oral argument not yet scheduled in the united states...
TRANSCRIPT
ORAL ARGUMENT NOT YET SCHEDULED
IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
Case Nos. 18-1224, 18-1280, 18-1308, 18-1309, 18-1310, 18-1311, 18-1312 and 18-1313 (Consolidated)
ATLANTIC COAST PIPELINE, LLC, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION,
Respondent.
ON PETITIONS FOR REVIEW OF ORDERS OF THE FEDERAL ENERGY REGULATORY COMMISSION
INITIAL BRIEF OF PETITIONER NORTH CAROLINA UTILITIES COMMISSION
Kathleen L. Mazure
Jason T. Gray Kenneth Holmboe Duncan & Allen
1730 Rhode Island Ave. NW Suite 700 Washington, DC 20036
(202) 289-8400 [email protected] [email protected] [email protected]
Attorneys for the North Carolina Utilities Commission
Dated: April 5, 2019
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 1 of 105
1
CERTIFICATE AS TO PARTIES, RULINGS, AND RELATED CASES
Pursuant to Circuit Rule 28(a)(1), Petitioner, the North Carolina Utilities
Commission, files this certificate regarding parties, rulings, and related cases.
A. Rulings Under Review The Federal Energy Regulatory Commission orders under the following
orders:
1. Atl. Coast Pipeline, LLC, Order Issuing Certificates, Docket Nos. CP15-554-000, CP15-554-001, CP15-555-000, and CP15-556-000, 161 FERC ¶ 61,042 (October 13, 2017); and
2. Atl. Coast Pipeline, LLC, Order on Rehearing, Docket Nos. CP15-554-
002, CP15-555-001, and CP15-556-001, 164 FERC ¶ 61,100 (August 10, 2018).
B. Parties and Intervenors
The Petitioner appearing in this Court is the North Carolina Utilities
Commission. The Respondent is the Federal Energy Regulatory Commission.
To counsel’s knowledge, the following additional parties have moved to
intervene in these consolidated proceedings:
Bold Alliance Bold Educational Fund Nancy Kassam-Adams Shahir Kassam-Adams Peter A. Agelasto, III, Individually and as chairman of Rockfish
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 2 of 105
2
Valley Foundation Judith Allen Eleanor M. Amidon Dawn Averitt Jill Averitt Richard Averitt Sandra Smith Averitt, Dr.
James R. Bolton
Constance Brennan
Joyce D. Burton
Carolyn L. Fischer
Bridget K. Hamre
Charles R. Hickox
Demian K. Jackson
Janice Jackson
Lisa Y. Lefferts
William Limpert
David Drake Makel
Carolyn Jane Maki
Wade Neely
Nelson County Creekside, LLC
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 3 of 105
3
Louis Ravina
Rockfish Valley Foundation
Rockfish Valley Investments
Victoria C. Sabin
Alice Rowe Scruby
Timothy Mark Scruby
Marilyn M. Shifflett
Sharon Summers
Chapin Wilson, Jr.
Wintergreen County Store Land Trust
Kenneth M. Wyner
Elizabeth G. Neely
Lora Baum
Victor Baum
Friends of Nelson
Wintergreen Property Owners Association, Inc.
Friends of Wintergreen, Inc.
Fairway Woods Homeowners Condominium Association
North Carolina Utilities Commission
Appalachian Voices
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 4 of 105
4
Chesapeake Climate Action Network
Sierra Club
Cowpasture River Preservation Association
Friends of Buckingham
Highlanders for Responsible Development
Shenandoah Valley Battlefields Foundation
Shenandoah Valley Network
Sound Rivers, Inc.
Virginia Wilderness Committee
Wild Virginia, Inc.
Winyah Rivers Foundation, Inc.
Chesapeake Bay Foundation, Inc.
Piedmont Environmental Council
Atlantic Coast Pipeline, LLC
Chesapeake Climate Action Network
Independent Oil & Gas Association of West Virginia, Inc.
Dominion Energy Transmission, Inc.
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 5 of 105
5
To counsel’s knowledge, the following parties appeared in the underlying
proceeding before the Federal Energy Regulatory Commission regarding Atlantic
Coast Pipeline, LLC, Docket No. CP15-554:
Pamela Farnham
Ernest Reed
Virginia Cross
Misty Boos
Marion Kanour
Christine Stinson
Nancy & Shahir Kassam-Adams
Kenneth Norwood
Kyle Lawrence
Caroline Bray
Suzanne Keller
Melissa Luce
Charlotte Rea
James Bolton
William Fenton
Mark Johnson
Thomas Eick
Michael Tabony
Laura Cross
Melissa Duquette
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 6 of 105
6
Jack Wilson
Carlos Arostegui
R. Craig Cooper
Dimitriyka Holmes
Marilyn Shifflett
Toni Ranieri
Marcia Gibbons
Joanna Salidis
Kate Wofford
Craig Vanderhoef
Hannah Beaman
David Roach
Cheryl Borgman
Lisa Tully
Prem Anjali
John Geary
Travis Geary
Christopher Crum
John Domena
Lawrence Luessen
Neil Gleberman
Kathleen Kelly
Sandee Gammon
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 7 of 105
7
Joanne White
Martha Szczur
Harry Eschenroader
Aurelia Lewis
Randolph Carroll
Diana Henderson
Darlene Spears
Kenneth Webster
Neil Gleberman
Faye Cooper
James Urquhart
Doris Marsh
Amanda Smith
Lawton Smith
Richard Souder
Patricia Kinser
Jill Reed
Victoria Sabin
Jonna Clarkson
Marie Flowers
Jill Averitt
Christina Courtenay
Kerrie Manthey
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 8 of 105
8
Gail Troy
Lee Diehl
Ronald Blake
Adrian Jones
Heidi Berthoud
Dan Lysy
John Laury
Peggy Quarles
David Makel
Martha Makel
Dan Lysy
Paula Alexander
Digna Gantt
Robert Day
Beverly Rayman
Anne Buteau
Dennis Bryant
Bruce Sutton
Samantha Embrey
Kathy Versluys
Trudy Hale
Jane Raup
John Minear
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 9 of 105
9
Michael Manthey
Peter Agelasto
Beth Musick
Richard Averitt
Lisa Lefferts
Elanor Amidon
Alda Curtis
Benjamin Brackett
Sara Agelasto
Philip Gordon
Deanna Lyerly
Christina Wulf
Vanessa McMullen
Nancy Crone
Tom Trykowski
Virginia Davis
Trew Bennett
Beverly McQuary
Robert Whitescarver
Gloria Diggs
James Garner
Janelle Carroll
Richard Brooks
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 10 of 105
10
Cindy Palmer
Brenda Nycum
William Barr
James Raup
Ellen Quade
Paul Leverone
Amelia Williams
Jonathan Norwood
Gavin McClung
Leslie Benz
Heidi Cochran
Elizabeth Tabony
David Holub
Tara Eckenroad
Ronald Fandetti
Joel Bennett
David Collins
Lucas Blanchard
Louis Ravina
David Sandrowitz
Yvette Ravina
Jeffrey Winn
Alen Engle
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 11 of 105
11
Susan Norton
Susan Garcia
Jane Morriss
Eleanor Labiosa
Fred Powell
Pamela Gibson
Jorge Garcia
Diana Woodall
Robert Pritchard
James Campbell
Vicki Wheaton
Ivy Melero Johnson
Eric Madren
Albert Morriss
Andrea Wasiewski
Warren Ross
Julia Araya
Daniel Lamay
Susan Baker
Carell Cassey
Timothy Keefer
Erin Carter
David Schwiesow
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 12 of 105
12
Reese Bull
C. Nelson Hoy
Michael Cook
Jennifer Constine
Peter Winik
Dianna Sicilia
Susanna Williams
Jean McConkey
Erin Johnson
Laurie Sandow
Nancy Avery
Faith Bryant
Heidi Reed
James Kindig
Lawrence Stopper
Richard Averitt
Kristina Adler
John Withers
William Thomson
Eric Lawson
Allen Ray Johnson
Laura Neale
Kenneth Wyner
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 13 of 105
13
Lorne Stockman
Dhyani Simonini
Louanne Fatora
Sandra Averitt
James Klemic
Sherry Robinson
Deborah Kushner
Lisa Madren
John Chaffee
Janice Jackson
Carolyn Maki
Lakshmi Fjord
Laura Greenleaf
Virginia Dawnswir
Catherine McNeal
Charles Hickox
Melanie Cramer
Carter Douglass
William McClain
W. Joseph Vogel
Peter Osborne
Jane Twitmyer
Constance Brennan
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 14 of 105
14
Russell Headley
James Wright
Demian Jackson
Joyce Burton
Carrie Dorsey
Maria Puente-Duany
J. Fulmer
Nancy Wood
David Gleberman
William Monroe
Eva Clarke
Patricia Pile
Chris Asmann
George Pipkin
Barbara Strauss
Nancy Baillie
Erin Shehane
David Sligh
Ruth Hall
Patricia Helterbran
Lynne Williams
David Cole
Jennifer Lewis
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 15 of 105
15
Andrew Friedberg
Thomas Lawless
Eugene Mills
William Baker
Louisa Averitt
Sally Hostetler
Michelle Van Doren
Erin Trzell
Alexa Boker
William Moore
Carl Van Doren
Cynthia Coy
