Air Riser 7 7 12-Feb-18 20-Feb-18

C-C01-2205 Fire Caulk / Seal Floor Penetration @ Riser 3 3 21-Feb-18 23-Feb-18

C-C01-2210 Install Smoke / Fire Damper 5 5 26-Feb-18 02-Mar-18

C-C01-2215 Install Shaft Walls / Access Panels 5 5 05-Mar-18 09-Mar-18

C-C01-2220 Tape, Bed, Paint 5 5 12-Mar-18 16-Mar-18

C-C01-2225 Re-Install Ceiling Grid & Tile 3 3 19-Mar-18 21-Mar-18

C-C01-2230 Re-Install Floor Finishes 3 3 22-Mar-18 26-Mar-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Set Roof Top Curb

Set Roof Top Equipment (NE)

Install NE Roof Top Equipment

Start Up NE Roof Top Equipment

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 22 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 32: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-2235 Test Smoke / Fire Damper 1 1 27-Mar-18 27-Mar-18

C-C01-2240 Remove Temp Walls 2 2 28-Mar-18 29-Mar-18

C-C01-2245 Final Clean 2 2 30-Mar-18 02-Apr-18

SE - Rooms 309.36 & 309 Middle Corridor Outside AirSE - Rooms 309.36 & 309 Middle Corridor Outside Air35 35 12-Feb-18 30-Mar-18

C-C01-2380 Install Temp Walls 2 2 12-Feb-18 13-Feb-18

C-C01-2385 Demo Walls & Ceilings 4 4 14-Feb-18 19-Feb-18

C-C01-2390 Saw Cut Floor 1 1 20-Feb-18 20-Feb-18

C-C01-2395 Install Outside Air Riser 5 5 21-Feb-18 27-Feb-18

C-C01-2400 Fire Caulk / Seal Floor Penetration @ Riser 2 2 28-Feb-18 01-Mar-18

C-C01-2405 Install Smoke / Fire Damper 4 4 02-Mar-18 07-Mar-18

C-C01-2410 Install Shaft Walls / Access Panels 4 4 08-Mar-18 13-Mar-18

C-C01-2415 Tape, Bed, Paint 4 4 14-Mar-18 19-Mar-18

C-C01-2420 Re-Install Ceiling Grid & Tile 2 2 20-Mar-18 21-Mar-18

C-C01-2425 Re-Install Floor Finishes 2 2 22-Mar-18 23-Mar-18

C-C01-2430 Test Smoke / Fire Damper 1 1 26-Mar-18 26-Mar-18

C-C01-2435 Remove Temp Walls 2 2 27-Mar-18 28-Mar-18

C-C01-2440 Final Clean 2 2 29-Mar-18 30-Mar-18

SE - 4th Floor Outside AirSE - 4th Floor Outside Air21 21 01-Jun-18 29-Jun-18

C-C01-2450 Demo Walls & Ceilings 4 4 01-Jun-18 06-Jun-18

C-C01-2455 Saw Cut Floor 1 1 07-Jun-18 07-Jun-18

C-C01-2460 Install Outside Air Riser 5 5 08-Jun-18 14-Jun-18

C-C01-2465 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Jun-18 18-Jun-18

C-C01-2470 Install Smoke / Fire Damper 4 4 19-Jun-18 22-Jun-18

C-C01-2475 Install Shaft Walls / Access Panels 4 4 25-Jun-18 28-Jun-18

C-C01-2495 Test Smoke / Fire Damper 1 1 29-Jun-18 29-Jun-18

SE - 5th Floor Outside AirSE - 5th Floor Outside Air35 35 08-Jun-18 27-Jul-18

C-C01-2510 Install Temp Walls 2 2 08-Jun-18 11-Jun-18

C-C01-2515 Demo Walls & Ceilings 4 4 12-Jun-18 15-Jun-18

C-C01-2520 Saw Cut Floor 1 1 18-Jun-18 18-Jun-18

C-C01-3815 Lay Out Steel 1 1 18-Jun-18 18-Jun-18

C-C01-3820 Install Steel 5 5 18-Jun-18 22-Jun-18

C-C01-2525 Install Outside Air Riser 5 5 19-Jun-18 25-Jun-18

C-C01-2530 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Jun-18 27-Jun-18

C-C01-2535 Install Smoke / Fire Damper 4 4 28-Jun-18 03-Jul-18

C-C01-2540 Install Shaft Walls / Access Panels 4 4 05-Jul-18 10-Jul-18

C-C01-2545 Tape, Bed, Paint 4 4 11-Jul-18 16-Jul-18

C-C01-2550 Re-Install Ceiling Grid & Tile 2 2 17-Jul-18 18-Jul-18

C-C01-2555 Re-Install Floor Finishes 2 2 19-Jul-18 20-Jul-18

C-C01-2560 Test Smoke / Fire Damper 1 1 23-Jul-18 23-Jul-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Remove Temp Walls

Final Clean

Demo Walls & Ceilings

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Test Smoke / Fire Damper

Install Temp Walls

Demo Walls & Ceilings

Saw Cut Floor

Lay Out Steel

Install Steel

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Install Shaft Walls / Access Panels

Tape, Bed, Paint

Re-Install Ceiling Grid & Tile

Re-Install Floor Finishes

Test Smoke / Fire Damper

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 23 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 33: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-2565 Remove Temp Walls 2 2 24-Jul-18 25-Jul-18

C-C01-2570 Final Clean 2 2 26-Jul-18 27-Jul-18

SE - 6th Floor Outside AirSE - 6th Floor Outside Air20 20 19-Jun-18 17-Jul-18

C-C01-2585 Saw Cut Floor 5 5 19-Jun-18 25-Jun-18

C-C01-2590 Install Outside Air Riser 5 5 26-Jun-18 02-Jul-18

C-C01-2595 Fire Caulk / Seal Floor Penetration @ Riser 5 5 03-Jul-18 10-Jul-18

C-C01-2600 Install Smoke / Fire Damper 5 5 11-Jul-18 17-Jul-18

SE - RooftopSE - Rooftop100 100 25-Jun-18 13-Nov-18

C-C01-3845 Set Roof Top Curb 5 5 25-Jun-18 29-Jun-18

C-C01-3830 Set Roof Top Equipment (SE) 3 3 10-Jul-18 12-Jul-18

C-C01-1110 Install SE Roof Top Equipment 40 40 05-Sep-18 30-Oct-18

C-C01-1120 Start Up SE Roof Top Equipment 10 10 31-Oct-18 13-Nov-18

SW - Rooms 404 & 408 CondensateSW - Rooms 404 & 408 Condensate5 4 17-Jul-17 A 21-Jul-17

C-C01-3955 Patch Walls as Required 3 2 17-Jul-17 A 19-Jul-17

C-C01-3960 Re-Install Ceiling 1 1 20-Jul-17 20-Jul-17

C-C01-3965 Remove Temp Walls 1 1 21-Jul-17 21-Jul-17

SW - Rooms 507 & 503 CondensateSW - Rooms 507 & 503 Condensate11 11 24-Jul-17 07-Aug-17

C-C01-3970 Install Temp Walls 2 2 24-Jul-17 25-Jul-17

C-C01-3975 Demo Walls / Ceilings 2 2 26-Jul-17 27-Jul-17

C-C01-3980 Core Drill 1 1 28-Jul-17 28-Jul-17

C-C01-3985 Install Condensate Drain 1 1 31-Jul-17 31-Jul-17

C-C01-3990 Patch Walls as Required 3 3 01-Aug-17 03-Aug-17

C-C01-3995 Re-Install Ceiling 1 1 04-Aug-17 04-Aug-17

C-C01-4000 Remove Temp Walls 1 1 07-Aug-17 07-Aug-17

NW - Room 109.20 CondensateNW - Room 109.20 Condensate11 11 08-Aug-17 22-Aug-17

C-C01-4005 Install Temp Walls 2 2 08-Aug-17 09-Aug-17

C-C01-4010 Demo Walls / Ceilings 2 2 10-Aug-17 11-Aug-17

C-C01-4015 Core Drill 1 1 14-Aug-17 14-Aug-17

C-C01-4020 Install Condensate Drain 1 1 15-Aug-17 15-Aug-17

C-C01-4025 Patch Walls as Required 3 3 16-Aug-17 18-Aug-17

C-C01-4030 Re-Install Ceiling 1 1 21-Aug-17 21-Aug-17

C-C01-4035 Remove Temp Walls 1 1 22-Aug-17 22-Aug-17

North - LSB West Wall of Server Closet CondensateNorth - LSB West Wall of Server Closet Condensate11 11 29-Aug-17 13-Sep-17

