optimised energy solutions report

Upload: sumbarzegaran

Post on 05-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Optimised Energy Solutions Report

    1/33

    Optimised Energy Solutions Ltd

    This document shall not be modified or copied to a third party under any circumstances, except with prior approval in writing from OptimisedEnergy Solutions Ltd.

    Copyright Optimised Energy Solutions Ltd. 2011. All rights reserved.

    DOCUMENT NO:

    DOCUMENT TITLE: Power System Studies For New Arc Furnace Installation

    PROJECT REFERENCE:

    - Client Project No:

    - Project Location: ROTHERHAM, UK

    - Project Title: NEW ARC FURNACE INSTALLATION

    - Client: TATA STEEL

  • 7/31/2019 Optimised Energy Solutions Report

    2/33

    Table of Contents

    1.0 SCOPE OF WORK ........................................................................................................................ 3

    2.0 EXECUTIVE SUMMARY................................................................................................................. 4

    33 kV Bustube Sizing ........................................................................................................................... 4

    Minimum 33 kV Bustube Clearances ................................................................................................... 4

    33 kV Bustube Supports ....................................................................................................................... 4

    Existing 33 kV CTs ............................................................................................................................... 4

    Fault Level Study Results ..................................................................................................................... 5

    Power Flow Study Results .................................................................................................................... 5

    Protection .............................................................................................................................................. 5

    Power Quality Issues ............................................................................................................................. 5

    3.0 POWER SYSTEM MODELLING ..................................................................................................... 6

    4.0 POWER SYSTEM STUDIES DESIGN CRITERIA ......................................................................... 6

    4.1 Power System Data Documents ...................................................................................................... 6

    4.2 Engineering Assumptions ............................................................................................................... 6

    5 0 DESCRIPTION OF POWER SYSTEM STUDIES 7

  • 7/31/2019 Optimised Energy Solutions Report

    3/33

    1.0 SCOPE OF WORK

    This scope of work is for the power system design work for the arc furnace transformer upgrade and system atthe Tata Steel plant in Rotherham.

    The scope of work will consist of the following two areas:

    Computer based analysis of new system and the interconnection to the grid as previously supplied.

    The following studies will be carried out:

    o Load Flow - steady state (continuous) thermal rating of electrical equipment and voltage levels

    o Fault rating for short time withstand, make and break duty

    o Busbar connector sizing and specification

    Report / specification to enable client to order equipment

    Section 2.0 of this report is the executive summary where the main conclusions of the report are highlighted.

    Section 3.0 of this report describes the software used for power system modelling.

    Section 4.0 of this report describes the design criteria for these studies

    Section 5.0 of this report describes the studies carried out in this report.

    Section 6.0 of this report describes the results of the studies.

    A di O f hi d h i d f h di d l l i

  • 7/31/2019 Optimised Energy Solutions Report

    4/33

    2.0 EXECUTIVE SUMMARY

    33 kV Bustube Sizing

    The bustube sizing calculations were carried out based on the following data and standards:

    UK Copper Development Associationo Publication 22: Copper For Busbars

    BS 7354: 1990: Code of practice for design of high voltage open terminal stations

    The selected high conductivity copper bustube is 75mm diameter with 10.2mm wall thickness

    Minimum 33 kV Bustube Clearances

    The clearances between the phases and phase to earth should be as follows as a minimum:

    Phase to earth minimum clearance = 500mm

    Phase to phase minimum clearance = 430 mm

    33 kV Bustube Supports

  • 7/31/2019 Optimised Energy Solutions Report

    5/33

    Fault Level Study Results

    The maximum 33 kV fault levels are:Peak asymmetrical current = 58 kARms symmetrical current = 21.33 kA

    The proposed 33 kV bustube will be adequately fault rated.

    Although not part of this scope of work, OES recommend that a full audit is carried out on the Tata Steel 33 kVsystem in order to verify that all electrical equipment is adequately fault rated in order that the requirements ofthe following UK statutory legislation is realised:

    Electricity At work Regulations 1989

    It should also be verified that the arc furnace transformer secondary circuits are complaint with these regulations

    with respect to fault level.

