osim fieldguide (apr 2008)

Upload: mtor86

Post on 14-Apr-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    1/50

    100

    0.05

    0.10

    0.15

    0.20

    0.30

    0.35

    0.40

    0.50

    0.60

    0.75

    1.00

    1.25

    1.50

    2.00

    2.50

    3.00

    4.00

    5.00

    Narrow Medium Wide

    GOOD FAIR POOR

    Concrete Crack Widths (mm)

    Hair

    Line

    10

    1.0

    2.5

    5.0

    6.0

    7.5

    10.0

    12.5

    LightMediumSevere

    GOODFAIRPOOR

    Asphalt(WearingSurface)CrackWidths(mm)

    5

    10

    15

    0

    1

    2

    3

    4

    6

    7

    8

    9

    11

    12

    13

    14

    16

    17

    1

    FIELD INSPECTIONGUIDE

    Apr 2008

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    2/50

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    3/50

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    4/50

    4

    TABLE OF CONTENTS

    Page

    1) STRUCTURAL INSPECTIONS

    1. Inspection Objectives 5

    2. Inspection Accuracy 5

    3. Additional Investigations 6

    4. Site Inspection 6

    5. Post Inspection Procedures 8

    2) HELPFUL HINTS

    1. Condition 10

    2. Excellent & Good 11

    3. Recommended Work 13

    4. Performance Deficiencies 15

    5. Maintenance 16

    APPENDIXAMATERIAL DEFECTS 171. Concrete Defects 18

    2. Steel/Aluminum Defects 24

    3. Wood Defects 30

    4. Masonry Defects 32

    6. Asphalt Defects 34

    7. Coatings 42

    APPENDIX B - ELEMENT LIST 49

    APPENDIX C - CONDITIONSTATETABLES 52

    APPENDIX DPERFORMANCE

    DEFICIENCIES & MAINTENANCE 77

    APPENDIX EOSIM FORMS 89

    TABLE OF CONTENTS

    STRUCT

    HINTS

    DEFECTS

    ELEMENT

    CONDITION

    DEFICIENCIES

    FORMS

    97

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    5/50

    96

    F

    O

    R

    M

    S

    5

    1. STRUCTURAL INSPECTIONS

    1.1 INSPECTION OBJECTIVES(Part 1, Sect. 1.2)

    The goal of the structural inspection is to ensure,within an economic framework, an acceptablestandard for structures in terms of public safety,comfort and convenience. The main objectives areto:

    maintain structures in a safe condition

    prolong the life of structures

    identify maintenance & repair needs

    provide the basis for structuremanagement

    1.2 INSPECTION ACCURACY(Part 1, Sect. 1.3)

    In order to achieve the inspection objectives andadequate accuracy, the inspector should spend atleast 2 hours at a typical bridge site to adequatelyassess the condition of all elements.

    The inspection should be a visual inspection per-formed Close enough to determine the element

    condition, and generally conducted within armslength of the element.

    In some cases it may be possible to inspect a por-tion of the bridge close-up and then estimating thecondition of the remaining inaccessible parts byvisually comparing them to the partial close-up in-spection. If this is done, periodic Enhanced OSIMinspections must be done to closely inspect allcomponents as described in Part 1, Section 1.3.2 ofthe OSIM.

    Additional equipment should be used to facilitate

    inspection, when necessary (Bridgemaster, buckettruck, ladder, etc).

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    6/50

    6

    Additional specialized testing (NDT, etc) shouldbe recommended for critical structures (fatigueprone, fracture critical, hangers, etc)

    1.3 ADDITIONAL INVESTIGATIONS(Part 1 Clause 1.3.4)

    If during a detailed visual inspection, theinspector feels that more detailed information isneeded, specialized inspections (within a certaintimeframe*)can be requested. Some of theseinvestigations are:

    Detailed Deck Condition Survey Non-destructive Delamination Survey

    of Asphalt Covered Decks

    Substructure Condition Survey

    Detailed Coating Condition Survey

    Underwater investigation

    Fatigue investigation

    Seismic investigation

    Structure evaluation

    Monitoring, etc.* Normal timeframe is with in 2 years

    1.4 SITE INSPECTION (Part 2-Clause 1.5.2)

    The inspector shall:

    Arrange forspecial equipment/trafficcontrol and safety devices, as requiredfor site.

    Complete an overview inspection of the siteto:

    Assess the overall i ntegrity of thestructure and identify areas where moredetailed examination may be required

    Observe the bridge under truck loadingand identify any abnormal flexibility,deflections or noises (rattling or vibration

    R

    C

    95

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    7/50

    94

    F

    O

    R

    M

    S

    7

    of members)

    Look forabnormal deflections, settlements orrotations by looking along the rail or barrier wallor other members

    Identify obstacles that may either interfere withthe inspection or indicate a need for additionalspecial equipment.

    Determine the quantities in each condition statebased on the severity of material defects in theappropriate units (m2, each, etc.), for eachelement. Details of condition states and materialdefects are included in Appendix A and C.The element list is included in Appendix B andthe OSIM form for recording information isincluded in Appendix E.

    Determine the performance deficiencies,maintenance needs, recommended work andtime frame for work for each element. Details ofthese are included in the Appendix D of thisGuide

    Take photographs to adequately describe thestructure and the defects found including all areas

    of POOR.

    Update element quantities/dimensions ifrequired.

    Correct missing/erroneous inventory data

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    8/50

    8

    1.5 POST INSPECTION PROCEDURES(Part 2 - Clause 1.5.3)

    The inspector shall:

    Ensure that all inspection equipment andtemporary traffic control devices are removedfrom the site and the site is left in workmanlikeorder

    Ensure the appropriate follow-up action is

    taken (notify bridge owner immediately) for anycritical structural defects or deficiencies (i.e.fatigue cracks in steel, imminent deck punchthrough, etc.) and all other unsafe conditionsthat are discovered in the field.

    Submit the Maintenance Needs list to themaintenance crew for action

    Ensure additional investigations are initiated inthe timeframe recommended

    Write all necessary follow-up correspondenceand reports

    R

    C

    93

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    9/50

    92

    O

    R

    M

    9

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    10/50

    10

    2. HELPFUL HINTS (Part 2, Section 4)

    CONDITION

    First look for areas of POOR

    Concrete Spalls, delaminations, severe

    scaling, wide cracks (4m=1 sq.mdefect area)

    Steel More than 10% section loss,

    cracks and deformations Actual inspection quantity (e.g. sq.m.)

    should be used for elements in Poorconditionnot percent.

    Next, look for areas of FAIR Concrete

    Medium defects (medium scaling,medium cracks, etc.)

    Steel 1% to 10% section loss

    Each Area of Poor (except for verylarge areas) should generally havean equal area of associated Fair sur-

    rounding it. Remainder of areas probably in Good orExcellent Condition. Actual Good or Excellent depends

    on visual inspection; however, age ofstructure can be used as a guide,depending on environmental expo-sure of element (see section 2.2 ofthis guide).

    Similar guidance based on age doesnot exist for the transition from Goodto Fair Condition. Fair is determined by visual iden-

    tification of defects.

    91

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    11/50

    9011

    2. EXCELLENT AND GOOD All materials must begin in the Excellent conditio

    state

    Once any defect is visible, it drops to the Goodcondition state

    The defects may not be visible from a distance, are from close-up.

    Guidance is provided below for the age of comnent when transition* from Excellent to Good isexpected:

    Concrete, ACR Steel, Coated Steel, Coatin

    Severe5 years

    Moderate15 years

    Benign25 years* Transition can be spread over afew inspections.

    Defects in Good condition state include(see Tables in Appendix C for completelist):

    ACR Steel First signs of patina flaking

    Coated Steel

    First signs of surface rust First signs of coating lifting from

    steel Re-coated steel that had rust previ

    ously Coating

    First signs of adhesion or coating relatedefects

    Concrete Hairline and Narrow cracks Surface carbonization Light scaling Other light defects

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    12/50

    12

    Examples of Environments

    Severe Moderate Benign

    ExposedConcreteDeck

    ConcreteDeck with wa-terproofing

    Exterior Soffit Interior Soffit

    Railings andinside faceof BarrierWalls

    Outside faceof barrier wall

    Abutment insplash zone

    Abutment atexpansion

    joint

    Abutment with nojoint (integralabutment)

    Pier insplash zone

    Pier at expan-sion joint

    Pier with no joint(where deck con-tinuous)

    End Portion of

    Beams (atjoints)

    Remainder of

    Beams

    Joints

    89

    OSIM FORMS

    (Part 2, Section 7)

    APPENDIX E

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    13/50

    8813

    3. RECOMMENDED WORK (Part 2, Sect. 7)

    Work on Element

    Recommended work- Must be consistent with condition of element.- Must be used for elements that cause a bridge to

    be placed on a capital construction program, typically the 5 main elements listed below.

    - Can be used for other elements as required.- Must not be used for work that is carried out as

    maintenance.- Must not be used for additional investigations or

    functional deficiencies.