Charles Wineberg
Michael Craig
Asha Greer
Joseph Madison
Karen Osborne
Sarah Ray
Carolyn Fischer
Elizabeth Leverone
Janet Lychock
Mark Graver
Lena Davis
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 16 of 105
16
Pamela Mckeithen
Robert Robinson
Lennice Werth
John McKeithen
Donna Hadden
Anna Samuels
Dane Webster
Swami Dayananda
K. Hanuman
Leslie Cook
Linda Heuer
Sarah Cross
Louise Wood
Maureen Gray
Samantha Gray
Douglas/Yvonne Harris
Sandra Schluadecker
Jonathan Ansell
David Cross
Rosalie Kerr
Bonnie Powell
Timothy Scruby
Alice Scruby
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 17 of 105
17
Jessica Troop
Dawn Averitt
William Goodwin
Sharon Summers
Graham Wiatt
Rebecca Trafton
Kathy Versluys
Martha Szczur
Tim Morse
Chris Wolfertz
Chris Prosise
Charles Burke
Fred Adkins
Anne Bryan
Linda Martin
Bert Carlson
Robert Moody
Ann Warner
Ross Waller
Marian Quinlan
Jeannette Robinson
Richard Watkins
Jean Howell
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 18 of 105
18
Tomas Epling
Lorentz Hodges
Harold King
Richard Brooks
Judy Allen
James McLean
Sally Adkins
James English
John Cowden
Joyce Alexander
Wade Neely
Bonnie Ralston
John Leyzorek
Ricki Carruth
Sarah Irwin
Mary Hodges
Ellen Ford
William Limpert
John Carruth
Mindy Brooks
Amanda McGuire
Scott Miller
Maron Ewald
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 19 of 105
19
Mary Forbes
Dempsie Hevener
William Limpert
Nancy Miller
Jackie Tan
Ronald Carpenter
Marjorie Hevener
Terry Jackson
Diana Green
Elfrieda McDaniel
Anthony Malanka
Karen Kelly
James Peterson
Maura McLaughlin
Carol Allen
Gil Willis
Stephanie Macgill
William Alexander
James Rice
Ann Williams
Mary Willis
William Smithdeal
Eileen Smithdeal
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 20 of 105
20
Tom Shipley
George Bell
Jeanne Bell
Philip Deemer
Edward Laikin
Beverley Vernon
Eric Clegg
Sharon Frazier
Aaron Cumashot
Graham Bell
Douglas Leslie
Michael Frazier
Judith Clark
Janet Starr
Daron Dean
Joseph Murray
Billy Crum
Elizabeth Dean
Laura Smith-Hos
Lisa Dean
Frank Reichel
Leslie King
Paul Benson
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 21 of 105
21
April Moncrief
Barry Marshall
Amy Scott
Gil Willis
Julie Weaver
George Phillips
Teresa Ling
Paul Filmer
Carson Ralston
William Limpert
Thomas Epling
Else Lauterbach
K Carpenter
William Moore
Helen Kimble
Russell Holt
Roberta Koontz
David Cowden
Brett Jones
Ann Mellen
Alain San Giorgio
K Hanuman
Charles Goodwin
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 22 of 105
22
Thomas Callahan
Colin Winter
Gordon Lipscombe
Morgan Lanier
Roberta Koontz
Sara Might
Richard Averitt
Paul Leverone
Mary Hoffman
Homer Bauserman
Hunter Gallimore
Kerrie Manthey
Tyler Paul
Energy Sure
Malcom Cameron
Aaron Kemmerer
Atlantic Coast Pipeline, LLC
County of Augusta
Dividing Waters Farm
The Wilderness
Dominion Pipeline Monitoring Coalition
Dominion Transmission, Inc.
Duke Energy Carolinas, LLC
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 23 of 105
23
Duke Energy Progress, LLC
Fayetteville Public Works Commission
Fenton Family Holdings, LLC
Fenton Inn, LLC
Heather Louie Finch
Jane Flowers Finch
Lamm Pearl Finch
Wade Raymond Finch
First Energy Service Company
Free Nelson
Friends of Buckingham
Friends of Nelson
Friends of Shenandoah Mountain
Friends of the Central Shenandoah
Friends of the Middle River
Friends of Water WV
Friends of Wintergreen, Inc.
Garden Ridge Camp, LLC
Greenville Utilities Commission
Hatchery Run Homeowners Association, Inc.
Headwaters Defense
Heartwood
Highland County Cave Survey
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 24 of 105
24
Highlanders for Responsible Development
Hop Gas, Inc.
Horizons Village
Clark A. Chinn
Georgianna Reid
IOGA of West Virginia
Jackson River Preservation Association Inc.
James River Association
Laborers International Union of NA
Monroe Institute
Natural Resources Defense Council
NC Warn
Nelson County Board of Supervisors
Nelson Hilltop, LLC
New Jersey Natural Gas Co.
NJR Energy Services Co.
North Carolina Electric Membership Corp.
North Carolina Farm Bureau Federation
North Carolina Utilities Commission
Ohio Valley Environmental Coalition
Peoples Gas WV LLC
Peoples Natural Gas Company LLC
Peoples TWP LLC
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 25 of 105
25
Piedmont Natural Gas Company, Inc.
Potomac Appalachian Trial Club – Southern Shenandoah Valley Chapter
Preservation Virginia
Public Service Company of North Carolina, Inc.
ROC Hard Partners, LLC
Rockfish Valley Foundation
Rockfish Valley Investments, LLC
Shenandoah Riverkeeper
Shenandoah Valley Battlefields Foundation
Shenandoah Valley Network
Slatyfork Farm Owners
Southern Environmental Law Center
Sunset Mountain Enterprises, Inc.
The Fairway Woods Homeowners Condominium Association
Trout Unlimited, Inc.
Valley Conservation Council, Inc.
Virginia Chamber of Commerce
Virginia Natural Gas, Inc.
Virginia Outdoors Foundation
Virginia Polytechnic Institute & State
Virginia Power Services Energy Corp, Inc.
Virginia Tech
Virginia Wilderness Committee
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 26 of 105
26
Washington Gas Light Company
Waterkeepers Chesapeake
West Virginia Oil and Natural Gas Association
West Virginia State Building and Construction Trades Council – AFL-CIO
White’s Wayside
Wild Virginia
Wintergreen Pacific, LLC
Wintergreen Property Owners Association Inc.
Winyah Rivers Foundation, Inc.
To counsel’s knowledge, the following parties appeared in the underlying
proceeding before the Federal Energy Regulatory Commission regarding Dominion
Transmission, Inc., Docket No. CP15-555:
Ernest Reed
Eleanor Amidon
William McClain
Debra Borowiec
Barbara Sims
Charlotte Rea
Christina Woods
Judith Mohr
Tyler Paul
James Rice
Edward Laikin
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 27 of 105
27
Richard Averitt
Allegheny Defense Project
Appalachian Mountain Advocates
Atlantic Coast Pipeline, LLC
Piedmont Natural Gas Company, Inc.
Atmos Energy Corp.
Atmos Energy Marketing LLC
Blue Ridge Environmental Defense League
Cabot Oil and Gas Corporation
Chesapeake Bay Foundation, Inc.
City of Richman, VA
City of Rocky Mount, NC
Clean Air Council
Dominion Transmission Inc.
Duke Energy Carolinas, LLC
Duke Energy Progress, LLC
Exelon Corporation
Fenton Inn, LLC
FirstEnergy Service Co.
Friends of Nelson
Greenville Utilities Commission
Headwaters Defense
Heartwood
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 28 of 105
28
Highlanders for Responsible Development
Hope Gas, Inc.
IOGA of West Virginia
Natural Resources Defense Council
NC WARN
New Jersey Natural Gas Co.
NJR Energy Services Co.
North Carolina Electric Membership Corp.
North Carolina Utilities Commission
Ohio Valley Environmental Coalition
Peoples Gas WV LLC
Peoples Natural Gas Company LLC
Peoples TWP LLC
Public Service Company of North Carolina, Inc.
Shenandoah Battlefields Foundation
Shenandoah Valley Network
South Carolina Office of Regulatory Staff
Southern Environmental Law Center
Trout Unlimited, Inc.
UGI Distribution Companies
Virginia Natural Gas, Inc.
Virginia Power Services Energy Corp, Inc.
Virginia Wilderness Committee
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 29 of 105
29
Washington Gas Light Co.
West Virginia oil and Natural Gas Association
West Virginia State Building and Construction Trades Council- AFL-CIO
Wild Virginia
C. Related Cases Case Nos. 18-1018, et al. before this Court, raised the same substantive issues
that the North Carolina Utilities Commission is raising with respect to Dominion
Transmission, Inc. Case Nos. 17-1721 and 18-1128 both address the policy allowing
new-entrant pipelines to develop recourse rates using a 14% return on equity, which
NCUC raises herein concerning Atlantic Coast Pipeline, LLC.
