order of precedence clause (nfas 5252.236-9312)...(2) part 1 - contract clauses. (3) part 2 -...
TRANSCRIPT
![Page 1: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/1.jpg)
1
ORDER Of PRECEDENCE CLAUSE(NFAS 5252.236-9312)
![Page 2: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/2.jpg)
2
WORKSHOP OBJECTIVES
1. WHY WE HAVE THE ORDER OF PRECEDENCE CLAUSE (NFAS 5252.236-9312).
2. TO UNDERSTAND THE ORDER OF PRECEDENCE WHEN THERE ARE CONFLICTS BETWEEN OR WITHIN THE RFP, PRPOPSAL, FINAL DESIGN AND THE 6 PARTS OF THE RFP DOCUMENT.
3. WHAT HAPPENS WHEN THE GOVERNMENT ACCEPTS THE CONTRACTOR’S PROPOSAL AND/OR FINAL DESIGN AND THEY DON’T MEET THE RFP REQUIREMENTS.
![Page 3: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/3.jpg)
3
Proposal Forms & Documents(FAR Clauses, etc.)
Performance Technical Specifications
Prescriptive Specifications(Generally Military Unique Specs)
Attachments(As-builts, soils data, asbestos &
lead surveys, concept design, etc.)
Project Program(Project Description, Objectives, Requirements, & Site Analysis)
General Requirements(Division 01 UFGS)
Statemen
t of work
PART 6
PART 5
PART 4
PART 3
PART 2
PART 1
Order Of Precedence
www.wbdg.org/ndbm
6 PARTS OF THE RFP
![Page 4: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/4.jpg)
4
Document
00001Document
00100Title Page
Table of Contents
Instructions to Proposers
Solicitation FORM 1442
+Price Schedule
Document
00010
Document
00010
Document
00202
Document
00800
Representations &Certifications
Contract Clauses(full text + referenced)
Davis-BaconWage Rates
Order Of Precedence
Evaluation Factors For Award
Document
00700
RFP PART 1 - DIVISION 00 FORMS & DOCUMENTS
Document
00600
![Page 5: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/5.jpg)
5
WHY WE HAVE THE ORDER OF PRECEDENCE CLAUSE?
1. REQUIRED TO CLARIFY WHEN THERE ARE CONFLICTS BETWEEN AND/OR WITHIN THE SOLICITATION (RFP), PROPOSAL AND THE FINAL DESIGN.
2. CONTRACTORS WERE MAKING CHANGES AND PROVIDING LOWER QUALITY MATERIALS AND PRODUCTS AFTER THEY ENCOUNTERED BUDGET PROBLEMS. THEY WERE CHANGING BETTERMENTS SHOWN IN THEIR PROPOSALS OR FINAL DESIGN TO THE MINIMUM REQUIRED BY THE RFP.
![Page 6: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/6.jpg)
6
In the event of conflict or inconsistency between any of the below described portions of the conformed contract, precedence shall be given in the following order:
a. Any portions of the proposal or final design that exceed the requirements of
the solicitation.
(1) Any portion of the proposal that exceeds the final design.
(2) Any portion of the final design that exceeds the proposal.
(3) Where portions within either the proposal or the final design conflict,
the portion that most exceeds the requirements of the solicitation has precedence.
b. The requirements of the solicitation, in descending order of precedence:
(1) Standard Form 1442, Price Schedule, and Davis Bacon Wage Rates.
(2) Part 1 - Contract Clauses.
(3) Part 2 - General Requirements.
(4) Part 3 - Project Program Requirements.
(5) Part 6 - Attachments (as-builts, asbestos surveys, etc., but not Concept Drawings).
(6) Part 5 - Prescriptive Specifications exclusive of performance specs.
(7) Part 4 - Performance Specifications exclusive of prescriptive specs.
(8) Part 6 - Attachments (Concept Drawings).
Government review or approval of any portion of the proposal or final design shall not relieve the contractor from responsibility for errors or omissions with respect thereto.
Con
flicts between
the
6-P
arts of the R
FP
Con
flicts between
the R
FP, P
roposal,&
Final D
eign(in
cludes “Fast
Track” Packages)
ORDER OF PRECEDENCE CLAUSEP
repa
red
by t
he
Gov
ern
men
tP
repa
red
by t
he
Con
trac
tor
![Page 7: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/7.jpg)
7
CONFLICTS BETWEEN/WITHIN THE CONTRACTOR PREPARED DOCUMENTS
• NFAS “a”: Any portions of the proposal or final design that exceed the requirements of the solicitation.