    Power Flow Study Results

    The power flow studies show there are various transformer overloads for various network operating conditions.The client should confirm the number of arc furnaces in operation per network operation configuration. Seesection 6.6 of this report.

    Although not part of this scope of work OES recommend that a full audit is carried out on the Tata Steel 33 kV

  • 7/31/2019 Optimised Energy Solutions Report

    6/33

    3.0 POWER SYSTEM MODELLING

    The power system studies were carried out using ETAP. This is a computer based power system simulationpackage based on the application of the rms phasor based approach to solve the load flow and fault levelalgebraic equations. Fault level calculations are based on the use of IEC 60909, which is considered the mostconservative method of fault level calculation as, due to its assumptions, produces the highest fault level results.This will be used as the basis of design.

    Bustube sizing will be based on the results from ETAP and supporting hand calculations.

    4.0 POWER SYSTEM STUDIES DESIGN CRITERIA

    4.1 Power System Data Documents

    The power system data is based on the following documents provided by the client:

    Tata Steel to OES email dated 21/10/11.

    o Transformer, VCB and cable data

    Tata Steel to OES email dated 26/10/11.

    o N Furnace transformer Electrical study

    o RC Study

    Tata Steel to OES email dated 27/10/11.

    ARC Furnace Tripping Scheme

  • 7/31/2019 Optimised Energy Solutions Report

    7/33

    c. Bustube maximum temperature rise during maximum load conditions = 35C

    d. Bustube emissitivity factor = 0.1 (ability for copper to dissipate generated heat energy byradiation effect)

    3. All fault level calculations have been carried out in accordance with IEC 60909 Short Circuit Currents InThree Phase AC Systems 2001.

    a. All fault impedance was considered zero, i.e. solid short circuit.

    4. Presently, no data has been provided by the client for the earthing study.

    5.0 DESCRIPTION OF POWER SYSTEM STUDIES

    5.1 Power System Study Scenarios

    The power system studies were carried out for the scenarios as the Tata Steel ARC Furnace Tripping Scheme:Rotherham Works Electrical Loading and Supply Capacities, 33 kV furnace board. Based on data from Tat Steelthe following operating configurations were considered:

    Tata Steel The furnace board and the works board are completely independent, this is because of theperformance of a furnace means that we would have a lot of flicker on the works board therefore wehave to have them completely independent.

  • 7/31/2019 Optimised Energy Solutions Report

    8/33

    6.0 POWER SYSTEM STUDIES SUMMARY OF RESULTS

    6.1 Bustube SizingThe bustube sizing calculations were carried out based on the following data and standards:

    UK Copper Development Associationo Publication 22: Copper For Busbars

    BS 7354: 1990: Code of practice for design of high voltage open terminal stations

    BS EN 13600: 2002 Copper and copper alloys Seamless copper tubes for electrical purposes

    The bustube size was selected based on the following parameters: Maximum continuous current based on 132 MVA transformer on full load (2309 A on 33 kV system)

    33 kV substation ambient temperature = 40C (this is on the high side but after the site inspection it wasfound that the 33 kV substation was very warm)

    Bustube maximum temperature rise during maximum load conditions = 35C

    Bustube emissitivity factor = 0.1 (ability for copper to dissipate generated heat energy by radiationeffect)

    Impact of skin effect on bustube rating (skin effect denotes the tendency of AC current to flow awayfrom the centre of a conductor).

    Short circuit withstand current

    Appendix Four shows the standard copper bustube ratings obtained from the UK Copper DevelopmentAssociation.

    OES calculations based on the UK Copper Development Association calculation methods have found that theexisting copper bustube of 50mm diameter with 10mm wall thickness is inadequately rated for the 33 kVcontinuous current of 2309 A for the new 132 MVA transformer.