C-C01-4040 Install Temp Walls 2 2 29-Aug-17 30-Aug-17

C-C01-4045 Demo Walls / Ceilings 2 2 31-Aug-17 01-Sep-17

C-C01-4050 Core Drill 1 1 05-Sep-17 05-Sep-17

C-C01-4055 Install Condensate Drain 1 1 06-Sep-17 06-Sep-17

C-C01-4060 Patch Walls as Required 3 3 07-Sep-17 11-Sep-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Remove Temp Walls

Final Clean

Saw Cut Floor

Install Outside Air Riser

Fire Caulk / Seal Floor Penetration @ Riser

Install Smoke / Fire Damper

Set Roof Top Curb

Set Roof Top Equipment (SE)

Install SE Roof Top Equipment

Start Up SE Roof Top Equipment

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 24 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 34: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-4065 Re-Install Ceiling 1 1 12-Sep-17 12-Sep-17

C-C01-4070 Remove Temp Walls 1 1 13-Sep-17 13-Sep-17

North - Rooms 322 & 323 CondensateNorth - Rooms 322 & 323 Condensate11 11 14-Sep-17 28-Sep-17

C-C01-4075 Install Temp Walls 2 2 14-Sep-17 15-Sep-17

C-C01-4080 Demo Walls / Ceilings 2 2 18-Sep-17 19-Sep-17

C-C01-4085 Core Drill 1 1 20-Sep-17 20-Sep-17

C-C01-4090 Install Condensate Drain 1 1 21-Sep-17 21-Sep-17

C-C01-4095 Patch Walls as Required 3 3 22-Sep-17 26-Sep-17

C-C01-4100 Re-Install Ceiling 1 1 27-Sep-17 27-Sep-17

C-C01-4105 Remove Temp Walls 1 1 28-Sep-17 28-Sep-17

North 430 East Closet CondensateNorth 430 East Closet Condensate11 11 29-Sep-17 13-Oct-17

C-C01-4110 Install Temp Walls 2 2 29-Sep-17 02-Oct-17

C-C01-4115 Demo Walls / Ceilings 2 2 03-Oct-17 04-Oct-17

C-C01-4120 Core Drill 1 1 05-Oct-17 05-Oct-17

C-C01-4125 Install Condensate Drain 1 1 06-Oct-17 06-Oct-17

C-C01-4130 Patch Walls as Required 3 3 09-Oct-17 11-Oct-17

C-C01-4135 Re-Install Ceiling 1 1 12-Oct-17 12-Oct-17

C-C01-4140 Remove Temp Walls 1 1 13-Oct-17 13-Oct-17

South - Gift Shop Front Lobby CondensateSouth - Gift Shop Front Lobby Condensate11 11 06-Nov-17 20-Nov-17

C-C01-4145 Install Temp Walls 2 2 06-Nov-17 07-Nov-17

C-C01-4150 Demo Walls / Ceilings 2 2 08-Nov-17 09-Nov-17

C-C01-4155 Core Drill 1 1 10-Nov-17 10-Nov-17

C-C01-4160 Install Condensate Drain 1 1 13-Nov-17 13-Nov-17

C-C01-4165 Patch Walls as Required 3 3 14-Nov-17 16-Nov-17

C-C01-4170 Re-Install Ceiling 1 1 17-Nov-17 17-Nov-17

C-C01-4175 Remove Temp Walls 1 1 20-Nov-17 20-Nov-17

NE - 100 NE Breakroom CondensateNE - 100 NE Breakroom Condensate11 11 17-Jan-18 31-Jan-18

C-C01-4180 Install Temp Walls 2 2 17-Jan-18 18-Jan-18

C-C01-4185 Demo Walls / Ceilings 2 2 19-Jan-18 22-Jan-18

C-C01-4190 Core Drill 1 1 23-Jan-18 23-Jan-18

C-C01-4195 Install Condensate Drain 1 1 24-Jan-18 24-Jan-18

C-C01-4200 Patch Walls as Required 3 3 25-Jan-18 29-Jan-18

C-C01-4205 Re-Install Ceiling 1 1 30-Jan-18 30-Jan-18

C-C01-4210 Remove Temp Walls 1 1 31-Jan-18 31-Jan-18

NE - Cashier 1 East Column & Room 218 CondensateNE - Cashier 1 East Column & Room 218 Condensate11 11 01-Feb-18 15-Feb-18

C-C01-4215 Install Temp Walls 2 2 01-Feb-18 02-Feb-18

C-C01-4220 Demo Walls / Ceilings 2 2 05-Feb-18 06-Feb-18

C-C01-4225 Core Drill 1 1 07-Feb-18 07-Feb-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 25 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 35: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-4230 Install Condensate Drain 1 1 08-Feb-18 08-Feb-18

C-C01-4235 Patch Walls as Required 3 3 09-Feb-18 13-Feb-18

C-C01-4240 Re-Install Ceiling 1 1 14-Feb-18 14-Feb-18

C-C01-4245 Remove Temp Walls 1 1 15-Feb-18 15-Feb-18

NE - Rooms 309.2C & 309.6 CondensateNE - Rooms 309.2C & 309.6 Condensate11 11 16-Feb-18 02-Mar-18

C-C01-4250 Install Temp Walls 2 2 16-Feb-18 19-Feb-18

C-C01-4255 Demo Walls / Ceilings 2 2 20-Feb-18 21-Feb-18

C-C01-4260 Core Drill 1 1 22-Feb-18 22-Feb-18

C-C01-4265 Install Condensate Drain 1 1 23-Feb-18 23-Feb-18

C-C01-4270 Patch Walls as Required 3 3 26-Feb-18 28-Feb-18

C-C01-4275 Re-Install Ceiling 1 1 01-Mar-18 01-Mar-18

C-C01-4280 Remove Temp Walls 1 1 02-Mar-18 02-Mar-18

NE - Rooms 423A & 425 CondensateNE - Rooms 423A & 425 Condensate11 11 05-Mar-18 19-Mar-18

C-C01-4285 Install Temp Walls 2 2 05-Mar-18 06-Mar-18

C-C01-4290 Demo Walls / Ceilings 2 2 07-Mar-18 08-Mar-18

C-C01-4295 Core Drill 1 1 09-Mar-18 09-Mar-18

C-C01-4300 Install Condensate Drain 1 1 12-Mar-18 12-Mar-18

C-C01-4305 Patch Walls as Required 3 3 13-Mar-18 15-Mar-18

C-C01-4310 Re-Install Ceiling 1 1 16-Mar-18 16-Mar-18

C-C01-4315 Remove Temp Walls 1 1 19-Mar-18 19-Mar-18

NE - Rooms 528 & 527B CondensateNE - Rooms 528 & 527B Condensate11 11 20-Mar-18 03-Apr-18

C-C01-4320 Install Temp Walls 2 2 20-Mar-18 21-Mar-18

C-C01-4325 Demo Walls / Ceilings 2 2 22-Mar-18 23-Mar-18

C-C01-4330 Core Drill 1 1 26-Mar-18 26-Mar-18

C-C01-4335 Install Condensate Drain 1 1 27-Mar-18 27-Mar-18

C-C01-4340 Patch Walls as Required 3 3 28-Mar-18 30-Mar-18

C-C01-4345 Re-Install Ceiling 1 1 02-Apr-18 02-Apr-18

C-C01-4350 Remove Temp Walls 1 1 03-Apr-18 03-Apr-18

SE - Governors Waiting & Restroom CondensateSE - Governors Waiting & Restroom Condensate11 11 17-Jan-18 31-Jan-18

C-C01-4355 Install Temp Walls 2 2 17-Jan-18 18-Jan-18

C-C01-4360 Demo Walls / Ceilings 2 2 19-Jan-18 22-Jan-18

C-C01-4365 Core Drill 1 1 23-Jan-18 23-Jan-18

C-C01-4370 Install Condensate Drain 1 1 24-Jan-18 24-Jan-18

C-C01-4375 Patch Walls as Required 3 3 25-Jan-18 29-Jan-18

C-C01-4380 Re-Install Ceiling 1 1 30-Jan-18 30-Jan-18

C-C01-4385 Remove Temp Walls 1 1 31-Jan-18 31-Jan-18

SE - Rooms 309.28 & 309.23E CondensateSE - Rooms 309.28 & 309.23E Condensate11 11 01-Feb-18 15-Feb-18

