otb-hay bypass line economic benefit study · pdf fileotb-hay bypass line economic benefit...
TRANSCRIPT
OTB-HAY Bypass Line Economic Benefit Study
Transpower NZ Limited
HVDC Bypass Line Economic Benefit Study
RZ024300_01 | B
09 December 2016
SUP-9506-28
HVDC Bypass Li ne Economic Benefit Study
Transpower NZ Li mited
HVDC Bypass Line Economic Benefit Study
RZ024300_01 i
OTB-HAY Bypass Line Economic Benefit Study
Project No: RZ024300
Document Title: HVDC Bypass Line Economic Benefit Study
Document No.: RZ024300_01
Revision: B
Date: 09 December 2016
Client Name: Transpower NZ Limited
Client No: SUP-9506-28
Project Manager: Project Manager
Author: Cameron Parker
File Name: I:\ZPINA\Projects\RZ024300 - Transpower OTB bypass\Deliverables\Final
Report\Transpower HVDC Bypass Line Economic Benefit Study (Final -
09Dec2016).docx
Jacobs New Zealand Limited
Carlaw Park
12-16 Nicholls Lane, Parnell
Auckland 1010
PO Box 9806, Newmarket
Auckland 1149
New Zealand
T +64 9 928 5500
F +64 9 928 5501
www.jacobs.com
© Copyright 2016 Jacobs New Zealand Limited. The concepts and information contained in this document are the property of Jacobs. Use or
copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This report has been prepared on behalf of, and for the exclusive use of Jacobs’ Client, and is subject to, and issued in accordance with, the
provisions of the contract between Jacobs and the Client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this report by any third party.
Document history and status
Revision Date Description By Review Approved
A 28/10/2016 Draft Final HVDC Bypass Line Economic Benefit Study C. Parker W. Gerardi R. McDougall
B 9/12/2016 Final HVDC Bypass Line Economic Benefit Study C. Parker W. Gerardi R. McDougall
HVDC Bypass Line Economic Benefit Study
RZ024300_01 ii
Contents
Executive Summary ............................................................................................................................................... 4
1. Introduction .............................................................................................................................................. 11
2. Background .............................................................................................................................................. 12
3. Modelling Approach ................................................................................................................................ 13
3.1 Model verification ....................................................................................................................................... 13
3.2 Simulations ................................................................................................................................................ 13
3.2.1 Market benefits based on generation costs............................................................................................... 13
3.3 Calculating market benefits ....................................................................................................................... 14
4. Key Modelling Assumptions .................................................................................................................. 16
4.1 Generators ................................................................................................................................................. 16
4.1.1 Thermal units ............................................................................................................................................. 17
4.1.2 Hydro ......................................................................................................................................................... 17
4.1.3 Geothermal ................................................................................................................................................ 18
4.1.4 Wind........................................................................................................................................................... 18
4.1.5 Embedded generators ............................................................................................................................... 18
4.1.6 Generation expansion plans ...................................................................................................................... 18
4.2 Fuel and carbon prices and generation costs ........................................................................................... 19
4.2.1 Transportation charges.............................................................................................................................. 19
4.2.2 Generation costs ....................................................................................................................................... 20
4.2.3 Carbon prices ............................................................................................................................................ 20
4.3 Load ........................................................................................................................................................... 21
4.4 Transmission ............................................................................................................................................. 21
4.4.1 HVDC limits and line losses ...................................................................................................................... 21
4.5 Reserve Market ......................................................................................................................................... 22
4.5.1 Reserve Requirement................................................................................................................................ 23
4.5.2 Risk subtractor formula.............................................................................................................................. 24
4.5.3 OTB-HAY outage configuration and the risk subtractor formula ............................................................... 24
4.5.4 Reserve Provision ..................................................................................................................................... 25
4.6 Hydro scenarios ......................................................................................................................................... 26
5. Modelling Results .................................................................................................................................... 28
5.1 Gross Market Benefits ............................................................................................................................... 29
5.1.1 Gross market benefits – Business as Usual (BAU) ................................................................................... 29
5.1.2 Gross market benefits – Huntly Retires ..................................................................................................... 30
5.1.3 Gross market benefits – Tiwai Closes ....................................................................................................... 31
5.1.4 Gross market benefits – BAU (U5) ............................................................................................................ 32
5.1.5 Gross market benefits – BAU (1987) ........................................................................................................ 33
5.2 HVDC Flows .............................................................................................................................................. 35
5.2.1 Daily HVDC Flows – Business as Usual (BAU) ........................................................................................ 35
5.2.2 Daily HVDC Flows – Huntly Retires .......................................................................................................... 36
5.2.3 Daily HVDC Flows – Tiwai Closes ............................................................................................................ 37
HVDC Bypass Line Economic Benefit Study
RZ024300_01 iii
5.2.4 Daily HVDC Flows – BAU (U5) ................................................................................................................. 38
5.2.5 Daily HVDC Flows – BAU (1987) .............................................................................................................. 39
5.3 Reserve Costs ........................................................................................................................................... 40
6. Conclusions ............................................................................................................................................. 43
6.1 Reserve Costs ........................................................................................................................................... 45
Appendix A. Overview of PLEXOS
A.1 SPD and Reserve Management Tool
A.2 PLEXOS Algorithms
A.3 Aggregating the model
Appendix B. Existing Power Plants
Appendix C. Maximum Generator Reserve Provision
Appendix D. Generation expansion Plans
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Executive Summary
Introduction
This report presents an evaluation of the potential market benefits arising from the installation of different
bypass options during a planned outage required in order for Transpower to re-conductor the Oteranga Bay
(OTB) to Haywards (HAY) circuits in early 2020. An evaluation of gross market generation costs when
considering the bypass options will assist Transpower to determine the optimum configuration when planning
for its OTB_HAY re-conductoring work in 2020.
This study evaluates the gross market benefits associated with a range of options presented by Transpower,
taking account of three key market scenarios.
The bypass options that Transpower has considered are:
Option 1: Installation of a 700 MW bypass line;
Option 2: Installation of a 500 MW bypass line and reconfigure the HVDC to ensure that pole 2 is
always on the bypass;
Option 3: Do not install a bypass line, balancing the required outages across each pole one outage at
a time; and
Option 4: Do not install a bypass line but reconfigure the HVDC to ensure that pole 2 is always the
pole taken out of service.
The three market scenarios initially considered are as follows:
Business as Usual (BAU): The remaining units at Huntly are not retired;
Huntly Retires: The final Huntly coal-fired units retire as initially planned, one in 2018 and the second
by 20201; and
Tiwai Closes: The NZAS aluminium smelter at Tiwai Point shuts down in combination with the
remaining Huntly units also retiring.
In addition to the above two further scenarios were developed whilst modelling was taking place and have also
been considered, these being:
BAU (U5): Business as usual, as above, however with a scheduled one week outage for Huntly Unit 5
during the OTB-HAY work; and
BAU (1987): Business as usual but with the 1987 hydrology pattern applied, representing a dry North
Island and wet South Island hydrology scenario in order to evaluate higher anticipated northward
transfers on the HVDC.
Discussion
An existing PLEXOS model of the New Zealand Electricity Market (NZEM) has been used to evaluate the
market outcomes related to each bypass scenario, taking account of the snapshot calendar year 2020.
Key assumptions agreed with Transpower prior to undertaking the final modelling include:
Three generation expansion planning scenarios provided by Transpower (committed, new entrant and
retiring generation);
Thermal unit constraints including Huntly Power Station’s likely future configuration;
1 It is noted that on 28 April 2016 Genesis Energy announced its intention to extend the life of the Huntly coal-fired units until
December 2022, however it was agreed to continue this analysis based on the 2018 date.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Generation profiling for renewable generation and projected profiles by technology, including demand
side reduction;
Generation costs, fuel costs and carbon prices;
Load forecasts, including Tiwai Point aluminium smelter;
Market reserve requirements, formula and inputs;
HVDC limits, line losses and risk subtractor option configuration; and
An agreed hydro scenario representing an average hydrological year (except in BAU (1987)).
For each market scenario the gross market costs in year 2020 and associated benefits have been calculated
drawing on the following components:
Fuel costs of electricity production;
Variable operating and maintenance costs;
Emission costs;
Costs of unserved energy (the product of unserved energy and VoLL2); and
Costs of reserve shortage (the product of reserve shortage and VoRS3).
Gross market benefits of each option have been calculated by comparing total system costs under each
scenario, where Option 1 is considered the base case. Net market benefits could be calculated by subtracting
the cost of installing the relevant bypass solution or HVDC reconfiguration cost from the gross market benefits
however Transpower has not provided these and for this reason Jacobs has focused on gross market benefits
only.
Results
At a high level the annual gross market costs appear intuitive, see Table 1 below. Option 1 presents the highest
overall capacity on the HVDC, with Option 2 marginally reducing this capacity. We note that this marginal
reduction in capacity does not differentiate gross market costs between these two bypass options. This is
consistent across all market scenarios.
Option 3 and Option 4 represent no bypass line installed and OTB-HAY outages either balanced between poles
or restricted to pole 2. This effectively reduces the transfer capacity of the HVDC resulting in an increase in
overall gross market generation costs. The increases in costs are small or insignificant when considering
Business as Usual, Huntly Retires and BAU (U5) scenarios however can be seen to increase when a higher
level of energy transfer is required under the Tiwai Closes and BAU (1987) scenarios.
Table 1 Annual gross market costs (all scenarios)
Annual Gross Market Costs ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ 540.14 $ 540.14 $ 540.49 $ 540.53
Huntly Retires $ 521.94 $ 521.94 $ 522.11 $ 522.14
Tiwai Closes $ 232.57 $ 232.57 $ 233.21 $ 238.93
Additional Scenarios
BAU (U5) $ 540.99 $ 540.99 $ 541.35 $ 541.11
BAU (1987) $ 395.03 $ 395.03 $ 439.92 $ 425.01
2 Value of Lost Load: Typically assigned a value of $20,000/MWh in New Zealand. 3 Value of Reserve Shortage: Typically assigned a value of $5,000/MWh in New Zealand.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Gross Market Benefits
Annual gross market benefits are set out in Table 2 below. This table draws comparison of annual gross market
costs, assuming Option 1 as the base case. We note there is no differentiation between Options 1 and Option
2, in terms of benefits. Benefits are read as negative i.e. Options 3 and 4 represent an increase in gross market
costs, suggesting benefits associated with Option 1, or negative benefits associated with Options 3 and 4.
Table 2 Annual gross market benefits
Annual Gross Market Benefits ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ - $ - -$ 0.35 -$ 0.39
Huntly Retires $ - $ - -$ 0.17 -$ 0.20
Tiwai Closes $ - $ - -$ 0.64 -$ 6.36
Additional Scenarios
BAU (U5) $ - $ - -$ 0.37 -$ 0.13
BAU (1987) $ - $ - -$ 44.89 -$ 29.98
Results suggest annual gross market benefits associated with Business as Usual, Huntly Retires and BAU (U5)
scenarios are particularly small, given an average hydrology year. Benefits range from between 0.02% to
0.07% of their respective annual gross market costs, are noted as statistically insignificant, and in recognition of
the potential for variability that can occur on such a system could be assumed as zero.