Dated: April 5, 2019 Respectfully submitted,
/s/ Kathleen L. Mazure Kathleen L. Mazure Jason T. Gray Kenneth Holmboe Duncan & Allen 1730 Rhode Island Ave. NW Suite 700 Washington, DC 20036 (202) 289-8400 [email protected] [email protected] [email protected] (202) 289-8400 (Telephone) (202) 289-8450 (Facsimile) Attorneys for the North Carolina Utilities Commission
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 30 of 105
1
RULE 26.1 CORPORATE DISCLOSURE STATEMENT FOR CASE NOS. 18-1018, 18-1019, and 18-1020
Pursuant to Rule 26.1 of the Federal Rules of Appellate Procedure and Rule
26.1 of the Circuit Rules for the United States Court of Appeals for the District of
Columbia Circuit, the North Carolina Utilities Commission (“NCUC”) states that it
is a regulatory body organized and existing under the laws of the State of North
Carolina. N.C. GEN. STAT. § 62, et seq. (2017). As a political subdivision of the
State of North Carolina, the NCUC is not a non-governmental corporate entity
subject to the requirements of Rule 26.1 of the Federal Rules of Appellate Procedure
and Rule 26.1 of the Rules of this Court.
Dated: April 5, 2019 Respectfully submitted,
/s/ Kathleen L. Mazure Kathleen L. Mazure Jason T. Gray Kenneth Holmboe Duncan & Allen 1730 Rhode Island Ave. NW Suite 700 Washington, DC 20036 (202) 289-8400 [email protected] [email protected] [email protected] (202) 289-8400 (Telephone) (202) 289-8450 (Facsimile) Attorneys for the North Carolina Utilities Commission
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 31 of 105
i
TABLE OF CONTENTS
TABLE OF AUTHORITIES ................................................................................ ii
GLOSSARY OF ABBREVIATED TERMS ..................................................... vii
JURISDICTIONAL STATEMENT ..................................................................... 1
STATUTES AND REGULATIONS .................................................................... 6
STATEMENT OF ISSUES ................................................................................... 6
STATEMENT OF THE CASE AND STATEMENT OF THE FACTS .......... 7
STATEMENT OF RULINGS PRESENTED FOR REVIEW ........................ 11
SUMMARY OF THE ARGUMENT ................................................................. 11
STANDING ........................................................................................................... 12
ARGUMENT ........................................................................................................ 15
A. The Challenged Orders Failed to Consider or Apply FERC’s Consumer-Protection Policies. ....................................................... 16
B. The Record is Devoid of Any Evidence Demonstrating that a 13.7% Pre-Tax Return or 14% ROE Reflect Current Capital Market Conditions. ......................................................................... 21
C. FERC’s “Hold the Line” Rationale is Flawed. ............................. 24
CONCLUSION ..................................................................................................... 26
CERTIFICATE OF COMPLIANCE
STATUTORY ADDENDUM
CERTIFICATE OF SERVICE
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 32 of 105
ii
TABLE OF AUTHORITIES
COURT CASES ANR Pipeline Co. v. FERC, 771 F.2d 507 (D.C. Cir. 1985) ............................................................................ 15 *ANR Pipeline Co. v. FERC, 71 F.3d 897 (D.C. Cir. 1995) ........................................................................ 16, 21 *Atl. Ref. Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378 (1959) ................................................................................ 16, 17, 26 *Bluefield Waterworks & Improvement Co. v. Pub. Serv. Comm’n of W. Va, 262 U.S. 679 (1923) ................................................ 8, 18 Burlington Truck Lines, Inc. v. United States, 371 U.S. 156 (1962) ............................................................................................ 16 Cal. Gas Producers Ass’n v. FPC, 421 F.2d 422 (9th Cir. 1970) .................................................................... 7, 16, 26 Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289 (D.C. Cir. 2001) ............................................................................ 20 City of Tacoma v. FERC, 331 F.3d 106 (D.C. Cir. 2003) .............................................................................. 5 Ciba-Geigy Corp. v. EPA, 801 F.2d 430 (D.C. Cir. 1986) .............................................................................. 5 Emera Maine,
854 F.3d 9 (D.C. Cir. 2017) .......................................................................... 22, 24 Elec. Power Supply Ass’n v. FERC, 136 S. Ct. 760 (2016) .................................................................................... 22, 24 Cases principally relied on are marked with an asterisk (*).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 33 of 105
iii
FPC v. Hope Natural Gas Co., 320 U.S. 591 (1944) ........................................................................................ 8, 18 Great Lakes Gas Transmission Ltd. P’ship v. FERC, 984 F.2d 426 (D.C. Cir. 1993) ............................................................................ 17 Lujan v. Defs. of Wildlife, 504 U.S. 555 (1992) ............................................................................................ 12 *Mo. Pub. Serv. Comm’n v. FERC, 337 F.3d 1066 (D.C. Cir. 2003) ...................................................................... …26 *Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) .............................................................................................. 16 *Nat’l Mining Ass’n v. McCarthy, 758 F.3d 243 (D.C. Cir. 2014) ............................................................................ 24 *Pac. Gas & Elec. Co. v. FPC, 506 F.2d 33 (D.C. Cir. 1974) .............................................................................. 24 *PPL Wallingford v. FERC, 419 F.3d 1194 (D.C. Cir. 2005) .................................................................... 16, 20 Pub. Sys. v. FERC, 606 F.2d 973 (D.C. Cir. 1979) ........................................................................ 7, 16 S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014) .............................................................................. 15 Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520 (D.C. Cir. 2010) ............................................................................ 15 TNA Merch. Projects, Inc. v. FERC, 616 F.3d 588 (D.C. Cir. 2010) ............................................................................ 15 Williams Gas Processing-Gulf Coast Co., L.P. v. FERC, 475 F.3d 319 (D.C. Cir. 2006) ............................................................................ 16
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 34 of 105
iv
ADMINISTRATIVE DECISIONS Atl. Coast Pipeline, LLC,
161 FERC ¶ 61,042 (2017) ........................ 1, 2, 3, 8, 9, 11, 13, 14, 15, 19, 20, 24 Atl. Coast Pipeline, LLC,
164 FERC ¶ 61,100 (2018) .................................... 1, 5, 10, 11, 15, 19, 20, 22, 25 Alternatives to Traditional Cost-of-Service Ratemaking for Natural Gas Pipelines, 70 FERC ¶ 61,139 (1995) ....................................... 17 *Alternatives to Traditional Cost-of-Service Ratemaking for Natural
Gas Pipelines, Regulation of Negotiated Transportation Services, 74 FERC ¶ 61,076 (1996), order on clarification, 74 FERC ¶ 61,194 (1996), reh’g denied, 75 FERC ¶ 61,024 (1996), petitions for review denied sub nom. Burlington Res. Oil & Gas Co. v. FERC, 172 F.3d 918
(D.C. Cir. 1998) ..............................................................................2, 7, 14, 17, 18 Interstate and Intrastate Natural Gas Pipeline, Rate Changes Relating to Federal Income Tax Rate, 162 FERC ¶ 61,226 (2018) ................................................................................. 26 N. Natural Gas Co., 105 FERC ¶ 61,299 (2003) ................................................................................. 18 Natural Gas Pipeline Co. of America, 101 FERC ¶ 61,125 (2002) ................................................................................. 18 *Natural Gas Pipeline Negotiated Rate Policies and Practices; Modification of Negotiated Rate Policy, 104 FERC ¶ 61,134 (2003), order on reh’g and clarification, 114 FERC ¶ 61,042 (2006), dismissing reh’g and denying clarification, 114 FERC ¶ 61,304 (2006) ........................................... 2, 7 Portland Natural Gas Transmission Sys., Opinion No. 510-A, 142 FERC ¶ 61,198 (2013) order on request for rehearing and refund report, Opinion No. 510-B, 150 FERC ¶ 61,106 (2015) ................. 18
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 35 of 105
v
Transcon. Gas Pipe Line Co., LLC, 156 FERC ¶ 61,022 (2016) ................................................................................. 20 WestGas InterState Inc., 59 FERC ¶ 61,029 (1992) ................................................................................... 26 FEDERAL STATUTES 5 U.S.C. § 706 .......................................................................................................... 15 15 U.S.C. § 717a(6) ................................................................................................... 1 15 U.S.C. § 717a(8) ................................................................................................. 13 15 U.S.C. § 717c .................................................................................................. 7, 16 15 U.S.C. § 717f(c) .......................................................................................... 1, 8, 16 15 U.S.C. § 717n(e) ................................................................................................. 13 15 U.S.C. § 717r(a) .................................................................................................... 3 15 U.S.C. § 717r(b) .................................................................................................... 6 STATE STATUTES N.C. GEN. STAT. § 62-2 ............................................................................................ 13 N.C. GEN. STAT. § 62-32 .......................................................................................... 13 N.C. GEN. STAT. § 62-36.01 ..................................................................................... 13 N.C. GEN. STAT. § 62-48 .......................................................................................... 13 N.C. GEN. STAT. § 62-133.4 ..................................................................................... 13
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 36 of 105
vi
REGULATIONS 18 C.F.R. § 385.207 .................................................................................................... 3 18 C.F.R. § 385.214(a)(2) ......................................................................................... 13 18 C.F.R. § 385.713 .................................................................................................... 3
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 37 of 105
vii
GLOSSARY OF ABBREVIATED TERMS
Abbreviation Full Term ACP Application The Application that Atlantic Coast Pipeline,
LLC, filed under Section 7 of the Natural Gas Act on September 18, 2015 in Docket No. CP15-554 before the Federal Energy Regulatory Commission seeking a certificate to construct and operate a new pipeline.