    Recommended work on an element can be either:- Rehabilitation- Replacement

    The timeframe for the work is either:- 1 to 5 years,- 6 to 10 years

    Typically, the 5 main elements require repair in 1 to 5

    years when:

    Deck Top 10% to 20% PoorDeck Soffit 5% to 15% PoorBarrier Wall 15% to 30% PoorExpansion Joint 15% to 25% PoorGirders 5% to 10% Poor

    o Sometimes, a lower percentage of Poor

    may also trigger a rehab for critical ele-ments.

    o If there are immediate safety concerns

    with some elements, a Structural Maintenance item should be recorded.

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    14/50

    14

    Work on Structure

    Work on structure is only required when there is enoughto warrant placing the bridge on the capital constructionprogram.

    Recommended work on the structure can be either:- Minor Rehabilitation that include work on ele-

    ments other than the deck (i.e. barriers, bear-ings, etc.)

    - Major Rehabilitation that include work to thedeck (i.e. patch-waterproof-pave, overlay, etc.)plus possibly other elements.

    - Replacement of entire structure.

    The timeframe for the work is either:- 1 to 5 years,- 6 to 10 years

    87

    M

    aintenanceNeed

    Description

    8R

    epairofBridgeConcrete

    Therepair

    ofallconcretecomponentsofthestructure,suchascurbs,pedestrianwalks,concrete

    handrailposts,parapetwalls,abutmentsandpiers,exceptwhentherepairismoredirectlyassociated

    withoneoftheotherdefinedbridgemaintenanceoperationsorthequantityofrepairisexcessivefora

    maintenan

    ceoperation.

    9R

    epairofBridgeTimber

    Therepair

    ofallbridgetimber,includingtherepairoftimberdecksonsteelbridges.

    10B

    aileyBridgesInstallation,

    M

    aintenanceandRemoval

    Theinstallation,removal,repairandmaintenanceworkthatisuniquetoBaileyBridges,butnot

    includingw

    orkdefinedbyotherstructuralmaintenanceoperations.

    11A

    nimal/PestControl

    Theinstallationandmaintenanceofanimal/pestcontrold

    evicesunderbridgestructuressuchas

    pigeon-pro

    ofing.

    12B

    ridgeSurfaceRepair

    Therepair

    ofbridgesurfacessuchaspotholepatching.

    13E

    rosionControlatBridges

    Operationsperformedtopreventorrepairdamageduetoerosion,suchasscouratabutmentsand

    aroundpie

    rs,andwashoutsonslopes.Includesremova

    lofobstructionstowaterflow,clearingof

    vegetation

    growth,extensionofdeckdrains,etc.

    14C

    oncreteSealing

    Thesealingortreatmentofbridgeconcretesurfaceswith

    approvedmaterials,aswellasthe

    preparationofsurfacespriortotreatment.

    15R

    outandSealConcreteand

    A

    sphaltPavementonBridgeDecks

    Theroutingofjointsand/orcracksinconcreteandaspha

    ltpavementandthefillingofsamewithjoint

    fillersorru

    bberizedasphalticsealingcompounds.

    16B

    ridgeDeckDrainage

    Therepair,maintenance,andreplacementofbridgedeckdrains.Includessteamingandcalcium

    application

    tounthaw.

    17S

    caling(LooseConcreteorACR

    S

    teel)

    Theremov

    alofloosedelaminatedconcreteordelaminatedpatinaofACRsteelgirdersthatposearisk

    asafalling

    hazard.

    18O

    therMaintenance

    Amaintenanceactivitythatdoesnotfitintoanyothercategory.

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    15/50

    86

    MaintenanceNeed

    Description

    1

    LiftandSwingBridge

    Maintenance

    Theoperation,maintenanceandrepairactivitiesthata

    reuniquetoliftandswingbridge

    structures,

    includingallmechanicalequipmentandelectricaldevicessuchassignals,flashers,

    lighting,navigationlights,etc.,butnotincludingworkd

    efinedbyotherstructuralmaintenance

    operations.

    2

    BridgeCleaning

    Thecleanin

    gofbridgecomponentsincluding:

    1)

    Washingofbearings,bearingseats,trussmembe

    rs,etc.

    2)

    Sweepingofbridgedecks,curbsandgutters.

    3)

    Removalofdebrisfromexpansionjoints.

    4)

    Debris

    pick-uporminorremovalofaggregate.

    5)

    Cleaningofcatch-basins,man-holesanddeckdrains.

    3

    BridgeRailingSystem

    Maintenance

    Thepaintin

    g,repairand/orreplacementofmetalhandrails,railingsystemsandposts,aswellas

    touch-uppaintingactivities.

    4

    Pa

    intingSteelBridgeStructures

    Thepreparation(sandblasting,etc.)andpaintingofstr

    ucturalsteel.Includeshandrailswhen

    performedaspartofanoverallbridgepaintingoperation.

    5

    BridgeDeckJointRepair

    Therepairand/orreplacementofexpansionand/orfixeddeckjointsandenddams.

    6

    BridgeBearingMaintenance

    Theadjustment,repairand/orreplacementofbridgebearings.Includesallworkdirectly

    associated

    withbridgebearings.

    7

    Re

    pairtoStructuralSteel

    Therepairofallstructuralsteel,includingrepairorreplacementofsteelcomponents,boltsand

    fasteners.

    Ta

    ble

    6.1

    :Ma

    intenance

    Nee

    ds

    (Part

    2,

    Sec

    tion

    6)

    DE

    F

    I

    C

    I

    E

    N

    C

    I

    E

    S

    15

    4. PERFORMANCE DEFICIENCIES(Part 2, Section 6)

    A Performance Defic iency should be recorded i fan elements ability to perform its intended functionis in question.

    Suspected Performance Deficiencies are re-corded for each element

    Potential Deficiencies categorized asSuspected since often difficult to ascertain thsignificance of defect at the time of the inspec-tion

    Suspected Performance Deficiencies usuallyindicate some follow-up action is required(strength evaluation, specialized inspection,monitoring, etc.)

    Standard List of possible deficiencies areshown on the inspection form (see Appendix Dand Appendix E).

    Follow-up action can be addressed underAdditional Investigations or Special Notesfor the bridge.

    Example:A severely corroded girder at the midspan

    Can the girder safely carry traffic loading? Inspector cannot determine this in the field

    Inspector can only indicate Suspected Per-formance Deficiency for a follow-up strengthevaluation

    Only then can decision be made whetherbridge needs strengthening or posting

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    16/50

    16

    5. MAINTENANCE (Part 2, Section 6)

    There are two types of maintenance work that areperformed:

    Structural Maintenance Work- Is work to improve the structural capacity of a

    specific element and not part of a larger con-struction contract

    - Is generally only done to one element- Include emergency repairs and holding strat-

    egy repairs- Is work that requires engineering drawings to

    complete the work.

    Routine Maintenance Work- Is for preventative maintenance and minor re-

    pair work that can be performed without engi-neering direction.

    - Is usually carried out by bridge crews or roadmaintenance contractors

    For all Maintenance work a standard list of mainte-nance needs are shown on the inspection form(see Appendix D, or Appendix E). The mainte-nance needs list should be forwarded to mainte-

    nance crews for action, with urgent items flaggedfor immediate attention.

    H

    NT

    S

    85

    15Unstable

    Embankments

    Embankments

    Settlementofembankment,slope

    protectionsorapproachroa

    dway;

    Slidingfailureofthetoeors

    lopesof

    theembankment;

    Surfaceordeepseatedslips;

    Lossofembankmentmaterialfrom

    underfoundations.

    Geotechnicalinvestigation

    16Other

    14Underminingof

    Foundation

    Streams&

    Waterwaysor

    Foundation

    Lossofmaterialsupporting

    foundationsduetoscouror

    erosion.

    UnderwaterInvestigation

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    17/50

    84

    Suspected

    Performance

    ElementName

    (Examples)

    DescriptionofDeficiency

    PossibleFollow-upActio

    n

    13Flooding/Channel

    Blockage

    Streams&

    Waterways

    Theinspectorshouldlookforthefo

    llowing

    evidenceofhighwaterlevels,inadequate

    openingatthestructureandadverseaffectson

    othercomponentsofthestructure:

    Bendingorbucklingofthelowerch

    ordofsteel

    trussesinthedownstreamdirectionbyiceor

    heavydebris;

    Icescarsanddamagetosubstructures;

    Coarsedebris,suchasbranchesa

    ndsmall

    trees,caughtorwedgedunderthe

    superstructure;

    Finedebris,suchasgrassandtwigs,on

    fences,trees,embankments,structures,etc.;

    Washlinesonbaresoilslopes;

    Mudorsiltdepositedonembankments;

    Marksandstainsonstructures.