• NFAS “a(1)”: Any portion of the proposal that exceeds the final design.
• NFAS “a(2)”: Any portion of the final design that exceeds the proposal.
• NFAS “a(3)”: Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence
![Page 8: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/8.jpg)
8
• RFP (Part 3): Metal Roofing System
• RFP (Part 4): Slate, Concrete Tile, Clay Tile, Asphalt Shingles, Galvanized Steel and Aluminum Panels
• Proposal: Copper Roof Panels
• Final Design: Aluminum Roof Panels
• Government gets: Copper Roof Panels
NFAS “a”: Any portions of the proposal or final design that exceed the requirements of the solicitation. NFAS “a(1)”: Any portion of the proposal that exceeds the final design.
Conflict between the RFP & Proposal
![Page 9: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/9.jpg)
9
• RFP (Part 3): Metal Roofing System
• RFP (Part 4): Slate, Concrete Tile, Clay Tile, AsphaltShingles, Minimum 24 Gauge Galvanized Steel or Aluminum Panels
• Proposal: 24 Gauge Aluminum Roof Panels
• Final Design: 22 Gauge Aluminum Roof Panels
• Government gets: 22 Gauge Aluminum Roof Panels -
NFAS “a”: Any portions of the proposal or final designthat exceed the requirements of the solicitation. NFAS “a(2)”: Any portion of the final design that exceeds the proposal.
Conflict between the RFP & Final Design
![Page 10: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/10.jpg)
10
• RFP (Part 4): Water mains: 12” and less shall be ductileiron, PVC or HDPE. Deeper than 10’ or larger than 12” shall be ductile iron.
• Proposal: Civil Sht C-1: 12” PVC Main
• Final Design: 12” Ductile Iron Main at 8 feet depth
• Government gets: 12” Ductile Iron
NFAS “a”: Any portions of the proposal or final designthat exceed the requirements of the solicitation. NFAS “a(2)”: Any portion of the final design that exceeds the proposal. NFAS “a(3)”: Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
Conflict between RFP and Final Design
![Page 11: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/11.jpg)
11
• RFP: Metal Gutters
• Proposal: (Drawings for same gutter work)
Arch Sht A-3: Aluminum Gutters
Arch Sht A-5: Copper Gutters (Downspout connection detail)
• Final Design: Aluminum Gutters
• Government gets: Copper Gutters
NFAS “a(3)”: Where portions within either the proposal or the final design conflict, the portionthat most exceeds the requirements of the solicitation has precedence.
Conflict between Proposal Drawings
![Page 12: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/12.jpg)
12
• RFP: 24 Gauge Minimum Metal Roofing System
• Proposal: 24 Gauge Aluminum Roof Panels
• Final Drawings: Arch Sht A-3: 24 Gauge Aluminum
Arch Sht A-5: 22 Gauge Aluminum
• Government gets: 22 Gauge Aluminum
NFAS “a”: Any portions of the proposal or final designthat exceed the requirements of the solicitation. NFAS “a(3)”: Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
Conflict between Final Drawings
![Page 13: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/13.jpg)
13
• RFP: 24 Gauge Minimum Metal Roofing System
• Proposal: 24 Gauge Aluminum Roof Panels
• Final Drawing: 22 Gauge Aluminum
• Final Specification: 24 Gauge Aluminum
• Government gets: 22 Gauge Aluminum Roof Panels
NFAS “a”: Any portions of the proposal or final designthat exceed the requirements of the solicitation. NFAS “a(3)”: Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
Conflict between Final Drawing & Spec.
![Page 14: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/14.jpg)
14
CONFLICTS BETWEEN/WITHIN THE GOV’T PREPARED RFP DOCUMENTS
NFAS “b”: The requirements of the solicitation, in descending order of precedence:
PART 3 - Project Program Requirements
PART 6 - Attachments (as-builts, asbestos survey, geotechnical report, etc.)
PART 5 - Prescriptive Specifications exclusive of performance specifications (usually only for military unique items)
PART 4 - Performance Specifications exclusive of prescriptive specifications
PART 6 - Attachments (Concept Design).
![Page 15: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/15.jpg)
15
• Part 3: Aluminum Windows
• Part 4: Aluminum Windows & Steel Windows
• Part 5: Stainless Steel Windows (Special Window)
• Part 6: Steel Windows
• Government gets:
Conflict between RFP Parts 3, 4, 5, & 6
Aluminum Windows
Part 3 - Project Program Requirements.Part 6 - Attachments (as-builts, asbestos surveys, etc).Part 5 - Prescriptive Specifications Part 4 - Performance SpecificationsPart 6 - Attachments (Concept Drawings).