Alternative Rates Policy Statement
Alternatives to Traditional Cost-of-Service Ratemaking for Natural Gas Pipelines, Regulation of Negotiated Transportation Services, 74 FERC ¶ 61,076 (1996), order on clarification, 74 FERC ¶ 61,194 (1996), reh’g denied, 75 FERC ¶ 61,024 (1996), petitions for review denied sub nom. Burlington Res. Oil & Gas Co. v. FERC, 172 F.3d 918 (D.C. Cir. 1998).
CATCO Atl. Ref. Co. v. Public Serv. Comm’n of N.Y., 360 U.S. 378 (1959).
Certificate Order Atlantic Coast Pipeline, LLC, 161 FERC ¶ 61,042 (2017).
DCF discounted cash flow DTI Application The Application that Dominion Transmission
Inc. filed under Section 7 of the Natural Gas Act on September 18, 2015 in Docket No. CP15-555 before the Federal Energy Regulatory Commission seeking a certificate to construct and operate the Supply Header Project
FERC Respondent, Federal Energy Regulatory Commission
JA Joint Appendix NCUC Petitioner, North Carolina Utilities Commission
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 38 of 105
viii
Abbreviation Full Term Negotiated Rate Policy Statement
Natural Gas Pipeline Negotiated Rate Policies and Practices; Modification of Negotiated Rate Policy, 104 FERC ¶ 61,134 (2003), order on reh’g and clarification, 114 FERC ¶ 61,042 (2006), dismissing reh’g and denying clarification, 114 FERC ¶ 61,304 (2006).
NGA Natural Gas Act NCUC’s CP15-554 Protest The North Carolina Utilities Commission’s
Comments in Support of Project and Protest of Proposed Recourse Rates, submitted on October 23, 2015 in Docket No. CP15-554
NCUC’s CP15-555 Protest The North Carolina Utilities Commission’s Notice of Intervention, Comments in Support of Project and Protest of Proposed Recourse Rates, submitted on October 23, 2015 in Docket No. CP15-555
NCUC’s CP15-554 Rehearing The North Carolina Utilities Commission’s request for rehearing, submitted on November 13, 2017 in Docket No. CP15-554.
NCUC’s CP15-555 Rehearing The North Carolina Utilities Commission’s request for rehearing, submitted on November 13, 2017 in Docket No. CP15-555.
p. Citation to “page(s)” in FERC Orders P Citation to “Paragraph(s)” in FERC Orders Piedmont Piedmont Natural Gas Company, Inc. PSNC Public Service Company of North Carolina, Inc. R. Citation Referring to the Certified Index of the
Record Filed in Case No. 18-1224 Recourse rate Rates designed on a cost-of-service, as opposed
to negotiated, basis and set forth in a pipeline’s tariff
Rehearing Order Atlantic Coast Pipeline, LLC, 164 FERC ¶ 61,100 (2018).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 39 of 105
1
JURISDICTIONAL STATEMENT
Petitioner in Case No. 18-1280, North Carolina Utilities Commission
(“NCUC”) challenges orders of Respondent, Federal Energy Regulatory
Commission’s (“FERC”), issuing certificates for new interstate natural gas pipeline
facilities:
Atl. Coast Pipeline, LLC, 161 FERC ¶ 61,042 (2017) (“Certificate Order”).1
Atl. Coast Pipeline, LLC, 164 FERC ¶ 61,100 (2018) (“Rehearing
Order”).2
NGA Section 7(c) requires FERC to determine whether certificate proposals
are required by the public convenience and necessity.3 Atlantic Coast Pipeline, LLC
(“ACP”) and Dominion Transmission, Inc. (“DTI”) are natural gas pipeline
companies under NGA Section 2(6).4 On September 18, 2015, DTI filed an
application for its Supply Header Project to provide service from supply areas on
DTI’s system to ACP (“DTI Application”).5 The DTI Application was assigned
Docket No. CP15-555. That same day, ACP filed an application to construct new
1 R.13700; [JA ____]. 2 R.14312; [JA ____]. 3 15 U.S.C. § 717f(c)(1)(A). 4 15 U.S.C. § 717a(6). 5 R.3535, DTI Application, at 1; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 40 of 105
2
facilities in West Virginia, Virginia, and North Carolina (“ACP Application”).6 The
ACP Application was assigned Docket No. CP15-554. ACP/DTI proposed to
provide service under “negotiated” rates.7 ACP will use its and the DTI capacity to
serve two North Carolina utilities that NCUC regulates, Piedmont Natural Gas
Company, Inc. (“Piedmont”) and Public Service Company of North Carolina, Inc.,
(“PSNC”).8 Therefore, NCUC’s constituents, i.e., North Carolina ratepayers, will
pay a portion the costs of ACP’s/DTI’s projects.
NCUC filed separate, timely Notices of Intervention in both proceedings9 and
separate comments supporting ACP’s/DTI’s respective projects but protesting their
proposed recourse rates.10 NCUC argued that the agreed-upon negotiated rates are
tainted because FERC failed to apply its policies11 that require pipelines to offer valid
6 R.3532, ACP Application, at 1-2; [JA ____-____]. 7 Id., 25; R.3535, DTI Application, at 16; [JA ____; ____]. 8 R.3942, Piedmont Comments, at 3-4; R.4204, PSNC Comments, at 5-6; R.13700, Certificate Order, at PP 7, 9; [JA ____; ____; ____]. 9 R.3694; R.4182 [JA ____; ____]. 10 R.4181; R.4182 [JA ____; ____]. 11 Alternatives to Traditional Cost-of-Service Ratemaking for Natural Gas Pipelines, Regulation of Negotiated Transportation Services, 74 FERC ¶ 61,076 (1996), order on clarification, 74 FERC ¶ 61,194, reh’g denied, 75 FERC ¶ 61,024, petitions for review denied sub nom. Burlington Res. Oil & Gas Co. v. FERC, 172 F.3d 918 (D.C. Cir. 1998) (“Alternative Rates Policy Statement”); Natural Gas Pipeline Negotiated Rate Policies and Practices; Modification of Negotiated Rate Policy, 104 FERC ¶ 61,134 (2003), order on reh’g and clarification, 114 FERC ¶
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 41 of 105
3
recourse rates during rate negotiations to prevent pipelines from exercising market
power when negotiating rates in 2015.12 Instead, DTI calculated recourse rates using
its last-stated pre-tax return of 13.70%, established in 199713 and ACP calculated
recourse rates using a 14% return-on-equity (“ROE”).14 NCUC concluded
ACP’s/DTI’s recourse rates could not serve as the requisite check on pipeline market
power because they were overstated and unsupported.15 Over NCUC’s objections,
FERC’s Certificate Order granted ACP’s/DTI’s applications.16
NCUC submitted separate, timely rehearing requests under NGA Section
19(a)17 and FERC Rules 207 and 713.18 Concerning DTI, NCUC argued:
It was error, and not the product of reasoned decision-making, for [FERC] to allow DTI to establish recourse rates that do not take into account the significant changes in the financial markets that have
61,042 (2006), dismissing reh’g and denying clarification, 114 FERC ¶ 61,304 (“Negotiated Rate Policy Statement”). 12 R.4181, NCUC’s CP15-554 Protest, at 3-4; R.4182, NCUC’s CP15-555 Protest, at 4-5; [JA ____-____; ____-____]. 13 R.4182, NCUC’s CP15-555 Protest, at 5-8 (discussing R.3535, DTI Application, at 17, Exhibit P); [JA ____-____]. 14 R.4181, NCUC’s CP15-554 Protest, at 4-7 (discussing R.3532, ACP Application, at 30, Exhibit P); [JA ____-____]. 15 R.4181, NCUC’s CP15-554 Protest, at 3-7; R.4182, NCUC’s CP15-555 Protest, at 4-8; [JA ____-____; ____-____]. 16 R.13700, Certificate Order, at PP 101-04, 110-11; [JA ____-____, ____-____]. 17 15 U.S.C. § 717r(a). 18 18 C.F.R. §§ 385.207, 385.713.
