order of magnitude estimator for public hospitals
TRANSCRIPT
Order of Magnitude Estimator for Public Hospitals, etc.
1 October 2014
• IUSS Guideline Norms and Standards are intended to replace the old SAH Norms but not as absolute rather a guideline.
• Norms have three components:– Need norm – population driven– Area norm – based on service requirements, HT– Cost norm – area*rate/m²
• Cost norms are linked to time and programme for planning and construction will influence norm cost for a specific project – therefore linked to a base date.
• Planning units are the common denominator for the three components. Strategic (Service) PU versus Departmental (Functional) PU
OoM Estimator = application of cost norm = quick and easy budget for
hospital at initiation stage of project
• 2014_07_11 OoM ESTIMATOR New Hospital IUSSonline.xlsx
• 2014_07_11 OoM ESTIMATOR New Clinic IUSSonline.xlsx
• 2014_07_11 OoM ESTIMATOR Upgrade Hospital IUSSonline.xlsx
• 2014_07_11 OoM ESTIMATOR Upgrade additions to Clinic IUSSonline.xlsx
How did we determine cost norms?• Analysis of cost of a number of hospitals into locations
or departments and into building elements linked to base dates determined the rate per m²
• JS Elemental breakdown .xlsx
• Determine norms bottom up. Currently rate/m² was determined by analysis of recently built hospitals. Acknowledge Ken, Steve and Riaan.
• Next phase: Design of ideal hospital departments which will then be measured and costed. Ongoing analysis of new hospital projects to inform norms.
• So what?
• ALL consultants to measure, estimate and report per department per element including E &M
Gazette 116 – 17 February 2014
Gazette 512 30 June 2014
Measurement in locations and elements
• Made compulsory by Gazette 116
• Detailed in document “Professional Service Provider instructions for Quantity Surveyors and Architects”
• 2014-03-31-IUSS-Space-guideline-QS-Architect-Instruction-development.pdf
• The above will apply equally to E&M Engineers
Detail Hospital Estimator under development (not peer reviewed)
• Purpose: Developed for use of project consultants and others to compare designed project against norms
• It uses more input and should be more accurate
• Will align with FAST(briefing tool) Facility Assembly Schedule Toolkit
• 2014_07_18 DETAIL NEW HOSPITAL ESTIMATOR unprotected.xlsx
Maintenance Order of Magnitude –working with building elements and
desk top assessments
• 30 Sept 2014 CLINIC Maintenance Estimator.xlsm
• 30 Sept 2014 Limpopo HOSPITAL MAINTENANCE.xlsm
Questions??????