    It as fo nd that the minim m b s t be si e as 70mm diameter ith a 10 2 mm all This ga e a ma im m

  • 7/31/2019 Optimised Energy Solutions Report

    9/33

    6.2 Minimum Bustube Clearances

    The clearances between the phases and phase to earth should be as follows as a minimum:

    Phase to earth minimum clearance = 500mm

    Phase to phase minimum clearance = 430 mm

    It is recommended that these clearances are exceeded at all times throughout the installation. It is assumed that

    specific vendor equipment purchased for the project is already compatible with the correct clearances based onthe standards governing its design.

    6.3 33 kV Bustube Supports

    The existing supports are based on the use of 33 kV post insulators for indoor substations. The supports willneed to be able to meet the following criteria in order to support the new bustube:

    Be of adequate mechanical strength to support the bustube

    Provide adequate creepage to maintain safe distance between the bustube and earthed steelworksupporting the post insulators.

    Appendix Five shows the proposed new 33 kV post insulators as provided by Connectors and Switchgear in theUK. After discussions with Connectors and Switchgear it is advisable that this 33 kV post insulator is used. Dueto the thickness of the new bustube, the bustube will be adequately supported as long as the distance betweenbrackets is less than 5m. Connectors and Switchgear can provide this information if an order is placed uponthem in the future. Based on the close proximity of the existing supports, the existing support spacings areconsidered adequate to support the new bustube.

  • 7/31/2019 Optimised Energy Solutions Report

    10/33

    CTs need to be rated for the maximum continuous current that can flow on the 33 kV system (2309 A). Basedon this the CTs are inadequately rated for the new transformer. The CT short circuit withstand time could not beobtained from the CT rating plate. It is unknown whether the CT is adequately rated for the short circuit currentscalculated in this report. The client has two options with regard to the CTs:

    Replace CTs for those of an adequate rating for the new transformer

    Carry out detailed testing of the CTs to establish the CT characteristics, this is also important to theprotection study. If the new transformer is energised using these CTs then the client must realise thatthe thermal withstand of the existing CTs could be exceeded, causing CT insulation breakdown and apossible system fault.

    6.5 Fault Study Results

    Tables 1 7 show the fault level results. Full detailed reports are given in Appendix Three of this document.It can be seen that the following Tata Steel electrical network operating configurations give the maximum faultconditions on the network.

    Table 1: Base Case: SGT1B, SGT3, SGT4 in ParallelTable 7: Case 6: SGT3, SGT4, SGT1A in Parallel

    It can be seen that the maximum fault levels on the 33 kV system are:Peak asymmetrical current = 58 kARms symmetrical current = 21.33 kA

    It can be seen that the maximum fault levels on the arc furnace transformer secondary are:Peak asymmetrical current = 647 kA

    R t i l t 240 kA

  • 7/31/2019 Optimised Energy Solutions Report

    11/33

    6.6 Power Flow Study Results

    Tables 8 14 show the power flow results. Full detailed reports are given in Appendix Two of this document.Voltage profiles and equipment power flows are given for the network configurations as described in section 5.1of this report. The 33 kV switchboard voltage is assumed to be at 1 pu based on the grid transformer automaticvoltage control. The power flow results are described below:

    Table 8/8.1: Base Case: SGT1B, SGT3, SGT4 in ParallelFrom Table 8.1, it can be seen that the transformer SGT1B is overloaded at 126 %. This is assumed to be due

    to the operation of the transformer tap changer control scheme. If there is a circulating current automatic voltagecontrol scheme, then any circulating current should be eliminated. It is understood that this is an NGC issue.

    Table 9/9.1: Case 1: SGT1B, SGT3 in ParallelFrom Table 9.1, it can be seen that the transformer SGT1B and SGT3 are overloaded. This isbased on all arc furnaces running. The client should confirm the loading scenario for this case.

    Table 10/10.1: Case 2: SGT1B, SGT3, SGT1A in Parallel

    From Table 10.1, it can be seen that the transformer SGT1B and SGT 1A are overloaded. This is assumed tobe due to the operation of the transformer tap changer control scheme. If there is a circulating current automaticvoltage control scheme, then any circulating current should be eliminated. It is understood that this is an NGCissue.

