operational performance june’12

11
OPERATIONAL PERFORMANCE JUNE’12 Month Carried Tonnage Monthly Traffic projection based on ATP Variation % (Over 2011 – 12) 2012-13 2011- 12 For June 0.34 0.32 0.39 6% Cumula tive – till June 1.08 0.81 1.13 33% Tonnage - MT

Upload: barny

Post on 23-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

OPERATIONAL PERFORMANCE JUNE’12. Tonnage - MT. COMMODITY-WISE LOADING – FOR THE MONTH OF JUNE’12. Tonnage in Lakhs. COMMODITY-WISE REVENUE – FOR THE MONTH OF JUNE’12. ` - Crores. Commodity wise Net Revenue Including OH. ` - Crores. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: OPERATIONAL PERFORMANCE  JUNE’12

OPERATIONAL PERFORMANCE JUNE’12

Month Carried Tonnage Monthly Traffic projection based

on ATP

Variation % (Over 2011 – 12)2012-13 2011-12

For June

0.34 0.32 0.39 6%

Cumulative – till June

1.08 0.81 1.13 33%

Tonnage - MT

Page 2: OPERATIONAL PERFORMANCE  JUNE’12

COMMODITY-WISE LOADING – FOR THE MONTH OF JUNE’12

Particulars Carried Tonnage 2012-13

Carried Tonnage 2011-12

Variation Over

Commodity June’12 Apr’12-June’12

June’11 Apr’11- June’11

Las t Yr June’11

Last Yr

Apr’11-June’12

Iron Ore/ Export

Domestic

Total

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.14

1.14

0.00

3.09

3.09

0%

-100%

-100%

0%

-100%

-100%

Cement 0.78 2.67 0.42 1.19 85% 125%

Fertilizer 0.47 0.97 0.90 1.91 -47% -49%

Food Grains 0.13 0.53 0.05 0.34 147% 57%

LPG/POL 0.26 0.76 0.29 0.75 -11% 1%

Coal 1.69 5.53 0.19 0.53 788% 942%

Gypsum 0.04 0.31 0.19 0.27 -80% 16%

Iron Sheet/Wood 0.03 0% -100%

Auto/Cont

Total 3.38 10.78 3.18 8.11 6% 33%

Tonnage in Lakhs

Page 3: OPERATIONAL PERFORMANCE  JUNE’12

COMMODITY-WISE REVENUE – FOR THE MONTH OF JUNE’12

Particulars Gross Revenue

2012-13

Gross Revenue

2011-12

Variation % Over

Commodity June’12 Apr’12-June’12

June’11 Apr’11- June’11

Las t Yr June’11

Last Yr

Apr’11-June’12

Iron Ore/ Export

Domestic

Total

0.00

0.00

0.00

0.00

0.00

0.00

0.00

2.95

2.95

0.00

7.97

7.97

0%

-100%

-100%

0%

-100%

-100%

Cement 2.21 7.55 0.92 2.58 140% 193%

Fertilizer 1.06 2.16 1.50 3.23 -29% -33%

Food Grains 0.26 0.98 0.07 0.47 266% 110%

LPG/POL 0.94 2.75 1.04 2.79 -10% -1%

Coal 4.47 14.64 0.37 1.04 1093% 1312%

Gypsum 0.11 0.86 0.40 0.56 -73% 52%

Iron Sheet/Wood 0.07 0% -100%

Auto/Cont 0.04 0.01 0% 279%

TOTAL 9.05 28.98 7.26 18.71 25% 55%

` - Crores

Page 4: OPERATIONAL PERFORMANCE  JUNE’12

Commodity wise Net Revenue Including OH

Particular June 2012 June 2011 Net Rev

Commodity Gross Reve

O&M Cost `. 152/ T

* Net Reve

Gross Reve

O&M Cost `.155/T

Net Reve

Varation %

Iron Ore/ Export

Domestic0.00

0.00

0.00

0.00

0.00

0.00

0.00

2.95

0.00

1.76

0.00

1.19

0%

-100%

Cement 2.21 1.19 1.02 0.92 0.66 0.26 289%

Fertilizer 1.06 0.72 0.34 1.50 1.39 0.11 204%

Food Grains

0.26 0.20 0.06 0.07 0.08 -0.01 -711%

LPG/POL 0.94 0.39 0.55 1.04 0.45 0.59 -8%

Coal 4.47 2.57 1.90 0.37 0.30 0.07 2441%

Gypsum 0.11 0.06 0.05 0.40 0.30 0.10 -51%

Iron Sheet/ Wood

0.00 0.00 0.00 0.00 0.00 0.00 0%

Auto/Cont 0.00 0.00 0.00 0.00 0.00 0.00 0%

TOTAL 9.05 5.13 3.92 7.26 4.94 2.32 69%

` - Crores

•June’12 - Net Revenue Includes OH of `. 87 Lakhs , O&M Cost Inclusive of OH - ` 178/T•June’11 – Net Revenue Includes OH of `. 84 Lakhs, O&M Cost Inclusive of OH - ` 181/T