Tiwai Closes and BAU (1987) scenario results, representing an increased level of electricity supply for the
NZEM from the South Island, largely from hydro generation, suggest benefits between 0.02% and 10.2% of
annual gross market costs.
Given the low level of market benefits identified further analysis has been undertaken to determine where the
benefits might be occurring in relation to the OTB-HAY outages and if any potential model optimisation could be
at play. Analysis has focused on the timing of the OTB-HAY outages compared with gross market benefits
arising, HVDC flow comparisons and an assessment of market reserve costs (refer to Section 5).
Conclusions
Our analysis shows that the gross market benefits associated with installing a bypass to facilitate the required
OTB-HAY re-conductoring work are small. Noting the small level of benefits, modelling results reveal evidence
of a level of “noise” or model optimisation that is unlikely to be removed entirely. Restricting calculation of gross
market benefits to the nominated OTB-HAY outage periods is deemed a suitable approach to draw comparison
between the HVDC bypass and configuration options, and the gross market benefits that arise.
Business as Usual, Huntly Retires and the additional BAU (U5) scenarios present gross market benefits
associated with installation of a bypass in the range of $1.2m to $3m. Tiwai closes and BAU (1987), which
simulate an increased level of available hydro generation from the South Island, provide for a greater measure
of gross market benefits. Installation of a bypass relating to the Tiwai Closes scenario represents benefits of
approximately $23.2m over Option 3, and $12.5m over Option 4. Installation of a bypass relating to the BAU
(1987) scenario represents gross market benefits of approximately $17.9m over Option 3 and $11.8m over
Option 4.
Without comparing the gross market benefits against nominal bypass investment costs a measure of the net
cost or benefit cannot be drawn.
Table 3 provides the gross market benefits (read as negative) when comparing the bypass base case, Option 1,
with the total generation costs in Options 2, 3 and 4. We note there is no difference in total generation costs
between Option 1 and Option 2.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 3 Gross market benefits (restricted to OTB-HAY outage period4)
Outage Period Gross Market Benefits ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ - $ - -$ 1.50 -$ 1.55
Huntly Retires $ - $ - -$ 3.01 -$ 2.99
Tiwai Closes $ - $ - -$ 23.18 -$ 12.46
Additional Scenarios
BAU (U5) $ - $ - -$ 1.43 -$ 1.21
BAU (1987) $ - $ - -$ 17.87 -$ 11.79
For illustrative purposes the following charts show weekly total generation costs for each market scenario over
the year 2020. Benefits arise from the least cost generation solution.
Figure 1: Weekly total generation cost – Business as Usual
Figure 2: Weekly total generation cost – Huntly Retires
4 An OTB-HAY outage start date of 15 January 2020 was nominated for the first outage, lasting six weeks to 25 February
2020. A second outage is run from 4 March to 14 April 2020
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 3: Weekly total generation cost – Tiwai Closes
Figure 4: Weekly total generation cost – BAU (U5)
Figure 5: Weekly total generation cost – BAU (1987)
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
$-
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Reserve Costs
Although unlikely to be a determining factor in decision making for Transpower reserve costs provide an
indication of market tension, particularly in regards to the optimisation of energy and reserves in market
dispatch.
Table 4 Market reserve costs
Reserve Costs ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ 0.34 $ 0.34 $ 0.58 $ 0.57
Huntly Retires $ 0.29 $ 0.29 $ 0.37 $ 0.39
Tiwai Closes $ 2.28 $ 2.28 $ 42.85 $ 21.63
BAU (U5) $ 0.39 $ 0.39 $ 0.51 $ 0.41
BAU (1987) $ 5.08 $ 5.08 $ 28.33 $ 28.17
Market reserve costs for scenarios Business as Usual, Huntly Retires and BAU (U5) range from $0.3m to
$0.6m, and are noted as insignificant, refer to Table 4 above.
Annual reserve costs under the Tiwai Closes scenario equate to approximately $2.3m for Options 1 and 2,
$42.9m for Option 3 and $21.6m for Option 4. Annual reserve costs under the BAU (1987) scenario equate to
approximately $5m for Options 1 and 2, and $28m for both Options 3 and 4.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Important note about your report
The sole purpose of this report and the associated services performed by Jacobs is to assess the market
benefits associated with installing a temporary bypass line on the New Zealand transmission grid Cook Straight
link in accordance with the scope of services set out in the contract between Jacobs and Transpower (‘the
Client’). That scope of services, as described in this report, was developed with the Client.
In preparing this report, Jacobs has relied upon, and presumed accurate, any information (or confirmation of the
absence thereof) provided by the Client and/or from other sources. Except as otherwise stated in the report,
Jacobs has not attempted to verify the accuracy or completeness of any such information. If the information is
subsequently determined to be false, inaccurate or incomplete then it is possible that our observations and
conclusions as expressed in this report may change.
Jacobs derived the data in this report from information sourced from the Client (if any) and/or available in the
public domain at the time or times outlined in this report. The passage of time, manifestation of latent conditions
or impacts of future events may require further examination of the project and subsequent data analysis, and re-
evaluation of the data, findings, observations and conclusions expressed in this report. Jacobs has prepared
this report in accordance with the usual care and thoroughness of the consulting profession, for the sole
purpose described above and by reference to applicable standards, guidelines, procedures and practices at the
date of issue of this report. For the reasons outlined above, however, no other warranty or guarantee, whether
expressed or implied, is made as to the data, observations and findings expressed in this report, to the extent
permitted by law.
This report should be read in full and no excerpts are to be taken as representative of the findings. No
responsibility is accepted by Jacobs for use of any part of this report in any other context.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
1. Introduction
Transpower New Zealand Limited (Transpower) is considering the market benefits associated with installing a
temporary bypass line during an outage required in order to re-conductor the Oteranga Bay (OTB) to Haywards
(HAY) circuits in early 2020.
The OTB-HAY transmission lines connect the Haywards Substation to the northern end of the High Voltage
Direct Current (HVDC) link, in Oteranga Bay, southeast of Karori in Wellington (Figure 1-1 below). When one of
the OTB-HAY circuits is out of service, transfer between the North and South Island is limited to one HVDC pole
only. Furthermore, a pole outage on the HVDC would result in zero transfer capacity resulting in an increase in
reserve risk to the market.
Figure 1-1: Transmission Map (source Transpower, Transmission Map: North Island)
This report provides the background, approach and methodology, key assumptions and findings from our
evaluation.
The remainder of this report has the following structure:
Chapter two provides high level background to Transpower’s study requirements;
Chapter three presents our approach to modelling market benefits;
Chapter four outlines the key assumptions incorporated in the PLEXOS database;
Modelling results are captured in Chapter five; and
Chapter six provides the study’s conclusions drawn from our analysis of results.
Also included, in Appendix A, is an overview of PLEXOS and how it has been applied to the New Zealand
Electricity Market (NZEM) and reserve function of the System Operator when undertaking this study.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
2. Background
Transpower is proposing work to re-conductor its OTB-HAY transmission lines, part of the HVDC that links New
Zealand’s North and South Island high voltage electricity systems. Transpower is seeking to identify the market
benefits associated with installing various bypass options during the planned outage and reconfiguring the
HVDC in a manner that enables the necessary work to be completed.
Jacobs has evaluated the gross market benefits associated with a range of options presented by Transpower,
taking account of three key market scenarios.
The bypass options that Transpower has considered are identified below:
Option 1: Installation of a 700 MW bypass line;
Option 2: Installation of a 500 MW bypass line and reconfigure the HVDC to ensure that pole 2 is
always on the bypass;
Option 3: Do not install a bypass line, balancing the required outages across each pole one outage at
a time; and
Option 4: Do not install a bypass line but reconfigure the HVDC to ensure that pole 2 is always the
pole taken out of service.
The options presented by Transpower ultimately represent a change in HVDC capacity and therefore the
available transfer of energy and reserves between the North and South Islands.
The five market scenarios considered are as follows:
Business as Usual (BAU): The remaining units at Huntly are not retired;
Huntly Retires: The final Huntly coal-fired units retire as initially planned, one in 2018 and the second
by 20205; and
Tiwai Closes: The NZAS aluminium smelter at Tiwai Point shuts down in combination with the
remaining Huntly units also retiring.
BAU (U5): Business as usual, as above, however with a scheduled one week outage for Huntly Unit 5
during the OTB-HAY work; and
BAU (1987): Business as usual but with the 1987 hydrology pattern applied, representing a dry North
Island and wet South Island hydrology scenario in order to evaluate higher anticipated northward
transfers on the HVDC.
The re-conductoring of OTB-HAY is expected to be managed over two specific periods for duration of
approximately six weeks each, and is likely to be carried out during the summer period in 2020 thus avoiding
higher winter period electricity demand. An outage start date of 15 January 2020 was nominated for the first
outage, lasting six weeks to 25 February 2020. A second outage is run from 4 March to 14 April 2020.
The resolution of PLEXOS modelling is 30 minute periods, reflecting real-time market intervals.
An evaluation of gross market generation costs when considering the bypass options will assist Transpower in
determining the optimum configuration when planning for its OTB_HAY re-conductoring work in 2020.
5 It is noted that on 28 April 2016 Genesis Energy announced its intention to extend the life of the Huntly coal-fired units until
December 2022, however it was agreed to continue this analysis based on the 2018 date.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
3. Modelling Approach
An existing PLEXOS model of the New Zealand Electricity Market (NZEM) has been used to evaluate the
market outcomes related to each bypass scenario, taking account of the snapshot calendar year 2020.
3.1 Model verification
Prior to undertaking the final market simulations, testing and review was undertaken so that the System
Operator could verify whether results and outcomes from the modelling emulated actual market outcomes. In
order to verify the modelling, the following summary data was provided to Transpower:
Generator dispatch and capacity factors;
HVDC Pole 2 & 3 flow;
Market energy price in both islands;
Market reserve cost; and
Reserve sharing quantities across the HVDC.
During this verification phase, simulations were undertaken for all options and scenarios. Additional checks
undertaken through discussion with Transpower included: spill; generator outages; Fast and Sustained
Instantaneous Reserve provision; and NFR and risk subtractor assumptions.
3.2 Simulations
The purpose of the analysis was to determine the market benefits associated with installing a temporary bypass
line during an outage of the OTB-HAY circuits during 2020.
3.2.1 Market benefits based on generation costs
Table 3-1 provides a description of the bypass options modelled, and both the HVDC configuration and potential
bypass capacity. A total of 12 simulations were initially required, each in the year 2020, with a further 8
simulations considering Huntly U5 and the 1987 hydrology scenario added for inclusion in the analysis.
Table 3-1 The OTB-HAY outage bypass options
Options Outage 1 (6 weeks) Outage 2 (6 weeks)
Option 1: 700 MW
bypass
Both poles in service.
