order adoption of tariff adani
TRANSCRIPT
-
8/3/2019 Order Adoption of Tariff Adani
1/22
Rajasthan Elec tric ity Regulatory Commission, Jaipur
Petition No. 217/ 10
In the matter of adoption of tariff & approval of extended time line for
procurement of 1000MW and additional 200MW of base load power
discovered through the process of competitive bidding under Case-1 as
per the guidelines for determination of tariff by competitive bidding
process .
..
Coram:Sh. D.C. Samant, Chairman
Sh. K. L. Vyas, Member
Sh. S.K. Mitta l, Member
Pet itioners : Ra jastha n Ra jya Vidyut Prasaran Nigam Ltd ., Ja ipurOn beha lf of: Ja ipur Vidyut Vitran Nigam Ltd .,
Ajmer Vidyut Vitran Nigam Ltd .,
Jod hpur Vidyut Vitran Nigam Ltd .
Date of hearing : 11.5.10, 8.4.10 & 19.3.10
Presents:
1. Sh. B.K.Ma khija , SE (NPP), RVPN, (on 19.03.10 & 08.04.10)
2. Sh. R.K. Kasliwa l, CE (NPP&R), RVPN(o n 19.03.10,08.04.10 & 11.05.10)
3. Sh. Sanja y Ra i, Co nsultant of RVPN (o n 19.03.10, 08.04.10 & 11.05.10)
4. Sh. R.K. Sha hi, Consultant of RVPN (on 19.03.10 & 08.04.10 &11.05.10)
5. Sh. A.K. Sharma, SE (NPP&R), RVPN (on 19.03.10, 08.04.10 &11.05.10)
6.
Sh. Bha vi Meena , SCO, Relianc e (on 11.05.10)7. Sh. Ritendra Bha tta c herjee, Ma na ger , Relianc e Pow er(on 11.05.10)
8. Sh. Achintya Dvived i, Ad voc a te , M/ s RKM Pow ergen (o n 11.05.10)
9. Sh. J. Mo ha n, GM, M/ s RKM Powergen (on 11.05.10)
Date of Order : 31.5.2010
-
8/3/2019 Order Adoption of Tariff Adani
2/22
seeking approval of the Commission for adoption of tariff quoted by
M/s Adani Power Rajasthan Ltd. (APRL) discovered through
competitive bidding under Case-1 in terms of section 63 of the
Elec tric ity Act, 2003 (hereinafter refe rred as the Ac t ). Pet ition w as
filed under c lause 5.16 & 6.4 of the Guidelines for Determina tion of
Tariff b y Bidd ing Proc ess for Proc urement o f Pow er by Distribution
Licensees (hereinafter referred to as Guidelines), issued by the
Ministry of Power, Government of India, vide notification No.
23/ 11/ 2004-R&R (Vol. II) da ted 19-01-2005 (inc luding its amendments
da ted 30.03.2006, 18.08.2006, 27.09.2007 and 27.03.09), und er sec tion
63 of the Ac t w ith a p rayer for:
(a ) Approval of deviations in respect of extended time line beyond
195 days as spec ified in c lause 5.19.
(b ) Adop tion of Tariff for purc hase of long term Base Loa d pow er as
quoted by the Suc c essful Bidder (M/ s Ad ani Pow er Ra jastha n
Limited) und er Ca se-1 Bidd ing Proc ess und er Sec tion 63 of the
Act.
(c ) Approval for procurement of additional 200 MW of base load
pow er offered by the Suc c essful Bidd er (M/ s Ad ani Pow er
Rajasthan Limited) at the quoted tariff on the same terms &
conditions.
2. The p et ition ha s bee n filed under Sec tion 63 of the Ac t. Sec tion 63
envisages that the appropriate Commission shall adopt the tariff if
such tariff has been determined through transparent process of
bidding, in accordance with the guidelines issued by the Central
Go vernment. The Ce ntra l Government, Ministry of Pow er has issued
the g uidelines c ontemp la ted unde r Sec tion 63 of the Ac t, titled
Guide lines for Determina tion o f Tariff by Bidd ing Process for
Procurement of Power by Distribution Licensees vide Resolution no.
23/ 11/ 2004-R&R Vol. II da ted 19.01.2005 and amendments the reo f.