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 42 of 105
4
occurred since DTI’s last rate case established a stated pre-tax return, which DTI used to calculate recourse rates in this case. That finding is inconsistent with (1) [FERC’s] obligations under the NGA; (2) FERC’s acknowledgment that the predicate for allowing a pipeline to charge a negotiated rate is that capacity is available at the recourse rate; and (3) [FERC] precedent recognizing the importance of using current market conditions to develop capital costs.19
Concerning ACP, NCUC argued:
1) It was error, and not the product of reasoned decision-making, for [FERC] to approve ACP’s proposed recourse rates, which used an unsupported and overstated 14 percent ROE. [FERC’s] analysis improperly relied on prior cases where FERC allowed a 14 percent ROE for new entrant pipelines, without providing any analysis of a proper ROE for ACP based on the facts of this case. FERC’s acceptance of the 14 percent ROE is inconsistent with (1) [FERC’s] obligations under the NGA; (2) court and [FERC] precedent recognizing the importance of using current market conditions to develop capital costs; and (3) any ROE approved for any pipeline after proper analysis in the past several years.
2) It was error, and not the product of reasoned decision-making, for [FERC] to allow ACP to enter into negotiated rate agreements without ensuring at the time those negotiated rates were entered into that the market power of the pipeline was checked via recourse rates that are not overstated. The failure to ensure that the negotiated rates were not tainted by the exercise of market power by the pipeline is inconsistent with (1) [FERC’s] obligations under the NGA; (2) FERC’s acknowledgment that the predicate for allowing a pipeline to charge a negotiated rate is that capacity is available at an appropriate recourse rate; and (3) court and [FERC] precedent recognizing the importance of using current market conditions to develop capital costs. [FERC’s] proposed remedy—to address rate of return and other cost of service elements after ACP files a cost and revenue study after three years of service, ignores the excessive ROE granted to ACP in the instant
19 R.13765, NCUC’s CP15-555 Rehearing, at 3-4; [JA ____-____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 43 of 105
5
proceeding that therefore fails to provide the needed check on ACP’s market power during the time period when ACP and its shippers agreed to negotiated rates.20
FERC rejected NCUC’s ACP rehearing request.21 Other than a blanket
dismissal in Order Paragraph (A), FERC did not explicitly address NCUC’s DTI
rehearing request. To conserve resources and promote administrative efficiency and
comity, NCUC sought expedited reconsideration so FERC could address NCUC’s
DTI rehearing request before the deadline for petitions for review.22 FERC never
acted on NCUC’s motion.
FERC’s orders issued certificates to construct facilities in North Carolina and
relied on negotiated-rate contracts with North Carolina utilities to find need, the
costs of which will be recovered from North Carolina ratepayers. Therefore, those
orders “firmly establish [FERC’s] position on the issues under review” and
“represent a ‘definitive [position that] has a direct and immediate . . . effect on the
day-to-day business of the parties challenging the action,’ manifesting that the orders
are sufficiently final for judicial review.”23 NCUC timely petitioned this Court to
20 R.13766, NCUC’s CP15-554 Rehearing, at 3; [JA ____] (footnotes omitted). 21 R.14312, Rehearing Order, at PP 64-74; [JA ____-____]. 22 See Docket No. CP15-555, NCUC’s Motion for Expedited Reconsideration; [JA ____]. 23 City of Tacoma v. FERC, 331 F.3d 106, 113 (D.C. Cir. 2003) (quoting Ciba-Geigy Corp. v. EPA, 801 F.2d 430, 436 (D.C. Cir. 1986)).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 44 of 105
6
review FERC’s orders per NGA Section 19(b).24 Jurisdiction is established by NGA
Section 19(b), Rule 15(a) of the Federal Rules of Appellate Procedure, and Circuit
Rule 15, as FERC’s orders constitute final judgments disposing of NCUC’s claims
and rendering NCUC aggrieved.
STATUTES AND REGULATIONS
Pertinent statutes and regulations are in the attached addendum.
STATEMENT OF ISSUES
1. Whether FERC acted arbitrarily and capriciously by failing to respond to
NCUC’s arguments on rehearing regarding DTI.
2. Whether FERC erred, failed to engage in reasoned decision-making, failed
to fulfill its consumer-protection obligations under the NGA, failed to
apply its own Alternative Rates Policy Statement and Negotiated Rate
Policy Statement—which require valid recourse rates be available to
shippers to serve as a check against the potential exercise of pipeline
market power at the time shippers are entering into negotiated rate
contracts for transportation service—or failed to explain its departure from
precedent, by relying on the existence of negotiated rate agreements to
make a determination of need under NGA Section 7 for the construction
of facilities in North Carolina, and relied on negotiated-rate contracts with
24 15 U.S.C. § 717r(b).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 45 of 105
7
North Carolina utilities to find need, the costs of which will be recovered
from North Carolina ratepayers, despite the fact that DTI calculated its
recourse rates using an outmoded, stale, and excessive return and ACP
calculated its recourse rates using a return that was “derived from another
case and another pipeline.”25
STATEMENT OF THE CASE AND STATEMENT OF THE FACTS
This appeal involves FERC policies that should work in concert and be
considered to fulfill the NGA’s consumer-protection mandate.26 One set of
policies—FERC’s Alternative Rates and Negotiated Rates Policy Statements—
permits pipelines to negotiate individualized rates that are not based on FERC’s
traditional approach of basing rates on the pipeline’s the cost-of-service.27 Those
policies require pipelines to make cost-of-service (i.e., recourse) rates available to
shippers negotiating rates to prevent pipelines from exercising market power during
negotiations.28 Another policy requires pipelines’ returns—i.e., the authorized
25 Sierra Club v. FERC, 867 F.3d 1357, 1378 (D.C. Cir. 2017). 26 See Cal. Gas Producers Ass’n v. FPC, 421 F.2d 422, 428 (9th Cir. 1970) (FERC’s “primary duty under the Natural Gas Act is the protection of the consumer”); see also Pub. Sys. v. FERC, 606 F.2d 973, 979 n.27 (D.C. Cir. 1979) (citing 15 U.S.C. § 717c(a), (b)). 27 Alternative Rates Policy Statement, at p. 61,240. 28 Id., at pp. 61,240-41; see also Negotiated Rate Policy Statement, at P 4.
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 46 of 105
8
profit pipelines may earn on investment—to be based on current capital market
conditions.29
In NGA Section 7(c) proceedings, FERC determines whether to issue
certificates of public convenience and necessity for new interstate pipeline
facilities.30 To promote expediency, FERC allows existing pipelines to calculate
recourse rates using their last-stated return,31 and new-entrant pipelines to calculate
recourse rates using a 14% ROE and 50/50 capital structure.32 The consumer
protections embedded in the Alternative Rates and Negotiated Rate Policy
Statements, and the requirement that returns reflect current capital market
conditions, must be considered, and should trump, the expediency-based policies.
Below, ACP/DTI sought certificates to construct new pipeline facilities.33 All
services ACP/DTI contracted to provide over the new facilities are under negotiated
rates,34 which should have triggered FERC’s Alternative Rates and Negotiated Rates
29 FPC v. Hope Natural Gas Co., 320 U.S. 591, 603 (1944); Bluefield Waterworks & Improvement Co. v. Pub. Serv. Comm’n of W. Va, 262 U.S. 679, 692-93 (1923). 30 15 U.S.C. § 717f(c). 31 R.13700, Certificate Order, at P 110 n.163; [JA ____]. 32 Id., at P 102; [JA ____]. 33 R.3535, DTI Application, at 1; R.3532, ACP Application, at 1-2; [JA ____; ____-____]. 34 R.3535, DTI Application, at 16-17; R.3532, ACP Application, at 25, 31; [JA ____-____; ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 47 of 105
9
Policy Statements. Rather than demonstrate compliance or show the proposed
returns used to calculate recourse rates reflected current capital market conditions,
DTI only followed the last-stated return policy35 and ACP only followed the policy
allowing new-entrant pipelines to calculate recourse rates using a 14% ROE.36
NCUC protested, arguing application of those policies below produced
excessive and unsupported recourse rates contrary to the Alternative Rates and
Negotiated Rate Policy Statements.37
FERC’s Certificate Order rejected NCUC’s protests.38 For DTI, FERC held
application of its last-stated return policy “is an appropriate exercise of its
discretion” because DTI’s initial rates “will ‘hold the line’ until just and reasonable
rates are adjudicated under section 4 or 5 of the NGA.”39 FERC found ACP’s
proposed 14% ROE “reasonably reflect[s]” current policy for new-entrant
pipelines.40 Without explanation, FERC ignored NCUC’s arguments concerning the
Alternative Rates and Negotiated Rate Policy Statements.