Pre-contingent limit: 1200 MW
Post-contingent limits:
4 weeks at BAU
2 weeks with post-contingent flow limited to 350 MW by single earthwire
Both poles in service.
Pre-contingent limit: 1200 MW
Post-contingent limits:
4 weeks at BAU
2 weeks with post-contingent flow limited to 350 MW by single earthwire
Option 2: 500 MW
bypass with HVDC
reconfiguration always
connected to pole 2.
Both poles in service.
Pre-contingent limit: 1200 MW
Post-contingent limits:
4 weeks with post-contingent flows limited to 500 MW due to bypass capacity.
2 weeks with post-contingent
Both poles in service.
Pre-contingent limit: 1200 MW
Post-contingent limits:
4 weeks with post-contingent flows limited to 500 MW due to bypass capacity.
2 weeks with post-contingent
HVDC Bypass Line Economic Benefit Study
RZ024300_01
flow limited to 350 MW by single earthwire
flow limited to 350 MW by single earthwire
Option 3: No bypass
with alternate Pole
outages
Pole 3 out of service.
Pre-contingent limits:
4 weeks with pre-contingent flows limited to 700 MW by pole 3
2 weeks with pre-contingent flow limited to 350 MW by single earthwire
Post-contingent limit: 0 MW
Pole 2 out of service.
Pre-contingent limits:
4 weeks with pre-contingent flows limited to 500 MW by pole 2
2 weeks with pre-contingent flow limited to 350 MW by single earthwire
Post-contingent limit: 0 MW
Option 4: No bypass
and reconfigure HVDC
so outage is always on
pole 2
Pole 2 out of service.
Pre-contingent limits:
4 weeks with pre-contingent flows limited to 700 MW by pole 3
2 weeks with pre-contingent flow limited to 350 MW by single earthwire
Post-contingent limit: 0 MW
Pole 2 out of service.
Pre-contingent limits:
4 weeks with pre-contingent flows limited to 700 MW by pole 3
2 weeks with pre-contingent flow limited to 350 MW by single earthwire
Post-contingent limit: 0 MW
Previous risk subtractor modelling results suggested some variation in translation of hydro volumes from the
PLEXOS MT to ST models making it difficult to determine which costs are attributable to constraints we were
evaluating and which costs are attributable to modelling artefacts, particularly when cost differences between
the risk subtractor options were small. To minimise this variation, in the modelling reported in this study
includes a single, average year, hydro volume scenario thus attempting to eliminate this potential noise in
modelling outcomes.
“Unit commitment” refers to a sequence of generating unit on and off decisions made across time. The unit
commitment problem is to find the optimal (least cost) combination of these on/off decisions for all generating
units across a given time horizon, taking start costs into account. Constraints such as a generating unit’s
minimum stable level and ramp up and down rates apply to the unit commitment problem.
The difficulty with optimising generator unit commitment in power systems modelling is that it requires Mixed
Integer Programming (MIP). The decision to commit a unit, or not, is represented by a binary variable.
Introducing MIP brings another layer of complexity and can have a significant impact on model run times,
however following discussions with Transpower, in our previous studies, it was agreed unit commitment
constraints would be enforced, therefore avoiding unrealistic dispatch of thermal units and any partial
commitment from Huntly Power Station.
3.3 Calculating market benefits
For each generation and demand scenario the total costs have been calculated incorporating the following
components:
Fuel costs from production;
Variable operating and maintenance costs;
Emission costs;
Costs of unserved energy (the product of unserved energy and VoLL); and
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Costs of reserve shortage (the product of reserve shortage and VORS).
Costs, if any, of unserved energy have been checked to ensure that the capacity expansion plans are
consistent with market outcomes. If the costs of unserved energy were greater than the cost of building an
additional OCGT, then additional OCGTs would need to be added. No additional OCGTs were needed.
Gross market benefits of each option have been calculated by comparing total system costs under each
scenario, where Option 1 is considered the base case. Net market benefits could be calculated by subtracting
the cost of installing the relevant bypass solution or HVDC reconfiguration cost from the gross market benefits.
The cost of the options would need to be provided by Transpower but have not and for this reason Jacobs has
focused on gross market benefits only.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
4. Key Modelling Assumptions
This section outlines the key generation, transmission, fuel, load and reserve assumptions that have been used
in the analysis.
4.1 Generators
The NZEM currently consists of a mix of thermal, hydro, geothermal and wind power plants. In 2014, hydro
power stations represented 54% of total installed capacity, thermal generation made up 29% of total installed
capacity, and 17% of installed capacity came from power plant using wind or geothermal resources, as shown
in Figure 4-16.
Figure 4-1 Estimated generating capacity by fuel type, 2014
As at the end of 2014 there was approximately 9,700 MW of installed capacity in the NZEM. Since then
Contact Energy and Mighty River Power both decommissioned combined cycle gas fired plant. This reduces
the total by 380 MW (Otahuhu B) plus 170 MW (Southdown). In addition the second of Genesis Energy’s coal-
fired units at Huntly was put into storage, leaving only the two remaining 250 MW units available.
Appendix B provides a summary of existing generators in the NZEM that are included in the PLEXOS database
for this study.
In PLEXOS, the method for determining generation dispatch is dependent on the technology. Though subject
to constraints, this is generally as follows:
Steam, open cycle gas turbines (OCGTs) and combined cycle gas turbines (CCGTs) are dispatched in
merit order, with lowest cost resources being dispatched first;
Host load profiles are assumed for cogeneration units and, if available, these generators must
generate to meet this host load (or to meet take-or-pay contract obligations);
Hydro units are treated as energy-constrained units or managed within storage limits, and the use of
water is optimised over the year such that the resource is available when it is most needed;
Wind is modelled using an expected hourly power profile, providing for stochastic variation – unless a
deterministic profile is preferred; and
Geothermal is modelled using expected hourly generation profiles.
6 Ministry of Business, Innovation and Employment, Energy Statistics, Electricity data tables: http://www.mbie.govt.nz/info-
services/sectors-industries/energy/energy-data-modelling/statistics/electricity.
Hydro 54%
Geothermal 10%
Oil 2%
Coal 6%
Gas 20%
Other (Biogas, Waste Heat,
Wood) 1%
Wind 7%
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Assumptions, including operating constraints relating to each technology, are discussed in more detail in the
next sections.
4.1.1 Thermal units
To reflect the market operation, there are a number of constraints imposed on thermal units in the system, as
discussed below.
The two “available” Huntly coal units have maximum generation constraints applied during the summer months
to reflect river heating consent obligations. Table 4-1 provides assumed capacity limit to avoid river heating
over the summer months7.
Table 4-1 Huntly Units 1 to 4 cooling constraints
Month Day (08:00 - 24:00) Night (00:00 – 07:59)
January 440 MW 470 MW
February 440 MW 470 MW
March 440 MW 470 MW
The Huntly units are not treated as must-run and do not have a start-up cost imposed. The only limit on
flexibility is the minimum stable level at around 50MW (depending on the unit, and gas firing). These units are
assumed to be running on gas only by 2020 (i.e. Huntly’s coal stockpile has been exhausted).
CCGTs are modelled with minimum stable levels set at a portion of the installed capacity of plant, approximately
50 percent of capacity. These are dispatched by the model when price is greater than the plants short run
marginal cost (SRMC). Transpower has supplied additional plant rules where they may be material to the
outcomes of this study (e.g. heat rates).
We assume that the electricity output of cogeneration plants is driven by the host load, rather than price signals.
Therefore, historical generation profiles are used to predict future hourly generation profiles. New cogeneration
plant are assumed to be available approximately 85% of the time.
Gas and diesel peakers are also assumed to be capable of providing FIR and SIR when operating. Small
minimum stable levels (estimated to be approximately 10% of maximum capacity) have therefore been specified
for these units to ensure that the model does not allow reserve provision without generation.
4.1.2 Hydro
The hydro river chains are modelled as storages and inter-connecting waterways. Several of the river sections
have minimum or maximum flow limits applied to match the physical reality. This setup is the same as previous
work carried out for Transpower such as the LSI Wind impact study, T2040 work and risk-subtractor
assessments.
The smaller existing plants and some new hydro units have annual energy limits or maximum capacity factors
applied.
For new run-of-river hydro generators, we assume a constant 50% rating based on advice previously received
from Transpower, and often more broadly accepted. These units are a relatively small component of the total
hydro system which uses the large storages to reflect the flexibility in dispatch.
New storage-based hydro plants are connected to storages as appropriate.
7 Summer months are represented by January, February and March.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Hydro inflows are discussed further in Section 4.6.
4.1.3 Geothermal
The projected geothermal profiles have been derived by averaging three years of historic hourly generation
profiles, preserving any weekday/weekend or diurnal pattern, but interpolating over periods of obvious plant
outages. The geothermal profiles have been reviewed by Transpower previously and where applicable these
have been updated to reflect more recent data, provided by Transpower.
4.1.4 Wind
The rating profiles for wind generators were previously provided by Transpower and are generated from
synthetic wind speed time-series data that the Electricity Commission had developed in 2009. The
transformation from wind speed to turbine capacity factor was completed by Transpower based on the
assumption that wind farm output grows quadratically for wind speeds up to 14.5 m/s, is flat from 14.5 to 20 m/s,
and falls quadratically between 20 and 25 m/s. The ratings profiles were also scaled by Transpower to achieve
the expected generation capacity factor for each site.
Each wind generator is matched to one of the profiles from a nearby location. Locations with several current or
proposed wind farms have up to three profiles defined for them. This provides both a degree of diversity and
correlation between the wind generation sites.
A deterministic wind profile is used in the modelling to reduce noise in modelling outcomes.
4.1.5 Embedded generators
The following embedded generators are modelled explicitly, and included in the load:
Aniwhenua (25 MW hydro)
Highbank (35 MW hydro)
Kaimai (42 MW hydro)
Rotokawa (40 MW geothermal)
Tararua_Bunnythorpe (34 MW wind)
Tararua_Linton (34 MW wind)
Ngawha (27 MW geothermal)
Tauha1 (25 MW geothermal)
White Hill (70 MW wind)
Glenbrook (74 MW cogen)
In addition Waipori is partially embedded (34 MW of 84 MW), with embedded load included in the demand
assumptions and full output modelled explicitly.
4.1.6 Generation expansion plans
Transpower has supplied generation expansion8 plans for each of the three market scenarios to be considered,
these being:
The remaining units at Huntly are not retired;
The final Huntly coal-fired units retire as planned, one in 2018 and the second by 20209; and
8 Expansions plans may include new generation, plant upgrades, decommissioned generation plant and demand side
response or any combination of. 9 On 28 April 2016 Genesis Energy announced its intention to extend the life of the Huntly coal-fired units until December
2022, however it was agreed to continue this analysis based on the 2018 date.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
The NZAS aluminium smelter at Tiwai Point shuts down in combination with the remaining Huntly unit
retiring.