Bidd i h ll b i iti t d i th St d d Bid D t (SBD)
-
8/3/2019 Order Adoption of Tariff Adani
3/22
(referred to as procurers for the purpose of competitive bidding)
ma y ad op t the g uide lines for long -term procurement for a p eriod of
7 years and above and medium term procurement for a period
exceed ing 1 year up to a period of seven years.
b ) Procurement by more than one distribution licensee through a
c om bined b id p roc ess is permitted and in suc h a c ase, the p roc urer
has the op tion of cond uc ting the b id p roc ess throug h an a uthorized
representative.
c ) The b id d oc umenta tion is req uired to b e p rep a red in ac c orda nce
with the guidelines and the standard bid documents issued by the
Central Government. In such cases, intimation shall be sent by the
procurer to the appropriate Regulatory Commission about initiation
of the bidding process. In the event of deviation from the bidding
conditions contained in the guidelines, approval of the Appropriate
Commission shall be sought by the procurers or their authorized
representative.
d ) The p roc urer ma y, at his op tion, adop t a single stage tend er process
for long term or medium term procurement under Case-1,
c ombining the RFP and RFQ p roc esses. Proc urer or authorized
representative shall prepare bid documents including the RFQ and
RFP (only RFP in single sta ge proc ess) in line with these guidelines andsta nd ard b id doc uments. The p roc urer sha ll pub lish a RFQ (RFP in
single stage process) notice in at least two national newspapers,
c ompa ny web site a nd preferab ly in trad e m ag azines also to ac cord
it wide pub licity. The b idd ing sha ll nec essarily be b y wa y of
International Competitive Bidding (ICB). In case, the bidders seek
any deviation and procurer finds that deviation is reasonable, theprocurer shall obtain approval of the appropriate Commission
be fore ag reeing to such de viation.
e) Procurer shall provide only written interpretation of the tender
document to any bidder / participant and the same shall be made
-
8/3/2019 Order Adoption of Tariff Adani
4/22
wa nts to c ontinue with the b idd ing process, the sam e m ay b e d one
with the c onsent of the Ap prop ria te Comm ission.
g ) The proc urer shall constitute a Comm ittee for eva lua tion of the bids
with at least one Member external to the procurer organization and
affilia tes. The external Mem ber sha ll have expe rtise in financ ial
matte rs/ b id eva lua tion. The p roc urer sha ll revea l pa st a ssoc iation
with the external Members directly or through its affiliates that could
c rea te p ote ntia l c onflic t of interest.
h) Eligible bidders shall be required to submit separate technical and
price b ids a long with nec essa ry bid -gua rantee. The b id sha ll be
opened in public and representatives of bidders desiring to
partic ipa te sha ll be a llow ed to rem ain p resent. The b idder, who has
quoted lowest levellised tariff as per evaluation procedure, shall be
c onsidered for aw ard o f the co ntrac t.
i) The Power Purcha se Ag ree ments (PPAs) sha ll be signed by the
procurers with the selected bidders consequent to the selection
proc ess in a c c orda nce with the terms and c ond itions as fina lized in
the bid document before the RFP stage. After signing of the PPAs,
the Evaluation Committee shall provide appropriate certification on
adherence to the guidelines and to the bid process established by
the p roc urer. The p roc urer sha ll a lso m ake the eva luation of b idpublic by indicating terms of minimum bid and anonymous
comparison of all other bids and also the contract signed with the
successful bidder.
j) The signed PPA a long w ith the c ertifica tion c ertific a tes p rovided by
the eva luation committee a nd by the p roc urer as provided in c lause
6.2 shall be forwarded to the Appropriate Commission for adoptionof ta riffs in terms of Sec tion 63 of the Ac t.
3. The pet ition was admitted by the Co mmission on 2.3.2010. The
Commission sought some additional information to establish that tariff
h b d t i d th h t t f biddi i
-
8/3/2019 Order Adoption of Tariff Adani
5/22
of each event and justification of additional 200MW of base load
po wer prop osed to b e p roc ured and c omp lete b id evaluation repo rt
a long w ith justific a tion about rea sona b ility of ta riff.
4. The petitioner submitted supp lementa ry petition c onta ining the
information desired by the Commission on 30.03.10 for further
consideration.