35 R.3535, DTI Application, Exhibit P at 4; [JA ____]. 36 R.3532, ACP Application, at 30; [JA ____]. 37 R.4182, NCUC’s CP15-555 Protest, at 5-7; R.4181, NCUC’s CP15-554 Protest, at 5-7; [JA ____-____; ____-____]. 38 R.13700, Certificate Order, at PP 97-104, 107-111 [JA ____-____, ____-____]. 39 Id., at P 111; [JA ____]. 40 Id., at P 104; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 48 of 105
10
NCUC filed separate, timely rehearing requests.41 Concerning DTI, NCUC
acknowledged FERC’s last-stated return policy but highlighted FERC’s obligation
to justify application of its policies.42 NCUC also explained FERC ignored NCUC’s
arguments concerning the Alternative Rates and Negotiated Rate Policy Statements
and the requirement to base returns on current market conditions,43 and the flaws in
FERC’s “hold the line” rationale.44 FERC’s Rehearing Order denied NCUC’s
arguments without acknowledging or addressing them.45
Concerning ACP, NCUC argued FERC erred, and failed to engage in
reasoned decision-making, by uncritically applying its 14% ROE policy without
applying, or even considering, its other relevant policies.46 FERC’s Rehearing Order
acknowledged those arguments but rejected them without analysis.47
The afore-mentioned actions are arbitrary and capricious.
41 R.13765, NCUC’s CP15-555 Rehearing; R.13766, NCUC’s CP15-554 Rehearing; [JA ____; ____]. 42 R.13765, NCUC’s CP15-555 Rehearing, at 9; [JA ____]. 43 Id., at 7-12; [JA ____-____]. 44 Id., at 13-14; [JA ____-____]. 45 R.14312, Rehearing Order, at Ordering Paragraph (A); [JA ____]. 46 R.13766, NCUC’s CP15-554 Rehearing, at 3-16 (citations omitted); [JA ____-____]. 47 R.14312, Rehearing Order, at PP 66-73; [JA ____-____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 49 of 105
11
STATEMENT OF RULINGS PRESENTED FOR REVIEW
NCUC challenges FERC’s:
blanket denial of NCUC’s DTI rehearing request without acknowledging or addressing NCUC’s arguments;48
reliance on negotiated rate contracts with North Carolina utilities, the costs of which will be recovered from North Carolina ratepayers, to issue certificates to ACP/DTI for new facilities, including those to be constructed in North Carolina, without ensuring rate negotiations underlying those contracts were not tainted by pipeline market power;
sole reliance on its last-stated return policy to approve DTI’s recourse rates;49
“hold the line” rationale;50 and
sole reliance on its new-entrant ROE policy to approve ACP’s proposal to calculate recourse rates using a 14% ROE.51
SUMMARY OF THE ARGUMENT
The challenged orders: (1) failed to respond meaningfully to NCUC’s
arguments regarding DTI; (2) relied on negotiated rate contracts with North Carolina
utilities, the costs of which will be recovered from North Carolina ratepayers, to
issue certificates to ACP/DTI for new facilities, including those to be constructed in
North Carolina, without ensuring rate negotiations underlying those contracts were
48 Id., at Ordering Paragraph (A); [JA ____]. 49 R.13700, Certificate Order, at P 111; [JA ____]. 50 Id., at PP 101, 103, 111; R.14312, Rehearing Order, at P 73; [JA ____, ____, ____; ____]. 51 R.13700, Certificate Order, at PP 101-04; R.14312, Rehearing Order, at P 66; [JA ____-____; ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 50 of 105
12
not tainted by pipeline market power as required by FERC’s Alternative Rates and
Negotiated Rate Policy Statements; (3) failed to explain its departure from
precedent; (4) failed to require ACP/DTI to provide substantial evidence to support
applying FERC’s last-stated return and 14% ROE policies; (5) accepted recourse
rates based on ACP’s 14% ROE and DTI’s 13.7% pre-tax return without analyzing
ACP’s/DTI’s market risks or current capital market conditions; and (6) offered a
flawed “hold the line” solution.
STANDING
Article III standing requires a party to demonstrate an injury-in-fact, or “an
invasion of a legally protected interest which is (a) concrete and particularized . . .
and (b) ‘actual or imminent,’ not ‘conjectural’ or ‘hypothetical[.]’”52 “[T]here must
be a causal connection between the injury and the conduct complained of—the injury
has to be ‘fairly. . . trace[able] to the challenged action of the defendant, and not . . .
the result [of] the independent action of some third party not before the court.’”53
Finally, “it must be ‘likely,’ as opposed to merely ‘speculative,’ that the injury will
be ‘redressed by a favorable decision.’”54 NCUC meets these requirements.
52 Lujan v. Defs. of Wildlife, 504 U.S. 555, 560 (1992) (internal citations omitted). 53 Id., at 560-61 (internal citations omitted). 54 Id., at 561 (internal citations omitted).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 51 of 105
13
The NGA55 and FERC’s regulations56 recognize NCUC’s right to participate
as a “party” in FERC proceedings. NCUC’s timely notices of intervention were
granted.57
NCUC has a legally protected interest in the issues on appeal.58 Organized
and existing under North Carolina state law,59 NCUC’s purpose includes regulating
the sale and transportation of natural gas within North Carolina.60 Its sphere of
interest includes rates paid by North Carolina public utilities for interstate natural
gas service because those costs are passed onto North Carolina consumers.61 Some
of the pipeline facilities ACP proposed below would be constructed in North
Carolina.62 ACP will serve Piedmont and PSNC, which serve customers in North
Carolina and are regulated by the NCUC.63 DTI’s Supply Header Project would
55 15 U.S.C. § 717n(e). 56 18 C.F.R. § 385.214(a)(2). 57 R.3694; R.4182; R.13700, Certificate Order, at P 19; [JA ____; ____; ____]. 58 N.C. GEN. STAT. § 62-48(a) (authorizing NCUC “to initiate or appear in . . . proceedings before federal . . . courts”). 59 N.C. GEN. STAT. § 62, et seq. 60 N.C. GEN. STAT. §§ 62-2, 62-32. NCUC is a “State commission” under the NGA. 15 U.S.C. § 717a(8). 61 N.C. GEN. STAT. §§ 62-32, 62-36.01, 62-133.4. 62 R.13700, Certificate Order, at P 1; [JA ____]. 63 Id., at P 6; R.3532, ACP Application, Exhibit I; [JA ____; ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 52 of 105
14
provide service from supply areas for delivery to ACP.64 ACP will use the DTI
capacity as an integrated part of the service it will provide in North Carolina.65 Thus,
the ACP/DTI capacity will serve, and the costs will be recovered from, North
Carolina ratepayers.
The challenged orders produce actual, concrete harm to NCUC’s interests in
rates paid by North Carolina customers. FERC’s Alternative Rates Policy Statement
relies on the availability of recourse rates to prevent the exercise of pipeline market
power by assuring that customers can revert cost-of-service recourse rates if, during
negotiations, “the pipeline unilaterally demands excessive prices or withholds
service.”66 “If the recourse service remains stagnant, in time, the recourse service
will become outmoded and cease to be a viable alternative to negotiated service.
Since the purpose of the recourse service is to act as a check against pipeline
market power, such a result is impermissible.”67 Even when all service is
provided under negotiated rates, FERC’s policy requires recourse rates be properly
designed to provide the necessary check on pipeline market power during
negotiations. There can be no legitimate doubt that NCUC’s interests were directly
64 R.13700, Certificate Order, at P 2; [JA ____]. 65 R.3532, ACP Application, at 8; [JA ____]. 66 Alternative Rates Policy Statement, at p. 61,240. 67 Id. (emphasis added).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 53 of 105
15
harmed when FERC certificated facilities in North Carolina and service to North
Carolina ratepayers through Piedmont and PSNC, without ensuring that recourse
rates checked pipeline market power during the negotiations.68 Accordingly, a
causal connection exists because the injury-in-fact is clearly traceable to the
challenged orders.69
A favorable decision here—i.e., remanding to FERC with direction to ensure
negotiated rates were not tainted by pipeline market power—will redress NCUC’s
harm.
ARGUMENT
FERC’s orders cannot be arbitrary or capricious, reflect an abuse of discretion,
be contrary to law, or be unsupported by substantial evidence.70 FERC has
affirmative obligations to “examine the relevant data and articulate a satisfactory
explanation for its actions, including a ‘rational connection between the facts found
68 R.13700, Certificate Order, P 55; R.14312, Rehearing Order, at P 41; [JA ____; ____]. 69 FERC’s determinations fix legal relationships affecting rates paid by North Carolina customers, which is sufficient to establish standing under this Court’s ruling in ANR Pipeline Company v. FERC, 771 F.2d 507, 516 (D.C. Cir. 1985). 70 5 U.S.C. § 706(2)(A); see also S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 54 (D.C. Cir. 2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 528 (D.C. Cir. 2010); TNA Merch. Projects, Inc. v. FERC, 616 F.3d 588, 591 (D.C. Cir. 2010).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 54 of 105
16
and the choice made,’”71 respond to facially-legitimate objections,72 and explain
departures from precedent.73 The challenged orders fail under this standard of
review.