C-C01-4390 Install Temp Walls 2 2 01-Feb-18 02-Feb-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 26 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 36: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-C01-4395 Demo Walls / Ceilings 2 2 05-Feb-18 06-Feb-18

C-C01-4400 Core Drill 1 1 07-Feb-18 07-Feb-18

C-C01-4405 Install Condensate Drain 1 1 08-Feb-18 08-Feb-18

C-C01-4410 Patch Walls as Required 3 3 09-Feb-18 13-Feb-18

C-C01-4415 Re-Install Ceiling 1 1 14-Feb-18 14-Feb-18

C-C01-4420 Remove Temp Walls 1 1 15-Feb-18 15-Feb-18

SE - Rooms 418 & 414 CondensateSE - Rooms 418 & 414 Condensate11 11 16-Feb-18 02-Mar-18

C-C01-4425 Install Temp Walls 2 2 16-Feb-18 19-Feb-18

C-C01-4430 Demo Walls / Ceilings 2 2 20-Feb-18 21-Feb-18

C-C01-4435 Core Drill 1 1 22-Feb-18 22-Feb-18

C-C01-4440 Install Condensate Drain 1 1 23-Feb-18 23-Feb-18

C-C01-4445 Patch Walls as Required 3 3 26-Feb-18 28-Feb-18

C-C01-4450 Re-Install Ceiling 1 1 01-Mar-18 01-Mar-18

C-C01-4455 Remove Temp Walls 1 1 02-Mar-18 02-Mar-18

SE - Rooms 522B & 520 CondensateSE - Rooms 522B & 520 Condensate11 11 05-Mar-18 19-Mar-18

C-C01-4460 Install Temp Walls 2 2 05-Mar-18 06-Mar-18

C-C01-4465 Demo Walls / Ceilings 2 2 07-Mar-18 08-Mar-18

C-C01-4470 Core Drill 1 1 09-Mar-18 09-Mar-18

C-C01-4475 Install Condensate Drain 1 1 12-Mar-18 12-Mar-18

C-C01-4480 Patch Walls as Required 3 3 13-Mar-18 15-Mar-18

C-C01-4485 Re-Install Ceiling 1 1 16-Mar-18 16-Mar-18

C-C01-4490 Remove Temp Walls 1 1 19-Mar-18 19-Mar-18

Attic SpaceAttic Space700 700 01-Jul-18 30-May-20

ConstructionConstruction700 700 01-Jul-18 30-May-20

Construction Phase SummariesConstruction Phase Summaries700 700 01-Jul-18 30-May-20

S-C02-1000 Construction - Attic Space 700 700 01-Jul-18* 30-May-20

Stairs / Public RestroomsStairs / Public Restrooms730 730 01-Jan-19 30-Dec-20

ConstructionConstruction730 730 01-Jan-19 30-Dec-20

Construction Phase SummariesConstruction Phase Summaries730 730 01-Jan-19 30-Dec-20

S-C03-1000 Construction - Stairs / Public Restrooms 730 730 01-Jan-19* 30-Dec-20

RotundaRotunda1095 1095 01-Jan-20 30-Dec-22

ConstructionConstruction1095 1095 01-Jan-20 30-Dec-22

Construction Phase SummariesConstruction Phase Summaries1095 1095 01-Jan-20 30-Dec-22

S-C04-1000 Construction - Rotunda 1095 1095 01-Jan-20* 30-Dec-22

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Install Temp Walls

Demo Walls / Ceilings

Core Drill

Install Condensate Drain

Patch Walls as Required

Re-Install Ceiling

Remove Temp Walls

Construction - Attic Space

Construction - Stairs / Public Restrooms

Construction - Rotund

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 27 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 37: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

Hole in FloorHole in Floor364 364 01-Jun-20 30-May-21

ConstructionConstruction364 364 01-Jun-20 30-May-21

Construction Phase SummariesConstruction Phase Summaries364 364 01-Jun-20 30-May-21

S-C05-1000 Construction - Hole in Floor 364 364 01-Jun-20* 30-May-21

Visitor's EntranceVisitor's Entrance1479 1479 18-Jul-17 04-Aug-21

ConstructionConstruction1479 1479 18-Jul-17 04-Aug-21

Construction Phase SummariesConstruction Phase Summaries1479 1479 18-Jul-17 04-Aug-21

S-C06-0900 Construction - By Others 930 930 18-Jul-17* 02-Feb-20

S-C06-1000 Construction - Visitor Entrance 549 549 03-Feb-20* 04-Aug-21

TenantsTenants1245 1196 20-Apr-17 A 02-Apr-22

1st Floor Secretary of State1st Floor Secretary of State177 128 20-Apr-17 A 18-Jan-18

Material ProcurementMaterial Procurement88 69 17-Jul-17 A 23-Oct-17

Floor CoveringFloor Covering87 69 17-Jul-17 A 23-Oct-17

P-T01-1135 Flooring Contracting & Submittal Prep 10 9 17-Jul-17 A 28-Jul-17

P-T01-1140 MCC Receive / Review Submittal - Flooring 10 10 31-Jul-17 11-Aug-17

P-T01-1145 AE2 (FSB) Receive / Review Submittal - Flooring 10 10 14-Aug-17 25-Aug-17

P-T01-1150 Fab & Deliver - Marble Tile 15 15 28-Aug-17 18-Sep-17

P-T01-1155 Fab & Deliver - Carpet 40 40 28-Aug-17 23-Oct-17

Doors / HardwareDoors / Hardware78 59 17-Jul-17 A 09-Oct-17

P-T01-1110 MCC Receive / Review Submittal - Doors & Hardware 10 9 17-Jul-17 A 28-Jul-17

P-T01-1115 AE2 (FSB) Receive / Review Submittal - Doors & Hardware 10 10 31-Jul-17 11-Aug-17

P-T01-1120 Fab & Deliver - Door Frames 15 15 14-Aug-17 01-Sep-17

P-T01-1125 Fab & Deliver - Doors & Hardware 40 40 14-Aug-17 09-Oct-17

MillworkMillwork40 40 18-Jul-17 12-Sep-17

P-T01-1070 MCC Receive / Review Submittal - MIllwork 10 10 18-Jul-17 31-Jul-17

P-T01-1075 AE2 (FSB) Receive / Review Submittal - MIllwork 10 10 01-Aug-17 14-Aug-17

P-T01-1090 Fab & Deliver - Base / Case / Crown 5 5 15-Aug-17 21-Aug-17

P-T01-1080 Fab & Deliver - MIllwork 20 20 15-Aug-17 12-Sep-17

P-T01-1095 Fab & Deliver - Painted Trim (Painted in Shop) 10 10 22-Aug-17 05-Sep-17

ConstructionConstruction177 128 20-Apr-17 A 18-Jan-18

Schedule Driven MilestonesSchedule Driven Milestones126 126 19-Jul-17 18-Jan-18

M-T01-1020 Conditioned Air Available 0 0 19-Jul-17

M-T01-1030 LV / FA / IT Complete 0 0 09-Aug-17

M-T01-1045 Interim Substantial Completion - Secretary of State 0 0 18-Jan-18

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - Hole in Floor

Construction - By Others

Construction - Visitor Entrance

Flooring Contracting & Submittal Prep

MCC Receive / Review Submittal - Flooring

AE2 (FSB) Receive / Review Submittal - Flooring

Fab & Deliver - Marble Tile

Fab & Deliver - Carpet

MCC Receive / Review Submittal - Doors & Hardware

AE2 (FSB) Receive / Review Submittal - Doors & Hardware

Fab & Deliver - Door Frames

Fab & Deliver - Doors & Hardware

MCC Receive / Review Submittal - MIllwork

AE2 (FSB) Receive / Review Submittal - MIllwork

Fab & Deliver - Base / Case / Crown

Fab & Deliver - MIllwork

Fab & Deliver - Painted Trim (Painted in Shop)

Conditioned Air Available

LV / FA / IT Complete

Interim Substantial Completion - Secretary of State

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 28 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 38: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

Construction Phase SummariesConstruction Phase Summaries152 185 20-Apr-17 A 18-Jan-18

S-T01-1000 Construction - 1st Floor Secretary of State 152 185 20-Apr-17 A 18-Jan-18