    Determinehistorical

    frequencyoffloodingand

    recordedwaterlevelsand

    comparetocurrenthigh

    waterelevation

    Monitorwaterelevations

    throughoutyear

    Performhydrologystudy

    Table

    5.1:SuspectedPerformance

    Deficiencies(Part2,

    Section

    5)

    D

    E

    F

    I

    C

    I

    E

    N

    C

    I

    ES

    17

    APPENDIX A

    MATERIAL DEFECTS

    This appendix contains a simplified table formaterial defects and condition states bycombining the information from OSIM Part1, Section 2 and Part 2, Section 4

    TABLES1. Concrete

    2. Steel/Aluminum3. Wood4. Masonry5. Asphalt Wearing Surface6. Asphalt Covered Deck7. Coating

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    18/50

    18

    1.

    CONCRETE(Part

    1,

    Sec

    t.2

    .2an

    dPar

    t2

    ,Ta

    ble4

    .5)

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Sca

    ling

    Localflaking/lossofsurfac

    eportionofconcreteormortardue

    tofreeze-thaw

    Up

    to5mm

    dep

    th

    6-

    10mm

    dep

    th

    >10mm

    dep

    th

    Disin

    tegra-

    tion

    Physicaldeteriorationorbreakingdownoftheconcreteintos

    mallfragments

    All

    Ero

    sion

    Deteriorationofconcreteb

    roughtaboutbywater-bornesand

    andgravelparticles

    scrubbingagainstsurfaces

    All

    Corro

    siono

    f

    Rein

    force-

    m

    en

    t

    Deteriorationofreinforcem

    entbyelectrolysis

    Due

    todra

    ins

    /cha

    irs

    Rus

    ts

    tains

    fromre

    inforcem

    en

    t

    Expose

    dre

    inforce-

    men

    tw

    ithrus

    t

    Dela

    mina-

    tion

    Discontinuityofthesurfaceconcretewhichissubstantially,butnotcompletely

    detachedfromconcretebe

    loworaboveit.

    All

    D

    C

    83

    10SurfacePonding

    Sidewalk,

    Wearingsurface

    Waterpondingonsidewalks/wearingsurface,

    asitpresents

    as

    afetyhazard,especiallyifallowedtofreeze

    ;

    Fillindepression

    withasphalt

    (Maintenance

    Operation)

    11DeckDrainage

    DrainageSystem

    Deckdrainsnotprovidedwherenecessary,orhaveinadequatesize

    ofo

    pening;

    Deckdrainsanddrainagesystemsimproperlyconstructedwith

    inadequateslopesorsharpdirectionalchanges;

    Drainagesystempluggedorpartiallypluggedandno

    tallowingfor

    freeandunobstructedflowofwater;

    Drainageoutletsdischargingdirectlyontostructurec

    omponentsor

    roa

    dwaysbelowthedeck;

    Drainageoutletsdischargingdirectlyontoembankmentwithout

    pro

    perprovisionforcollecting,channellingandcontrollingof

    dischargewithsplashpads,spillwaysorgutters;

    Ina

    dequateprovisionfordrainageatthestructureap

    proaches.

    Reviewdeck

    drainage

    requirements

    12Slipp

    erySurfaces

    DeckTop

    Lossinridingcomfortandpotentiallossofvehiclecontrol

    duetodefectsinthecomponentmaterial;

    Lossofprotectiontounderlyingsurfacesduetodefectsin

    the

    wearingsurfacematerials;

    Resurfaceproblem

    area(Maintenance

    Operation)

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    19/50

    82

    Su

    spected

    Pe

    rformance

    ElementName

    (Examples)

    DescriptionofDeficiency

    PossibleFollow-upAction

    9Ro

    ughRiding

    Su

    rface

    WearingSurface,

    Approachslabs

    R

    oughapproaches,settlementorconsolidationof

    approachembankments,ordeteriorationofthe

    approachslabsorramps,resultinginvehicle

    s

    "b

    ouncing"ontothebridge.Inadditiontoapp

    lying

    excessivedynamicloadingtothebridge,this

    may

    alsoresultindifficultyinmaintainingvehiclecontrol

    D

    epressionsandcracksintheroadwaypave

    ment

    aboveculvertsandsoil-steelstructures;

    Smoothoutasphaltat

    approach(Maintenance

    operation)

    Strengthevaluation

    8Pe

    destrian/

    vehicularhazard

    Armouring/

    retainingdevices,

    Sidewalk

    Verticalorhorizontalmisalignmentacrossthejoint;

    Severematerialdefects(e.g.Spalling)

    H

    orizontal,verticalorrotationaldisplacementsin

    curbsandsidewalksastheyarehazardousto

    pedestrianandvehicularsafety,andpresent

    obstructionstosnowplows.

    In

    adequatecurbheight,orlossofcurbheigh

    tfor

    sidewalksduetotheplacementofanadditional

    la

    yerofwearingsurfaceordeckoverlay

    Removeobstruction

    (Maintenanceoperation)

    ReviewCoderequirements

    forcurbheight

    Ta

    ble5

    .1:

    Suspec

    tedPerformance

    De

    fic

    ienc

    ies

    (Part

    2,

    Sec

    tion

    5)

    19

    1.

    CONCRETE

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Sp

    alling

    Fragmentswhichhavebe

    endetachedfromalargerconcretemass

    All

    Crac

    king

    Linearfracturewhichextendspartlyorcompletelythroughthemember.

    1

    .0mmw

    ide

    A

    lka

    li-

    Aggrega

    te

    Re

    ac

    tion

    Aggregatesreactadverselywiththealkaliesincementtoproduceahighlyexpansivealkali-

    silicagel

    Ha

    irlinepa

    tterncracks

    0

    .3mmw

    ide

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    20/50

    20

    1.

    CONCRETE

    D

    EFECT

    CONDITIONSTATE

    GOOD(LIGH

    T)

    FAIR(MEDIUM)

    POOR

    (SEVEREandVERYSEVERE)

    Honey

    com

    bing

    Producedduetotheimproperorincompletevibrationof

    theconcretewhichresultsin

    voidsbeingleftinthe

    concretewherethemortarfailedto

    completelyfillthespaces

    betweenthecoarseaggregateparticles

    Ho

    lesup

    to25m

    mdia

    .

    Ho

    les

    25-

    50mm

    dia.

    Ho

    lesmore

    than

    50mm

    dia

    .

    Pop-O

    uts

    Shallowconicaldepre

    ssionsresultingfromthebreaking

    awayofsmallportionsofthe

    concretesurface,due

    totheexpansionofsomeaggrega

    tesduetofrostaction.

    Ho

    lesup

    to25m

    mdia

    .

    Ho

    les

    25-

    50mm

    dia.

    Ho

    lesmore

    than

    50mm

    dia

    .

    81

    Sus

    pected

    Per

    formance

    Def

    iciency

    ElementName

    (Examples)

    Des

    criptionofDeficiency

    PossibleFollow-upAction

    5

    SeizedBearings

    Bearings

    B

    indingorjammingofexpansionorrotationa

    l

    componentsduetocorrosion,lackoflubricationor

    d

    amagetoslidingsurfaces;

    Strengthevaluationto

    accountforchangein

    articulation

    LubricateBearings

    (MaintenanceOperation)

    6

    Bea

    ringnot

    uniformlyloaded/

    uns

    table

    ElastomericBearing,

    RockerBearing,etc

    N

    on-uniformcontactofbearingsurfaceswith

    each

    o

    therorwithbearingseat

    E

    xcessiveinclinationsofbearings

    Regularmonitoringofbearing

    movements

    7

    Jam

    medexpansion

    Joint

    Armouring/

    retainingdevices

    Inadequatejointgaptoaccommodateanticip

    ated

    furthermovement;

    S

    urfacingmaterialshavejammedinthejointsduring

    resurfacingofdeck;

    D

    esignorconstructionproblemsnotallowing

    proper

    m

    ovementofmulti-sealjoints.

    Regularmonitoringofdeck

    movements

    Cleanoutgap(Maintenance

    operation)

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    21/50

    80

    Suspected

    Performance

    Deficiency

    ElementName

    (Examples)

    Description

    ofDeficiency

    PossibleFollow-upAction

    4Continuing

    Movements

    AbutmentWall,

    Pier,DeckTop,

    Bearings,etc

    Outofplu

    mbofabutmentwalls,piles,piersorother

    componentssupportedonthem;

    TiltingorbulgingofRetainedSoilSystem(RSS)walls

    Unusualo

    runexpectedsubstructuremovementsocc

    urring

    duringthe

    passageofheavyvehiclesoverthebridge

    ;

    Taperingormisalignmentofcracksandjointsinfoun

    dations,

    abutments,piersorothercomponentssupportedonthem;

    Suddend

    ropsorkinksinthestructureprofileoverpiersor

    abutment

    wallswhensightingalongrailingsorbeam

    lines;

    Abnormallylargeorsmallopeningsormisalignmentofdeck

    expansionjointsatabutmentsandpiers;

    Abnormaldisplacementsorinclinationsofbearings;

    Abnormallylargeorsmallclearancebetweenballast

    wall

    andsuperstructure;

    Cracksin

    abutmentwallandballastwall

    Shiftinalignmentfromoriginalposition;

    Regularmonitoringand

    measurementofmovements,

    inclinations,crackwidths,etc.