A. The Challenged Orders Failed to Consider or Apply FERC’s Consumer-Protection Policies.
The NGA is a consumer-protection statute.74 The Supreme Court explained
the NGA:
afford[s] consumers a complete, permanent and effective bond of protection from excessive rates and charges. The heart of the [NGA] is found in those provisions requiring initially that any ‘proposed service, sale, operation, construction, extension, or acquisition . . . will be required by the present or future public convenience and necessity . . . and that all rates and charges ‘made, demanded, or received’ shall be ‘just and reasonable’ . . . .75
71 See Motor Vehicle Mfrs. Ass’n of United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168 (1962)). FERC must “articulate[] a rational explanation for its action.” Williams Gas Processing-Gulf Coast Co., L.P. v. FERC, 475 F.3d 319, 326 (D.C. Cir. 2006) (citation omitted). 72 PPL Wallingford, LLC v. FERC, 419 F.3d 1194, 1198 (D.C. Cir. 2005) (quotations omitted). 73 ANR Pipeline Co. v. FERC, 71 F.3d 897, 901 (D.C. Cir. 1995). 74 See Cal. Gas Producers Ass’n, 421 F.2d at 428 (FERC’s “primary duty under the [NGA] is the protection of the consumer”); see also Pub. Sys., 606 F.2d at 979 n.27 (citing 15 U.S.C. § 717c(a), (b)). 75 Atl. Ref. Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378, 388 (1959) (citing 15 U.S.C. § 717f(c), (e)) (emphasis added). The orders below refer to Atlantic Refining as “CATCO.” NCUC maintains that reference to avoid confusion.
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 55 of 105
17
Indeed, this Court has affirmed “[t]he NGA’s certification provisions form the ‘heart
of the Act’ and are the means by which [FERC] effectuates the purposes of the Act,
‘to underwrite just and reasonable rates to the consumers of natural gas and to afford
consumers a complete, permanent and effective bond of protection from excessive
rates and charges.’”76
FERC traditionally establishes rates based on the cost of providing service,
i.e., cost-of-service ratemaking.77 Cost-of-service ratemaking establishes the
“recourse” rates, which are the maximum and minimum rates pipelines may charge
for open access transportation service.78 As an alternative, FERC permits pipelines
to negotiate individualized rates with shippers.79 Because they are not constrained
by maximum and minimum rates in pipelines’ tariffs, negotiated rates can expose
shippers to improper exercises of pipeline market power. FERC protects shippers
from that risk by requiring pipelines to “permit shippers to opt for use of the
traditional cost-of-service ‘recourse rates’ in the pipeline’s tariffs, instead of
76 Great Lakes Gas Transmission Ltd. P’ship v. FERC, 984 F.2d 426, 431-32 (D.C. Cir. 1993) (quoting CATCO, 360 U.S. at 388). 77 See Alternatives to Traditional Cost of Service Ratemaking for Natural Gas Pipelines, Request for Comments, 70 FERC ¶ 61,139, at p. 61,393 (1995). 78 Alternative Rates Policy Statement, at p. 61,241. 79 Id., at pp. 61,240-41.
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 56 of 105
18
requiring them to negotiate rates for any particular service.”80 The availability of
recourse rates prevents pipelines from exercising market power by assuring the
customer can revert to the just and reasonable tariff rate if the pipeline unilaterally
demands excessive prices or withholds service.81 FERC is “particularly concerned”
with maintaining the recourse rates’ integrity.82
[T]he recourse service must remain a viable alternative to negotiated service. Otherwise, if the service remains stagnant, in time, the recourse service will become outmoded and cease to be a viable alternative to negotiated service. Since the purpose of the recourse service is to act as a check against pipeline market power, such a result is impermissible.83
Supreme Court precedent and FERC practice requires public utilities’ ROEs
to be based on current capital market conditions.84 Basing returns underlying
recourse rates on current capital market conditions avoids stagnant and outmoded
recourse rates and protects the integrity of recourse rates.
80 N. Natural Gas Co., 105 FERC ¶ 61,299, P 3 (2003); see also Natural Gas Pipeline Co. of America, 101 FERC ¶ 61,125, P 39 (2002) (invalidating an open season for new capacity where the pipeline solicited negotiated rate bids without offering shippers recourse rates). 81 Alternative Rates Policy Statement, at pp. 61,240-41. 82 Id., at p. 61,240. 83 Id. (emphases added). 84 Hope, 320 U.S. at 603; Bluefield, 262 U.S. at 692-93; Portland Natural Gas Transmission Sys., Opinion No. 510-A, 142 FERC ¶ 61,198, P 233 (2013), order on request for rehearing and refund report, Opinion No. 510-B, 150 FERC ¶ 61,106 (2015).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 57 of 105
19
Capital costs are the major cost component for new pipelines.85 For existing
pipelines, FERC “policy is to require that a pipeline’s cost-based recourse rates for
incrementally-priced expansion capacity be designed using the rate of return from
its most recent general rate case approved by [FERC] under section 4 of the NGA in
which a specified rate of return was used to calculate the rates.”86 FERC allows
new-entrant pipelines to calculate recourse rates using a 14% ROE.87 This appeal is
not a direct challenge to those policies. Rather, it challenges FERC’s application of
those policies below because FERC uncritically exalted them above its consumer-
protection obligations and policies to the detriment of ratepayers in North Carolina
that are responsible for the costs passed through by Piedmont and PSNC.
Highlighting FERC’s consumer-protection obligations and policies, NCUC’s
protests demonstrated the returns ACP/DTI used to calculate their respective
recourse rates were overstated. Unless FERC applied its Alternative Rates and
Negotiated Rate Policy Statements and determined ACP’s/DTI’s recourse served as
the requisite check on pipeline market power when ACP/DTI were negotiating
precedent agreements, there is simply no basis to assume pipeline market power did
85 R.3532, ACP Application, Statement P at 3; R.3535, DTI Application Statement P at 3; [JA ____; ____]. 86 R.13700, Certificate Order, at P 110; [JA ____]. 87 Id., at P 102, R.14312, Rehearing Order, at P 66; [JA ____; ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 58 of 105
20
not taint ACP’s/DTI’s negotiated rates.88 Thus, more analysis was required to ensure
that North Carolina ratepayers would not be responsible for excessive rates passed
through by Piedmont and PSNC.
Contrary to its obligation to respond meaningfully to NCUC’s arguments,89
FERC’s Certificate Order ignored NCUC’s arguments to the detriment of North
Carolina ratepayers. NCUC reiterated its arguments on rehearing, noting FERC’s
obligation to respond meaningfully.90 Rather than address the merits of this
fundamental consumer-protection issue,91 FERC’s Rehearing Order simply
acknowledged NCUC’s arguments regarding ACP,92 ignored them all together
concerning DTI, and rejected them.93 Failing to respond meaningfully to NCUC’s
arguments is patently arbitrary and capricious.
88 R.4181, NCUC’s CP15-554 Protest, at 3-4; R.4182, NCUC’s CP15-555 Protest, at 4-5; R.13765, [JA ____-____; ____-____]. 89 See, e.g., PPL Wallingford, 419 F.3d at 1198 (quotations omitted). 90 R.13765, NCUC’s CP15-555 Rehearing, at 8 (citing Canadian Ass’n of Petroleum Producers, 254 F.3d 289, 299 (D.C. Cir. 2001); R.13766, NCUC’s CP15-554 Rehearing, at 7 (citing same); [JA ____; ____]. 91 Elsewhere, FERC agreed “the predicate for permitting a pipeline to charge a negotiated rate is that capacity is available at the recourse rate.” See, e.g., Transcontinental Gas Pipe Line Co., LLC, 156 FERC ¶ 61,092, P 26 (2016). 92 R.14312, Rehearing Order, at P 65; [JA ____]. 93 Id., Ordering Paragraph (A); [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 59 of 105
21
While FERC can depart from its Alternative Rates and Negotiated Rate Policy
Statements if it provides a reasoned basis for such departure,94 it offered no reasoned
explanation below. FERC did not even acknowledge the departure despite NCUC’s
pleas for FERC to protect ratepayers from excessive rates. Thus, FERC’s orders are
arbitrary and capricious.
B. The Record is Devoid of Any Evidence Demonstrating that a 13.7% Pre-Tax Return or 14% ROE Reflect Current Capital Market Conditions.
No party maintained that ACP’s 14% ROE or DTI’s 13.7% pre-tax return
reflect current capital market conditions, or submitted evidence rebutting the
NCUC’s demonstration95 the proposed returns are outdated and overstated. Rather,
the sole support for DTI’s 13.7% pre-tax return was a footnote identifying DTI’s
1997 rate case as that figure’s source.96 The sole support for ACP’s proposed 14%
ROE was: (1) the statement that “[t]he proposed rate of return reflects the risk
inherent in a new, major project venture like the ACP and is consistent with returns
authorized for other new pipeline companies;” and (2) a single footnote citing cases
94 ANR Pipeline, 71 F.3d at 901. 95 See R.4182, NCUC’s CP15-555 Protest, at 7; R.4181, NCUC’s CP15-554 Protest, at 7 (citing recent FERC orders establishing returns on equity between 10.55%-11.55% (for median returns) and 11.59% (for a very-risky pipeline at the top of the range of reasonableness)); [JA ____; ____]. 96 R.3535, DTI Application, Exhibit P at 4 n.2; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 60 of 105
22
from 2010 to 2014 to 2015, none of which demonstrates a 14% ROE reflects current
market conditions or complies with FERC’s Alternative Rates and Negotiated Rate
Policy Statements.97
FERC’s uncritical prior applications of its last-stated return and 14% ROE
policies do not demonstrate that the proposed recourse rates are supported by
substantial evidence. The “substantial evidence” standard requires more than mere
citation to instances where FERC accepted recourse rates generally without
discussion. North Carolina ratepayers deserve more.
