ONE London Road March Build Update

Upload: others

Post on 27-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

ONE London RoadMarch

Build Update

Page 2: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block One, View of External Facade

Block One, Roof Covering to Roof Terrace Area

Block 1 roof structure has now been completed and the smoke ventilation system installed at roof level. The coverings to the roof terrace are being installed along with parapet detailing.

Block OneAll external windows have now been installed.

Cladding brackets have been installed to all external faces, which has permitted the gradual removal of

scaffold and preparation of external hard-standings. Where scaffold has been removed the installation of

cladding panels has commenced.

Page 3: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View from Roof Top of Block Two

Rear of Block One: Scaffold Removed and Cladding Brackets Fixed

Cladding Installation to Rear of Block One

Externally the elevated parking area steelwork has been installed and the pre-cast planks installed, awaiting final surfacing in the future. Facing brickwork has been applied to the existing retaining wall that runs between Block One and Block Two.Building Control and Build Warranty visits/reports are ongoing. Further visits will be required at key stages of the construction.

Page 4: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View from the Front of Block One View of Block One from Block Two - External Windows Being Fitted

Plasterboard & Insulation Being Fitted on Higher Floors

Each Room is Being Dried Out Using Large Heaters Being Pumped Outside

External Facades Being Fit Internal Hallways Being Installed

Page 5: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View of Block One Rooftop Area

CGI Rendition of Rooftop Area

Rooftop Area on Block One

Back of Block One Overlooking the Park

Internal Window in Staircase of Block One

Page 6: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block One Internal Showroom Progressing to Completion

Block One Internal – Dry Lining Progression and First Fix Services

Internally all floors are now screeded. Dry-lining and mechanical and electrical works (first-fix) are progressing to completion. Two show flats have been selected and work is progressing in each to provide a

typical finished unit.

Page 7: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Appliances have Been Installed in the Showroom

Showroom in Block One - Kitchenette Fitted

Block One

Page 8: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block TwoBlock Two, External View towards London Road

Block Two, Roof Covering Complete and Smoke VentilationEquipment Installed

Page 9: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block Two, Typical Internal Corridor Progression

Block Two, Insulation Progression Throughout Apartments and Hallways

Page 10: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

External View of Block Two Progression of Gym Area on the Ground Floor

View from Block Two Across to Block One

Internal Walls of Apartments in Block Two Internal Walls of Apartments in Block Two Rooftop View of London Road from Block Two

Page 11: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block Two and Elevated Parking AreaView of Block Two from Block One

Page 12: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Area Between Block One and Block Two, Aerial ParkingPlatform and Facing Brickwork to Existing Retaining Wall

No other information. Any Other Information

Page 13: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Elevated Parking Area, Frontal View Facing Block Two

Aerial View of Elevated Parking Area Adjacent to Block Two

Design/Construction InformationK&T are to issue a Planning Matrix and Confirm which consents have been discharged/remain outstanding.

Design Team Meetings are ongoing with Contractor, Architect and Structural Engineer.

Commercial/ContractualContract Documents executed and issued to both parties. Valuation No.16 from K&T received and processed.

Page 14: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Both Internal and External Blockwork Walls and Floors have been completed

up to second floor level. Blockwork walls have commenced to third floor level, with

an anticipation that the thirdfloor-planks will be installed by the end of

March.

Floor screeding has been completed to the ground floor and some external

drainage and ductwork has been completed.

Detailed Design of the Block is well underway with both architectural and

structural engineering drawings being issued and developed.

Block Three

Block Three, Front Elevation - Ground Floor BlockworkProgressing & Scaffolding Erection

Page 15: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block Three Front Elevation- Second Floor Precast FloorInstalled and Blockwork Commencing

View from Block Two towards Block Three GroundFloor Construction.

Page 16: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View of Block Three and Block One from Porta Cabins

View of External Facade of Block Three

Page 17: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View of Block Three from Block One View of Block Three and Site from Block One

Block Three External Facade

Internal Walls of Apartments in Block Three Brickwork Progressing On Higher Floors Internal Hallways in Block Three

Page 18: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

View of Block Three over the Site

View of Block One and Block Three

Design/Construction InformationK&T are to issue a Planning Matrix and Confirm which consents have been discharged/remain outstanding.Design Team Meetings are ongoing with Contractor, Architect and Structural Engineer.

Page 19: ONE London Road March Build Update - Real Estate Worldwide · 2020-03-31 · ONE London Road March. Build Update. Block One, ... Dry Lining Progression and First Fix Services

Block Three Overlooking the Park from Block One

Rear of Block Three Overlooking the Park

Commercial/ContractualContract Documents executed and issued to both

parties. Valuation No.08 from K&T received and processed.