    Underwaterinvestigation

    Geotechnicalinvestigation

    Ta

    ble5

    .1:

    Suspec

    tedPerformance

    De

    fic

    ienc

    ies

    (Part

    2,

    Sec

    tion

    5)

    21

    1.

    CONCRETE

    DEFECT

    CONDITIONSTATE

    GOOD(LIG

    HT)

    FAIR(MEDIUM)

    POOR

    (SEVEREandVERYSEVERE)

    Stratifica

    tion

    Separationofconcreteintolayerspriortohardeningd

    uetoover-vibration.

    ALL

    Segr

    ega

    tion

    Concretenotuniformduetofallingconcrete(poorplacement)

    ALL

    Cold

    Jo

    ints

    Causedbyhardene

    dconcretepriortothenextadjace

    ntpour

    ALL

    Depo

    sits

    Waterseepedthrou

    ghconcrete,leachingchemicalsanddepositingthemonthe

    surface-efflorescence

    ALL

    Abra

    sion

    ALL

    Wearingcausedby

    vehiclesorsnow-ploughblades

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    22/50

    22

    1.

    CONCRETE

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVEREandVERYSEVERE)

    Wea

    r

    Resultofdynamic

    and/orfrictionalforcesgenerated

    byvehiculartraffic,coupledwith

    theabrasiveinfluxofsand,dirtanddebris

    ALL

    Slippery

    Con-

    crete

    Surface

    Smoothsurfaceresultingfromthepolishingoftheco

    ncretedecksurfacebytheaction

    ofrepetitivevehiculartraffic

    Act

    ive

    We

    tAreas

    Concretesoffitsurfaceiswetordamp

    We

    tbu

    tnocrac

    ks

    We

    tw

    ithcrac

    ks

    ALL

    *includesuspected

    per-

    formancesdeficiencyof

    slipperysurface

    D

    E

    F

    E

    C

    TS

    79

    Mis-align

    ment,lateraldeformation,warping,etc.ofcomponents;

    Inabilityoftheabutmenttowithstandlateralearthpr

    essures,as

    indicated

    bylong,mediumhorizontalcracksinabutments;

    Deformationoftheroofslab,floorslaborwallsofcu

    lverts.

    Deformationofsoil-steelstructuressuchasflattenin

    gorpeakingof

    thesoffit

    orbucklingoftheshouldersorhaunches;

    Up-liftat

    endsofsoil-steelstructures

    Movementscausingdistressinabearingorit'scomponents,orin

    otherstructurecomponents;

    3Cont

    inuing

    settle

    ment

    Foundation

    Lossofs

    trengthorsupportforappliedloadsduetomaterialdefects;

    Lossofm

    aterialsupportingfoundationsduetoscourorerosion

    Consolid

    ationorfailureofunderlyingsoilresultingin

    crackingor

    movementoffoundations,abutmentsorpiers

    Lossofc

    ontactbetweenpilesandpilecaporpiercap;

    Changes

    intheinclinationofpiles.

    Rotationalmovementofpilecapsandlossoffullcontactwithpiles.

    RegularMonitoringof

    settlement,pierand

    abutmentelevations

    andcrackwidths

    Strengthevaluation

    Geotechnical

    investigation

    Underwater

    investigation

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    23/50

    78

    Suspected

    Performance

    Deficiency

    ElementName

    (Examples)

    De

    scriptionofDeficiency

    PossibleFollow-up

    Action

    1Lo

    adCarrying

    Capacity

    Girder,DeckTop,Railing

    System,etc

    Materialdefectsleadingtolossofstrength,orwhichare

    indicativeofinadequatestrengthofthecom

    ponent

    (eg.20%sectionlossatmid-spanofgirder)

    Detrimentalmodificationsmadesubsequen

    tto

    construction;

    Strongevidenceofunderdesigntocurrent

    loads

    Strengthevaluation

    Monitoringofdeforma-

    tionsdisplacementsor

    rotations)orcracks

    2Excessive

    Deformations

    RailingSystem,

    DeckTop,TrussChord,

    AbutmentWall,

    Bearings,etc

    Overloading,eithersingleorrepetitiveoccu

    rrence,

    resultinginpermanentdeformationsofthe

    deckordeck

    components.

    Permanentdeformations,especiallyincom

    pression

    components

    Unanticipatedorexcessivevibrationordeflectionof

    components,connectionsorjointsunderliv

    eloads

    Unexpectednoisefromcomponentsorcon

    nectionsdueto

    vehiclesmovingacrossthestructure.

    Strengthevaluation

    Monitoringof

    deformations

    (displacementsor

    rotations)

    Ta

    ble5

    .1:

    Suspec

    tedPerformance

    De

    fic

    ienc

    ies

    (Part

    2,

    Sec

    tion

    5)

    23

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    24/50

    24

    2.

    STEEL/ALUMINUM(Part

    1,

    Sec

    t.2

    .3an

    d2

    .6,

    Part2Ta

    ble4

    .15

    ,4.1

    6,

    an

    d4

    .17)

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Corros

    ion

    Deteriorationofsteelbychemical/electro-chemicalreaction

    resultingfromexposuretoair,

    moisture,de-icingsalts,industrialfumesandotherchemica

    ls/contaminantsintheenvironment

    inwhichitisplaced

    Nosec

    tion

    loss,

    looserus

    t/

    pitting

    inpa

    int-

    10%sec

    tion

    loss,

    ex-

    tens

    iverus

    t/

    perfora

    tions

    Earlys

    ignso

    fpa

    tinad

    amage

    Flakingo

    fpa

    tina

    Permanen

    t

    Deforma

    tions

    Steelmemberscantake

    theformofbending,buckling,twistingorelongation.

    CorrugateSteelPipe(CS

    P)culvertscanexhibitcusping(ab

    ruptchangeincurvature,typically

    atseam),crimping(local

    bucklingofculvertwall),globaldeformation(changeinoriginal

    curvedshape),andbolttilting(bearingfailureofbolts).

    For

    Mem

    bers:

    ALL

    (Es

    tima

    terepa

    irarea)

    D

    E

    F

    E

    C

    T

    S

    77

    Performance Deficiencies andMaintenance Needs

    APPENDIX

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    25/50

    76Wood

    Su

    bs

    truc

    tureor

    Supers

    truc

    ture

    Adetailedinvestigationofthewood

    componentsusingtechniquessuchasprobing,

    drilling,coring,etc.

    10%ofelemen

    tin

    PoorConditio

    nState

    Part4ofthismanual

    Struc

    tura

    lStee

    l

    Coating

    Adetailedsurveyoftheconditionofthecoating

    toconfirmthefeasib

    ilityofover-coating.The

    surveyinvolvestestingcoatingadhesion,dry

    filmthickness,etc.Ifdeteriorationisstillinthe

    earlystages(CombinedareaofFairandPoor

    greaterthan25%,a

    ndPoorislessthan10%at

    thevisualinspection

    stage),over-coatingof

    thesteelmaybeav

    iablerehabilitationoption.

    Thisinvolvescleaningthesurfacewithawire

    brushandover-coa

    tingtheentiresurface.If

    deteriorationexceedsthethreshold,traditional

    coatingtechniques(sandblastingthesurface,

    priming,etc,)would

    probablyhavetobeused.

    25%ofcombin

    edarea

    inFairandP

    oor

    ConditionStatesand

    alsothepercentagein

    Poorlessthan

    10%.

    StructuralSteelCoating

    Manual

    C

    O

    N

    D

    I

    T

    I

    O

    N

    *Thistableindicatesthematerialdefectpr

    oportionsthatwouldgenerallytrigger

    the

    needforadetailedconditionsurveytobedone.

    25

    2.

    STEEL/ALUMINUM

    DE

    FECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Cuspingorcrimpingofc

    ulverts

    10mminheight*

    GlobalDeformation10%

    ofculvertdiameterandre-

    versecurvature*

    BoltTilting

    Crac

    king

    Arelinearfractureinthe

    steelextendingpartiallyorcompletelythroughthemember.Theyare

    mainlycausedbyfatigue

    ,whichcanleadtobrittlefracture(membercrackscompletely)

    throughwithoutpriorwarning)

    Cracksperpendiculartostressareveryseriousandshould

    have

    immediateactiontaken.

    ALL

    (Es

    tima

    terepa

    irarea)

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    26/50

    26

    2.

    STEEL/ALUMINUM

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Connec

    tion

    De

    fic

    ienc

    ies

    Looseconnectionscanoccurinbolted,rivetedorclamp

    edconnections.Theymaybe

    causedbycorrosionoftheconnector,gussetplatesorfasteners,excessivevibration,

    overstressing,cracking,orthelackofpropertightening

    duringconstruction.