NCUC’s request for rehearing of the ACP rulings was explicit that FERC’s
mere explanation “it had done so ‘in the past’” does not establish the necessary
rational connection between the record evidence and FERC’s decision.98 Rather
than address that precedent, FERC reiterated all it need do is apply the same 14%
ROE it has provided other new-entrant pipelines. It is somewhat mystifying that
FERC cites to Sierra Club as affirming its conclusion “in relevant part”99 that bare
97 R.4181 NCUC’s CP15-554 Protest, at 5 n.15-16 (citing R.3532, ACP Application, at 30 n.24 (demonstrating that the cases relied on by ACP to support its 14% ROE did not rely on substantial evidence, but rather were a daisy chain of cases citing prior cases applying the 14% ROE)); [JA ____; ____]. 98 R.13766, NCUC’S CP15-554 Rehearing, at 9 (citing Emera Maine, 854 F.3d 9, 27-29 (D.C. Cir. 2017) (citing Elec. Power Supply Ass’n v. FERC, 136 S. Ct. 760, 782 (2016)); [JA ____]. 99 R.14312, Rehearing Order, at P 66 n.166; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 61 of 105
23
citation to precedent supported its application of a 14% ROE. Sierra Club
undermines FERC’s position. The Court:
confess[ed] to being skeptical that a bare citation to precedent, derived from another case and another pipeline, qualifies as the requisite ‘substantial evidence.’ See NCUC [v. FERC] 42 F.3d. at 664 (citing Maine Pub. Serv. Co. v. FERC, 964 F.2d 5, 9 (D.C. Cir. 1992), for the proposition that ‘FERC’s use of a particular percentage in a ratemaking calculation was not adequately justified by citation of a prior use of the same percentage without further reasoning or explanation’).100
That skepticism should be applied here to find FERC’s reliance on previous cases
using a 14% ROE for new entrants (which was derived from another case and
another pipeline) lacks the requisite “substantial evidence” necessary to affirm its
findings.
Regarding DTI, following FERC’s last-stated return policy, without regard to
whether the pre-tax return reflects current market conditions, fails to constitute
substantial evidence that would permit an analysis of the majority of the cost-of-
service underlying its proposed recourse rates. The totality of the support for DTI’s
13.70% pre-tax return is the footnote identifying Docket No. RP97-406 as that
figure’s source.101 Since the record lacks any current analysis of DTI’s risk or
market conditions, FERC’s acceptance of DTI’s pre-tax return from 1998, because
100 Sierra Club, 867 F.3d at 1378. 101 R.3535, DTI Application, Exhibit P at 4 n.2; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 62 of 105
24
“it had done so ‘in the past,’” does not establish the necessary rational connection
between the record evidence and FERC’s decision.102
FERC must justify its policy each time it is applied, and analyze “whether the
adjudicated facts conform to the rule and whether the rule should be waived or
applied in [the] particular instance.”103 Because the challenged orders do not meet
that obligation, FERC’s acceptance of DTI’s return cannot stand. To protect North
Carolina ratepayers from excessive costs being passed through by Piedmont and
PSNC, the Court should remand the challenged orders.
C. FERC’s “Hold the Line” Rationale is Flawed.
Contending Section 7 review is less rigorous than review under Section 4,
FERC’s Certificate Order held that conducting DCF analyses in individual
certificate cases would not be “the most effective or efficient way for determining
the appropriate [returns on equity] for proposed pipeline expansions.”104 FERC
explained it would difficult to complete a section 4-type analysis of return in section
7 cases in a timely manner, unnecessarily delaying proposed projects with time
102 Emera Maine, 854 F.3d at 27-29; Elec. Power Supply Ass’n, 136 S. Ct. at 782. 103 Pac. Gas & Elec. Co. v. FPC, 506 F.2d 33, 38 (D.C. Cir. 1974); see also Nat’l Mining Ass’n v. McCarthy, 758 F.3d 243, 253 (D.C. Cir. 2014) (quoting Pac. Gas & Elec. Co., 506 F.2d at 38). 104 R.13700, Certificate Order, at P 111; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 63 of 105
25
sensitive in-service schedules.105 Citing the 1959 CATCO decision, FERC claims to
have discretion in NGA section 7 proceedings to approve initial rates that will “hold
the line” until just and reasonable rates are adjudicated under NGA Sections 4 or
5.106 NCUC sought rehearing of FERC’s findings, explaining that addressing
recourse rates in a future rate case does nothing to ensure the recourse rates provided
the requisite check on the pipeline’s market power when the pipeline entered into
the negotiated rate agreements.107 FERC’s Rehearing Order reiterated its “hold the
line” justification.108 These findings are fundamentally flawed.
Negotiated rates did not exist in 1959. CATCO could not have addressed
instances where, as here, pipelines propose service under negotiated rates, or
whether recourse rates satisfy the Alternative Rates and Negotiated Rate Policy
Statements. FERC’s argument —that it would be too difficult or time consuming to
ensure appropriate recourse rates in section 7 proceedings—abdicates FERC’s
105 Id. 106 Id., at PP 101 n.148, 111; [JA ____, ____]. 107 R.13766, NCUC’s CP15-554 Rehearing, at 2-4, 12-16; R.13765, NCUC’s CP15-555 Rehearing, at 4, 7-8, 11, 13-14; [JA ____, ____; ____, ____-____, ____, ____-____]. 108 R.14312, Rehearing Order, at P 73; [JA ____].
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 64 of 105
26
obligation to protect consumers from excessive rates,109 an obligation that CATCO
emphasizes.110
FERC has a duty under Section 7 to protect consumers.111 To fulfill that duty
and ensure that Piedmont and PSNC to not pass excessive costs onto North Carolina
ratepayers, FERC could have followed the practice used in other instances and
looked to DCF analyses to inform its rate of return findings.112 Or, FERC could use
means other than a full DCF analysis to protect ratepayers from excessive returns.113
It cannot do nothing, which, unfortunately for customers of Piedmont and PSNC, is
exactly what FERC did below. This result is arbitrary and capricious and not the
result of reasoned decision-making.
CONCLUSION
Wherefore, the North Carolina Utilities Commission respectfully asks the
Court to remand the challenged orders and direct the Federal Energy Regulatory
Commission to ensure negotiated rates were not tainted by pipeline market power.
109 See, e.g., Cal. Gas Producers Ass’n, 421 F.2d at 428. 110 CATCO, 360 U.S. at 388. 111 Mo. Pub. Serv. Comm’n v. FERC, 337 F.3d 1066, 1070 (D.C. Cir. 2003). 112 See, e.g., WestGas InterState Inc., 59 FERC ¶ 61,029, at p. 61,065 (1992) (considering a DCF analysis to find pipeline’s requested 15% ROE should be reduced to 12.50% in section 7 proceeding). 113 See Interstate and Intrastate Natural Gas Pipeline, Rate Changes Relating to Federal Income Tax Rate, 162 FERC ¶ 61,226, at P 34 (2018) (requiring use of a 10.5% ROE for cost and revenue studies).
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 65 of 105
27
Dated: April 5, 2019 Respectfully submitted,
/s/ Kathleen L. Mazure Kathleen L. Mazure Jason T. Gray Kenneth Holmboe Duncan & Allen 1730 Rhode Island Ave. NW Suite 700 Washington, DC 20036 (202) 289-8400 [email protected] [email protected] [email protected]
Attorneys for the
North Carolina Utilities Commission
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 66 of 105
CERTIFICATE OF COMPLIANCE Per the Court’s March 5, 2019 order, I certify that this brief complies with the
type-volume limitation of Fed. R. App. P. 32(a)(7)(B) because its textual portions,
including headings, footnotes, and quotations contain 5,810 of the 21,800 words
allotted to Petitioners other than Atlantic Coast Pipeline, LLC, as counted by the
“Word Count” feature of Microsoft Word 2010, the program with which this brief
was prepared. This word count excludes: (1) the cover page; (2) certificates; (3) the
corporate disclosure statement; (4) the table of contents; (5) the table of authorities;
(6) the glossary of abbreviated terms; (7) the signature block; (8) the statutory
addendum; and (9) the certificate of service.
Dated: April 5, 2019 Respectfully submitted,
/s/ Kathleen L. Mazure Kathleen L. Mazure Duncan & Allen 1730 Rhode Island Ave. NW Suite 700 Washington, DC 20036 (202) 289-8400
USCA Case #18-1224 Document #1781431 Filed: 04/05/2019 Page 67 of 105