The generation expansion plans provided have been transferred into the PLEXOS database and generation
profiles constructed where necessary for new geothermal, wind and hydro generation. Any new profiles created
are based on existing data, such as typical geothermal or wind generation profiles and existing run of river
inflow profiles, and scaled to fit each generators installed capacity.
The three generation expansion plans provided by Transpower are included in Appendix D.
4.2 Fuel and carbon prices and generation costs
The fuel prices, shown in Figure 4-2, have been provided by Transpower for the purposes of this study, and are
aligned with the draft Electricity Demand and Generation scenarios (Draft EDGS 2015) developed by the
Ministry of Business, Innovation & Employment10.
Figure 4-2 Fuel price assumptions
4.2.1 Transportation charges
In addition to the fuel prices discussed above, some thermal units also incur a transportation charge to get the
fuel delivered to the gate. The transportation charges assumed in the database are summarised in Table 4-2
and are consistent with previously provided modelling assumptions. New build transportation charges provided
by Transpower have been updated in the table.
10 http://www.mbie.govt.nz/info-services/sectors-industries/energy/energy-data-modelling/modelling/electricity-demand-and-
generation-scenarios/draft-edgs-2015
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 4-2 Transportation charges for thermal units
Fuel Region Generator Fuel delivery cost
Natural gas
Waikato
HlyUnit6
HuntlyG1-4
Te Rapa Cogen
$0.50/GJ
HlyUnit5 $1.00/GJ
Generic OCGT Peaker
(Huntly or Otorohanga)
$2.60/GJ
Hamilton Proposed Cogen $0.50/GJ
Taranaki Stratford peaker
ToddPeaker_McKee
ToddPeaker_npl
Generic OCGT peaker
(Junction Rd)
$2.00/GJ
Woodwaste Kinleith Cogen (Waikato) $1.00/GJ
4.2.2 Generation costs
Variable and fixed operating and maintenance costs and heat rate assumptions are consistent with the
modelling assumptions provided by Transpower.
The Electricity Authority’s recently proposed Transmission Pricing Methodology (TPM)11 represents a change in
market cost structure which will affect participants to varying degrees, including generators. Specific TPM
changes are not accounted for in this study. It is assumed that the final TPM results in no penalty on South
Island generation.
4.2.3 Carbon prices
The New Zealand Emissions Trading Scheme (ETS) places an obligation on CO2-emitters to surrender units
each year, according to the level of emission production. The scheme is no longer internationally linked, as of
June 2015, now a domestic-only scheme where NZ units (NZUs) can be surrender.
Transpower has provided the price assumptions as shown in Figure 4-3, based on EDGS 2015, IEA Current
Policies Scenario.
11 http://www.ea.govt.nz/industry/transmission/transmission-pricing/
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 4-3 NZU Carbon Price assumptions
4.3 Load
Transpower has supplied load forecasts based on the Base Case (Mixed Renewables) scenario from the draft
EDGS 2015 for use in this study, allocated by node (including TWI which reflects demand from New Zealand
Aluminium Smelter). Load growth modelling within PLEXOS has not been included as part of this study.
4.4 Transmission
Three levels of transmission detail can be modelled in PLEXOS: regional, zonal and nodal.
At the nodal level, the transmission network can be formulated using a linearised DC approximation of OPF
equations, with or without losses.
At the regional and zonal level, a transportation model is used to represent the network, with transmission limits
being applied to flow between regions/zones, but not within regions/zones.
For the purposes of this study we have modelled the NZEM system as two regions: North and South Island.
The DC losses on the HVDC link are modelled explicitly, and AC losses approximated using generator loss
factors and including an estimate of losses in the load forecasts.
It is assumed that when modelling the NZAS closure any inter-regional constraints would be alleviated without
delay through Transpower’s existing and approved grid investment authorisation. The focus of this study is
solely on market benefits brought about by change to the HVDC cable transfer limits as a result of the proposed
bypass line options and outage requirements.
4.4.1 HVDC limits and line losses
The capacity of the HVDC transfer prior to any potential outages in year 2020 is assumed to be 1,200 MW.
Losses represented when modelling HVDC transfers are the same as those line losses implemented in
Transpower’s SPD model, as previously supplied by Transpower:
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 4-3 HVDC line losses
DC transfer (MW) Line losses (MW)
50 0.228735
100 0.914939
200 3.659755
300 8.234449
400 14.63902
500 22.87347
600 32.93780
700 44.83200
The HVDC line losses applied in PLEXOS are expressed as the quadratic function of flow on the line, derived
by fitting a polynomial (Figure 4-4) to the data provided in Table 4-3:
f(x) = 0.000915x2 + 0.000x
The HVDC is modelled as two cables with respective capabilities of 500 MW and 700 MW sent. Internally,
PLEXOS represents this quadratic function as a number of piece-wise linear segments.
Figure 4-4 HVDC transfer losses
This loss function is applied to all configurations of the HVDC and is deemed to be a reasonable representation
of HVDC transfer losses in the context of this study.
4.5 Reserve Market
Historically each of the North and South Island has had its own reserve market; however since 2014
Transpower has begun implementation of its Reserve and Frequency Management Programme (RFM). The
y = 0.0000915x2 + 0.0000000x
0
5
10
15
20
25
30
35
40
45
50
0 100 200 300 400 500 600 700 800
Lin
e L
oss
es
(MW
)
DC Transfer (MW)
HVDC Bypass Line Economic Benefit Study
RZ024300_01
goal of this programme is to achieve a fully co-optimised national market for reserves and frequency
management, using the HVDC capability to facilitate the sharing of reserves between islands.
This study has assumed a national market for Fast and Sustained Instantaneous Reserve in 2020, of up to approximately 200MW able to be shared across the HVDC. Further, with respect to frequency keeping, modelling assumptions are that no national market exists and therefore same-island frequency keeping provision only exists. However it is assumed that the frequency-keeping controller has a reduced requirement of 15 MW per island (reduced from 50MW per island), and that when using the frequency-keeper controller, a modulation risk of 30 MW applied to the HVDC, and is added to the DC CE risk calculation, as included the following section.
4.5.1 Reserve Requirement
There are three types of reserve requirements in the NZEM: Fast Instantaneous Reserve (FIR), Sustained
Instantaneous Reserve (SIR) and Frequency. The same capacity can be offered for the FIR and SIR markets,
but not for frequency control. FIR capacity must be online within 6 seconds and maintained for 60 seconds, SIR
capacity must be on within 60 seconds and maintained for 15 minutes.
In any half-hour period the amount of FIR and SIR reserve on the system must be sufficient to cover three
identified risks: AC CE risk, DC CE risk, and DC extended contingent event (ECE) risk, taking into consideration
net free reserve (NFR) which, for ECE, includes Automatic Under-Frequency Load Shedding (AUFLS).
Accordingly, in the PLEXOS formulation, the FIR and SIR requirements is the greater of:
FIR/SIR ≥ largest generator - NFR
FIR/SIR ≥ ∑HVDC(received) + Modulation Risk (30 MW) – risk subtractor(received) – NFR
FIR/SIR ≥ ∑HVDC(received) – AUFLS – NFR
For each of the reserve types and risks, typical values for NFR (including AUFLS) have previously been
provided by Transpower and these formulae are used in this study.
The FIR NFR applicable to the three risks identified above is set out in the following tables. NFR applicable to
AC and DC CE risk is split into two distinct time periods, day (06:00 to 21:30) and night (22:00 to 05:30), stated
as a constant in PLEXOS formulation.
NFR applicable to ECE CE risk takes into account AUFLS and is stated as a function of either North or South
Island load (NIPS or SIPS), less non-compliant generation. That is, generation that trips before minimum
frequency is reached. Once AUFLS are calculated each island’s total NFR can be determined.
All SIR NFR values for CE risk are set to zero. SIR NFR relating to DC ECE risk is equal to the AUFLS
formulation included in Table 4-6, dependant on island.
Table 4-4 AC CE risk NFR
Time (period starting) North Island South Island
06:00 to 21:30 150 60
22:00 to 05:30 120 25
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 4-5 DC CE risk NFR
Time (period starting) North Island South Island
06:00 to 21:30 125 35
22:00 to 05:30 95 0
Table 4-6 AUFLS as a function of load
Island Formula
North Island AUFLS 0.2976 * (NIPS) - 65
South Island AUFLS 0.288 * (SIPS) - 106
South Island AUFLS (NZAS exit)12 0.288 * (SIPS) - 106
The Tiwai Point load has been included in the South Island AUFLS formula and all current North Island
exemptions from AUFLs have been removed from the North Island formula. Should the NZAS exit the market a
secondary South Island AUFLS function is used in PLEXOS, as stated in Table 4-6.
Table 4-7 DC ECE risk NFR (including AUFLS)
Time (period starting) North Island South Island
06:00 to 21:30 NI AUFLS + 125 SI AUFLS + 35
22:00 to 05:30 NI AUFLS + 95 SI AUFLS + 0
4.5.2 Risk subtractor formula
In both the North and South Island, the amount of FIR and SIR provided must be greater than the combined
flow on the HVDC plus modulation risk for frequency keeping, less the risk subtractor and the net free reserve
(NFR) – assuming the HVDC is setting the reserve risk. That is:
FIR >= HVDC flow + Modulation Risk – FIR risk subtractor – DC CE NFR
SIR >= HVDC flow + Modulation Risk – SIR risk subtractor
The risk subtractor varies depending on the amount of overload capacity assumed on the HVDC pole 2, and
whether unbalanced pole operation is allowed. The risk subtractor to be included in this study is stated on a
MW received basis as indicated in Table 4-8, and assumes balanced pole operation.
Table 4-8 The assumed risk subtractor input
Risk subtractor for FIR (MW sent) Risk subtractor for SIR (MW sent)
560 (528 received) 560 (528 received)
4.5.3 OTB-HAY outage configuration and the risk subtractor formula
The OTB-HAY transmission outage options are to be modelled as two separate six week outages, and are likely
to be carried out during the summer period in 2020, thus avoiding higher winter period electricity demand. Each
12 If the exit of NZAS from the market is staggered its calculated AUFLS, as a function of load, may not be correct, although it
is unlikely to be materially different.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
six-week outage accounts for a four week period where the pole conductor is out and two weeks where the pole
conductor and the earthwire are isolated.
The pole conductor is required to be isolated whilst the earthwire is safely replaced and a single earthwire
further reduces capacity. It only reduces the post-contingent limits in bipole configuration but will reduce the
pre-contingent limits in the monopole cases.
The impact of the described approach on pre-contingent and post-contingent flows is summarised in the Table
3-1. Translation of these options into the risk subtractor formula is stated below.