    Table 11/11.1: Case 3: SGT1B, SGT4 in ParallelFrom Table 11.1, it can be seen that the transformer SGT1B and SGT4 are overloaded. This is based on all arcfurnaces running. The client should confirm the loading scenario for this case.

    T bl 12/21 1 C 4 SGT1B SGT4 SGT1A i P ll l

  • 7/31/2019 Optimised Energy Solutions Report

    12/33

    Optimised Energy Solutions Ltd

    Vanguard House, Daresbury SIC, Keckwick Lane, Daresbury, Cheshire WA4 4AB United KingdomTelephone: 0151 606 422 email: [email protected]

    Registered in England, Company No: 3593777 Registered Office: Vanguard House, Daresbury SIC, Keckwick Lane, Daresbury, Cheshire WA4 4AB

    FAULT STUDY RESULTS FOR DIFFERENT SCENARIOS

    Table 1: Base Case (red coloured font shows worse case fault level)

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD

    Voltage

    Level(kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc(t=60ms)

    Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 647.066 239.743 239.743 183.42 301.86 239.743

    2 33kV - 1 33 57.2 21.334 21.334 14.895 26.019 21.334

    3 33kV-2 33 57.2 21.334 21.334 14.895 26.019 21.334

    4 33kV-3 33 55.409 20.884 20.884 12.681 24.433 20.884

    5 33kV-SGT1B 33 56.394 21.1 21.1 14.134 25.396 21.1

    6 33kV-SGT3 33 56.501 21.116 21.116 14.362 25.537 21.116

    7 33kV-SGT4 33 56.388 21.08 21.08 14.276 25.459 21.08

    8 275kV 275 47.505 16.796 16.796 3.606 17.178 16.796

  • 7/31/2019 Optimised Energy Solutions Report

    13/33

    Optimised Energy Solutions Ltd

    Vanguard House, Daresbury SIC, Keckwick Lane, Daresbury, Cheshire WA4 4AB United KingdomTelephone: 0151 606 422 email: [email protected]

    Registered in England, Company No: 3593777 Registered Office: Vanguard House, Daresbury SIC, Keckwick Lane, Daresbury, Cheshire WA4 4AB

    Table 2: Case 1

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD Voltage

    Level(kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc(t=60ms)

    Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 539.499 203.216 203.216 124.124 238.125 203.216

    2 33kV - 1 33 39.923 14.819 14.819 11.043 18.481 14.819

    3 33kV-2 33 39.923 14.819 14.819 11.043 18.481 14.819

    4 33kV-3 33 39.043 14.601 14.601 17.618 9.859 14.601

    5 33kV-SGT1B 33 39.851 14.798 14.798 10.978 18.425 14.798

    6 33kV-SGT3 33 40.027 14.85 14.85 11.145 18.567 14.85

    7 275kV 275kV 41.472 16.796 16.796 3.606 17.178 16.796

  • 7/31/2019 Optimised Energy Solutions Report

    14/33

    14 | P a g e

    Table 3: Case 2

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD VoltageLevel(kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc(t=60ms)

    Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 625.2 236.486 236.486 136.367 272.987 236.486

    2 33kV - 1 33 55.371 20.644 20.644 14.489 25.221 20.644

    3 33kV-2 33 55.371 20.644 20.644 14.489 25.221 20.644

    4 33kV-3 33 53.691 20.222 20.222 12.398 23.72 20.222

    5 275kV 275 41.472 16.796 16.796 3.606 17.178 16.796

    6 33kV-SGT 1A 33 54.505 20.392 20.392 13.673 24.552 20.392

    7 33kV-SGT 1B 33 54.662 20.438 20.438 13.817 24.67 20.438

    8 33kV-SGT3 33 54.78 20.459 20.459 14.039 24.813 20.459

  • 7/31/2019 Optimised Energy Solutions Report

    15/33

    15 | P a g e

    Table 4: Case 3

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD Voltage

    Level (kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc (t=60ms) Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 534.871 201.433 201.433 123.37 236.21 201.433