Secretary of StateSecretary of State131 128 13-Jul-17 A 18-Jan-18

C-T01-1105 Insulate Mechanical 5 2 13-Jul-17 A 19-Jul-17

C-T01-1125 Hang Sheetrock 7 9 17-Jul-17 A 28-Jul-17

C-T01-1130 Tape / Bed / Paint Sheetrock 10 10 27-Jul-17 09-Aug-17

C-T01-1150 Install Ceiling Grid with Borders 5 5 10-Aug-17 16-Aug-17

C-T01-1155 Overhead Device Out 3 3 14-Aug-17 16-Aug-17

C-T01-1025 80% Fire Marshall Inspection 0 0 16-Aug-17

C-T01-1160 Above Ceiling Inspections 3 3 17-Aug-17 21-Aug-17

C-T01-1170 Drop Ceiling Tile 2 2 22-Aug-17 23-Aug-17

C-T01-1135 Install Door Frames 3 3 05-Sep-17 07-Sep-17

C-T01-1145 Install Base / Case / Crown 10 10 06-Sep-17 19-Sep-17

C-T01-1140 Plaster in Rotunda 30 30 08-Sep-17 19-Oct-17

C-T01-1165 Install Marble Tile 15 15 20-Sep-17 10-Oct-17

C-T01-1175 Install Carpet / LVT / SDT 10 10 24-Oct-17 06-Nov-17

C-T01-1180 Test & Balance 7 7 07-Nov-17 15-Nov-17

C-T01-1185 Install Millwork 10 10 07-Nov-17 20-Nov-17

C-T01-1190 Install Countertops 5 4 21-Nov-17 28-Nov-17

C-T01-1195 Hang Doors & Install Hardware 2 2 29-Nov-17 30-Nov-17

C-T01-1200 Final Paint 10 10 29-Nov-17 12-Dec-17

C-T01-1205 MCC Pre-punch 10 10 29-Nov-17 12-Dec-17

C-T01-1210 Install Glazing 4 4 30-Nov-17 05-Dec-17

C-T01-1030 100% Fire Marshall Inspection (Final) 0 0 30-Nov-17

C-T01-1215 FSB / OMES Punchlist 10 10 13-Dec-17 27-Dec-17

C-T01-1220 AE1 / Owner Punchlist 15 15 28-Dec-17 18-Jan-18

C-T01-1225 Owner Move In 0 0 18-Jan-18

6th Floor Senate6th Floor Senate220 188 02-Jun-17 A 12-Apr-18

Material ProcurementMaterial Procurement141 148 14-Jun-17 A 15-Feb-18

OAU & Heat PumpsOAU & Heat Pumps21 21 12-Sep-17 10-Oct-17

P-T02-1000 MCC Receive / Review Submittal - Heat Pumps 1 1 12-Sep-17 12-Sep-17

P-T02-1030 AE2 (FSB) Receive / Review Submittal - Heat Pumps 10 10 13-Sep-17 26-Sep-17

P-T02-1035 Fab & Deliver - Heat Pumps 10 10 27-Sep-17 10-Oct-17

Floor CoveringFloor Covering69 69 12-Sep-17 19-Dec-17

P-T02-1015 Solicit & Advertise Flooring for Bid 19 19 12-Sep-17 06-Oct-17

P-T02-1050 Flooring Contracting 10 10 09-Oct-17 20-Oct-17

P-T02-1085 Fab & Deliver - Marble Tile 15 15 23-Oct-17 10-Nov-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - 1st Floor Secretary of State

Insulate Mechanical

Hang Sheetrock

Tape / Bed / Paint Sheetrock

Install Ceiling Grid with Borders

Overhead Device Out

80% Fire Marshall Inspection

Above Ceiling Inspections

Drop Ceiling Tile

Install Door Frames

Install Base / Case / Crown

Plaster in Rotunda

Install Marble Tile

Install Carpet / LVT / SDT

Test & Balance

Install Millwork

Install Countertops

Hang Doors & Install Hardware

Final Paint

MCC Pre-punch

Install Glazing

100% Fire Marshall Inspection (Final)

FSB / OMES Punchlist

AE1 / Owner Punchlist

Owner Move In

MCC Receive / Review Submittal - Heat Pumps

AE2 (FSB) Receive / Review Submittal - Heat Pumps

Fab & Deliver - Heat Pumps

Solicit & Advertise Flooring for Bid

Flooring Contracting

Fab & Deliver - Marble Tile

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 29 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 39: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

P-T02-1090 Fab & Deliver - Carpet 40 40 23-Oct-17 19-Dec-17

Doors / HardwareDoors / Hardware60 67 14-Jun-17 A 19-Oct-17

P-T02-1045 Doors & Hardware Pricing & Submittal Prep 10 7 14-Jun-17 A 26-Jul-17

P-T02-1070 MCC Receive / Review Submittal - Doors & Hardware 10 10 27-Jul-17 09-Aug-17

P-T02-1100 AE2 (FSB) Receive / Review Submittal - Doors & Hardware 10 10 10-Aug-17 23-Aug-17

P-T02-1125 Fab & Deliver - Door Frames 15 15 24-Aug-17 14-Sep-17

P-T02-1145 Fab & Deliver - Doors & Hardware 40 40 24-Aug-17 19-Oct-17

MillworkMillwork50 50 12-Sep-17 20-Nov-17

P-T02-1040 Millwork Pricing & Submittal Prep 10 10 12-Sep-17 25-Sep-17

P-T02-1065 MCC Receive / Review Submittal - MIllwork 10 10 26-Sep-17 09-Oct-17

P-T02-1095 AE2 (FSB) Receive / Review Submittal - MIllwork 10 10 10-Oct-17 23-Oct-17

P-T02-1115 Fab & Deliver - Base / Case / Crown 5 5 24-Oct-17 30-Oct-17

P-T02-1120 Fab & Deliver - Painted Trim (Painted in Shop) 10 10 24-Oct-17 06-Nov-17

P-T02-1140 Fab & Deliver - MIllwork 20 20 24-Oct-17 20-Nov-17

StairsStairs79 79 12-Sep-17 04-Jan-18

P-T02-1020 Solicit & Advertise Stairs for Bid 19 19 12-Sep-17 06-Oct-17

P-T02-1055 Stairs Contracting & Submittal Prep 10 10 09-Oct-17 20-Oct-17

P-T02-1075 MCC Receive / Review Submittal - Stairs 10 10 23-Oct-17 03-Nov-17

P-T02-1105 AE2 (FSB) Receive / Review Submittal -Stairs 10 10 06-Nov-17 17-Nov-17

P-T02-1130 Fab & Deliver - Stairs 30 30 20-Nov-17 04-Jan-18

ChairliftChairlift109 109 12-Sep-17 15-Feb-18

P-T02-1025 Solicit & Advertise Chairlift for Bid 19 19 12-Sep-17 06-Oct-17

P-T02-1060 Chairlift Contracting & Submittal Prep 10 10 09-Oct-17 20-Oct-17

P-T02-1080 MCC Receive / Review Submittal - Chairlift 10 10 23-Oct-17 03-Nov-17

P-T02-1110 AE2 (FSB) Receive / Review Submittal -Chairlift 10 10 06-Nov-17 17-Nov-17

P-T02-1135 Fab & Deliver - Chairlift 60 60 20-Nov-17 15-Feb-18

ConstructionConstruction220 188 02-Jun-17 A 12-Apr-18

Schedule Driven MilestonesSchedule Driven Milestones100 100 17-Nov-17 12-Apr-18

M-T02-1010 LV / FA / IT Complete 0 0 17-Nov-17

M-T02-1015 Interim Substantial Completion - 6th Floor Senate 0 0 12-Apr-18

Construction Phase SummariesConstruction Phase Summaries181 224 02-Jun-17 A 26-Feb-18

S-T02-1000 Construction - 6th Floor Senate 181 224 02-Jun-17 A 26-Feb-18

6th Floor Senate6th Floor Senate198 188 10-Jul-17 A 12-Apr-18

C-T02-1265 Re-Design for Existing Condtions 15 9 10-Jul-17 A 28-Jul-17

C-T02-1240 Demo Overhead Abandoned MEP 10 10 18-Jul-17 31-Jul-17

C-T02-1250 Remove Scaffold 5 5 01-Aug-17 07-Aug-17

C-T02-1030 Post-Demo Conference 1 1 09-Aug-17 09-Aug-17

C-T02-1045 Rough-In Overhead Electric 5 5 10-Aug-17 16-Aug-17

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Fab & Deliver - Carpet

Doors & Hardware Pricing & Submittal Prep

MCC Receive / Review Submittal - Doors & Hardware

AE2 (FSB) Receive / Review Submittal - Doors & Hardware

Fab & Deliver - Door Frames

Fab & Deliver - Doors & Hardware

Millwork Pricing & Submittal Prep

MCC Receive / Review Submittal - MIllwork

AE2 (FSB) Receive / Review Submittal - MIllwork

Fab & Deliver - Base / Case / Crown

Fab & Deliver - Painted Trim (Painted in Shop)