![Page 16: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/16.jpg)
16
• Part 3: Metal Windows
• Part 4: Steel Windows
• Part 5: Stainless Steel Windows
• Part 6: Concept Drawings show Steel Windows
• Government gets: Stainless Steel Windows
Part 3 - Project Program RequirementsPart 6 - Attachments (as-builts, asbestos surveys, etc.)Part 5 - Prescriptive Specifications Part 4 - Performance SpecificationsPart 6 - Attachments (Concept Drawings)
Conflict between RFP Parts 4, 5 & 6
![Page 17: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/17.jpg)
17
• RFP: As-Built drawing shows 12” thick concrete footing. Concept drawings shows removal of existing 10” thick concrete footing.
• Actual site condition: 12” thick footing
• What must the Contractor remove at no cost to the Government?
Conflict between Concept Design& As-Built Drawings
Contractor shall remove 12” thick footing at no additional cost to the government, unless PART 3 specifically states to remove 10” thick concrete footing.
Part 3 - Project Program RequirementsPart 6 - Attachments (as-builts, asbestos surveys, etc).Part 5 - Prescriptive Specifications Part 4 - Performance SpecificationsPart 6 - Attachments (Concept Drawings).
![Page 18: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/18.jpg)
18
• RFP: Stainless Steel Handrails
• Proposal: Galvanized Handrails
• Final Design: Galvanized Handrails
• Government accepts the Proposal & Final Design.
• What does the Government get?
Conflict when Government accepts or approves and it doesn’t meet the RFP
Stainless Steel
NFAS: Government review or approval of any portion of the proposal or final design shall not relieve the Contractor fromresponsibility for errors or omissions with respect thereto.
Contractor must still meet minimum “RFP” requirements even if Government accepts “Proposal” or approves “Final Design” that did not meet the “RFP” requirements.
![Page 19: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/19.jpg)
19
• Part 3: Provide windows to match existing• Part 4: Aluminum Windows• Part 5: (No specifications)• Part 6: As-Built Drawings show Wood Windows• Government conducts a pre-proposal site visit with
Contractors and observe that existing windows are aluminum.
• What does the Government get and why? WoodPart 3 - Project Program RequirementsPart 6 - Attachments (as-builts, asbestos surveys, etc.)Part 5 - Prescriptive Specifications Part 4 - Performance SpecificationsPart 6 - Attachments (Concept Drawings)
SCENARIO
![Page 20: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/20.jpg)
20
• The Contractor submits a Final Electrical Design for a generator that is signed and stamped by the Contractor’s DOR and certified by the Quality Control Managers. The Government accepts and signs the Final Design and incorporates it into the contract with a modification.
• The Government later discovers that the generator does not meet the minimum requirements of the RFP.
• What is the Government entitled to receive and why? • Answer: Government is entitled to a generator that
meets minimum RFP requirements. Government review or approval of any portion of the proposal or final design shall not relieve the Contractor fromresponsibility for errors or omissions with respect thereto.
SCENARIO
![Page 21: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/21.jpg)
21
The solicitation is a “Best Value” contract process.
The RFP states in Part 3 that the roofing system shall be Aluminum.
The Contractor submits a Proposal providing a Copper Roof.
The TEB meets and identifies that the Proposal exceeds the RFP requirements.
What should the Government get and why:Aluminum Roofing
If discussion are held, the Contract Specialist needs to let the Contractor know that their Proposal does not meet the RFP. Contractor can exceed minimum RFP requirements, but not contract specific requirements.
SCENARIO
![Page 22: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/22.jpg)
22
1. NEED TO BE FAMILIAR WITH ORDER OF PRECEDENCE CLAUSE.
2. EVEN IF THE GOVERNMENT ACCEPTS/APPROVES THE CONTRACTOR’S PROPOSAL AND/OR FINAL DESIGN PACKAGES AND ERRORS/OMISSIONS ARE DISCOVERED LATER, THE CONTRACTOR IS STILL LIABLE TO MEET THE RFP REQUIREMENTS.
TAKEAWAYS
![Page 23: ORDER Of PRECEDENCE CLAUSE (NFAS 5252.236-9312)...(2) Part 1 - Contract Clauses. (3) Part 2 - General Requirements. (4) Part 3 - Project Program Requirements. (5) Part 6 - Attachments](https://reader034.vdocuments.net/reader034/viewer/2022050207/5f5a852e08a962218877ba7e/html5/thumbnails/23.jpg)
23
QUESTIONS?