5. Based on the submissions made by the petitioner and subsequent
submissions made in response to the information desired by the
Commission it is observed that RVPN on behalf of Jaipur Vidyut Vitran
Nigam Ltd., Ajmer Vidyut Vitran Nigam Ltd. and Jodhpur Vidyut Vitran
Nigam Ltd., invited bid for procurement of power for long term under
Case -1 bidding meeting the Base load power requirements of the
proc urers in ac c orda nc e w ith the g uidelines issued by the Go I. The
petitioner obtained valid authorizations from the procurer i.e. three
Disc om s to undertake b id p roc ess. The Pet itioner ha d ea rlier filed a
petition before Commission p raying to a llow proc urement of 1500 MW
of p ow er on long term b asis for 25 yea rs and to take note of initiation
of b id p roc ess. The Co mmission vide its order da ted 3.11.08 allowed
petitioner to proceed with bid to procure 1000 MW of base load
pow er (round the yea r) throug h Ca seI. The a lloc a tion of the
c apac ity am ong three Disc oms wa s p rop osed as unde r:
Jaipur VVNL 360 MW 36%
Ajmer VVNL 360 MW 36%
Jod hp ur VVNL 280 MW 28%
6. The pet itioner op ted for single sta ge b id p roc ess. The Req uests for
Prop osa l (RFP) fo r selec tion of sellers in line w ith the Sta nd ard Bidd ing
Doc ument (SBD) approved by the C entral Government w ere invited
throug h the follow ing news papers :
-
8/3/2019 Order Adoption of Tariff Adani
6/22
7. Further, in order to generate a better response, tariff bids were also
advertised through electronic media by way of putting up details of
the p rojec t on RVPN website. The c om me nc em ent of sa le of RFP
document was from 25.2.2009 with the last date of submission of bid
as 1.6.2009. The RFP doc ument was revised in line with the SBD no tified
by Ministry of Power on 27.3.2009. The last d a te for sub mission w as
rescheduled to 21.7.2009. On request of the prospective bidders the
bid submission date was further extended to 06.08.09 wherein it was
ensured that the bidders are provided with at least 45 days for bid
submission. As per RFP the bidders were to submit their bids for the
requisitioned capacity of 1000 MW (+/- 20%) with a minimum bid
c ap ac ity of 100 MW.
8. Seve n p arties purc hased RFP doc ument of w hich the follow ing six
b idd ers submitted the ir b ids by the d ue d a te i.e 6.8.09.
S. No. Name of Bidde rs Cap ac ity Offered
1 Essar Power Limited 510 MW
2 Jind a l Ind ia Therma l Pow er Limited 450 MW
3 Relianc e Pow er Limited 1000 MW
4 Ad ani Pow er Ra jastha n Limited 1200 MW
5 RKM Powergen Pvt. Ltd . 300 MW
6 PTC Ind ia Limite d (Trad ing Licensee)
throug h the follow ing deve lop ers:
GMR Kamalanga Energy Ltd.
("Developer-1") Ind-Barath Energy (Utkal) Ltd.
("Developer-2")
KVK Nilanchal Power Pvt. Ltd.
("Developer-3")
Monnet Power Co Ltd
100 MW
200 MW
150 MW
-
8/3/2019 Order Adoption of Tariff Adani
7/22
external member, directly or indirectly that could create potential
c onflic t o f interest. The eva lua tion c om mittee c om prised of the
follow ing memb ers :
(i) Sh. N. M. Mathur, CE(PPC&F) RVUN Jaipur.
(ii) Sh. R.K.Jain, Zona l CE,(O&M) JVVNL Jaipur
(iii) Sh. Deep ak Srivasta va , CCO A, RVPN Jaipur
(iv) Sh. B. K. Ma khija, Ad visor Projec t RVPN Jaip ur
(v) Sh. R. K. Kasliwa l, Dy CE (NPP&R), RRVPNL Ja ipur
(vi) Sh. A. K. Khand elwa l, CA Externa l Member (Financ ial Expert)
10. Besides, constituting the aforementioned BEC the petitioner also
appointed M/s Power Finance Corporation Consultancy Ltd. (PFCCL)as its consultants to evaluate the bids. BEC after serious deliberations
in series of meetings held on 7.8.09, 28.8.09, 7.9.09, 25.9.09 & 30.9.09
c onsidered the sta tus of a ll firms reg a rd ing Qua lific a tion Req uirem ents
(QR) and op ined as under :
It was stated by the consultants that based on the requirements of the
RFP (Meeting all the QRs on the bid deadline i.e. 06.8.09) strictly, only onebidder i.e. M/s RKM Power Gen Pvt. Ltd. offering 300 MW power, meets
QR. The c om mittee is of the op inion tha t suc h a situa tion will lea d to
annulment of the bid process, which may not be in the interest of the
Sta te. In view of this it w as c onsidered approp ria te to have some
relaxations in few c ond itions of QR and other co mp lianc es. How ever, the
relaxations in the terms of QR, which ma y a ffec t the c om missioning o f the
projec t/ ava ilab ility of the po wer to the state, should not b e c onside red .
11. The BEC the refo re recom me nded tha t the p rice o ffers of fo llow ing
firms ma y be c onsidered for ope ning:
-
8/3/2019 Order Adoption of Tariff Adani
8/22
12. The p etitioner before ac c ep ting the rec om mendations of BEC
considered in detail the provisions laid down in the guidelines, RFP
document and decided that consultant should give their firm
recommendation through the BEC on the deficiencies/deviations
pointed out in the b ids. The releva nt extrac t of the me eting o f the
Boa rd of Direc tors of p etitioner held o n 20.10.2009 a re q uoted below :
The Boa rd d isc ussed and deliberated on the issues and dec ided tha t
consultants should give their recommendation through the BEC on the
deficiencies/deviations pointed out in the bids received, clearly
indicating there in the nature of deficiencies/deviations as major or
minor, keep ing in view their comp at ib ility w ith the p rovisions in the tend er
doc uments and sugg est the future c ourse o f ac tion to ensure transparent
b id p roc ess.