    2 33kV - 1 33 39.232 14.56 14.56 10.871 18.171 14.56

    3 33kV-2 33 39.232 14.56 14.56 10.871 18.171 14.56

    4 33kV-3 33 38.382 14.35 14.35 9.725 17.335 14.35

    5 33kV-SGT1B 33 39.181 14.545 14.545 10.828 18.133 14.545

    6 33kV-SGT4 33 39.316 14.586 14.586 10.956 18.242 14.586

    7 275kV 275 41.472 16.796 16.796 3.606 17.178 16.796

  • 7/31/2019 Optimised Energy Solutions Report

    16/33

    16 | P a g e

    Table 5: Case 4

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD Voltage

    Level (kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc (t=60ms) Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 622.293 235.357 235.357 135.951 271.801 235.357

    2 33kV - 1 33 54.748 20.409 20.409 14.351 24.95 20.408

    3 33kV-2 33 54.748 20.409 20.409 14.351 24.95 20.408

    4 33kV-3 33 53.105 19.997 19.997 12.301 23.477 19.997

    5 275kV 275 41.472 16.796 16.796 3.606 17.178 16.796

    6 33kV-SGT1A 33 53.921 20.168 20.168 13.57 24.309 20.168

    7 33kV-SGT1B 33 54.071 20.212 20.212 13.709 24.422 20.212

    8 33kV-SGT4 275 54.091 20.204 20.204 13.849 24.495 20.204

  • 7/31/2019 Optimised Energy Solutions Report

    17/33

    17 | P a g e

    Table 6: Case 5

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD Voltage

    Level (kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)Ibsym(t=60ms)

    Idc (t=60ms) Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 552.316 208.184 208.184 125.988 243.338 208.184

    2 33kV - 1 33 41.902 15.564 15.564 11.494 19.348 15.564

    3 33kV-2 33 41.902 15.564 15.564 11.494 19.348 15.564

    4 33kV-3 33 40.934 15.323 15.323 10.206 18.411 15.323

    5 33kV-SGT3 33 41.939 15.574 15.574 11.539 19.384 15.574

    6 33kV-SGT4 33 41.889 15.559 15.559 11.497 19.346 15.559

    7 275kV 275 47.505 16.796 16.796 3.606 17.178 16.796

  • 7/31/2019 Optimised Energy Solutions Report

    18/33

    18 | P a g e

    Table 7: Case 6 (red coloured font shows worse case fault level)

    S.No

    3P Fault - IEC60909 Methods at the Following Times

    SWBD Voltage

    Level (kV)

    Rating Calculated Results

    Make(kA)

    Break(kA)

    Ip (t=10ms) I

    k(t=0ms)

    Ibsym(t=60ms)

    Idc (t=60ms) Ibasym(t=60ms)

    I k sym

    1 1.2kV SWBD 1.2 633.319 239.658 239.658 137.399 276.251 239.658

    2 33kV - 1 33 57.155 21.321 21.321 14.85 25.983 21.321

    3 33kV-2 33 57.155 21.321 21.321 14.85 25.983 21.321

    4 33kV-3 33 55.368 20.872 20.872 12.645 24.403 20.872

    5 275kV 275 41.472 16.796 16.796 3.606 17.178 16.796

    6 33kV-SGT1A 33 56.175 21.036 21.036 13.934 25.232 21.036

    7 33kV-SGT3 33 56.459 21.103 21.103 14.323 25.505 21.103

    8 33kV-SGT4 33 56.346 21.068 21.068 14.237 25.428 21.068

  • 7/31/2019 Optimised Energy Solutions Report

    19/33

    19 | P a g e

    LOAD FLOW STUDY RESULTS FOR DIFFERENT SCENARIOS WITH TAP SETTINGS (33 kV System Voltage Control)

    Table 8: Base Case: Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage (kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.082 90.17

    33kV - 1 33 32.521 98.55

    33kV - 2 33 32.521 98.55

    33kV - 3 33 32.449 98.33

    33kV - SGT 1B 33 32.575 98.71

    33kV- SGT 3 33 32.591 98.76

    33kV - SGT4 33 32.592 98.76

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    20/33

    20 | P a g e

    Table 8.1: Base Case: Load Flow Branch Power Flow

    ID Type Rating

    Power Flow

    (MVA)