    Basedontheconditionoftheworstcompone

    ntwithintheconnection

    DependsonpercentageofLooseBoltsorPlanAreawithseverecorrosion

    10%

    *-

    Thesenaturallyoccurringcracksinthewood,causedbyshrinkage,arenotassevereasoverload

    crackingorsplinteringsincewoodfibresexisttobridgethecrackandreducetheimpactonthem

    ember

    capacity.Theactualareacontainingthedefec

    tshallbedeterminedforareascontainingnumerous

    defects.Forisolatedcracks,8mofcrackleng

    thisequalto1squaremetreofdefectforchecks,shakes

    andsplits;while4mofcracklengthisequalto

    1squaremetreofdefectforcracking,splintering,crush-

    ingandshattering.Thelengthofcracks,shakes,splits,etc.shallbemeasuredonallsurfaces.

    C

    O

    N

    D

    I

    T

    I

    O

    N

    27

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    28/50

    2873

    Tab

    le4

    .18:

    Streamsan

    dWa

    terw

    ays

    Exc

    ellen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    No

    observedmaterial

    defects

    Afewlocationsofscour

    ordegradation

    ofthe

    streambedorstream

    banksbutnotexposing

    thefoundations

    Numerouslocationsof

    scourordegradationofthe

    streambedorstream

    bankstothetopofthep

    re-

    viouslycoveredfounda-

    tions

    Scourordegradationofthe

    streambedorstreambanks

    tothebottomofpreviously

    coveredfoundations

    Slightscourat

    inletor

    outletofculver

    tsand

    soil-steelstructures

    Moderatescouratthein

    let

    oroutletofculvertsand

    soil-steelstructures

    Extensivescouraroundthe

    inletoroutletofculvertsand

    soil-steelstructureswithloss

    ofembankmentfill

    Streamalignment

    shiftedbutnot

    en-

    croachingagainstcom-

    ponentsprevio

    uslynot

    subjecttostreamflow

    Streamalignmentshifted

    andencroachingcloseto

    componentsnotpreviously

    subjecttostreamflow

    Streamalignmentshifted

    withstreamflowdirectly

    againstmostofacomponent

    notpreviouslysubjectto

    stream

    Afewlocationsofag-

    gradationnota

    ffecting

    thestreamflow

    atthe

    structure

    Mediumaggradationhav-

    ingasignificanteffecton

    thestreamflowatthe

    structure

    Extensiveaggradationvery

    severelyaffectingthestream

    flowatthestructure)

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    29/50

    72

    Tab

    le4

    .17:

    Stee

    lor

    Alum

    inum-

    Ra

    ilings

    Ex

    ce

    llen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    P

    oor

    Con

    dition

    Noobservedmaterial

    de

    fects

    Lightcorrosionno

    sectionloss

    Mediumcorrosion-up

    to10%sectionloss

    S

    evereandverysevere

    c

    orrosionmorethan

    1

    0%sectionloss

    Slightlossofcableten-

    sionorslightslippage

    ofcableanchorsand

    splices

    Moderatelossofcable

    tensionorslightslip-

    pageofcableanchors

    andsplices

    S

    ignificantlossofcable

    tensionorslightslip-

    p

    ageofcableanchors

    a

    ndsplices

    B

    rokencablestrands/

    s

    upports

    C

    ollisionorvandalism

    d

    amage/missingsec-

    tions

    P

    ermanentdeforma-

    tions

    Lightconnectiondefi-

    ciencies

    Mediumconnection

    deficiencies

    S

    evereconnectiondefi-

    c

    iencies

    C

    O

    N

    D

    I

    T

    I

    O

    N

    29

    3.WOOD(Part1,Sect.2.4andPart2Table4.19)

    DEFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    W

    eathering

    Gradualdeteriorationofwoodduetoexposuretotheactionso

    fsun,rain,wind,

    frostandatmospheric

    pollutants

    Checks

    Longitudinaltissueseparationsonthesidegrainofwoodmem

    bers

    Splits

    Severetissueseparatio

    nsextendingfromthesideintotheend

    Shakes

    Tissueseparationswhic

    hfollowthecircularannualgrowthrings,andarevisibleontheendgrain

    Weathering

    10%intomember

    Checks,Splits,

    Shakes

    10%intomember

    Biologicalde

    compositionofwoodcausedbym

    icro-organismscalledfungi

    Slightchangeincolo

    urbut

    woodsolid(10%

    Loss)

    RotorDecay

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    30/50

    30

    D

    E

    F

    E

    C

    T

    S

    3.WOOD

    DEFECT

    CONDITIONSTAT

    E

    GOOD(LIGH

    T)

    FAIR(MEDIUM)

    POOR(SEVERE/VERYSEVERE)

    InsectDamage

    Consequenceofthetunnelling/boringbylarvae/matureinsectsthroughthewoodre-

    sultinginlossofs

    ection

    Holesarepres

    ent

    (10%loss)

    Abr

    asionandWearDeteriorationofw

    oodbroughtaboutbyvehiclesors

    nowploughbladesscraping

    againstwoodsurfaces,coupledwiththeabrasiveinfluenceofsand,dirtordebris.

    10%loss

    Cra

    cking,Splinter-

    ing,Crushingand

    Sha

    ttering

    Physicaldamage

    whichresultsfromvehicularcollis

    ionfromoverloadingofamember

    10%loss

    71

    T

    able4

    .16:

    Stee

    lor

    Alum

    inum

    Su

    bs

    truc

    turesan

    dSupers

    tructures

    E

    xce

    llen

    tCon

    dition

    Goo

    dCond

    ition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    N

    oobservedmaterial

    d

    efects

    Lightcorrosionnosec-

    tionloss

    Mediumcorrosion-up

    to10%sectionloss

    Severeandverysevere

    corrosionmorethan

    10%sectionloss

    Allcracks(immediate

    actionisrequired-

    estimaterepairarea)

    Permanentdeformations

    Lightconnectiondefi-

    ciencies

    Mediumconnectiond

    efi-

    ciencies

    Severeconnectiondefi-

    ciencies

    Evaluationandcondition

    survey*if

    >10%inthisstate.

    *Involvesmeasuringthicknessofcriticalmemberstodeterminesectionlossasitvariesacrosstheele-

    m

    ent

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    31/50

    70

    Table4

    .15:

    Stee

    l

    Atmosp

    heric

    Corros

    ion

    Res

    istan

    tSu

    b-

    st

    ruc

    turesan

    dSupers

    truc

    tures

    Exce

    llen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    Noobservedmaterial

    defectswithsmooth

    uniformrustlayer

    (patina)

    Earlysigns

    ofpatina

    flakingand

    nosection

    loss

    Flakinganddelamina-

    tionofPatinaupto1

    0%

    sectionloss

    Morethan10%section

    loss

    Allcracks

    Permanentdeforma-

    tions

    Lightconnectiondefi-

    ciencies

    Mediumconnectiondefi-

    ciencies

    Severeconnectiondefi-

    ciencies

    Evaluationandcondition

    survey*if

    >10%inthisstate.

    31

    3.

    WOOD

    D

    EFECT

    CONDITIONSTATE

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Firea

    ndChem

    i-

    ca

    lDamage

    Fireisevidencedbycharringandisusuallyconfinedtothewoodsurface.Chemicaldam-

    agemayresultfromth

    euseofnonpreservativechemica

    lsonthewoodsurfaceovera

    longperiodoftime

    Slig

    htc

    harr

    ingor

    so

    ften

    ingw

    ith10%sec

    tion

    loss

    Connec

    tion

    De

    ficienc

    ies

    10mmwide

    65

    Tab

    le4

    .10:

    Expans

    ion

    Jo

    int

    Seals

    /Sea

    lan

    ts

    Exce

    llen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    Noobservedmaterial

    defects

    Abrasionsinsealwithno

    perforations

    Lossofresiliencyof

    seal

    butnoperforations

    Cracks,tearsorholesin

    theseal

    Sealhasdebonded

    Sealisallowingleakage

    onthesubstructure.

    Sealantdebonded,

    pulledoutorsettled

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    37/50

    64

    Table4.9:ExpansionJointArmou

    ringandRetainingDevices

    Ex

    ce

    llen

    tCon

    dition

    Goo

    dCond

    ition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    No

    observedmaterial

    de

    fects

    LightCorros

    ion*

    MediumCorrosion*

    SevereCorrosion*

    Bolts,anchors,armour-

    ing,clampingdevicesor

    weldsareloose,broken

    ormissing

    *A

    sdefinedinTable4.16.

    C

    O

    N

    D

    I

    T

    I

    O

    N

    37

    DEFECT

    5.