13. The BEC subseq uently sub mitted fo llow ing op tions and
rec om mended the o p tion (b)a s below in tune w ith its ea rlier dec ision:
a ) Proceed further with the single bid which is meeting the
qua lifying requirem ent stric tly as per RFP but for 300MW only.
b ) Consider the minor deficiencies/deviations as recommended
by the consultant.
c ) Consider to d rop the te nder and re-invite.
14. The p etitioner dec ide d to a cc ep t the rec ommenda tions of BEC to
ignore minor deficiencies in the Qualifying Requirements on the
follow ing g round s :
(i) The fresh bidd ing m ay de lay the proc ess of selec tion of the p ow erplant developers and hence will delay in commissioning of the plant
and supp ly of p owe r to the Sta te w hic h ma y lea d to pe rsistent p owe r
shorta ge in the Sta te .
(ii) Othe rs Sta tes have a lso initiated p roc urem ent of p ow er throug h c ase-1 bidding process. Further, the number of bidders/developers in the
country are limited, therefore, if we annul the process, the capacity
offered to us in the p resent b id w ill ge t unloc ked and m ay be o ffered
-
8/3/2019 Order Adoption of Tariff Adani
9/22
provided by the deve loper @ Rs. 30lac s per MW and initiate fresh b id
p roc ess.
15. Accordingly the financial bids of the aforementioned qualified
bidders were opened on 1st December 2009 in the presence of
qualified bidders.
16. Based on evaluation of the Financial Bids submitted by all the
qualified bidders, the Bid Evaluation Committee on 3rd December
2009 recommended M/s Adani Power Rajasthan Limited as the lowest
evaluated bidder at a levellised tariff of Rs. 3.2483 per kWh for
procurement of total offered capacity of 1000 MW, as approved by
the Commission, plus additional 200 MW (subject to approval of the
Commission).
17. The rec ommend ation of the Bid Evaluation Co mm ittee wa sconsidered by the petitioner and the representative of M/s Adani
Power Rajasthan Limited was called to extend some commercial
reb a te in view of the supp ort being e xtende d to them by the Govt. of
Rajasthan. M/s Adani Power Rajasthan Limited agreed to extend a
rebate of one paise per kWh in the quoted non-escalable capacity
c harge for the ent ire term of the quoted term o f 25 yea rs. Thelevellised tariff on account of the discount offered works out to Rs.
3.2383 per kWh. The rec om mend ation o f the Bid Eva lua tion
Committee, the negotiated offer of M/s Adani Power Rajasthan
Limited the successful bidders and procurement of additional
quantum of 200 MW, subject to approval of the Commission, was
ap proved b y the p etitioner.
18. Ac c ord ingly, Let ter of Intent (LoI) wa s issued to Ad ani Pow er Ra jastha n
Limited (Suc c essful Bidd er) on Dec em ber 17, 2009 for supp ly of long
term 1000 MW, which was approved by the Commission, plus
additional 200 MW (subject to approval of the Commission although
-
8/3/2019 Order Adoption of Tariff Adani
10/22
20. In compliance to the provisions of clause 6.2 of the Guidelines, the
pet itione r has furnished nec essary c ertifica tion o f BEC on c onfo rmity o f
the bid process evaluation according to the provisions of the RFP
document and certification of procurer on conformity of the bid
process with the Guidelines.
21. In c om plianc e to the p rovisions of c lause 6.3 of the Guidelines, for the
purpose of transparency, the petitioner has made the bids publicthrough public notice published in leading news papers i.e. Dainik
Navjoyti on 24.2.10, Times of Ind ia & Hindusta n Time s on 25.2.10. The
public notice me ntioned tha t M/ s Ad ani Pow er Ra jasthan Limited has
won the bid with the evaluated levelised tariff of Rs. 3.2383/kWh and
an anonymous comparison of all other bids together with the details
of PPA signed is ava ilab le on the w eb site o f RVPN.
22. The b id p roc ess (From da te of issue of RFP on 25.02.09 to signing of
PPA & RFP documents on 28.01.10) has taken 337 days. Whereas as
per guide lines the p roc ess should ha ve been c om pleted in 195 da ys.
As per c lause 5.19 of the Guidelines, ap prova l of Hon b le Co mmission
is req uired under c lause 5.16 of the Guidelines, in c ase the b id p roc ess
ta kes mo re than 195 da ys.