Fab & Deliver - MIllwork

Solicit & Advertise Stairs for Bid

Stairs Contracting & Submittal Prep

MCC Receive / Review Submittal - Stairs

AE2 (FSB) Receive / Review Submittal -Stairs

Fab & Deliver - Stairs

Solicit & Advertise Chairlift for Bid

Chairlift Contracting & Submittal Prep

MCC Receive / Review Submittal - Chairlift

AE2 (FSB) Receive / Review Submittal -Chairlift

Fab & Deliver - Chairlift

LV / FA / IT Complete

Interim Substantial Completion - 6th Floor Senate

Construction - 6th Floor Senate

Re-Design for Existing Condtions

Demo Overhead Abandoned MEP

Remove Scaffold

Post-Demo Conference

Rough-In Overhead Electric

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 30 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 40: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

C-T02-1040 Layout, Frame Walls & Install Door Frames 15 15 15-Sep-17 05-Oct-17

C-T02-1060 Rough-In In Wall 5 5 06-Oct-17 12-Oct-17

C-T02-1070 Frame Hard Lids 5 5 06-Oct-17 12-Oct-17

C-T02-1050 Rough-In Overhead Mechanical 5 5 11-Oct-17 17-Oct-17

C-T02-1095 Rough-In @ Hard Lids 5 5 13-Oct-17 19-Oct-17

C-T02-1085 Rough-In Fire Suppression 5 5 16-Oct-17 20-Oct-17

C-T02-1065 Rough-In Mechanical Piping 5 5 16-Oct-17 20-Oct-17

C-T02-1075 Insulate Mechanical 10 10 16-Oct-17 27-Oct-17

C-T02-1100 Overhead @ Hardlids & In-Wall Inspec tions 3 3 20-Oct-17 24-Oct-17

C-T02-1080 50% Fire Marshall Inspection 0 0 20-Oct-17

C-T02-1105 Hang Sheetrock 7 7 30-Oct-17 07-Nov-17

C-T02-1110 Tape / Bed / Paint Sheetrock 10 10 06-Nov-17 17-Nov-17

C-T02-1125 Install Base / Case / Crown 10 10 15-Nov-17 30-Nov-17

C-T02-1130 Install Ceiling Grid with Borders 5 5 20-Nov-17 28-Nov-17

C-T02-1150 Install Marble Tile @ Restroom 5 5 20-Nov-17 28-Nov-17

C-T02-1135 Overhead Device Out 3 3 22-Nov-17 28-Nov-17

C-T02-1140 80% Fire Marshall Inspection 0 0 28-Nov-17

C-T02-1145 Above Ceiling Inspections 2 2 29-Nov-17 30-Nov-17

C-T02-1155 Drop Ceiling Tile 2 2 01-Dec-17 04-Dec-17

C-T02-1160 Install Carpet / LVT / SDT 10 10 20-Dec-17 04-Jan-18

C-T02-1165 Install Millwork 5 5 28-Dec-17 04-Jan-18

C-T02-1175 Install Countertops 2 2 05-Jan-18 08-Jan-18

C-T02-1180 Hang Doors & Install Hardware 2 2 05-Jan-18 08-Jan-18

C-T02-1260 Installation of Stairs 40 40 05-Jan-18 01-Mar-18

C-T02-1170 Test & Balance 7 7 09-Jan-18 17-Jan-18

C-T02-1185 Final Paint 10 10 09-Jan-18 22-Jan-18

C-T02-1190 MCC Pre-punch 10 10 09-Jan-18 22-Jan-18

C-T02-1205 FSB / OMES Punchlist 10 10 23-Jan-18 05-Feb-18

C-T02-1210 AE1 / Owner Punchlist 15 15 06-Feb-18 26-Feb-18

C-T02-1055 Installation of Chairlift 40 40 16-Feb-18 12-Apr-18

C-T02-1215 Owner Move In 0 0 26-Feb-18

C-T02-1200 100% Fire Marshall Inspection (Final) 0 0 12-Apr-18

1st Floor OMES East1st Floor OMES East212 194 19-Jan-18 31-Jul-18

ConstructionConstruction212 194 19-Jan-18 31-Jul-18

Construction Phase SummariesConstruction Phase Summaries212 194 19-Jan-18 31-Jul-18

S-T03-1000 Construction - OMES East 212 194 19-Jan-18 31-Jul-18

5th Floor Senate East5th Floor Senate East245 245 01-Aug-18 02-Apr-19

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Layout, Frame Walls & Install Door Frames

Rough-In In Wall

Frame Hard Lids

Rough-In Overhead Mechanical

Rough-In @ Hard Lids

Rough-In Fire Suppression

Rough-In Mechanical Piping

Insulate Mechanical

Overhead @ Hardlids & In-Wall Inspec tions

50% Fire Marshall Inspection

Hang Sheetrock

Tape / Bed / Paint Sheetrock

Install Base / Case / Crown

Install Ceiling Grid with Borders

Install Marble Tile @ Restroom

Overhead Device Out

80% Fire Marshall Inspection

Above Ceiling Inspections

Drop Ceiling Tile

Install Carpet / LVT / SDT

Install Millwork

Install Countertops

Hang Doors & Install Hardware

Installation of Stairs

Test & Balance

Final Paint

MCC Pre-punch

FSB / OMES Punchlist

AE1 / Owner Punchlist

Installation of Chairlift

Owner Move In

100% Fire Marshall Inspection (Final)

Construction - OMES East

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 31 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 41: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

ConstructionConstruction245 245 01-Aug-18 02-Apr-19

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-18 02-Apr-19

S-T04-1000 Construction - 5th Floor Senate East 245 245 01-Aug-18 02-Apr-19

4th Floor Senate East4th Floor Senate East245 245 01-Aug-18 02-Apr-19

ConstructionConstruction245 245 01-Aug-18 02-Apr-19

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-18 02-Apr-19

S-T05-1000 Construction - 4th Floor Senate East 245 245 01-Aug-18 02-Apr-19

2nd Floor Governor2nd Floor Governor365 365 03-Mar-19 01-Mar-20

ConstructionConstruction365 365 03-Mar-19 01-Mar-20

Construction Phase SummariesConstruction Phase Summaries365 365 03-Mar-19 01-Mar-20

S-T06-1000 Construction - 2nd Floor Governor 365 365 03-Mar-19 01-Mar-20

Court of Criminal AppealsCourt of Criminal Appeals365 365 03-Mar-19 01-Mar-20

ConstructionConstruction365 365 03-Mar-19 01-Mar-20

Construction Phase SummariesConstruction Phase Summaries365 365 03-Mar-19 01-Mar-20

S-T07-1000 Construction - Court of Criminal Appeals 365 365 03-Mar-19 01-Mar-20

1st Floor OMES North1st Floor OMES North242 242 03-Apr-19 30-Nov-19

ConstructionConstruction242 242 03-Apr-19 30-Nov-19

Construction Phase SummariesConstruction Phase Summaries242 242 03-Apr-19 30-Nov-19

S-T08-1000 Construction - OMES North 242 242 03-Apr-19 30-Nov-19

1st Floor Photographer1st Floor Photographer181 181 03-Apr-19 30-Sep-19

ConstructionConstruction181 181 03-Apr-19 30-Sep-19

Construction Phase SummariesConstruction Phase Summaries181 181 03-Apr-19 30-Sep-19

S-T09-1000 Construction - 1st Floor Photographer 181 181 03-Apr-19 30-Sep-19

1st Floor LSB1st Floor LSB181 181 03-Apr-19 30-Sep-19

ConstructionConstruction181 181 03-Apr-19 30-Sep-19

Construction Phase SummariesConstruction Phase Summaries181 181 03-Apr-19 30-Sep-19

S-T10-1000 Construction - 1st Floor LSB 181 181 03-Apr-19 30-Sep-19

2nd Floor Judicial2nd Floor Judicial427 305 01-Aug-19 31-May-20

ConstructionConstruction427 305 01-Aug-19 31-May-20

Construction Phase SummariesConstruction Phase Summaries427 305 01-Aug-19 31-May-20