    ASPH

    ALTWEARINGSURFACE(Part1

    Sec

    t.2

    .7,

    Part

    2Ta

    ble4

    .1)

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE

    /

    VERYSEVERE)

    Surface

    Defec

    ts

    Progressivedeteriorationandlossofthepavemen

    tmaterialfromsurfacedownward

    No

    ticea

    blel

    osso

    f

    pavemen

    tm

    ateria

    l

    Sha

    llow

    disintegra

    tion

    ofpavemen

    tw

    ithan

    open

    tex

    tureappear-

    ance

    Sha

    llow

    todeep

    disintegra

    tion

    ofpavemen

    tw

    ithsma

    ll/

    numerouspo

    tho

    les,

    open

    tex-

    turean

    dloosesurfacema

    teria

    l

    Slippery

    Surface

    Mayresultfrom

    flushingorfromthepolishingofth

    ecoarsesurfaceaggregatesbythe

    actionofrepetitivevehic

    ulartraffic

    Therearenoseveri

    tydescrip

    tionsg

    iven

    forsl

    ipperysurfacesas

    thisisaseri-

    ousan

    dpo

    tentia

    lly

    hazardouss

    itua

    tionresulting

    inlosso

    fri

    dingcom

    fortand

    losso

    fve

    hicle

    con

    tro

    l(in

    dica

    tesuspec

    tedper

    form

    de

    fic

    iencyo

    fs

    lipperysur-

    face

    )

    Flus

    hing

    Themigrationofasphaltupwardstothepavementsurfaceinpavementswithtoo

    muchasphaltinthe

    mix.

    Visibleco

    lou

    ringo

    f

    thepavement

    surface

    occurr

    ing

    inloca

    lize

    d

    areas

    Distinc

    tiveco

    louringo

    f

    thepavemen

    tsurface

    withexcessasp

    ha

    lt

    freeon

    thepavement

    surface

    Excess

    ive

    freeasp

    ha

    ltg

    ives

    thepavemen

    tsurfacea

    wet

    loo

    k

    .Visibleimprin

    tsleftfrom

    foo

    tprin

    tsorve

    hicu

    lar

    tra

    ffic

    Rave

    lling

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    38/50

    38

    D

    E

    F

    E

    C

    T

    S

    DEFECT

    5.

    ASPH

    ALTWEARINGSURFACE(Part

    1Sec

    t.2

    .7,

    Part

    2Ta

    ble4

    .1)

    GOOD

    (LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Sur

    face

    Disto

    rtion

    Whee

    ltrac

    k

    rutting

    Theformatio

    noflongitudinaldepressionsinthepavementatthelocationsof

    thewheeltracksofvehicles

    Ru

    tting

    20mm

    deep

    Loca

    lUn-

    derly

    ing

    Defec

    ts

    Po

    tho

    les

    Bowl-shapedholesinthepavementcausedby

    thepenetrationofwaterthrough

    thepavementandsubsequentheavingofthep

    avementduetofreezingofthe

    entrappedw

    aterandbreakingupofthepavem

    entduetotrafficaction

    20mm

    deep

    Pro

    trus

    ions

    (Delaminations)

    Localdelaminationisvisibleasprotrusionsorbumps(oftencircularinshape)

    20mm

    inhe

    ight

    63

    ExcellentCondition

    GoodCondition

    FairCondition

    PoorCondition

    Noobservedmaterialde-

    fe

    cts

    Upto10%lo

    ssofmaterial

    forembankm

    entsnotdi-

    rectlysupportingfounda-

    tions;or,upto5%

    lossfor

    embankment

    sdirectlysup-

    portingfoundations

    10%-30%lossofmaterial

    forembankmentsnotdi-

    rectlysupportingfounda-

    tions;or5%to15%lo

    ss

    forembankmentsdirectly

    supportingfoundations;or,

    lossofmaterialtothetop

    offoundations

    Morethan30%lossofmate-

    rialforembankmentsnot

    directlysupportingfounda-

    tions;or,morethan15%

    lossforembankmentsdi-

    rectlysupportingfounda-

    tions;or,lossofmaterialto

    thebottomoffoundations

    Tab

    le4

    .8:

    Em

    ban

    kmen

    ts

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    39/50

    62Ta

    ble

    4.7

    :Dra

    inage

    Sys

    tem

    Ex

    ce

    llen

    tCon

    dition

    Goo

    dCond

    ition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    No

    observedmaterial

    de

    fects

    Upto20%o

    findividual

    drainagesystemhas

    looseordeterioratedcom-

    ponents,connectionsor

    fasteners

    20%to60%ofindivid-

    ualdrainagesystemhas

    looseordeteriorated

    components,connec-

    tionsorfasteners

    Morethan60%ofindivid-

    ualdrainagesystemhas

    looseordeterioratedcom-

    ponents,connectionsor

    fasteners

    Brokenpipecomponents

    resultinginwaterdraining

    ontosubstructure

    C

    O

    N

    D

    I

    T

    I

    O

    N

    39

    DEFECT

    5.

    ASPHAL

    TCOVEREDCONCRETEDECK(P

    art

    1Sec

    t.2

    .7,

    Part

    2Ta

    ble4

    .6)

    GOOD

    (LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    BOT TOM-UP DEFECTSW

    ide

    Is

    olated

    Crac

    ks

    Transverse,

    long

    itu

    dina

    l

    crac

    ks

    Long

    itu

    dina

    lparalleltothedirectionoftrave

    l,andgenerallylocatedator

    nearthecen

    treofthewheeltrack,pavementedgeorcentre-lineofbridge

    Transverse

    acrosspavementeitherfullyorp

    artially

    >10mmw

    idesing

    le

    crac

    ks

    Loca

    l

    Un

    derly-

    in

    gDe-

    fe

    cts

    Po

    tho

    les

    Bowl-shapedholesinthepavementcausedby

    thepenetrationofwaterthrough

    thepavementandsubsequentheavingofthep

    avementduetofreezingofthe

    entrappedw

    aterandbreakingupofthepavementduetotrafficaction

    ALL

    Pro

    trus

    ions

    (Delaminations)

    Localdelaminationisvisibleasprotrusionsorb

    umps(oftencircularinshape)

    ALL

    Pa

    ttern

    Crac

    ks

    Map,

    edge,

    alliga

    tor,

    radial

    ALL

    Incompletes

    eparationintooneormorepartsw

    ithorwithoutspacebetween

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    40/50

    40

    6.

    ASPHALTCOVEREDCONCRETEDECKS

    GOOD

    (LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    TOP-DOW

    NDEFECTS

    Bon

    d

    De

    fec

    ts

    Losso

    f

    bon

    d

    Widespreadlossofbondanddelaminationmayoccurbetweentheasphalt

    pavementanddecksurface,betweenthewaterproofingandthedecksurface,

    betweenthewaterproofingandtheasphaltpa

    vementorbetweenindividuallifts

    ofpavement

    A

    LL

    Ripp

    ling

    Theformationoftransverseundulationsinthe

    pavementsurfaceconsistingof

    closelyspa

    cedvalleysandcrests

    A

    LL

    Surface

    De

    fec

    ts

    Rave

    llingProgressivedeteriorationandlossofthepave

    mentmaterialfromthesurface

    downward

    A

    LL

    Slippery

    Surface

    Mayresultfromflushingorfromthepolishing

    ofthecoarsesurfaceaggregates

    bytheactio

    nofrepetitivevehiculartraffic

    A

    LL

    DEFECT

    61

    E

    xcellentCondition

    GoodCondi

    tion

    FairCondition

    PoorCondition

    AllBondDe

    fects(e.g.rippling,loss

    ofbond)inasphalt.

    AllSurfaceDefects(e.g.ravelling,

    flushing,slip

    perysurface)inasphalt.

    AllSurfaceDistortions(wheeltrack

    rutting)inasphalt.

    Conditionsurveyiftheareaofdete-

    riorationinthisstate>10%ifnot

    alreadydone.

    Bas

    edon

    Visua

    lInspec

    tiono

    fAspha

    lt

    Notes

    :

    (1)Forallcalculations,

    theactualareashallbedeterminedforareascontainingnumerouscracks(i.e.alliga-

    to

    rcracks,radialcracks).Forisolat

    edcracks,

    4mo

    fcracklengthisto

    equalto1squaremetreofdefect

    re

    pairarea.

    (2)If

    abridgehasbeenrecentlyrepavedwithoutrehabilitatingthedeck,th

    einspectormustestimatethecon-

    ditionoftheconcretedeckusingothermeans.

    Thiswouldincludeusingpreviousinspectioninformation,

    Table4

    .6:

    Concre

    te

    Topo

    fDe

    ckBenea

    thAsp

    ha

    ltWearing

    Surface

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    41/50

    60

    Exc

    ellentCondition

    GoodCo

    ndition

    FairCondition

    PoorCondition

    NoAsphaltDefects.

    Top-Dow

    nAsphaltDe-

    fects

    Bottom-

    UpAsphaltDefects

    Localprotrusionsinasphalt.AllPotholesinasphalt.

    Lightand

    medium

    isolatedcracksin

    asphalt.

    Wideisolatedcracksin

    as-

    phalt.