Table 4-9 The assumed risk subtractor formula for OTB-HAY outage bypass options
Option Definition Outage 1 Outage 2
Option 1: 700
MW bypass
Configuration
Pre-contingent limit
Risk-subtractors (received)
Both poles in service
1,200 MW
4 weeks: 528MW
2 weeks: 350MW
Both poles in service
1,200 MW
4 weeks: 528 MW
2 weeks: 350 MW
Option 2: 500
MW bypass
(Pole 2
connected)
Configuration
Pre-contingent limit
Risk-subtractors (received)
Both poles in service
1,200 MW
4 weeks: 500 MW
2 weeks: 350 MW
Both poles in service
1,200 MW
4 weeks: 500 MW
2 weeks: 350 MW
Option 3: No
bypass
Configuration
Pre-contingent limits
Risk-subtractors (received)
Pole 3 outage
4 weeks: 500 MW
2 weeks: 350 MW
0 MW
Pole 2 outage
4 weeks: 700 MW
2 weeks: 350 MW
0 MW
Option 4: No
bypass (Pole
2 outage)
Configuration
Pre-contingent limits
Risk-subtractors (received)
Pole 2 outage
4 weeks: 700 MW
2 weeks: 350 MW
0 MW
Pole 2 outage
4 weeks: 700 MW
2 weeks: 350 MW
0 MW
4.5.4 Reserve Provision
For the purpose of this study, it is assumed that a national reserve market will be fully implemented by the year
2020, enveloping both the North and South Island markets, but excluding frequency. This enables generators
from one island to provide FIR or SIR to meet a CE risk in the other island, subject to availability of spare
capacity across the HVDC. ECE risk is still required to be met from generation in the island importing power.
In order to account for the provision of reserve between the two islands taking into consideration potential time
delay differences between different generators, reserve provided by South Island generators to meet a North
Island AC CE risk is discounted13
. For example, for each MW of reserve provided by a North Island generator,
approximately 1.2 MW of reserve would need to be provided by a South Island generator.
The appropriate ratio to apply has been provided by Transpower previously (see Table 4-10) and has been
reapplied in this study.
13 Discounting of generator reserve provision is limited to South Island generators for two reasons; (1) flow on the HVDC is
predominantly northward flowing, and (2) North Island generators represent a higher level of risk to the market where additional reserves may be of benefit.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 4-10 CE risk reserve provision ratios
Reserve Provision Reserve Sent Reserve Received
North Island FIR 1 1 (SI)
North Island SIR 1 1 (SI)
South Island FIR 1 0.81 (NI)
South Island SIR 1 1 (NI)
Transpower has provided a basis for determining the maximum reserve provision for both FIR and SIR.
Thermal generators provide FIR based on 5% of capacity and SIR based on 10% of capacity. Hydro plant
reserve provision is based on 10% of capacity, relating to a single turbine/unit, for both FIR and SIR reserve
types. Frequency keeping is provided from existing plant, without change, throughout the planning horizon.
The maximum reserve provision stated in MWs by generator and reserve type is provided in Appendix C and
includes new entrant generation.
In addition to generator reserve provisions, purchasers of electricity can offer quantities of consumption to be
disrupted for a given price per MW, thus providing Interruptible Load (IL).
Transpower has also previously provided typical quantities and taken account of the expected position of the IL
reserve in the FIR and SIR offer stacks. North Island IL is typically a price taker in the market however South
Island IL, largely provided by the NZAS, provides IL based on price signal, at approximately $10/MW. Provision
of IL included in the model is presented below in Table 4-11 including the adjusted scenario accounting for
NZAS exiting the market.
Table 4-11 Interruptible Load (IL)
Reserve Provision Offer Quantity Offer Price
North Island FIR IL 150 $0.02/MW
North Island SIR IL 210 $0.02/MW
South Island FIR IL 170 $10.00/MW
South Island SIR IL 170 $10.00/MW
South Island FIR IL (NZAS Exit) 20 $10.00/MW
South Island SIR IL (NZAS Exit) 20 $10.00/MW
For the avoidance of doubt, Interruptible Load does not contribute to reserve sharing across the HVDC.
In the NZEM, where there can be insufficient capacity to meet both energy and reserve requirements, FIR and
SIR reserves are shed first to maintain energy and frequency. Beyond that, load is shed before frequency
keeping constraints are violated.
4.6 Hydro scenarios
Hydrology has a significant impact on the utilisation of the HVDC, therefore impacting on potential market
benefits. For the purposes of this study each generation scenario is accompanied by a fixed hydro scenario,
representing an average year before and during outages to be modelled.
For the purposes of this study we have used the year 1956 to represent average inflows. Figure 4-5 shows
inflows for the major storage lakes for this average hydrological year.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 4-5: Mean inflows for major storage lakes
To better understand the magnitude of change in benefits associated with hydrology an additional scenario has
been considered. The 1987 hydrology pattern has also been applied, against the Business as Usual Option,
representing a dry North Island and wet South Island hydrology scenario in order to assess the effect of higher
anticipated northward transfers on the HVDC.
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Manapouri Taupo Tekapo Pukaki Hawea
HVDC Bypass Line Economic Benefit Study
RZ024300_01
5. Modelling Results
For each market scenario the gross market costs in year 2020 and associated benefits have been calculated
drawing on the following components:
Fuel costs of electricity production;
Variable operating and maintenance costs;
Emission costs;
Costs of unserved energy (the product of unserved energy and VoLL ($20,000/MWh)); and
Costs of reserve shortage (the product of reserve shortage and VoRS ($5,000/MWh)).
A comparison of gross market costs associated with each bypass option and based on each of the identified
market scenarios is shown below (Table 5-1).
For ease of reference the bypass options considered are:
Option 1: Installation of a 700 MW bypass line;
Option 2: Installation of a 500 MW bypass line and reconfigure the HVDC to ensure that pole 2 is
always on the bypass;
Option 3: Do not install a bypass line, balancing the required outages across each pole one outage at
a time; and
Option 4: Do not install a bypass line but reconfigure the HVDC to ensure that pole 2 is always the
pole taken out of service.
Table 5-1 Annual gross market costs (all scenarios)
Annual Gross Market Costs ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ 540.14 $ 540.14 $ 540.49 $ 540.53
Huntly Retires $ 521.94 $ 521.94 $ 522.11 $ 522.14
Tiwai Closes $ 232.57 $ 232.57 $ 233.21 $ 238.93
Additional Scenarios
BAU (U5) $ 540.99 $ 540.99 $ 541.35 $ 541.11
BAU (1987) $ 395.03 $ 395.03 $ 439.92 $ 425.01
At a high level the annual gross market costs shown in Table 5-1 appear intuitive. Option 1 presents the
highest overall capacity on the HVDC, with Option 2 marginally reducing this capacity. We note that this
marginal reduction in capacity does not differentiate gross market costs between these two bypass options. This
is consistent across all market scenarios.
Option 3 and Option 4, represent no bypass line installed and OTB-HAY outages either balanced between poles
or restricted to pole 2. This effectively reduces the transfer capacity of the HVDC resulting in an increase in
overall gross market generation costs. The increases in costs are small when considering Business as Usual,
Huntly Retires and BAU (U5) scenarios however can be seen to increase when a higher level of energy transfer
is required under the Tiwai Closes and BAU (1987) scenarios
The magnitude of these result are discussed in the following sections.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
5.1 Gross Market Benefits
Annual gross market benefits are set out in Table 5-2 below. This table draws comparison of annual gross
market costs, assuming Option 1 as the base case. We note there is no differentiation between Options 1 and
Option 2, in terms of benefits. Benefits are read as negative i.e. Options 3 and 4 represent an increase in gross
market costs, suggesting benefits associated with Option 1, or negative benefits associated with Options 3 and
4.
Table 5-2 Annual gross market benefits
Annual Gross Market Benefits ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ - $ - -$ 0.35 -$ 0.39
Huntly Retires $ - $ - -$ 0.17 -$ 0.20
Tiwai Closes $ - $ - -$ 0.64 -$ 6.36
Additional Scenarios
BAU (U5) $ - $ - -$ 0.37 -$ 0.13
BAU (1987) $ - $ - -$ 44.89 -$ 29.98
Results suggest annual gross market benefits associated with Business as Usual, Huntly Retires and BAU (U5)
scenarios are particularly small, given an average hydrology year. Benefits range from between 0.02% to
0.07% of their respective annual gross market costs.
Tiwai Closes and BAU (1987) scenario results, representing an increased level of electricity supply for the
NZEM from the South Island largely from hydro generation, suggest benefits between 0.02% and 10.2% of
annual gross market costs.
Given the low level of market benefits identified further analysis has been undertaken to determine where the
benefits might be occurring in relation to the OTB-HAY outages and if any potential model optimisation could be
at play.
The following sections explore each market scenario in more detail.
5.1.1 Gross market benefits – Business as Usual (BAU)
The Business as Usual scenario reflects the current NZEM generation fleet with the addition of 200 MW of gas
fired plant and approximately 160 MW of renewable plant prior to year 2020. Approximately 100 MW of
demand side response is also added prior to 2020.
Trading interval gross market benefits associated with the Business As Usual scenario have been aggregated
to the daily level in order to make the data more manageable and assist with analysis. Figure 5-1 provides an
indication of when the daily benefits occur for each scenario throughout the year, when compared to Option 1.
Transpower’s nominated OTB-HAY outage period is identified by the red circle on the chart.
Differences in benefits identified across the various HVDC configurations are particularly small and the anomaly
at the tail end of the year is noted. This is understood to be linked with hydrological patterns at this time of year
and model optimisation of water storage targets.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-1: Daily gross market benefits – Business as Usual14
Average daily generation costs for the BAU scenario are estimated at approximately $1.5m per day. Figure 5-2
provides a closer look at the benefits restricted to the OTB-HAY outage periods, so excluding days external to
the planned outages and their associated benefits.
Figure 5-2: Restricted gross market benefits – Business as Usual
Options 3 and 4 present reasonably consistent negative benefits over both six week OTB-HAY outage periods.
Based on this restricted view, gross market benefits attributed to Option 1 and 2 when compared to Option 3 are
estimated at $1.5m, and Options 4 $1.55m – noting there is no difference between Options 1 and 2.
5.1.2 Gross market benefits – Huntly Retires
The Huntly Retires scenario sees the last of Huntly’s coal-fired units retire before 2020, 400MW of North Island
gas fired plant enter the market between 2017 and 2019, and a further approximately 400MW of renewable
generation come on line. Demand side response of approximately 100MW is also available prior to 2020.
Daily gross market benefits identified under the Huntly Retires scenario for the year 2020 are identified in Figure
5-3 below. As in Figure 5-1, Transpower’s OTB-HAY outage periods are circled in red (see Figure 5-3).
14 Benefits are read as negative numbers i.e. a negative number represents a higher generation cost.
-$150
-$100
-$50
$0
$50
$100
$150
$200
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-$140
-$120
-$100
-$80
-$60
-$40
-$20
$0
$20
$40
$60
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Negative benefits are apparent over the outage periods, as a result of the HVDC capacity reduction under
Options 3 and 4 and the requirement for North Island thermal generation to respond to demand.