23. The list o f events with their da te of o c currenc e in the b idd ing p roc ess
are a s under:
S.No. Events Dt. as per
RFP
Date
(actual)1 Intima tion of b id p roc ess
to RERC
19.08.08
2 Ap prova l of Qua ntum 3.11.08
3 Da te of issue of RFP 25.2.09 25.2.09
4 RFP bid b i i 12 3 09 01 06 09
-
8/3/2019 Order Adoption of Tariff Adani
11/22
11 Certificate by bid
eva luation committee
11.2.10
12 Certific a te by p roc urersJa ipur Discom
Ajme r Discom
Jod hpur Disc om
22.2.10
11.2.10
15.2.10
13 Pub lic not ice in new s
papers & website
25.02.10
14 Pet ition filed for adop tion 25.02.10
24. The c hrono log y of events as per guide lines with the ir sc hed uled da tes
/ ac tual are a s under:
Event Time line
as per
guidelines
Scheduled Ac tual Exc ess
time taken
Date ofissue of RFP
Zero da te 25.2.09 (Zerodate)
25.2.09 --
RFP bid
sub mission
75 days 10.5.09 6.8.09 86 days
Bid
evaluation
& Issua nc e
of LoI
100 days 4.6.09 17.12.09 108 days
PPA
becomes
effective
120 days 24.6.09 28.1.10 22 days
216 da ys
Filing of Petition for ap prova l of Bid Price and related issues:25. The p etitioner filed a petition b efore the Comm ission to approve the
bid p ric e a s req uired in sec tion 63 of the Ac t.
26. Even b efore the petition w as filed , Commission rec eived a c op y of a
-
8/3/2019 Order Adoption of Tariff Adani
12/22
forge d one a nd tha t a rep ort has be en filed at the loc al po lic e station
in tha t respec t. He requested to ignore tha t letter.
27. The Com mission ha d pointed out to the petitioner c ertain ga ps of
information in the petition and non availability of supporting
documents with the petition and to explain the facts through a
representative. Meanwhile it received a letter dated 14.3.2010 from
M/s Reliance Power Ltd. which was also a bidder representing that
large scale discrepancies/deviations are evident from the evaluationreport of the bid evaluation committee wherein the qualification
requirement with respect to land has only been considered as a
c ritica l fac tor for c om missioning o f any po wer p rojec t. The C ompany
further alleged that the procurer has favoured the successful bidder
M/ s Ad ani Pow er Ltd . by w ay of qualifying it on the basis of imp orted
Coal where as the tariff submitted by the party is based on domesticCoal.
28. Simila rly anothe r bidder M/ s R.K.M. Power Gen Pvt. Ltd . rep resented
before the Commission that their firm has been deprived of the
contract even though they were the only bidder meeting all the
qua lifying req uirem ents.
29. The Co mmission in orde r to ensure the transparenc y in the p rocess,
invited comments of the petitioner on the representation of M/s
Reliance Power Ltd., and allowed both the representatives of M/s
Relianc e Pow er Ltd . and M/ s R.K.M. Pow er Ge n Pvt. Ltd . to participa te
in the hearing of the petition on 11.5.2010. During the hearing M/s
Reliance Power Ltd. stated that they have nothing more to submit
while RKM Power Gen Ltd. stated that they were deprived of the
contract even though they were the only qualifying bidder meeting
the req uirem ent o f guide lines stric tly. The lea rned c ounsel of M/ s RKM
Powergen Ltd. during the hearing said that relaxation cannot be
-
8/3/2019 Order Adoption of Tariff Adani
13/22
regarding adoption of tariff which has also been the first bidding
process completed by or on behalf of distribution entities under the
guide lines of Go I issued on 27.3.2009 for Case-I bidd ing.
31. For unde rstanding the role a s we ll as approa ch to be follow ed in such
a matter, the Commission has also considered the following
observa tions in dec isions of APTEL and CERC:
(i) The APTEL in Appea l No.109/2009 he ld tha t:
20. While the b idd ing guidelines a llow the role o f the Sta te
Commission to be only ministerial for the adoption of tariff when
there is mo re than one b idder, there is a spec ific reference to the
consent in c ase of sing le b id . This va ria tion d eno tes tha t
adoption is routine and consent is the outcome of the
p roa c tive c onsideration.
(ii)The CERC in pe tition 18/2007 ha s he ld tha t :15. It is evident from the guidelines that in contrast to the
elab orate role o f the Comm ission in the ta riff dete rmination und er
Sec tion 62 of the Ac t, its role in c ase of ta riff d isc ove ry through
the com petitive b idd ing p roc ess unde rtaken unde r Sec tion 63 is
essentially confined to adoption of tariff, on being satisfied that
transparent p roc ess of b idd ing in acc orda nc e w ith the guidelines
have been followed in determination of such tariff. Whileadopting the tariff discovered through the competitive bidding
process, the Commission is not required to go into the merits or
analysis of the tariff so discovered. Neither is it possible for the
Commission to do so as not supporting details are required to be
subm itted b y the bidd ers .
