Operator of Leading Edge Technologies. Multiphase Pumping. Miscible gas injection. HP/HT Operations. United Kingdom: Dunbar -Most powerful units ever installed (2 x 4.5 MW). United Kingdom: Alwyn North. United Kingdom: Elgin Franklin development - Largest HP/HT project - PowerPoint PPT PresentationTRANSCRIPT
Operator of Leading Edge Technologies
Multiphase PumpingMultiphase PumpingUnited Kingdom:Dunbar - Most powerful units ever
installed (2 x 4.5 MW)
Extra - heavy oilExtra - heavy oil Venezuela:Sincor project -largest extra heavy oil project
(200 kb/d of synthetic crude)
Extended reach drillingExtended reach drillingArgentina:Ara & Kausdevelopments- largest high departure wells:
(offset: 11,000 m)
Miscible gas injectionMiscible gas injectionUnited Kingdom:Alwyn North
HP/HT OperationsHP/HT OperationsHP/HT OperationsHP/HT OperationsUnited Kingdom:Elgin Franklin development- Largest HP/HT project- Reservoir pres. 16.000 psi, temp. 210
°C
Multiphase transportMultiphase transportMultiphase transportMultiphase transport
Iran:South Pars pipeline- longest 3-phase transportation
system (32”, 100 km
Secondary and tertiarySecondary and tertiarySecondary and tertiarySecondary and tertiary
United Arab Emirates:Gas injection conducted in most
of UAE onshore and offshore fields)
Deepwater Grands FondsDeepwater Grands FondsDeepwater Grands FondsDeepwater Grands FondsAngola:Block 17 Girassol Field- Largest stand alone deepwater
project (water depth 1,400 m - 40 subsea wells)
Ultra deepwater developmentUltra deepwater developmentUltra deepwater developmentUltra deepwater developmentGulf of Mexico: Aconcagua (water depth 2,100 m) - Appraisal underway (dry gas)- Canyon Express Project
Ultra Deepwater explorationUltra Deepwater explorationGabon:Anton / Astrid Marin Blocks- Exploration wel planned
(2,400 - 2,750 m water depth)Brazil: BC2- Exploration ongoing (2,485 m water depth)
Multiphase transportMultiphase transportMultiphase transportMultiphase transportArgentina:Carina
Growth challenges and R&D projects:
Reservoir characterisation
Monitoring
Tight reservoirs
Multiphase transfer
Transverse projects
Well costs
Seismic technology
Well oper. & characteris.
Struct. & sedim. Interpretation
Technology projects
Growth projects
Extra-Heavy Oils
Deepwater offshore Sour gases
Deeply buried reservoirs
Mature fields
Residual gases
TOTAL Subsurface R&D contact in Norway: Rune Teigland, e-mail: [email protected]
Project Elgin Franklin Girassol Sincor South Pars
TechnicalTechnical HP/HT Deep Water X Heavy Oil multiphase
GeographicalGeographical UK ANGOLA VENEZUELA IRAN
ContractualContractual Concession PSC Strat. Assoc. Buy back
Investment (100%) 2.4 B$ 2.9 B$ 4.2 B$ 2.0 B$ On stream 03 / 2001 12 / 2001 03 / 2002 06 / 2002
Current plateau plateau plateau plateau Production(100%) 220 kboe/d 200 kb/d 200 kb/d 380 kboe/d
Total Operator or Reference Partner
Four technology-leading projects