Figure 5-3: Daily gross market benefits – Huntly Retires
Considerable “noise”, at a low level, due to model optimisation remains present. Figure 5-4 provides a
restricted view on gross market benefits for each scenario. Options 3 and 4 shows negative gross market
benefits of approximately $3m each, over the nominated OTB-HAY outage periods.
Figure 5-4: Restricted gross market benefits – Huntly Retires
5.1.3 Gross market benefits – Tiwai Closes
The Tiwai Closes scenario allows for an increase in available generation from Manapouri hydro station given
closure of the Tiwai aluminium smelter in the South Island. Huntly’s last coal –fired unit is retired prior to 2020
and a single gas peaker plant is added to the North Island.
Negative benefits associated with Options 3 and 4 over the OTB-HAY outage period are pronounced in the
Tiwai Closes scenario. Limited transfer capacity on the HVDC means costly thermal generators in the North
Island are needed to meet demand.
The positive benefits associated with Option 3 and 4 following the OTB-HAY outage periods suggest some
ability for water to be stored during the outage periods and run later in the year, thus providing a level of benefit
post the designated outage periods.
-$150
-$100
-$50
$0
$50
$100
$150
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option1 & 4
-$120
-$100
-$80
-$60
-$40
-$20
$0
$20
$40
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option1 & 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-5: Daily gross market benefits – Tiwai Closes
Figure 5-6 shows the gross market benefits associated with the identified outage periods only. This suggests
Options 1 and 2 provide benefits of approximately $23.2m over Option 3 and $12.5m over Option 4.
Figure 5-6: Restricted gross market benefits – Tiwai Closes
5.1.4 Gross market benefits – BAU (U5)
The BAU (U5) scenario seeks to identify the effect on benefits when introducing an outage to major North Island
thermal generation during the planned OTB-HAY outages. Huntly Unit 5 has been taken out of service for a
week in late January, 25th January 2020 to 1
st February, with all else in the initial scenario remaining
unchanged.
Daily gross market benefits are shown in Figure 5-7, the OTB-HAY outage period highlighted by the red circle.
Overall, benefits again appear small with a level of market cost reduction noted given high cost thermal plant
withdrawn from the market.
We note again the model optimisation at the tail end of the year, as per the initial BAU scenario.
-$600
-$500
-$400
-$300
-$200
-$100
$0
$100
$200
$300
$400
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-$600
-$500
-$400
-$300
-$200
-$100
$0
$100
$200
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-7: Daily gross market benefits – BAU (U5)
Examining the OTB-HAY outage periods in isolation of the rest of year provides an indication that the impact of
Huntly U5 not being available during the planned OTB-HAY outage has minimal effect. Figure 5-8 shows
negative benefits are in fact reduced for Option 4, given the withdrawal of Huntly Unit 5s costly generation and
great utilisation of capacity of the HVDC. However Option 3s negative benefits increase as a shift in reserve
risk from thermal generation to the HVDC occurs and higher cost thermal units are brought on to meet demand
– see section 5.3 below for further discussion on reserve costs.
Figure 5-8: Restricted gross market benefits – BAU (U5)
5.1.5 Gross market benefits – BAU (1987)
Our last scenario provides for an alternative hydrological pattern added to the Business as Usual study. The
1987 hydrological scenario represents a dry year in the North Island and a wet year in the South Island, thus
increasing the need for a greater level of transfer northward across the HVDC, both for evacuating energy from
the southern reservoirs and supplying North Island demand.
Figure 5-9 shows a greater level of negative benefits associated with Options 3 and 4 than observed in previous
scenarios (similar to Tiwai Closes), meaning an increased level of costly thermal generation exists. In addition
to the outage period, highlighted by the red circle, daily negative gross market benefits are evident immediately
following the OTB-HAY outages (identified in the blue circle).
-$150
-$100
-$50
$0
$50
$100
$150
$200
$250
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-$150
-$100
-$50
$0
$50
$100
$150
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Investigation into the strong surge of negative benefits directly following the second OTB-HAY outage reveals it
is driven by an increase in northward transfer on the HVDC for sustained periods, along with an increase in
reserve risk that allows thermal generators to operate at higher levels without having to balance their own
reserve risk requirements, as was evident throughout the OTB-HAY outage periods.
Figure 5-9: Daily gross market benefits – BAU (1987)
Figure 5-10 provides a restricted view on gross market benefits for the BAU (1987) scenario meaning benefits
are limited to OTB-HAY outage intervals only. Results translate into gross market benefits of approximately
$17.9m for Option 1 or 2 over Option 3, and benefits in order of $11.9m for Option 1 or 2 over Option 4.
Figure 5-10: Restricted gross market benefits – BAU (1987)
Examination of the modelling results above suggest a level of optimisation occurring in the model when
balancing water volumes across the market over the 12 month period, whilst taking account of the HVDC
constraint calculations applied in each Option, thus resulting in a level of variability unlikely to be removed. The
“noise” identified impacts perceived gross market benefits when taken as an annualised figure. A suitable
approach to isolating this variability, to the extent where possible, and consistently applied across all options is
to restrict the aggregation of gross market benefits to the planned OTB-HAY outage periods only.
Table 5-3 provides the gross market benefits when restricted to outage periods only for the year 2020 across all
options.
-$500
-$400
-$300
-$200
-$100
$0
$100
$200
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-$500
-$400
-$300
-$200
-$100
$0
$100
Be
ne
fits
('0
00
)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Table 5-3 Gross market benefits (restricted to OTB-HAY outage period)
Outage Period Gross Market Benefits ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ - $ - -$ 1.50 -$ 1.55
Huntly Retires $ - $ - -$ 3.01 -$ 2.99
Tiwai Closes $ - $ - -$ 23.18 -$ 12.46
Additional Scenarios
BAU (U5) $ - $ - -$ 1.43 -$ 1.21
BAU (1987) $ - $ - -$ 17.87 -$ 11.79
Restricted gross market benefits associated with Business as Usual, Huntly Retires and BAU (U5) scenarios are
in the range between 0.2% to 0.7% of their respective annual gross market costs (or approx. $1.2m to $1.6m).
Under scenarios Tiwai Closes and BAU (1987) restricted gross market benefits range between 2.8% and 10.0%
of annual gross market costs, or approximately $11.8m to $23.2m.
5.2 HVDC Flows
This section provides a brief illustration of the HVDC flows observed in each scenario modelled.
5.2.1 Daily HVDC Flows – Business as Usual (BAU)
Figure 5-11 shows that the daily HVDC flows under the Business as Usual scenario separate for Options 3 and
4 once the OTB-HAY outages commence in mid-January. Between the first and second OTB-HAY outage
HVDC flows increase markedly, and again immediately following the second outage.
Figure 5-11: Daily HVDC flows – Business as Usual
Convergence of HVDC flows appears to occur well beyond the completion of the second outage in mid-April,
closer to June 2020. This suggests ability for the system to store constrained water and use this to generate at
a later time.
Figure 5-12 provides an alternative view of the same data, illustrating the difference in daily HVDC flows
between options. HVDC outage constraints are clearly defined in the Option 3 and 4 data, followed by dramatic
increases in flow as capacity is increased on the link, and then convergence noted earlier.
-
2
4
6
8
10
12
Dai
ly H
VD
C T
ran
sfe
r (G
Wh
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-12: Daily HVDC flow differences – Business as Usual
5.2.2 Daily HVDC Flows – Huntly Retires
Similarly to the previous scenario, Figure 5-13 illustrates the separation of Options 3 and 4 daily HVDC flows
under the Huntly Retires scenario and convergence of flows across all options over an extend period.
Figure 5-13: Daily HVDC flows – Huntly Retires
Figure 5-14 provides an alternative view of HVDC flows where an increase in volatility is noted, and in general
HVDC flows appear stronger for Options 3 and 4 over the long term. This is likely to be a result of model
optimisation and is largely considered to be “noise”.
-3.00
-2.00
-1.00
-
1.00
2.00
3.00
Dai
ly H
VD
C D
iff
(GW
h)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-
2
4
6
8
10
12
Dai
ly H
VD
C T
ran
sfe
r (G
Wh
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-14: Daily HVDC flow differences – Huntly Retires
5.2.3 Daily HVDC Flows – Tiwai Closes
Daily HVDC flows relating to the Tiwai Closes scenario can be observed in Figure 5-15 below. A similar pattern
to previous scenarios exist however given the increased availability of generation available to the market from
the South Island considerably more pressure is placed on the HVDC.
Option 3s Pole 3 outage from mid-January to the end of February is clearly identifiable, along with the additional
capacity that is provided by Option 4. Options 1 and 2 remain indifferent to each other.
Figure 5-15: Daily HVDC Flows – Tiwai Closes
Figure 5-16 provides a similar illustration, from a differential point of view, and notably the time it takes for
HVDC flow differences to converge with Option 3 showing signs of simply not settling.
-2.50
-2.00
-1.50
-1.00
-0.50
-
0.50
1.00
1.50
2.00
2.50
Dai
ly H
VD
C D
iff
(GW
h)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-
5
10
15
20
25
Dai
ly H
VD
C T
ran
sfe
r (G
Wh
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-16: Daily HVDC flow differences – Tiwai Closes
5.2.4 Daily HVDC Flows – BAU (U5)
The nominated outage in late January for Huntly Unit 5 has a minor effect on daily HVDC flows. Figure 5-17
illustrates a small change in daily flows compared to the Business as Usual scenario presented in 5.2.1 above.
The Huntly Unit 5 outage period is identified by a red circle.
Figure 5-17: Daily HVDC Flows – BAU (U5)
Figure 5-18 provides a comparison of HVDC flows to Option 1, and indicates an increase in HVDC flows for
Option 4 during the Huntly Unit 5 outage period, where additional capacity on the HVDC appears to be utilised
in order to meet demand in the North Island.
Option 3 daily HVDC flows appear to decrease further when Huntly Unit 5 is out of service, coupled with an
increase in reserve costs (see also Figure 5-24: Daily reserve cost – BAU (U5)). The remainder of the HVDC
flows under this scenario are not largely dissimilar to our initial Business as Usual scenario, noting a level of
model optimisation or variability exists.
-12.00
-10.00
-8.00
-6.00
-4.00
-2.00
-
2.00
4.00
6.00
8.00
Dai
ly H
VD
C D
iff
(GW
h)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
0
2
4
6
8
10
12
Dai
ly H
VD
C T
ran
sfe
r (G
Wh
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-18: Daily HVDC flow differences – BAU (U5)
5.2.5 Daily HVDC Flows – BAU (1987)
The 1987 hydrological pattern included in this scenario utilises much of the HVDC capacity to export electricity
from the South Island to the North Island, particularly over the first half of the year where inflows are high.
Figure 5-19 provides a clear illustration of the different HVDC flows and constraints modelled under each option
– noting Option 1 and 2 remain indifferent.
Figure 5-19: Daily HVDC Flows – BAU (1987)
Option 3 is highly constrained over the first OTB-HAY outage period, noting Pole 3 is out of service and flow is
limited to Pole 2. Option 4 provides a consistent illustration of transfer limited to Pole 3 alone over both outage
periods.