32. Obviously the role of the Commission is essentially of being satisfiedtha t transparent p roc ess of b idd ing in ac c orda nce w ith guide lines has
been follow ed in ta riff disc ove ry. The Co mm ission ha s, ac c ording ly,
de c ide d to follow the p rinciple laid d ow n in the a bo ve referred orde rs
to the effect that adoption is a routine exercise to arrive at
-
8/3/2019 Order Adoption of Tariff Adani
14/22
time the issues relevant to transparency of the process and
adherence to guidelines by the procurer have been given due
consideration.
34. As far as rep resenta tion o f M/ s. Reliance Pow er Ltd . is c onc erned , the
ma in issue, which emerges relates to the a lleg ed deviation, which has
been ignored by the procurer in qualifying some bidders for opening
of p ric e b id . In the rep resenta tion filed by the pa rty it has been
argued that procurer should have either sought approval of theCo mmission und er c lause 3.4.1 of RFP or else c anc elled the b id.
35. It may b e m entioned that Bid Evaluation Com mittee b ased on fac ts
and circumstances, as narrated in para 10 came to the conclusion
that some of the deviations, being of minor nature and not likely to
affect commissioning of projects, need to be ignored, as otherwise
only one bidd er would qua lify for ope ning of p ric e b ids and that to o
for 300 MW as aga inst 1000 MW ind ica ted in the b id doc ume nt. They
c ame to the c onc lusion tha t to a void re-b idd ing, which would result in
loss of time, minor deviation could be ignored for getting power in
time.
36. They acc ordingly op ined tha t the p rice b ids of the p arties mentionedin para 11 meeting by and large the major qualification requirements
with minor deviations may be opened. When confronted with the
situation as emerged in the instant case, Bid Evaluation Committee
while finalising its first recommendation visualised two options i.e. the
annulment of the b id p roc ess, which they thought would not b e in the
inte rest of the Sta te a nd the o ther op tion being som e relaxa tions infew c ond itions of q ua lifying req uirements without a ffec ting the time ly
commissioning of project and availability of power, which they
c onside red ap propriate .
37 Si Bid E l i C i d id d d f i
-
8/3/2019 Order Adoption of Tariff Adani
15/22
qualified bid; even in that situation permission of Commission under
clause 3.5.1 of RFP read with para 5.7 of guidelines is required only if
the procurer still wants to proceed with a single bid. BEC considered
only two o p tions i.e. relaxa tion in som e d evia tions considered minor or
c ancella tion o f the p roc ess, which in their op inion w as within amb it o f
the guide lines.The o ther issue o f the sa id p arty rega rd ing canc ella tion
of the p roc ess a t tha t stage and invita tion o f fresh b id has been dea lt
with late r in this orde r while a rriving a t the final view on the m atte r.
38. It may be mentioned that there is no provision in the guidelines or in
the RFP document for the Commission to grant mid-course approval
on any deviation except in the single bid situation and prior approval
of the Com mission envisaged in the guide lines in respec t of d evia tions
is req uired before doc uments a re issued for inviting o ffers. This
observation is being made with reference to the point raised by thelearned counsel of M/s RKM Powergen Pvt. Ltd., that the relaxation
c ould b e g ranted only by the Comm ission.
39. The o ther imp ortant p oint raised by the p arty relates to relaxing the
qualifying requirements for the fuel in case of M/s. Adani Power
Ra jastha n Limited . This ma tte r has been elab orately dea lt with in the
first rep ort of the Bid Eva lua tion Com mittee , who found the p arty to b equalified as far as requirement for fuel is concerned based on tie-up
for imported coal and at the same time found the option of use of
do mestic c oa l wo rth conside ration on a c c ount of likely ad vanta ge of
lower escalation in tariff for domestic fuel than that of imported coal.
The p roc urer has subseq uent ly taken und ertaking from the b idd er that
lower escalation in two situations i.e. domestic coal or imported coalwould be applied in tariff and by this they have tried to derive
advantage of incurring low er fuel esc a la tion cost. It ma y be
mentioned that neither the guidelines of GoI nor the bid documents
anticipate such a situation w herein imp orted c oa l and domestic c oa l
-
8/3/2019 Order Adoption of Tariff Adani
16/22
approva l of the Comm ission in a single q ua lified bid situa tion and tha t
the Commission would have necessarily accorded permission to the
procurer to proceed further on single bid and also that the quoted
rate would have been accepted without judging the reasonability
and ma rket rate . It ma y be mentioned that the need for
Commissions approval in such a situation arises only when procurer
dec ides to p roc eed further on a single b id . The p ric e b id of the party
wa s in any ca se o pened with their quoted ra te, when leve lised , being
Rs. 4.3043/ kWh a s aga inst the ra te of Rs. 3.2483/ kWh o f M/ s Ad ani
Pow er Ra jasthan Ltd ., ac c ep ted by the Proc urer.