    Real Power

    (P)

    Reactive

    Power (Q) % Loading

    Cable(275kV) Cable 302.81 236.881 188.623

    Cable (SGT4) Cable 120MVA 89.79 78.979 42.717

    Cable (SGT3) Cable 100MVA 93.74 82.453 44.597

    Cable (SGT 1B) Cable 75MVA 84.08 73.988 39.946

    C (33kV-1 - 33kV-2) Cable 117.29 98.24 64.07

    C1(33kV-2 - 33kV-3) Cable 37.39 32.271 18.885

    C2(33kV-2 - 33kV-3) Cable 37.39 32.271 18.885

    C3(33kV-2 - 33kV-3) Cable 42.75 33.699 26.302

    SGT 1B Transf. 2W 75MVA/ 275kV 95.17 74.449 59.289 126.90

    SGT 3 Transf. 2W 120MVA / 275kV 106.05 82.964 66.063 88.4

    SGT 4 Transf. 2W 120MVA / 275kV 101.58 79.468 63.271 84.6

    T (132MVA) Transf. 2W 132MVA /33kV 117.03 98.109 63.8 88.7

  • 7/31/2019 Optimised Energy Solutions Report

    21/33

    21 | P a g e

    Table 9: Case 1: Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage(kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.081 90.08

    33kV - 1 33 32.607 98.81

    33kV - 2 33 32.607 98.81

    33kV - 3 33 32.535 98.59

    33kV - SGT 1B 33 32.688 99.05

    33kV- SGT 3 33 32.712 99.13

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    22/33

    22 | P a g e

    Table 9.1: Case 1: Load Flow Branch Power Flow

    ID Type Rating

    Power Flow

    (MVA) Real Power (P)

    Reactive Power

    (Q)

    %

    Loading

    Cable(275kV) Cable 324.95 238.771 220.41

    Cable (SGT3) Cable 100MVA 141.75 124.683 67.436

    Cable (SGT 1B) Cable 75MVA 127.12 111.882 60.345

    C (33kV-1 - 33kV-2) Cable 117.49 98.573 63.94

    C1(33kV-2 - 33kV-3) Cable 37.46 32.375 18.838

    C2(33kV-2 - 33kV-3) Cable 37.46 32.375 18.838

    C3(33kV-2 - 33kV-3) Cable 42.82 33.824 26.264

    SGT 1B Transf. 2W 75MVA/ 275kV 153.69 112.927 104.249 204.9

    SGT 3 Transf. 2W 120MVA / 275kV 171.26 125.844 116.161 142.7

    T (132MVA) Transf. 2W 132MVA /33kV 117.78 98.44 64.669 88.8

  • 7/31/2019 Optimised Energy Solutions Report

    23/33

    23 | P a g e

    Table10: Case 2: Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage (kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.094 91.17

    33kV - 1 33 32.99 99.97

    33kV - 2 33 32.99 99.97

    33kV - 3 33 32.99 99.97

    33kV - SGT 1B 33 33.05 100.14

    33kV- SGT 3 33 33.062 100.19

    33kV - SGT 1A 33 33.058 100.18

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    24/33

    24 | P a g e

    Table10.1: Case 2: Load Flow Branch Power Flow

    ID Type Rating

    Power Flow

    (MVA)

    Real Power

    (P)