Interestingly the modelling outputs reveal elevated HVDC flows for both Options 3 and 4 prior to the outages,
between outages, and again following the second outage. This reflects an ability to evacuate energy from the
South Island at times outside of the nominated OTB-HAY outage periods given high availability of South Island
generation as a result of high inflows.
Figure 5-20 illustrates the BAU (1987) scenario HVDC flows based on differences between the Option 1 as the
base case and Options 2, 3 and 4. Convergence of all option HVDC flows is noted as being particularly swift
and understood to relate to the pressure on the HVDC to utilise its capacity to meet demand.
-3.00
-2.00
-1.00
-
1.00
2.00
3.00
4.00
5.00
Dai
ly H
VD
C D
iff
(GW
h)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
-
5
10
15
20
25
Dai
ly H
VD
C T
ran
sfe
r (G
Wh
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-20: Daily HVDC flow differences – BAU (1987)
5.3 Reserve Costs
This section provides a brief summary of the NZEM reserve costs observed in model results. Daily reserve
costs have been plotted for each option under each market scenario.
A common occurrence in results from the Business as Usual and Huntly Retires scenarios is the increase in
reserve costs for Option 3s first outage, where Pole 3 is taken out of service and HVDC transfers rely on Pole 2
alone, with no bypass installed. Reserve costs to the market are observed at $5k to 20k per day.
Figure 5-21 and Figure 5-22 show the increase in reserve costs during OTB-HAY outage periods for both the
noted scenarios. Winter peak reserve costs are somewhat variable across the different options, and in part this
is to be expected given the optimisation of hydro storage apparent in the NZEM.
Figure 5-21: Daily reserve cost – Business as Usual
Annual reserve costs for both the Business as Usual and Huntly Retires scenarios range between $300k per
annum to approximately $600k per annum.
-14.00
-12.00
-10.00
-8.00
-6.00
-4.00
-2.00
0.00
2.00
4.00
6.00
Dai
ly H
VD
C D
iff
(GW
h)
Diff Option 1 & 2 Diff Option 1 & 3 Diff Option 1 & 4
$0
$5
$10
$15
$20
$25
$30
$35
$40
$45
$50
Dai
ly R
ese
rve
Co
st (
'00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-22: Daily reserve cost – Huntly Retires
The Tiwai Closes scenario illustrated in Figure 5-23 below shows HVDC constraints applied under Option 3 and
4 translate into substantial reserve costs during the OTB-HAY outage periods. The excess of available energy
in the South Island due to closure of the Tiwai aluminium smelter appears to exacerbate reserve market
outcomes and are in line with the high level of HVDC flows observed in the previous section for this scenario.
Annual reserve costs under the Tiwai Closes scenario equate to approximately $2.3m for Options 1 and 2,
$42.9m for Option 3 and $21.6m for Option 4.
Figure 5-23: Daily reserve cost – Tiwai Closes
Winter peak reserve costs can also be seen to be higher than in other scenarios, as HVDC flows remain
significantly higher throughout the year, and optimisation of energy and reserve comes under pressure during
this peak demand period.
Daily reserve costs in the BAU (U5) scenario (see Figure 5-24 below) appear similar to both the Business and
Usual and Huntly Retires scenarios. A small increase in reserve costs is observed during Huntly Unit 5s outage
in the end of January and optimisation of energy and reserve influences market costs during Option 3s Pole 3
outage.
Reserve costs for this scenario range from approximately $400k to $500k per annum and are not considered
significant.
$0
$5
$10
$15
$20
$25
$30
$35
Dai
ly R
ese
rve
Co
st (
'00
0)
Option 1 Option 2 Option 3 Option 4
$0
$100
$200
$300
$400
$500
$600
Dai
ly R
ese
rve
Co
st (
'00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 5-24: Daily reserve cost – BAU (U5)
Much like the Tiwai Closes scenario, Figure 5-25 illustrates the increased reserve costs driven by pressure on
the HVDC to transfer energy up to its capacity, impacting on energy and reserve trade-offs and the ability for a
constrained HVDC to effectively share reserves between islands.
The winter period reserve costs under this scenario are largely reduced. Transfer on the HVDC appears to drop
back to a comfortable level post early year inflows and HVDC outages, meaning energy and reserve sharing on
the HVDC are able to be optimised over the peak demand period without significant impact on costs.
Figure 5-25: Daily reserve cost – BAU (1987)
Annual reserve costs under the BAU (1987) scenario equate to approximately $5m for Options 1 and 2, $28m
for both Options 3 and 4.
$0
$5
$10
$15
$20
$25
$30
$35
$40
$45
$50
Dai
ly R
ese
rve
Co
st (
'00
0)
Option 1 Option 2 Option 3 Option 4
$0
$50
$100
$150
$200
$250
$300
$350
$400
$450
$500
Dai
ly R
ers
erv
e C
ost
('0
00
)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
6. Conclusions
Our analysis shows that the gross market benefits associated with installing a bypass to facilitate the required
OTB-HAY re-conductoring work are small. Noting the small level of benefits, modelling results reveal evidence
of a level of “noise” or model optimisation that is unlikely to be removed. Restricting the calculation of gross
market benefits to the nominated OTB-HAY outage periods is deemed a suitable approach to draw comparison
between the HVDC bypass and configuration options, and the gross market benefits that arise.
Market scenarios Business as Usual, Huntly Retires and the additional BAU (U5) scenario present gross market
benefits associated with installation of a bypass in the range of $1.2m to $3m. Market scenarios Tiwai closes
and BAU (1987), which simulate an increased level of available hydro generation from the South Island, provide
for a greater measure of gross market benefits. Installation of a bypass relating to the Tiwai Closes scenario
represents benefits of approximately $23.2m over Option 3, and $12.5m over Option 4. Installation of a bypass
relating to the BAU (1987) scenario represents gross market benefits of approximately $17.9m over Option 3
and $11.8m over Option 4.
Without comparing the gross market benefits against nominal bypass investment costs a measure of the net
cost or benefit cannot be drawn.
Table 6-1 provides the gross market benefits (read as negative) when comparing the bypass base case, Option
1, with the total generation costs in Options 2, 3 and 4. We not there is no difference in total generation costs
between Option 1 and Option 2.
Table 6-1 Gross market benefits (restricted to OTB-HAY outage period)
Outage Period Gross Market Benefits ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ - $ - -$ 1.50 -$ 1.55
Huntly Retires $ - $ - -$ 3.01 -$ 2.99
Tiwai Closes $ - $ - -$ 23.18 -$ 12.46
Additional Scenarios
BAU (U5) $ - $ - -$ 1.43 -$ 1.21
BAU (1987) $ - $ - -$ 17.87 -$ 11.79
For illustration purposes the following charts show weekly total generation costs for each market scenario over
the year 2020. Benefits arise from the least cost generation solution.
Figure 6-1: Weekly total generation cost – Business as Usual
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 6-2: Weekly total generation cost – Huntly Retires
Figure 6-3: Weekly total generation cost – Tiwai Closes
Figure 6-4: Weekly total generation cost – BAU (U5)
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
$6,000
$7,000
$8,000
$9,000
$10,000
$11,000
$12,000
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 6-5: Weekly total generation cost – BAU (1987)
6.1 Reserve Costs
Although unlikely to be a determining factor in decision making for Transpower reserve costs provide an
indication of market tension, particularly in regards to the optimisation of energy and reserves in market
dispatch.
Table 6-2 Market reserve costs
Reserve Costs ($m)
Scenario Option 1 Option 2 Option 3 Option 4
Business as Usual (BAU) $ 0.34 $ 0.34 $ 0.58 $ 0.57
Huntly Retires $ 0.29 $ 0.29 $ 0.37 $ 0.39
Tiwai Closes $ 2.28 $ 2.28 $ 42.85 $ 21.63
BAU (U5) $ 0.39 $ 0.39 $ 0.51 $ 0.41
BAU (1987) $ 5.08 $ 5.08 $ 28.33 $ 28.17
Market reserve costs for scenarios Business as Usual, Huntly Retires and BAU (U5) range from $0.3m to
$0.6m, and are noted as insignificant.
Annual reserve costs under the Tiwai Closes scenario equate to approximately $2.3m for Options 1 and 2,
$42.9m for Option 3 and $21.6m for Option 4. Annual reserve costs under the BAU (1987) scenario equate to
approximately $5m for Options 1 and 2, and $28m for both Options 3 and 4.
$-
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
We
ekl
y To
tal G
en
era
tio
n C
ost
s ('
00
0)
Option 1 Option 2 Option 3 Option 4
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Appendix A. Overview of PLEXOS
PLEXOS is a mixed integer programming model that optimises dispatch using the same techniques that are
used in the Scheduling, Pricing and Dispatch model (SPD) to clear the NZEM.
Generation dispatch, transmission power flow and ancillary services are co-optimised and integrated with hydro
and emissions modelling, providing a versatile suite of features that may be adapted to accommodate most
electricity markets.
Prior to optimising dispatch, PLEXOS schedules planned maintenance and randomly pre-computes a user-
specified number of forced outage scenarios and/or stochastic samples for Monte Carlo simulation.
Dispatch is then optimised to meet load and ancillary service requirements at minimum cost subject to a number
of operating constraints, which may include:
Generation constraints – availability (planned and unplanned outages), unit commitment and other
technical constraints;
Transmission constraints – availability (planned and unplanned outages), linearised DC optimal power
flow (OPF) equations, interconnector ratings, and other transmission constraints that may be a function
of load, generation or line flow;
Hydrology constraints – hydro units may be energy-constrained, or more detailed storage models may
be represented with stochastic hydro inflows;
Fuel constraints – for example, daily fuel limits or annual take-or-pay constraints;
Ancillary service constraints – maximum unit response, calculation of dynamic risk; and
Emission constraints – limits on emission production may be imposed, or carbon prices specified.
In determining this least-cost dispatch, generators formulate bids that are offered into the market to be cleared.
These bids may be manually input, or they may be derived dynamically by PLEXOS based on either the short-
run marginal cost (SRMC) of the unit, or strategic objectives. For the purpose of this analysis, SRMC bidding is
assumed. Therefore, competition benefits are not captured in our market benefit analysis.
A.1 SPD and Reserve Management Tool
The steady state operation of the NZEM power system is based on the SPD model. As part of the scheduling
and dispatch process, reserve offers are co-optimised with the energy offers from generators. The System
Operator uses the Reserve Management Tool (RMT) to calculate the instantaneous reserves required to meet
the markets Reserve Management Objective, see Figure 6-6 (Source: Transpower – RMT Functional
Specification, 2011).
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Figure 6-6 Role of RMT in the SPD Process
When calculating the instantaneous reserve requirements RMT determines the net free reserve (NFR)
according to the risk in each island. The NFR must represent the reserve requirement offset from the risk.