    (Cracksinclude:longitudinal

    cracks,abovelocation

    of

    voids,edgeofbeamflanges,

    jointbetweenprecastu

    nits,

    constructionjoints,etc.,or

    transversecracks)

    AllPatterncrackingin

    asphalt

    (e.g.map,alligator,radial,

    edgecracking).

    BasedonVisualInspectionofAsphalt

    T

    able4

    .6:

    Concre

    te

    TopofD

    ec

    kBenea

    thAsp

    ha

    lt

    W

    earing

    Surface

    41

    DEFECT

    6.

    ASPHALTCOVERED

    CONCRETEDECKS

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    TOP-DOWN DEFECTS

    Surface

    De-

    fec

    ts

    Flus

    hingT

    hemigrationofasphaltupwardsto

    thepavementsurfaceinpave-

    m

    entswithtoomuchasphaltinthemix.

    ALL

    Surface

    Dis-

    tort

    ion

    Whee

    ltrac

    k

    rutting

    T

    heformationoflongitudinaldepres

    sionsinthepavementattheloca-

    tionsofthewheeltracksofvehicles

    ALL

    Lightan

    d

    Me

    dium

    Iso

    lated

    Crac

    ks

    Iso

    lated

    crac

    ksan

    d

    Transverse,

    long

    itu

    dina

    l

    crac

    ks

    L

    inearfractureextendingpartiallyorcompletelythroughthepavement

    10%forsubstructures

    DeckConditionSurveyif

    areaofdeteriorationinthis

    state>10%forsuperstruc-

    tures

    Tab

    le4.5:Concrete

    Su

    bs

    truc

    turesandSuperstructures

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    43/50

    58

    ExcellentCondition

    GoodConditio

    n

    FairCondition

    PoorCondition

    Noo

    bserve

    dma

    teria

    l

    defe

    cts

    Lightscaling

    Mediumscaling

    Severetoveryseverescal-

    ing,erosionanddisintegra-

    tion

    Ruststainson

    con-

    creteduetocorroding

    rebarchairs

    Ruststainsonconcretedueto

    corrodingreinforcingsteel

    Mediumtoveryseverecor-

    rosionofreinforcingsteel

    Surfacecarbo

    nation

    (Reactionwith

    CO2,

    associateddis

    colour-

    ation,shrinkageand

    cracks)

    Surfacedefectssuchasstrati-

    fication,segregation,cold

    joints,abrasion,wear,slippery

    surfaces,wetareasandsur-

    facedeposits(excepton

    soffits).

    Lighthoneyco

    mbing

    andpop-outs

    Mediumhoneycombinga

    nd

    pop-outs

    Severetoveryseverehon-

    eycombingandpop-outs

    HairlineandN

    arrow

    cracks

    Mediumcracks

    Allwidecracks

    Lightalkali-ag

    gregate

    reaction

    Mediumalkali-aggregate

    reac-

    tion

    Severeandverysevereal-

    kali-aggregatereaction

    Tabl

    e4.5:Concrete

    Substructur

    esandSuperstructures

    C

    O

    N

    D

    I

    T

    I

    O

    N

    43

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    44/50

    44

    DEFECT

    7.COATING(PART1,Section2.8&Part2Table4.4)

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR(SEVERE/VERYSEVERE)

    Rutsconditionratingisavisualratingofthesurfaceappe

    aranceandisbasedonASTMD610

    sketchesandisalsoshowninAppendixCandOSIMPart2,Figure4.1

    RustConditionRating2RustConditionRating3

    RustConditionRating4ormore

    Co

    ating

    Re

    lated

    De

    fects

    Checkingor

    Crazing

    Finesystem

    ofminutecracksinacheckerboardpattern.Causedbyweatheringand

    exposureduringcuring

    ALL

    Cracking

    Linearpatternofcrackpenetratedthroughcoating.

    Resultsfromweathering,continuing

    polymerizatio

    norshrinkage

    ALL

    Alligatoring

    Largeirregularchecksacrosssurface.Causedbynoncompatiblelayersofcoatingand

    hardening/sh

    rinkageprocess

    ALL

    ChemicalAt-

    tack

    Coatingreac

    tingadverselywithairbornechemicals

    oraccidentalspills

    ALL

    Chalking

    Powderyapp

    earanceofcoatingsurface.Causedb

    yreactionofcoatingresinstosunlight

    andprocess

    ofweathering.

    AL

    L

    Rust

    ConditionRating

    57

    Figure 4.4b: Rust Condition Rating Categories for Coatin

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    45/50

    56

    Exce

    llen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    NoObservedMaterial

    Defects

    Chalking

    Checking,cracking,alli-

    gatoring

    Intercoatdelamination,

    peeling(topcoaton

    ly)

    Undercutting,blisters,

    peeling(primecoat),un-

    derfilmcorrosion

    Signsofchemicala

    ttack

    Overspray,runs,sags,

    pinholing

    Bridging,edgedefe

    cts,

    shadows

    RUSTCONDITION**

    RATING

    CATEGORY1

    RUSTCONDITION**

    RATING

    CATEGO

    RY2

    RUSTCONDITION

    **

    RATING

    CATEGORY3

    RUSTCONDITION**

    RATING

    CATEGORY4orhigher

    CoatingConditionSurveyisrequiredifcombined

    areaintheFairand

    PoorConditionStatesis

    greaterthan25%andtheareainthePoorCondi-

    tionStateislessthan10%***

    Ta

    ble

    4.4

    a:

    Coa

    ting

    *-

    Struc

    tura

    lSteelSu

    bs

    truc

    turesan

    dSuper-

    Struc

    tures

    45

    DEFECT

    7.

    COATING(PART1

    ,Sec

    tion2

    .8&Part

    2Ta

    ble4

    .4)

    DEFECTS

    *

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR(SEVERE/VERYSEVERE)

    Adh

    es

    ion

    Re

    lated

    De

    fec

    ts

    Un

    dercu

    ttingSpreading

    ofcorrosionundercoatingfromab

    reak.Causedbypoorsurface

    preparation

    Blis

    ters

    Domeshapedprojectionsofcoating.Caused

    bysolventorwatertrapped

    withinpaintfilm

    Intercoa

    t

    De

    lam

    ina

    tion

    Onecoats

    eparatesfromanother.Causedby

    contaminatedsurfacesor

    excessivecuringbetweencoats

    Pee

    ling

    Separation

    ofcoatingfromsteelduetopoora

    dhesion

    Corrosionunderthecoatingwiththehelpoffromabreak.Causedbypoor

    preparation

    orporouscoating

    Un

    derf

    ilm

    Corros

    ion

    ALL

    ALL

    ALL

    ALL

    ALL

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    46/50

    46

    DEFECT

    7.

    COATING(PART1

    ,Sec

    tion2

    .8&Part

    2Ta

    ble4

    .4)

    DEFECTS

    *

    GOOD

    (LIGHT)

    FAIR(MEDIUM)

    POOR

    SEVERE/VERYSEVERE)

    Bri

    dg

    ing

    Coatingbridgesacrosstightcornerordebrisformingvoid.Voidcantrap

    moistureandoxygen

    Edge

    De

    fec

    tsCoatingpu

    llsawayfromsharpedgesandcor

    ners.Duetoinsufficient

    application

    ofcoatingatedge

    Sha

    dows

    Coatingisappliedtoothinintheshadowofa

    rivet,bolts,orotherabruptchange

    insurface

    Overspray

    Somepain

    tparticleoutsidespraypatterndry

    priortofullcoating.Leadsto

    someabso

    rbedsolventandamoreporoussurface

    ALL

    Appl

    ica

    tion

    Rela

    ted

    Defec

    ts

    ALL

    ALL

    ALL

    55

    Ta

    ble4

    .3:

    Coa

    ting

    *

    Stee

    lRa

    iling

    s

    Exce

    llen

    tCon

    dition

    Goo

    dCon

    dition

    Fa

    irCon

    dition

    Poor

    Con

    dition

    RUSTCONDITION**

    RATING

    CATEGORY1

    RUSTCONDITION

    RATING

    CATEGOR

    Y2

    RUSTCONDITION

    RATING

    CATEGORY3

    RUSTCONDITION

    RATING

    CATEGORY4orhigher

    *

    Galvanizedelementsareincluded

    undertheCoatingcategory

    **

    RustConditionRatingsareshown

    inFigure4.1.Foradditionalinform

    ation,seetheStruc-

    turalSteelCoatingManual.

    ***Inordertoconsiderovercoatinga

    saviablerehabilitationoption,ad

    etailedconditionsur-

    veyshouldbetriggeredbeforedeteriorationistoowidespread.