    Reactive

    Power (Q) % Loading

    Cable(275kV) Cable 311.96 243.611 194.859

    Cable (SGT3) Cable 120MVA 98.48 86.667 46.764

    Cable (SGT 1B) Cable 75MVA 88.33 77.77 41.885

    Cable (SGT1A) Cable 75MVA 88.17 77.64 41.793

    C (33kV-1 - 33kV-2) Cable 120.27 100.903 65.451

    C1(33kV-2 - 33kV-3) Cable 38.34 33.14 19.283

    C2(33kV-2 - 33kV-3) Cable 38.34 33.14 19.283

    C3(33kV-2 - 33kV-3) Cable 43.84 34.623 26.885

    Cable (Furnace Board) Cable 87.99 77.565 41.548

    SGT 1B Transf. 2W 75MVA/ 275kV 100.24 78.264 62.629 133.7

    SGT 1A Transf. 2W 75MVA/ 275kV 100.02 78.132 62.446 133.4

    SGT 3 Transf. 2W 120MVA / 275kV 111.70 87.215 69.784 93.1

    T (132MVA) Transf. 2W 132MVA /33kV 120.01 100.767 65.174 90.9

  • 7/31/2019 Optimised Energy Solutions Report

    25/33

    25 | P a g e

    Table11: Case 3: Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage (kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.096 91.33

    33kV - 1 33 33.052 100.16

    33kV - 2 33 33.052 100.16

    33kV - 3 33 32.979 99.94

    33kV - SGT 1B 33 33.136 100.41

    33kV - SGT4 33 33.163 100.49

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    26/33

    26 | P a g e

    Table11.1: Case 3: Load Flow Branch Power Flow

    ID Type Rating PowerFlow

    (MVA) Real Power (P)Reactive Power

    (Q) % Loading

    Cable(275kV)Cable

    335.41 245.388 228.651

    Cable (SGT4)Cable 120MVA

    142.69 125.502 67.902

    Cable (SGT 1B)Cable 75MVA

    133.59 117.569 63.425

    C (33kV-1 - 33kV-2)

    Cable

    120.72 101.279 65.695

    C1(33kV-2 - 33kV-3)Cable

    38.48 33.263 19.355

    C2(33kV-2 - 33kV-3)Cable

    38.48 33.263 19.355

    C3(33kV-2 - 33kV-3)Cable

    44.00 34.752 26.986

    SGT 1BTransf. 2W 75MVA/ 275kV

    162.24 118.692 110.61 216.3

    SGT 4Transf. 2W 120MVA / 275kV

    173.16 126.696 118.042 144.3

    T (132MVA) Transf. 2W 132MVA /33kV 120.45 101.143 65.417 91.3

  • 7/31/2019 Optimised Energy Solutions Report

    27/33

    27 | P a g e

    Table12: Case 4 : Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage (kV) Actual voltage (%)

    1.2 kV SWBD 1.2 1.091 90.92

    33kV - 1 33 32.922 99.76

    33kV - 2 33 32.922 99.76

    33kV - 3 33 32.85 99.55

    33kV - SGT 1B 33 32.978 99.93

    Furnace board 33 32.922 99.76

    33kV - SGT4 33 32.996 99.99

    33kV - SGT 1A 33 32.991 99.97

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    28/33

    28 | P a g e

    Table12.1: Case 4: Load Flow Branch Power Flow

    ID Type RatingPowerFlow

    (MVA)

    Real Power

    (P)

    Reactive

    Power (Q)

    %

    Loading

    Cable(275kV) Cable 311.31 242.632 195.048

    Cable (SGT4) Cable 120MVA 95.38 83.94 45.298

    Cable (SGT 1B) Cable 75MVA 89.32 78.636 42.357

    Cable (SGT1A) Cable 75MVA 89.16 78.505 42.264

    C (33kV-1 - 33kV-2) Cable 119.77 100.485 65.181

    C1(33kV-2 - 33kV-3) Cable 38.19 33.003 19.208

    C2(33kV-2 - 33kV-3) Cable 38.19 33.003 19.208

    C3(33kV-2 - 33kV-3) Cable 43.66 34.488 26.78

    Cable (Furnace Board) Cable 88.97 78.428 42.012

    SGT 1B Transf. 2W 75MVA/ 275kV 101.56 79.143 63.653 135.1

    SGT 1A Transf. 2W 75MVA/ 275kV 101.34 79.01 63.467 135.1

    SGT 4 Transf. 2W 120MVA /275kV 108.40 84.479 67.928 90.3

    T (132MVA) Transf. 2W 132MVA /33kV 119.51 100.35 64.904 90.6

  • 7/31/2019 Optimised Energy Solutions Report

    29/33

    29 | P a g e

    Table13: Case 5: Load Flow Bus Voltage Profile

    Bus ID Nominal (kV) Actual Voltage (kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.088 90.67