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - 5th Floor Senate East

Construction - 4th Floor Senate East

Construction - 2nd Floor Governor

Construction - Court of Criminal Appeals

Construction - OMES North

Construction - 1st Floor Photographer

Construction - 1st Floor LSB

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 32 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 42: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

S-T11-1000 Construction - 2nd Floor Judicial 427 305 01-Aug-19 31-May-20

2nd Floor House West2nd Floor House West245 245 01-Aug-19 01-Apr-20

ConstructionConstruction245 245 01-Aug-19 01-Apr-20

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-19 01-Apr-20

S-T12-1000 Construction - 2nd Floor House West 245 245 01-Aug-19 01-Apr-20

2nd Floor Senate North2nd Floor Senate North245 245 01-Aug-19 01-Apr-20

ConstructionConstruction245 245 01-Aug-19 01-Apr-20

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-19 01-Apr-20

S-T13-1000 Construction - 2nd Floor Senate North 245 245 01-Aug-19 01-Apr-20

2nd Floor Treasurer2nd Floor Treasurer184 184 01-Oct-19 01-Apr-20

ConstructionConstruction184 184 01-Oct-19 01-Apr-20

Construction Phase SummariesConstruction Phase Summaries184 184 01-Oct-19 01-Apr-20

S-T14-1000 Construction - 2nd Floor Treasurer 184 184 01-Oct-19 01-Apr-20

1st Floor Lt Governor1st Floor Lt Governor184 184 01-Oct-19 01-Apr-20

ConstructionConstruction184 184 01-Oct-19 01-Apr-20

Construction Phase SummariesConstruction Phase Summaries184 184 01-Oct-19 01-Apr-20

S-T15-1000 Construction - 1st Floor Lt Governor 184 184 01-Oct-19 01-Apr-20

3rd Floor House West3rd Floor House West244 244 01-Oct-19 31-May-20

ConstructionConstruction244 244 01-Oct-19 31-May-20

Construction Phase SummariesConstruction Phase Summaries244 244 01-Oct-19 31-May-20

S-T16-1000 Construction - 3rd Floor House West 244 244 01-Oct-19 31-May-20

3rd Floor Senate North3rd Floor Senate North244 244 01-Oct-19 31-May-20

ConstructionConstruction244 244 01-Oct-19 31-May-20

Construction Phase SummariesConstruction Phase Summaries244 244 01-Oct-19 31-May-20

S-T17-1000 Construction - 3rd Floor Senate North 244 244 01-Oct-19 31-May-20

1st Floor Gov Elect1st Floor Gov Elect213 213 02-Mar-20 30-Sep-20

ConstructionConstruction213 213 02-Mar-20 30-Sep-20

Construction Phase SummariesConstruction Phase Summaries213 213 02-Mar-20 30-Sep-20

S-T18-1000 Construction - 1st Floor Gov Elect 213 213 02-Mar-20 30-Sep-20

1st Floor Auditor1st Floor Auditor152 152 02-Mar-20 31-Jul-20

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - 2nd Floor Judicial

Construction - 2nd Floor House West

Construction - 2nd Floor Senate North

Construction - 2nd Floor Treasurer

Construction - 1st Floor Lt Governor

Construction - 3rd Floor House West

Construction - 3rd Floor Senate North

Construction - 1st Floor Gov Elect

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 33 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 43: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

ConstructionConstruction152 152 02-Mar-20 31-Jul-20

Construction Phase SummariesConstruction Phase Summaries152 152 02-Mar-20 31-Jul-20

S-T19-1000 Construction - 1st Floor Auditor 152 152 02-Mar-20 31-Jul-20

4th Floor Senate North4th Floor Senate North182 182 02-Mar-20 30-Aug-20

ConstructionConstruction182 182 02-Mar-20 30-Aug-20

Construction Phase SummariesConstruction Phase Summaries182 182 02-Mar-20 30-Aug-20

S-T20-1000 Construction - 4th Floor Senate North 182 182 02-Mar-20 30-Aug-20

419 A & B419 A & B182 182 02-Mar-20 30-Aug-20

ConstructionConstruction182 182 02-Mar-20 30-Aug-20

Construction Phase SummariesConstruction Phase Summaries182 182 02-Mar-20 30-Aug-20

S-T21-1000 Construction - 419 A & B 182 182 02-Mar-20 30-Aug-20

511 A511 A182 182 02-Mar-20 30-Aug-20

ConstructionConstruction182 182 02-Mar-20 30-Aug-20

Construction Phase SummariesConstruction Phase Summaries182 182 02-Mar-20 30-Aug-20

S-T22-1000 Construction - 511 A 182 182 02-Mar-20 30-Aug-20

1st Floor Multipurpose1st Floor Multipurpose153 153 01-Aug-20 31-Dec-20

ConstructionConstruction153 153 01-Aug-20 31-Dec-20

Construction Phase SummariesConstruction Phase Summaries153 153 01-Aug-20 31-Dec-20

S-T23-1000 Construction - 1st Floor Multipurpose 153 153 01-Aug-20 31-Dec-20

5th Floor Senate North5th Floor Senate North245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T24-1000 Construction - 5th Floor Senate North 245 245 01-Aug-20 02-Apr-21

5th Floor Conf. Rooms South5th Floor Conf. Rooms South245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T25-1000 Construction - 5th Floor Conference Rooms South 245 245 01-Aug-20 02-Apr-21

4th Floor House Committee N4th Floor House Committee N245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - 1st Floor Auditor

Construction - 4th Floor Senate North

Construction - 419 A & B

Construction - 511 A

Construction - 1st Floor Multipurpose

Construction - 5th Floor Senate North

Construction - 5th Floor Conference Rooms South

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 34 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 44: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

Activity ID Activity Name Orig Dur

RemDur

Start Finish

S-T26-1000 Construction - 4th Floor House Committe North 245 245 01-Aug-20 02-Apr-21

4th Floor Press North4th Floor Press North245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T27-1000 Construction - 4th Floor Press North 245 245 01-Aug-20 02-Apr-21

4 & 5th Large Conf. Rms South4 & 5th Large Conf. Rms South245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T28-1000 Construction - 4 & 5th Large Conference Rooms South 245 245 01-Aug-20 02-Apr-21

4th Floor House West4th Floor House West245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T29-1000 Construction - 4th Floor House West 245 245 01-Aug-20 02-Apr-21

5th Floor House West5th Floor House West245 245 01-Aug-20 02-Apr-21

ConstructionConstruction245 245 01-Aug-20 02-Apr-21

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-20 02-Apr-21

S-T30-1000 Construction - 5th Floor House West 245 245 01-Aug-20 02-Apr-21

6th Floor House West6th Floor House West181 181 03-Mar-21 30-Aug-21

ConstructionConstruction181 181 03-Mar-21 30-Aug-21

Construction Phase SummariesConstruction Phase Summaries181 181 03-Mar-21 30-Aug-21

S-T31-1000 Construction - 6th Floor House West 181 181 03-Mar-21 30-Aug-21

Senate ChambersSenate Chambers245 245 01-Aug-21 02-Apr-22

ConstructionConstruction245 245 01-Aug-21 02-Apr-22

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-21 02-Apr-22

S-T32-1000 Construction - Senate Chambers 245 245 01-Aug-21 02-Apr-22

House ChambersHouse Chambers245 245 01-Aug-21 02-Apr-22

ConstructionConstruction245 245 01-Aug-21 02-Apr-22

Construction Phase SummariesConstruction Phase Summaries245 245 01-Aug-21 02-Apr-22

S-T33-1000 Construction - House Chambers 245 245 01-Aug-21 02-Apr-22

J A A J A A J A A J A A J A A J A A J

2017 2018 2019 2020 2021 2022 2023

Construction - 4th Floor House Committe North

Construction - 4th Floor Press North

Construction - 4 & 5th Large Conference Rooms Sout

Construction - 4th Floor House West

Construction - 5th Floor House West

Construction - 6th Floor House West

Construction - Senate Chambers

Construction - House Chambers

Start Date 23-Feb-15

Finish Date 30-Dec-22

Data Date 18-Jul-17

Run Date 21-Jul-17

Page 35 of 35

3707-CR28

TASK filter: Not Complete.