41. The Co mm ission wo uld no w like to dea l with the ma in issue, which has
arisen in the matter through the representations or otherwise i.e. the
so-called deviations and its implications on transparency and
c om pliance o f guidelines of Go I.
42. As has been mentioned earlier, when the technical bid was opened,
it transpired that only one bidder was fully compliant if the qualifying
criteria was applied strictly and that too for a capacity of 300 MW as
aga inst a tend er enq uiry of 1000 MW. Based o n the fac ts and
c ircumstanc es the eva luation co mm ittee c am e to the c onc lusion tha t
some relaxations, which may not affect commissioning of projects ofbidder may be considered and accordingly they found following
parties meeting the major qualifying requirements and opined that
their pric e bid c ould b e op ened :
1. M/ s RKM Powergen Priva te Limited
2. M/ s Jinda l Ind ia Therma l Power Limited
3. M/ s Ad ani Pow er Ra jastha n Limited
4. M/ s PTC Ind ia Power Limited (Trad er), thru.
(i) M/ s GMR Kama langa Energy Limited
(ii)M/ s Ind Bara th Energy (Utka l) Limited
43 The matte r wa s c onsidered by the Boa rd of RVPN in its mee ting he ld
-
8/3/2019 Order Adoption of Tariff Adani
17/22
44. Bid Eva lua tion Committee a ga in ga ve its rep ort and p ointed o ut that
there are following three options in the matter and they again
reitera ted their op inion in favour of opt ion-(b) g iven b elow:
a ) Proc eed further with the single b id which is me et ing the
qua lifying requirem ent stric tly as per RFP but for 300MW only.
b ) Consider the m inor de fic ienc ies/ deviations as rec om mende d
by the consultant.
c ) Consider to d rop the te nder and re-invite.
45. The m atte r wa s aga in c onsidered by the Boa rd of RVPN in themeeting held on 3rd December, 2009 and the Board decided to
ignore minor deficiencies in the qualifying requirements on the
ground s g iven in p ara 14 of this orde r.
46. It is apparent tha t Bid Eva lua tion Co mm ittee c onsistently held the view
that some deviations being of minor nature need to be ignored in the
la rger interest of ge tting pow er. The same wa s c arefully co nsidered
by the Boa rd in two meetings and finally ac c ep ted . The Boa rd in its
decision has also given justification and reasons for ignoring minor
deficiencies/deviations in consideration of the objectives of the
guidelines.
47. Based on the said decision the price bids were opened and M/s.Adani Power Rajasthan Limited was declared as successful bidder.
The rates quoted by various parties whose p rice b ids were op ene d
are a s under:
1. M/ s Ad ani Power Ra jasthan Limited Rs. 3.2483/ kWh L-1
2. M/ s PTC Ind ia Power Limited (Trad er), thru.
(i) M/ s GMR Kamalanga Energy Limited Rs. 3.8107/ kWh L-2
(ii) M/ s Ind Barath Energy (Utkal) Limited Rs. 3.9520/ kWh L-3
-
8/3/2019 Order Adoption of Tariff Adani
18/22
49. The pet itioner a lso submitted tha t Maharashtra has rec ent ly finalized
the b id rec eived on 7.8.2009 as under:
Bidd er Pow er Offered Levelised Tariff
1. EMCO 200 MW Rs.2.88
2. Ind ia Bulls 450 MW Rs.3.26
3. Adani Power 1200 MW Rs.3.28
50. In view of the above facts, the lowest quoted tariff accepted by the
procurer is quite competitive when compared with prevailing rates
and m ore so w ith cost of pow er landed in the Sta te.
51. The Bid Eva lua tion Comm ittee ha ve g iven the c ertifica te , as req uired
in the guidelines that bid evaluation process has been carried out in
c onformity with the p rovisions of RFP doc ument. Simila rly c ertifica tes
have been furnished to the Commission by the Chairman of threeDiscoms as well as Managing Directors to the effect that bid process
has bee n c arried out in confo rmity w ith guidelines issued by GoI. The
Commission has noted that this is the first case of bidding process
under Case-1for which no past experience is available for which the
petitioner has utilised the consultancy services of a central public
sec to r fina nc ial institution i.e. Power Financ e Co rpora tion (PFC). Thepetitioner took the decision after detailed deliberation in the Boards
meeting with due consideration on recommendations/views of PFC
and the Bid Eva luat ion Com mittee .