    33kV - 1 33 32.81 99.42

    33kV - 2 33 32.81 99.42

    33kV - 3 33 32.738 99.21

    33kV- SGT 3 33 32.912 99.73

    33kV - SGT4 33 32.914 99.74

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    30/33

    30 | P a g e

    Table13.1: Case 5: Load Flow Branch Power Flow

    ID Type Rating

    Power Flow

    (MVA) Real Power (P) Reactive Power (Q) % Loading

    Cable(275kV) Cable 326.97 241.676 220.231

    Cable (SGT4) Cable 120MVA 133.22 117.182 63.373

    Cable (SGT3) Cable 100MVA 139.08 122.335 66.157

    C (33kV-1 - 33kV-2) Cable 118.96 99.802 64.737

    C1(33kV-2 - 33kV-3) Cable 37.92 32.778 19.073

    C2(33kV-2 - 33kV-3) Cable 37.92 32.778 19.073

    C3(33kV-2 - 33kV-3) Cable 43.36 34.245 26.592

    SGT 3 Transf. 2W 120MVA / 275kV 167.01 123.438 112.492 139.2

    SGT 4 Transf. 2W 120MVA / 275kV 159.96 118.238 107.739 133.3

    T (132MVA) Transf. 2W 132MVA /33kV 118.70 99.668 64.463 89.9

  • 7/31/2019 Optimised Energy Solutions Report

    31/33

    31 | P a g e

    Table 14: Case 6: Load Flow Bus Voltage Profile

    Bus ID Nominal kV Actual Voltage (kV) Actual Voltage (%)

    1.2 kV SWBD 1.2 1.078 89.83

    33kV - 1 33 32.53 98.58

    33kV - 2 33 32.53 98.58

    33kV - 3 33 32.458 98.36

    33kV- SGT 3 33 32.599 98.78

    33kV - SGT4 33 32.601 98.79

    33kV - SGT 1A 33 32.596 98.78

    Grid 275 275 100.00

  • 7/31/2019 Optimised Energy Solutions Report

    32/33

    32 | P a g e

    Table 14.1: Case 6: Load Flow Branch Power Flow

    ID Type Rating Power Flow (MVA) Real Power (P)Reactive Power

    (Q)% Loading

    Cable(275kV) Cable 302.45 236.826 188.116

    Cable (SGT4) Cable 120MVA 89.77 79.003 42.626

    Cable (SGT3) Cable 100MVA 93.72 82.478 44.501

    Cable (SGT1A) Cable 75 MVA 83.91 73.887 39.772

    C (33kV-1 - 33kV-2) Cable 116.94 98.106 63.637

    C1(33kV-2 - 33kV-3) Cable 37.28 32.221 18.749

    C2(33kV-2 - 33kV-3) Cable 37.28 32.221 18.749

    C3(33kV-2 - 33kV-3) Cable 42.62 33.664 26.14

    Cable (Furnace Board) Cable 83.74 73.818 39.544

    SGT 1A Transf. 2W 75MVA/ 275kV 94.92 74.345 59.011 126.6

    SGT 3 Transf. 2W 120MVA / 275kV 106.00 82.989 65.946 88.3

    SGT 4 Transf. 2W 120MVA / 275kV 101.53 79.492 63.159 84.6

    T (132MVA) Transf. 2W 132MVA /33kV 116.68 97.974 63.368 88.4

  • 7/31/2019 Optimised Energy Solutions Report

    33/33

    33 | P a g e

    APPENDIX ONE: POWER SYSTEM STUDIES INPUT DATA

    APPENDIX TWO: LOAD FLOW RESULTS

    APPENDIX THREE: FAULT LEVEL RESULTS

    APPENDIX FOUR: STANDARD COPPER BUSTUBE RATINGS

    APPENDIX FIVE: 33 kV POST INSULATOR DATA