PLEXOS uses typical NFR values, provided by Transpower, as input to determining the risk and reserve
requirement in each island and, as in the SPD RMT interaction, the NFR represents the reserve requirement
offset from the risk.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
A.2 PLEXOS Algorithms
To enable modelling of long-term objectives and short-term constraints, PLEXOS includes four integrated
algorithms:
PASA/preschedule – optimising maintenance scheduling, and prescheduling unplanned outages for
Monte Carlo simulation;
Long-term simulation (LT) – using load duration curve (LDC) analysis to allow modelling of horizons
spanning more than one year in a single step. Suitable for long-term planning where decisions need to
take account of future market changes;
Mid-term simulation (MT) – using LDC analysis to model up to one year in a single step. Suitable for
mid-term operational planning; and
Short-term simulation (ST) – modelling chronological dispatch in every trading period (typically one
hour or half-hour). Suitable for operational decision making.
Users may select any combination of these four algorithms to fit their modelling requirements. For the NZ
system, expansion plans are an input to the model rather than be determined by the LT. Of importance is the
integration of the algorithms, with results from the MT being used to inform the ST, such as hydro storage
trajectories. This flow of information from one algorithm to another, used for this study, is demonstrated in
Figure 6-7.
Figure 6-7 Integration of PLEXOS algorithms for the NZ study
A.3 Aggregating the model
It is important that the length of each step used in the MT at least spans the duration of all inter-temporal
constraints. For example, if there is an annual hydro energy constraint in the model, the MT must be able to run
at least one year in a single step in order to determine when best to use the available hydro throughout the
year.
There is often a trade-off that must be made between the complexity of the model and the length of the horizon
that can be spanned in one step. To enable months or years to be spanned in a single step in the MT, hourly
load profiles are aggregated into blocks, whereas in the ST the full chronology is modelled.
Mid - term simulation
Short - term simulation
Annual storage
trajectories decomposed
to weekly end storage
targets
Detailed weekly
chronological dispatch
PASA and
preschedule
Mid - term simulation
Short - term simulation
PASA and
preschedule
Forced outages
and maintenance
schedule
HVDC Bypass Line Economic Benefit Study
RZ024300_01
For hydro systems such as the NZEM, it is generally recommended that the length of the period over which load
is aggregated is equal to the length of the step used in the ST simulations. For example, if load is aggregated
into blocks using weekly load duration curves in the MT, then the ST should ideally model one week at a time,
with weekly storage targets passed down from the MT simulation. This ensures that the weekly end storage
targets in the ST are consistent with the outcomes from the MT modelling.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Appendix B. Existing Power Plants
Power station Size (MW) Plant type
HlyUnit5 1 x 385 Thermal
HlyUnit6 1 x 50 Thermal
Huntly U1 1 x 250 Thermal
Huntly U2 1 x 250 Thermal
MangaTodd 1 x 10 Thermal
Stratpeaker 1 x 200 Thermal
TaranCC 1 x 380 Thermal
ToddPeak_McKee 2 x 50 Thermal
Whirinaki 3 x 155 Thermal
Aniwhenua 1 x 25 North Island Hydro
Arapuni 8 x 24.6 North Island Hydro
Atiamuri 4 x 21 North Island Hydro
Kaimai 1 x 42 North Island Hydro
Kaitawa 2 x 18.5 North Island Hydro
Karapiro 3 x 32 North Island Hydro
Mangahao 1 x 39 North Island Hydro
Maraetai 10 x 36 North Island Hydro
Matahina 2 x 40 North Island Hydro
Ohakuri 4 x 28 North Island Hydro
Patea 3 x 10.2 North Island Hydro
Piripaua 2 x 22.5 North Island Hydro
Rangipo 2 x 60 North Island Hydro
Tokaanu 4 x 60 North Island Hydro
Tuai 3 x 19.3 North Island Hydro
WaikHyd_ARA 3 x 28 North Island Hydro
Whakamaru 4 x 25 North Island Hydro
Wheao 2 x 13 North Island Hydro
Amethyst 1 x 6 South Island Hydro
Aviemore 4 x 55 South Island Hydro
Benmore 6 x 90 South Island Hydro
Clyde 4 x 108 South Island Hydro
Cobb 1 x 32 South Island Hydro
Coleridge 1 x 41 South Island Hydro
Highbank 1 x 34.5 South Island Hydro
Manapouri 6 x 121.7 South Island Hydro
Manapouri MTAD 1 x 75 South Island Hydro
Ohau A 4 x 66 South Island Hydro
Ohau B 4 x 53 South Island Hydro
Ohau C 4 x 53 South Island Hydro
Paerau 1 x 12 South Island Hydro
Roxburgh1_5 5 x 40 South Island Hydro
Roxburgh6_8 3 x 40 South Island Hydro
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Tekapo A 1 x 25 South Island Hydro
Tekapo B 2 x 80 South Island Hydro
Waipori 1 x 84 South Island Hydro
Waitaki 7 x 15 South Island Hydro
Glenbrk 1 x 74 Cogen
Hawera 1 x 70 Cogen
Kapuni 1 x 25 Cogen
Kinleith 1 x 40 Cogen
TeRapa 1 x 44 Cogen
Kawerau1 1 x 90 Geothermal
Mokai 1 1 x 72 Geothermal
Mokai 2 1 x 38 Geothermal
Nga Awa Purua 1 x 138 Geothermal
Ngatamariki 1 x 83 Geothermal
Ngawha 1 x 5 Geothermal
Ohaaki 1 x 69 Geothermal
Poihipi 1 x 53 Geothermal
Rotokawa 1 x 34 Geothermal
Tauha1 1 x 25 Geothermal
TeMihi 1 x 166 Geothermal
Wairaki (after Te Mihi is commissioned) 1 x 114 Geothermal
Mahinerangi 1 x 36 Wind
MillCreek 1 x 60 Wind
TararWd3 1 x 93 Wind
TaraW12 1 x 32 Wind
Te Rere Hau 1 x 48 Wind
TeApiti 1 x 91 Wind
TeUku 1 x 64 Wind
WestWnd 1 x 143 Wind
WhiteHill 1 x 58 Wind
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Appendix C. Maximum Generator Reserve Provision15
Existing Generators NI FIR NI SIR SI FIR SI SIR Freq
Arapuni 2.46 3.69 2.46 3.69 Yes (NI)
Atiamuri 2.1 3.15 2.1 3.15 Yes (NI)
Aviemore 4.46 4.46 5.5 5.5 Yes (SI)
Benmore 7.29 7.29 9 9 Yes (SI)
Clyde 8.75 8.75 10.8 10.8 Yes (SI)
HlyUnit5 19.25 38.5 19.25 38.5 -
HuntC1 12.15 24.3 12.15 24.3 Yes (NI)
HuntC2 12.15 24.3 12.15 24.3 Yes (NI)
Kaitawa 1.85 2.78 1.85 2.78 -
Karapiro 3.2 4.8 3.2 4.8 Yes (NI)
Manapouri 9.72 9.72 12 12 -
Manapouri MTAD 7.29 7.29 9 9 -
Mangahao 3.2 4.8 3.2 4.8 -
Maraetai 3.6 5.4 3.6 5.4 Yes (NI)
Matahina 4 6 4 6 -
Ohakuri 2.8 4.2 2.8 4.2 Yes (NI)
Ohau A 5.35 5.35 6.6 6.6 Yes (SI)
Ohau B 4.29 4.29 5.3 5.3 Yes (SI)
Ohau C 4.29 4.29 5.3 5.3 Yes (SI)
Patea 1.02 1.53 1.02 1.53 -
Rangipo 6 9 6 9 -
Roxburgh1_5 3.24 3.24 4 4 Yes (SI)
Roxburgh6_8 3.24 3.24 4 4 Yes (SI)
Stratpeaker 10 20 10 20 -
TaranCC 19 38 19 38 -
Tekapo A 2.03 2.03 2.5 2.5 Yes (SI)
Tekapo B 6.48 6.48 8 8 Yes (SI)
Tokaanu 6 9 - - -
ToddPeak_Mckee 2.5 5 2.5 5 -
Waitaki 1.22 1.22 1.5 1.5 Yes (SI)
Whakamaru - - - - Yes
IL0 50 50 No
Total Existing 272.7 424.2 238.7 390.2
New Generators NI FIR NI SIR SI FIR SI SIR Freq
HaweaCG 1.38 1.38 1.7 1.7 -
Lake Pukaki 2.84 2.84 3.5 3.5 -
OCGTPkrG6 10 20 10 20 -
ToddPeak_Otor 5 10 10 10 -
ToddPeakJnctnRd 5 10 10 10 -
Wairau 5.67 5.67 7 7 -
WhkmruExp 2 2 2 2 -
Total Existing 31.88 51.88 34.2 54.2 -
15 The reserve provision figures stated exclude effectiveness of NI FIR being provided by SI generators (refer Section 4.5.4).
HVDC Bypass Line Economic Benefit Study
RZ024300_01
Appendix D. Generation expansion Plans
Three key market scenarios have been considered as follows, and applied to the four options above resulting in
a total of 12 market modelling runs:
The final Huntly coal-fired units retire as planned, one in 2018 and the second by 202016;
The remaining units at Huntly are not retired; and
The NZAS aluminium smelter at Tiwai Point shuts down in combination with the remaining Huntly unit
retiring.
The three market scenario generation expansion plans shown below:
Scenario 1 – Huntly coal-fired stations retire as originally planned.
Installed MW / Year
Station / DSR 2016 2017 2018 2019 2020
CCGTCHP1 40
OCGTPkrG6 200
ToddPeak_Otor 100
ToddPeakJnctnRd 100
GGeoNgawh1 25
KA22TeAhi 20
Tauha2 250
HaweaCG 17
LakePukaki 35
CastleHill_s1 60
WhkmruExp 20
DSRchch1 22.4
DSRnthd1 8
DSRnshr1 6
DSRotag1 8
DSRakld1 40
DSRslnd1 5
DSRwaik1 6
Huntly unit 1 -250
Huntly unit 2 -250
Scenario 2 – Business as usual and the coal-fired units at Huntly are not retired
Installed MW / Year
Station / DSR 2016 2017 2018 2019 2020
ToddPeak_Otor 100
ToddPeakJnctnRd 100
KA22TeAhi 20
Rotoma 35
16 It is noted that on 28 April 2016 Genesis Energy announced its intention to extend the life of the Huntly coal-fired units until
December 2022, however it was agreed to continue this analysis based on the 2018 date.
HVDC Bypass Line Economic Benefit Study
RZ024300_01
HaweaCG 17
Wairau 70
WhkmruExp 20
DSRchch1 22
DSRnthd1 8
DSRnshr1 6
DSRotag1 8
DSRakld1 40
DSRslnd1 5
DSRwaik1 6
Scenario 3 - NZAS aluminium smelter at Tiwai Point retires by 2020, along with Huntly
Installed MW / Year
Station / DSR 2016 2017 2018 2019 2020
Huntly unit 1 -250
Huntly unit 2 -250
ToddPeakJnctnRd 100
KA22TeAhi 20
WhkmruExp 20