Page 5: OPERATIONAL PERFORMANCE  JUNE’12

Commodity wise Gross & Net Revenue Including OH (Per Tonne)

Particular June 2012 June 2011 Net Rev

Commodity Gross Rev

O&M Cost /T

Net Rev

Gross Rev

O&M Cost /T

Net Rev Varation %

Iron Ore

Export

Domestic

0

0

0

0

0

0

0

259

0

155

0

104

0%

-100%

Cement 282 152 130 218 155 63 107%

Fertilizer 224 152 72 167 155 12 493%

Food Grains 199 152 47 134 155 -21 -321%

LPG/POL 365 152 213 362 155 207 3%

Coal 264 152 112 197 155 42 170%

Gypsum 276 152 124 209 155 54 131%

Iron Sheet /Wood

0 0 0 0 0 0 0%

Auto/Cont 0 0 0 0 0 0 0%

Amt - `

•June’12 - Net Revenue Includes OH of `. 26/T , O&M Cost Inclusive of OH - ` 178/T•June’11 – Net Revenue Includes OH of `. 26/T, O&M Cost Inclusive of OH - ` 181/T

Page 6: OPERATIONAL PERFORMANCE  JUNE’12

Operating Ratio for the month of June 2012For June

2012To End of June 2012

Gross Revenue 9.05 19.93

Total Income 9.05 19.93

Operating Expenses

O&M Costs (Inc of Def. OH) 6.60 25.57

Administrative Expenses 0.08 0.21

Depreciation 2.83 8.49

Total Expenses (i) 9.51 34.27

Operating Ratio (%) 105% 172%

Cost of Maintenance works (ii) 0.00 0.00

Total Expenses (I) + (II) 9.51 34.27

Operating Ratio (Cumulative) 105% 172%

Surplus/Deficit -0.47 -14.34

Surplus % -6% -72%

` - Crores

NOTE : In O&M costs, cost of fuel is calculated as per service & direction wise

Page 7: OPERATIONAL PERFORMANCE  JUNE’12

COST OF FUEL (SERVICE WISE/ DIRECTION WISE) for June’12

Cost of Fuel From April ’12 – June’12 – 9.30 Cr

Particulars No of Wagons Cost of Fuel ` - Crores

Total ` - Crores

Wagon Type UP DN UP DN UP + DN

BCN Load 985 1382 0.56 0.29 0.85

BOXN Load 2639 0 1.21 0.00 1.21

BTPG Load 469 0 0.26 0.00 0.26

BTPN Load 200 0 0.08 0.00 0.08

BLCA/BFKN Load 0 0 0.00 0.00 0.00

BCNHL Ld 0 0 0.00 0.00 0.00

BOXN Empty 0 2997 0.00 0.19 0.19

BTPG Empty 0 498 0.00 0.12 0.12

BTPN Empty 0 303 0.00 0.05 0.05

BLCA/BFKN Empty 0 0 0.00 0.00 0.00

BRN Empty 134 0 0.02 0.00 0.02

Cost of Fuel of CLE + Other (UP+DN) 0.00 0.00 0.01

TOTAL 4427 5180 2.13 0.65 2.79

Cost of Lube Oil + Others 0.20

TOTAL 2.99

Page 8: OPERATIONAL PERFORMANCE  JUNE’12

Line Capacity Utilization for the month of June’12 :

Direction Loaded Empties Total No of Trains

*CLE *Others Total

UP Trains 89 3 92 57

(84)

4

(12) 259Down Trains 34 72 106

123 75 198 57 4 259

Permissible Capacity : 240

Utilized : 259

Percentage of Utilization : 108%

Percentage of Utilization Loaded : 51%

Engine Hour Cost : 52.31 Lakhs

NOTE:

* Moved between SKLR-SBHR-SKLR

Page 9: OPERATIONAL PERFORMANCE  JUNE’12

WAGON DAYS – JUNE 2012

No of Days

TotalUP Down

Actual 3172 2221 5393

Abnormal Detention

841 138 979

Rate per Day in terms of 8 wheeler : ` 967.75

Wagon Hire Charges (Actual) : ` 52.19 Lakhs

Wagon Hire Charges for Abnormal : ` 9.47 Lakhs

Detention (Avoidable)

*Abnormal Detention : Time taken for completing the journey > 15 Hrs

Page 10: OPERATIONAL PERFORMANCE  JUNE’12

Details of Payments Received from Mysore Division after adjusting O&M Costs

Months Due Date Actual date of Receipt

Amount Rs - Cr

Prov. Pay Final Pay (Prov Pay)

April ’12 05.05.12 31.05.12 02.06.12 4.22

May ’12 05.06.12 30.06.12

June’12 05.07.12 30.07.12

Page 11: OPERATIONAL PERFORMANCE  JUNE’12

Details of Payments made by HMRDC to SWR

Particulars For the month of June’12

To the End

(Crores)

Contractual payment for maintenance works (Provisional bill from --)

----- ----