Actual Level of Effort

Actual Work

Remaining Work

Suspension

Remaining LOE

Critical Remaining Work

Milestone

Critical Milestones

Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma

MCC Project #3707

Page 45: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

RFI LOG

SECTION 4

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

4-1

RFI # Subject Author

Company

Answer

Company

Date

Created

Date

Req'd

Date Resp Dwg

Impact

001 Existing Wall Condition 8/4/2015 8/14/2015 Not Sure8/11/2015Manhattan Construction Company

Frankfurt Short Bruza

002 Demo Existing 6" Concrete Wall 8/13/2015 8/14/2015 Not Sure8/20/2015Manhattan Construction Company

Frankfurt Short Bruza

003 Slab Infills details 8/25/2015 8/28/2015 Not Sure9/1/2015Manhattan Construction Company

Frankfurt Short Bruza

004 MC Feeder Cables 8/27/2015 9/8/2015 Not Sure9/3/2015Manhattan Construction Company

Frankfurt Short Bruza

005 New Door Lay Out Senate 3rd Floor 8/28/2015 8/28/2015 Not Sure9/4/2015Manhattan Construction Company

Frankfurt Short Bruza

006 Bid Questions 9/1/2015 9/2/2015 Not Sure9/8/2015Manhattan Construction Company

Frankfurt Short Bruza

007 Tie in of Existing Plumbing 3rd Floor 9/3/2015 9/10/2015 Not Sure9/10/2015Manhattan Construction Company

Frankfurt Short Bruza

008 House UPS 9/9/2015 9/18/2015 Not Sure9/15/2015Manhattan Construction Company

Frankfurt Short Bruza

009 Door Hardware Specs vs Plans 9/14/2015 9/22/2015 Not Sure9/18/2015Manhattan Construction Company

Frankfurt Short Bruza

010 Lead Paint Abatement 9/25/2015 10/12/2015 Not Sure9/29/2015Manhattan Construction Company

Mass Architects, Inc.

011 Building Envelope 9/25/2015 10/12/2015 Not Sure9/29/2015Manhattan Construction Company

Mass Architects, Inc.

012 Voltage for H1, H1E, H2, H2E 9/30/2015 10/1/2015 Not Sure10/2/2015Manhattan Construction Company

Frankfurt Short Bruza

013 New Paint Schedule 10/22/2015 10/29/2015 Not Sure10/29/2015Manhattan Construction Company

Frankfurt Short Bruza

014 Keying 11/3/2015 1/4/2016 Not Sure11/18/2015Manhattan Construction Company

Mass Architects, Inc.

015 Exterior Windows 11/3/2015 1/4/2016 Not Sure11/18/2015Manhattan Construction Company

Mass Architects, Inc.

016 Color Selection Fabric Wrapped Panels 11/12/2015 11/17/2015 Not Sure11/17/2015Manhattan Construction Company

Frankfurt Short Bruza

017 Security 11/12/2015 11/24/2015 Not Sure11/27/2015Manhattan Construction Company

Mass Architects, Inc.

018 Capitol Maintenance 11/17/2015 3/25/2016 Not Sure11/23/2015Manhattan Construction Company

Mass Architects, Inc.

RFI’s

Page 46: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

RFI LOG

SECTION 4

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

4-2

RFI’s

018-R001

Capitol Maintenance - Water Infiltration 4/27/2016 5/12/2016 Not Sure5/17/2016Manhattan Construction Company

Mass Architects, Inc.

019 Structual Load 12/16/2015 12/22/2015 Not Sure12/23/2015Manhattan Construction Company

Frankfurt Short Bruza

020 H 109 Dog House Electrical Panel 4/25/2016 5/11/2016 Not Sure5/2/2016Manhattan Construction Company

Frankfurt Short Bruza

021 Window Infill 5/10/2016 5/17/2016 Not Sure5/12/2016Manhattan Construction Company

Frankfurt Short Bruza

022 Structural Infill Confirmation 5/11/2016 7/11/2016 Not Sure5/13/2016Manhattan Construction Company

Frankfurt Short Bruza

023 Mounting Heights 5/17/2016 5/19/2016 Not Sure5/24/2016Manhattan Construction Company

Frankfurt Short Bruza

024 Plaster at Rotunda 5/17/2016 5/19/2016 Not Sure5/20/2016Manhattan Construction Company

Frankfurt Short Bruza

025 Confirmation of Ceiling Height Room 109.11 5/17/2016 5/19/2016 No5/24/2016Manhattan Construction Company

Frankfurt Short Bruza

026 New Duct Chase Location 5/17/2016 5/19/2016 No5/20/2016Manhattan Construction Company

Frankfurt Short Bruza

027 Door 109.45 Swing Change 6/2/2016 6/3/2016 Not Sure6/9/2016Manhattan Construction Company

Frankfurt Short Bruza

028 Slab Penetration at Duct Chase 6/2/2016 6/21/2016 Not Sure6/10/2016Manhattan Construction Company

Frankfurt Short Bruza

029 Column Framing at Exterior Walls 6/2/2016 6/8/2016 Not Sure6/9/2016Manhattan Construction Company

Frankfurt Short Bruza

030 Structural In-fill Detail for NW Dog house 6/21/2016 6/24/2016 Not Sure6/24/2016Manhattan Construction Company

Frankfurt Short Bruza

031 109 Entry Clerk Return Air 6/29/2016 7/8/2016 Not Sure7/6/2016Manhattan Construction Company

Frankfurt Short Bruza

032 Urinal Mounting Heights 8/11/2016 8/17/2016 Not Sure8/18/2016Manhattan Construction Company

Frankfurt Short Bruza

RFI # Subject Author

Company

Answer

Company

Date

Created

Date

Req'd

Date Resp Dwg

Impact

033 Guardrails at Rotunda 10/4/2016 11/17/2016 Not Sure10/11/2016Manhattan Construction Company

Mass Architects, Inc.

034 Future Fiber Distribution Plans 10/10/2016 Not Sure10/17/2016Manhattan Construction Company

Mass Architects, Inc.

035 Elevator Pit Infill - Area 4 10/14/2016 11/4/2016 Not Sure10/21/2016Manhattan Construction Company

Frankfurt Short Bruza

036 Partial Footing Removal for Electrical Trenching 1/16/2017 1/27/2017 Not Sure1/23/2017Manhattan Construction Company

Frankfurt Short Bruza

7/10/2017

Page 47: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

RFI LOG

SECTION 4

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

4-3

RFI’s

Company

037 State Capitol Grounding 1/24/2017 1/27/2017 Not Sure1/31/2017Manhattan Construction Company

Frankfurt Short Bruza

038 Ground Rod Access Well 1/25/2017 2/20/2017 Not Sure2/1/2017OESCO Frankfurt Short Bruza

039 3.2 - Structural Clarifications 2/6/2017 2/21/2017 Not Sure2/13/2017Basden Steel Corporation Frankfurt Short Bruza

040 Variable Frequency Motor Controllers 2/9/2017 2/20/2017 Not Sure2/16/2017Manhattan Construction Company

Frankfurt Short Bruza

041 3.2 - Structural Clarifications 2/9/2017 2/21/2017 Not Sure2/16/2017Basden Steel Corporation Frankfurt Short Bruza

042 Structural Steel Connection 2/9/2017 2/22/2017 Not Sure2/16/2017Manhattan Construction Company

Frankfurt Short Bruza

043 3.2 - Stair Loads and Serviceability Confirmation 2/10/2017 2/22/2017 Not Sure2/17/2017Manhattan Construction Company

Frankfurt Short Bruza

044 Temporary Smoke Evacuation 2/14/2017 2/16/2017 Not Sure2/21/2017Manhattan Construction Company

Frankfurt Short Bruza

045 Miscellaneous Mechanical Piping Insulation 2/14/2017 2/20/2017 Not Sure2/21/2017Matherly Mechanical Contractors, LLC

Frankfurt Short Bruza

046 3.2 Stair and Railing Details 2/14/2017 2/22/2017 Not Sure2/21/2017Manhattan Construction Company

Frankfurt Short Bruza

047 3.2 Damper Clarifications 2/15/2017 2/16/2017 Not Sure2/22/2017Manhattan Construction Company

Frankfurt Short Bruza

048 3.2 Beam to Column Connection in Generator Area 2/21/2017 2/21/2017 Not Sure2/28/2017Manhattan Construction Company

Frankfurt Short Bruza

049 3.2 HSS8x4 Connections 2/24/2017 2/28/2017 Not Sure3/3/2017Manhattan Construction Company

Frankfurt Short Bruza

049-R001

3.2 HSS8x4 Connections 2/27/2017 3/13/2017 Not Sure3/6/2017Manhattan Construction Company

Frankfurt Short Bruza

050 3.2 - G-5 Diffuser Specification 2/24/2017 2/28/2017 Not Sure3/3/2017Manhattan Construction Company

