Page 1: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination

Process and New Equipment

1

Page 2: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Introduction

This presentation is intended to increase knowledge of outage coordination and NOMCR submittal processes

2

Page 3: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ObjectivesAt the completion of this course of instruction you

will:Identify the ERCOT Outage Coordination

timelinesIdentify the timeline requirement for a

maintenance level outageIdentify the maximum size of a group outageIdentify the correct process order for new

equipment in the ERCOT system

3

Page 4: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Definitions

NOMCR – Network Operations Model Change Request

ResTran – RESource Owned TRANsmission Equipment

4

Page 5: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination Planned Transmission Timeline

Request for Approval* ERCOT must Approve or Reject*

More than 90 days 75 days

46–90 days 30 days

9–45 days 4 days

4–8 days No later than 1800 hours 3 days

3 days No later than 1800 hours 2 days

*Prior to Planned Start Date/Time

5

Page 6: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination Planned Resource Timeline

QSE Request for Approval

ERCOT Approval or Rejection

Three days 1800 hours, two days prior to start of proposed Outage

Four to eight days 1800 hours, three days prior to start of proposed Outage

Nine to 45 days Five Business days after submission. Outages are automatically accepted if not rejected at the end of the fifth Business Day following receipt of request.

Greater than 45 days ERCOT must accept, but may discuss reliability and scheduling to minimize cost.

6

Page 7: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

•Timelines for Reliability Resource Planned Outages(RMR and Black Start)

Note: ERCOT may, at its discretion, relax the 30 day Notice requirement.

Request for Approval

ERCOT Approval or Rejection

Not less than 30 days

15 days before start of proposed Outage

More than 45 days 30 days before the start of proposed Outage

7

Outage Coordination Planned Resource Timeline

7

Page 8: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination Maintenance Timeline

Definition: Initiated manuallyto remove equipment fromservice to perform work on components than could be postponed briefly but is required to prevent potential forced outage and cannot be postponed until the next planned outage.

Level 1: Applies to equipment which must be removed from service within 24 hours. (M1)

Level 2: Identifies equipment which must be removed from service within 7 days. (M2)

Level 3: Applies to equipment which must be removed from service within 30 days. (M3)

8

Page 9: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran

Forms are available on resquestEmail forms to

[email protected] forms for Forced Outages

9

Page 10: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran - Planned or Maintenance

10

Page 11: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran - Planned or Maintenance

11

Page 12: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran - Forced Outages

12

Page 13: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

d

ResTran - Forced Outages

13

Page 14: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran - Outage Form

14

Page 15: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ResTran - Outage Form

15

Page 16: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

ALWAYS review the outages after they were submitted by ERCOT on your behalf to make sure that the outage does exactly what you want it to do when you want it to.

To update an outage email the most up-to-date form with the new updated information added.

ResTranOutage Form

16

Page 17: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination Approvals

Approved Outages can be withdrawn any time before it is completed.

Planned transmission outages are always studied.

Approved -> Done by coordinatorsAccepted -> Automatic

17

Page 18: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

Outage Coordination Availability

• Short Term: M-F 6AM-6PM, Sa-Su 6AM – 2PM– Rotating Shifts*

• Long Term: M-F 6AM-5PM

• Use OC Blast Accounts– Email: [email protected]– Phone: (512) 248 – 6841

• No Voicemail*

18

Page 19: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

New Equipment

Create plan for switching from old to new equipmentMay require pseudo equipment

i.e. Breakers to switch between equipment…

Submit a NOMCR for all new and pseudo equipment

19

Page 20: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

New Equipment

Pseudo Equipment

Pseudo Breaker

BreakerNew Breaker

Old Breaker

20

Page 21: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

NOMCRs

A

21

Page 22: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

22

NOMCRs

Page 23: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

NOMCRs

23

Page 24: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

NOMCRs

24

Page 25: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

NOMCRs

A

25

Page 26: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

New Equipment Outages

After the NOMCR has been processed and the equipment has been added to the OS Database

Planned End Date is the Energization Date

NOMCR >> OS >> Model

26

Page 27: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

**BONUS**

Extending an outageNew Planned End DateUnlimited extensionsFR->FE || (PL,M1,M2,M3)->UE

Adding Requestor Notes1000 Characters Only once per group outage

The maximum Group Outage size is 30 pieces of equipment

27

Page 28: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

**BONUS MIS**

28

Outage Approved/Accepted Outage Rejected

Removed from MIS

2 Hrs. After Actual End Entered

Out

age

With

draw

n

Planned End > 1 Yr. Old

Planned End > 1 Yr. Old

*All reports are automatically updated every hour on the hour

*When an outage is added to one report it is removed from

the previous report

Or Outage Canceled

Outage Canceled

Outage Submitted

Rejected Transmission

Outages

Withdrawal of Approved and

Accepted Transmission Outages

Approved and Accepted

Transmission Outages

Proposed Transmission

Outages

Page 29: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

????29

Page 30: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

1. The last day to enter a Planned Transmission Outage is ________ before the Planned Start Date.

A) 1 Day

B) 3 Days

C) 8 Days

D) 45 Days

30

Page 31: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

2. Planned Resource Outages must be accepted when entered ______ before the Planned Start Date.

A) >3 Days

B) >9 Days

C) >30 Days

D) >45 Days

31

Page 32: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

3. A level 2 maintenance outage (M2) means that the outaged equipment must be removed _______ to prevent a forced outage.

A) <7 Days

B) <30 Days

C) <7 Hours

D) <1 Hour

32

Page 33: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

4. The maximum size of a group outage is _______.

A) 10 pieces of equipment

B) Unlimited

C) 30 pieces of equipment

D) 2 megabytes of equipment

33

Page 34: Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal

QuestionsQuestions

5. What is the correct process order for new equipment in the ERCOT system?

A) NOMCR >> OS >> Model

B) NOMCR >> Model >> OS

C) OS >> Model >> NOMCR

D) Model >> NOMCR >> OS

34