52. The Com mission a fter careful considerat ion of the fac ts and
circumstances of the case; the reasons recorded by both Evaluation
Committee as well as Board of RVPN for coming to the conclusionthat deviations are minor and should be relaxed/ignored, which in
their view , did not a mount to non-ad herenc e to guidelines and they
have so c ertified before the Comm ission a nd c onsidering tha t the ra te
arrived at is highly competitive and reasonable; is satisfied about the
-
8/3/2019 Order Adoption of Tariff Adani
19/22
54. Based on the forgoing consideration and facts produced, we are
satisfied that the tariff discovery under Case-1 bidding process is
transparent and is in adherence with the guidelines of GoI.
Accordingly the tariff quoted by the lowest bidder by M/s Adani
Power Rajasthan Ltd. And given at the annexure-I, levelisied Rs.
3.2483/kWh with reduction of 1p/kWh as finally agreed is hereby
adop ted u/ s 63 of the Ac t for supp ly to p roc urer Disc om s in the sha re
on perc entage ba sis as at p ara 5 ab ove and shall be c harged as pe r
PPA exec uted on 28.1.10.
Quantum o f Power:
55. The p et itione r s p rayer is for allow ing 200 MW ad d itiona l power ove r
and a bove 1000 MW ap proved by the Com mission. It wa s submitted
by the petitioner that the standard bid documents has the standard
stipulation of + 20% power and hence additional 200MW can beproc ured . The p roc urer Disc om s have a lrea dy g iven the ir c onsent fo r
procurement of this additional power. In support of its justification the
petitioner submitted that firstly the tariff discovered is reasonable.
Sec ond ly, there a re slipp ages in the a va ilab ility of pow er from va rious
Central Sec tor Pow er Sta tions env isaged in XI p lan a nd have slipp ed
to XII plan period . The Co mm ission ha d ea rlier co nsidered theava ilab ility of p ow er from these Ce ntral Pow er Sta tions while a rriving
a t the q uantum o f powe r to b e p roc ured as 1000MW. The to ta l
slippages being to the extent of 1395 MW of which 220 MW capacity
has go ne o ut to p riva te sec tor from which a va ilab ility is uncertain.
56. Looking the submissions made as above, the additional purchase of
200 MW power being permissible under the standard bidding RFPdo cument, is ap proved.
Approva l of Delay:
57 The p et itione r submitted tha t the b id p roc ess was initiate d throug h
-
8/3/2019 Order Adoption of Tariff Adani
20/22
in the b idd ing p roc ess. It has been brought out by the pe titioner tha t
revised escalation factors were notified by CERC finally on 29.7.2009
hence the date of issue of RFP though was 25.2.2009, the bid
submission d a te had to be extended up to 6.8.2009. Thus this delay of
86 day, if ignored, lea ds to a delay o f 55 da ys p rima rily on a c c ount o f
the case being first of its kind requiring various clarifications by the
bidders and review of e va luat ion rep ort be fore fina liza tion.
58. The pet itione r further submitted tha t since the likely sc hed ule for thecompletion of bid process as per the RFP document was of 187 days,
as could be seen from the table below, which is well within the limit
stipulated in the guidelines, hence the advance approval of the
Commission to meet the requirement of para 5.16 of the bidding
guide lines was not soug ht:
1 Da te of issue of RFP 25.2.2009
2. Cla rifica tion by b idd ers 12.3.2009
3. Pre b id mee ting of required 23.3.2009
4. Revision in RFP 15.4.2009
5. Non Financ ial b id op ening 8.6.2009
6. Financ ial Bid Opening 30.7.2009
7. Issue of LOI 10.8.2009
8. Signing of RFP 31.8.2009
59. Looking to the facts and circumstances submitted by the petitioners
the effective delay of 55 day has in no way affected the tariff
d isc overy though transparent p roc ess. In view of the a bove , the to ta l
delay of 142 days in the b idd ing p roc ess is being a llow ed .
Conclusion
60. In the light o f the p osition d isc ussed in the p rec ed ing p aragrap h the
-
8/3/2019 Order Adoption of Tariff Adani
21/22
adopted tariff shall be charged in accordance with PPA signed
on 28.1.2010.
(c ) Approves the procurement of additional 200 MW of base load
pow er offered by the Suc c essful Bidd er (M/ s Ad ani Pow er
Rajasthan Limited) at the adopted tariff on the same terms &
conditions.
61. The p et ition is d isposed of a c c ording ly. The c op y of the orde r ma y be
sent to Sta te Go vt., CEA, pet itione r and Disc om s and parties whohave rep resented before the Comm ission.
(S.K.Mitta l) (K.L.Vyas) (D.C. Samant)
Mem be r Mem be r Chairma n
-
8/3/2019 Order Adoption of Tariff Adani
22/22