    C

    O

    O

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    47/50

    54

    Ex

    ce

    llen

    t

    Co

    ndition

    Goo

    d

    Con

    dition

    Fa

    ir

    Con

    dition

    Poor

    Con

    dition

    NoObs

    ervedMate-

    rialDefects

    Hairlinecracksinelastomericpads

    Narrowtomediumcracksin

    elastomericpads

    Verywidecracksinelastomericpads

    and/orsteelplatesdebonded

    Lightbulgingorsheardeform

    ationsin

    elastomericpads,orlightlocal

    deformationofroller/rockerp

    lates

    Mediumbulging/sheardeformations

    inelastomericpads,ormediumlocal

    deformationofroller/rockerplates

    Severebulging/sheardeformations

    inelastomericpads,severelocal

    deformationofroller/rockerplates

    Lightscoring/scratchesinTF

    Eor

    stainlesssteel

    Mediumscoring/scratchesinT

    FEor

    stainlesssteel

    Severescoring/scratchesorripsand

    tearsinTFEorstainlesssteel

    LightCorrosion

    MediumCorrosion

    Severeandveryseverecorrosion

    andorcracksinsteel

    Anchorboltsslightlybent

    Anchorboltsseverelybent/cra

    cked

    Anchorboltsarebroken

    Guidebarsandthrustplates

    slightlywornGuidebarsandthrustplatesm

    oder-

    atelyworn

    Guidebarsandthrustplatesse-

    verelywornand/orlooseormissing

    nuts

    Upto5%ofbondedslidings

    urfaceis

    debonded

    5%to20%ofbondedslidings

    urface

    isdebonded

    Over20%ofbondedslidingsurface

    isdebonded

    Internallyconfinedcompressionma-

    terialissqueezing/squeezedout

    T

    able4.2

    :Bearings

    C

    O

    N

    D

    I

    T

    I

    O

    N

    47

    DEFECT

    7.

    COATING(PART1

    ,Sec

    tion2

    .8&Part

    2Ta

    ble4

    .4)

    DEFECTS*

    GOOD(LIGHT)

    FAIR(MEDIUM)

    POOR

    (SEVERE/VERYSEVERE)

    Appl

    ica

    tion

    Rela

    ted

    Defec

    ts

    Pinho

    ling

    Airbubbles

    trappedincoatingcreatingvoids.

    Causedbyholdingsprayguntoo

    close

    AL

    L

    Runs

    Downwardmovementofpaint.Causedbyover-thinningordepositingtoomuch

    paintatone

    time

    AL

    L

    Sags

    Similartoru

    ns,thedownwardmovementofcurtainofpaint

    AL

    L

    Pinpo

    int

    Rus

    ting

    Rustingvisibleatpointlocations.Causedbyinsufficientcoatingthicknesson

    peaksofblastcleanedsubstrate

    RatebasedonappearanceandRustConditionRating

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    48/50

    4853

    ExcellentCondition

    GoodCondition

    FairCondition

    Poor

    Condition

    No

    ObservedMate-

    rialDefects

    Lightcracking

    Mediumcracking

    Seve

    retoverysevere

    cracking

    Lightravelling

    Mediumravelling

    Seve

    reandverysevere

    ravelling

    Allareaswithlossof

    bond

    LightPotholes

    MediumPotholes

    Seve

    reandverysevere

    potholes

    Lightwheeltrackrut-

    ting

    Mediumwheeltrack

    rutting

    Seve

    reandverysevere

    whee

    ltrackrutting

    LightRippling

    MediumRippling

    Seve

    reandVerySevere

    Rippling

    LightFlushing

    MediumFlushing

    Seve

    reandverysevere

    flushing

    For

    allcalculations,

    theactualareashallbedeterminedforareascontainingnumerouscracks(i.e.

    allig

    atorcracks,radialcracks).Foriso

    latedcracks,

    4m

    ofcrack

    Tab

    le4

    .1:

    Asp

    ha

    ltWearing

    Su

    rface

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    49/50

    52

    C

    O

    N

    D

    T

    O

    N

    APPENDIX C: MATERIAL CONDITIONSTATE TABLES

    (Part 2, Section 4)

    Four Condition States have been defined for bridgeelements, namely, Excellent, Good, Fair and Poor.

    The condition of bridge elements is defined to be inany one or more of these Condition States.The severity and extent philosophy is used where,for each bridge element, the inspector assesses andrecords the amount (area, length or unit as appropri-ate) of the element in each of the four ConditionStates.

    49

    Element List and Condition StateCross Reference Table (Part 2, Ta

    APPENDIX B

  • 7/27/2019 OSIM FieldGuide (Apr 2008)

    50/50

    50

    Element Group Element Name6,7,8

    Unit forQuantity

    1,2,3,4Appl icab le Condit ionState Table Number

    5

    Abutments Abutment walls Sq.m. 4.5, 4.11, 4.19

    Ballast walls Sq.m. 4.5, 4.11, 4.19

    Bearings Each 4.2

    Wingwalls Sq.m. 4.5, 4.11, 4.19

    Accessories(Attachments & Signs)

    Bridge Mounted SignSupports 9

    Each 4.12

    Electrical 9 Each 4.12

    Noise Barriers m10 4.12

    Other Each 4.12

    Signs Each 4.12

    Utilities Each 4.12

    Approaches Approach slabs Sq.m. 4.5, 4.6

    Barriers 9 m10 4.17, 4.19

    Curb and Gutters m. 4.5

    Drainage System Each 4.7

    Sidewalk/Curbs Sq.m. 4.5

    Wearing surface Sq.m. 4.1, 4.5, 4.6

    Barriers Barrier/Parapet Walls Sq.m. 4.5

    Hand Railings m. 10 4.17

    Posts Each 4.5, 4.16, 4.19

    Railing Systems m.10

    4.17, 4.19

    Beams/Main Longitu-dinal Elements

    Diaphragms Each (Sq.m ifConcrete)

    4.5, 4.15, 4.16, 4.19

    Floor beams Sq.m. 4.5, 4.16, 4.19

    Girders Sq.m. 4.5, 4.15, 4.16, 4.19

    Inside boxes (sides &bottom)

    Sq.m. 4.5 , 4.15

    Stringers Each 4.5 , 4.16, 4.19

    Bracing Bracing Each 4.15, 4.16, 4.19

    Coatings Railing Systems /Hand Railings

    Sq.m. 4.3

    Structural Steel Sq.m. 4.4

    Culverts Barrels Sq.m. 4.5, 4.14

    Inlet Components Sq.m. 4.5

    Outlet Components Sq.m. 4.5

    Decks Deck Top Sq.m. 4.5, 4.6, 4.19

    Drainage System Each 4.7

    Soffit Inside Boxes Sq.m. 4.5

    Soffit Thick slab Sq.m. 4.5

    Soffit Thin Slab Sq.m. 4.5, 4.19

    Wearing Surface Sq.m. 4.1

    Embankments &Streams

    Embankments Each 4.8

    Slope protection Each 4.13

    Streams and Water-ways

    All 4.18

    Foundations Foundation (belowground level)

    N/A Rate performance only.

    Joints Armouring/retainingdevices

    m. 4.9

    Concrete end dams Sq.m 4.5

    Seals/sealants each 4.10

    Table 2.1: Element List and Condition State Cross Reference Table

    51

    Element Group Element Name6,7,8

    Unit forQuantity

    1,2,3,4Appl icab le Con dit ionState Table Number

    5

    Piers Bearings Each 4.2

    Caps Sq.m. 4.5, 4.11, 4.16, 4.19

    Shafts/columns/PileBents

    Sq.m. 4.5, 4.11, 4.16, 4.19

    Retaining walls Barrier Systems onwalls

    Sq.m. 4.5, 4.17, 4.19

    Railing Systems m10 4.17, 4.19

    Drainage Systems All 4.7

    Walls Sq.m. 4.5

    Sidewalks/curbs Curbs Sq.m. 4.5

    Sidewalks and medi-ans

    Sq.m. 4.5

    Trusses/Arches Bottom chords Sq.m. 4.5, 4.16, 4.19

    Connections Each 4.16, 4.19

    Top chords Sq.m. 4.5, 4.16, 4.19Verticals/diagonals Sq.m. 4.5, 4.16, 4.19

    Notes: 1 For All, place the entire component (100%) in one condition state.2 For Each, give the number of occurrences of the component in each state.3 For cracks in concrete, estimate repair area (4m of crack = 1 sq. m of repair).4 For cracks in steel, estimate required repair area.5 Tables given are typical for element. Use appropriate table for applicable

    material. (See Section 4).6 Sub-elements (End/Middle) to be used for the following elements at expansion

    joint locations: Deck Top, Girders, Inside BoxesSub-elements (End/Intermediate) to be used for the following elements at

    expansion joint locations:: Floor Beams, Stringers, Bracing and Dia-phragms

    Sub-elements (End/Interior/Exterior) to be used for SoffitsSub-elements (Interior/Exterior) to be used for Barrier/Parapet Walls

    7 For an explanation of which bridge components are included in each element,see Table 3.1.

    8 Similar element types should be grouped together (e.g. I-girders, x-frames, etc.)9 Optional element. Not required for MTO use

    10 For these elements that are inspected by linear metre, a defect in the post shallbe assumed to affect the tributary area for that post.