Frankfurt Short Bruza

051 3.2 Duct Transition 2/28/2017 3/2/2017 Not Sure3/7/2017Manhattan Construction Company

Frankfurt Short Bruza

RFI # Subject Author

Company

Answer

Company

Date

Created

Date

Req'd

Date Resp Dwg

Impact

052 5th Floor SW Doghouse EM Bus Duct and Spiral Stair Conflict 3/8/2017 3/15/2017 Yes3/15/2017OESCO Frankfurt Short Bruza

053 3.2 FS Dampers at SW Doghouse 3/17/2017 3/22/2017 Not Sure3/24/2017Manhattan Construction Company

Frankfurt Short Bruza

054 RFI 054 - Electrical Panels BSE1 and BSE2 - Location Confirmation Request

3/30/2017 4/3/2017 Not Sure4/6/2017Manhattan Construction Company

Frankfurt Short Bruza

055 3.2 - Concrete Lintel at SW Elevator 4/3/2017 Not Sure4/10/2017Manhattan Construction Company

Frankfurt Short Bruza 4/14/2017

Page 48: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

RFI LOG

SECTION 4

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

4-4

RFI’s

Company

056 3.2 - Supply Grille Elevations at SW doghouse 4/4/2017 4/7/2017 Not Sure4/10/2017Manhattan Construction Company

Frankfurt Short Bruza

057 3.2 - Fire Smoke Damper at G-5 Supply Grille 4/5/2017 4/14/2017 Not Sure4/12/2017Manhattan Construction Company

Frankfurt Short Bruza

058 3.2 Steel Framing for ACCU's 4/13/2017 5/8/2017 Not Sure4/13/2017Manhattan Construction Company

Frankfurt Short Bruza

059 3.2 - Supply Air Duct Conflict in SW Doghouse 4/17/2017 4/28/2017 Not Sure4/24/2017Manhattan Construction Company

Frankfurt Short Bruza

060 3.2 - Slab Cores in SW Doghouse 4/19/2017 5/8/2017 Not Sure4/26/2017Manhattan Construction Company

Frankfurt Short Bruza

061 3.2 - Column to Beam Connx in SW Doghouse 5/5/2017 5/8/2017 Not Sure5/12/2017Manhattan Construction Company

Frankfurt Short Bruza

062 3.3 - Detail at Coffered Ceiling 5/9/2017 5/17/2017 Not Sure5/16/2017Manhattan Construction Company

Frankfurt Short Bruza

063 3.3 - Millwork Conflict in Office 122.5 5/9/2017 5/15/2017 Not Sure5/16/2017Manhattan Construction Company

Frankfurt Short Bruza

064 Clay Masonry Endwall Support 5/22/2017 6/23/2017 Not Sure5/29/2017Manhattan Construction Company

Frankfurt Short Bruza

065 Outside Air Wall Penetration Reinforcement 5/22/2017 6/9/2017 Not Sure5/29/2017Manhattan Construction Company

Frankfurt Short Bruza

066 Granite Removal for Waterproofing at Generator Areaway 5/24/2017 6/2/2017 Not Sure5/31/2017Manhattan Construction Company

Mass Architects, Inc.

067 3.2 & 3.3 - Finish Clarification 6/1/2017 6/8/2017 Not Sure6/8/2017Manhattan Construction Company

Frankfurt Short Bruza

068 3.3 - K1 Substitution in Area 122 6/22/2017 7/7/2017 Not Sure6/29/2017Manhattan Construction Company

Frankfurt Short Bruza

069 1SE1 Panel Clarification 6/28/2017 7/7/2017 Not Sure7/5/2017Manhattan Construction Company

Frankfurt Short Bruza

070 Dowels for Walls at Generator Areaway 6/28/2017 6/28/2017 Not Sure7/5/2017Manhattan Construction Company

Frankfurt Short Bruza

071 Generator Room Roof Structure Rust Remediation 7/5/2017 7/21/2017 No7/12/2017Manhattan Construction Frankfurt Short Bruza

Company

RFI # Subject Author

Company

Answer

Company

Date

Created

Date

Req'd

Date Resp Dwg

Impact

Company

072 Existing Beam Conflict for 6th Floor Framing 7/12/2017 7/14/2017 Not Sure7/19/2017Manhattan Construction Company

Frankfurt Short Bruza

073 East Elevator Rail to Beam Connection 7/13/2017 7/14/2017 Not Sure7/20/2017Manhattan Construction Company

Frankfurt Short Bruza

074 Fabric Wall Panels & Acoustic Plaster 7/20/2017 Not Sure7/27/2017Manhattan Construction Company

Page 49: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

RFI LOG

SECTION 4

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

4-5

RFI’s

Company

075 Stair Details at Machine Room 7/24/2017 Not Sure7/31/2017Manhattan Construction Company

Frankfurt Short Bruza

076 Generator Exhaust Installation 7/31/2017 Not Sure8/7/2017Manhattan Construction Company

Frankfurt Short Bruza

077 Generator Pad Detail 8/1/2017 Not Sure8/8/2017Manhattan Construction Company

Frankfurt Short Bruza

79Total Number of RFIs for this project: 5

Total Created Total Outstanding

Company

RFI # Subject Author

Company

Answer

Company

Date

Created

Date

Req'd

Date Resp Dwg

Impact

Page 50: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

OUTSTANDING SUBMITTAL LOG

SECTION 5

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

5-1

Submittals

Capitol Interior Restoration Project # 37072300 N Lincoln Blvd. Oklahoma City, OK 73105 Tel: 405-521-2147 Fax:

Number-Rev From Company Description To Company Sent Due Rec'd ActionDays +/-

Mass Architects, Inc.

-130004-26 2416-0 Manhattan Construction Company 3.2 - Panelboards - Product Data - SW Floors 1-6

Mass Architects, Inc. 8/1/2017 8/15/2017 Action Pending

20001-23 2116-0 Manhattan Construction Company 3.2-Hydronic Piping Specialties - SSF-1 Mass Architects, Inc. 7/17/2017 7/31/2017 Action Pending

-140003-26 2200-0 Manhattan Construction Company 3.2 - Low Voltage Transformers - SW Floors 1-6 - Product Data

Mass Architects, Inc. 8/2/2017 8/16/2017 Action Pending

-60021-00 4253-0 Manhattan Construction Company 15151DB - Phase 6.0 35% SD Group 5 Mass Architects, Inc. 7/25/2017 8/8/2017 Action Pending

-60004-06 2023-0 Manhattan Construction Company 3.3 Interior Finish Carpentry - Secretary of State

Mass Architects, Inc. 7/25/2017 8/8/2017 Action Pending

-50002-04 4313.13-0

Manhattan Construction Company Masonry - Interior Limestone - Sample Mass Architects, Inc. 7/24/2017 8/7/2017 Action Pending

6Number of Submittal Packages in this Project:

Page 51: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration

July 2017

6-1

Secretary of State Build-out

Pictured Left: Sheetrock at

the ceiling in the new

Secretary of State corridor.

Pictured Right: Sheetrock,

tape and bed in the State

Room.

Page 52: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-2

Ground Level West Corridor Framing

Pictured Right and Below:

Coffered ceiling framing

continues down the Ground

Level West Corridor.

Page 53: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-3

Generator Areaway Walls

Pictured: Wall forms

were set to pour the

walls at the new

Generator Areaway.

Page 54: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-4

Mechanical Room

Pictured Left: New

condensing water pumps

were set and started up.

Pictured Right: New

VFD’s prepared to be set

in the mechanical room.

Page 55: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-5

Fitness Framing and Plumbing

Pictured Left: Historic replica

frame installed at the fitness

center entrance.

Pictured Right: In-wall

plumbing and blocking for the

fitness restrooms.

Page 56: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-6

Elevator Pit Construction

Pictured Left: SW elevator pit

slab being finished.

Pictured Right: SW elevator

walls being formed

Page 57: Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/08/... · Start Up New Condensing Water Pumps Projected August 14 , 2017 2. Sanitary Sewer Main Tie

PROGRESS PHOTOS

SECTION 6

Monthly Progress Report – Oklahoma Capitol Restoration July 2017

6-7

SW Elevator Front Demo

Pictured Left: The old

elevator frame and sill was

removed to make room for

the new elevator fronts

Pictured Left: Structural

supports were installed

behind the existing masonry

wall in the elevator shaft to

support the masonry above

the elevator opening.