overall power core configuration and system … · 2012. 10. 2. · major parameters of the...
TRANSCRIPT
OVERALL POWER CORE
CONFIGURATION AND SYSTEM
INTEGRATION FOR ARIES-ACT1
FUSION POWER PLANT
X.R. Wang, M. S. Tillack, S. Malang,
F. Najmabadi and the ARIES Team
20th TOFE
Nashville, TN
August 26-31, 2012
MAJOR PARAMETERS OF THE ARIES-ACT1
POWER PLANT
2
Parameter Value
Major radius R 6.25 m
Aspect ratio A 4
Elongation k 2.1
Toroidal field on axis Bo 6 T
Plasma Current Ip 10.93 MA
Fusion power Pf 1813 MW
Thermal power Pth 2016 MW
Recirculating power Precirc 154 MW
Net electric power Pe 1006 MW
Average wall load at FW Pn 2.3 MW/m2
Maximum wall load at FW 3.6 MW/m2
Power conversion efficiency ᵑth 57.9 %
ARIES-ACT1 Power Core
A COMPARISON OF THE ARIES-AT AND
ARIES-ACT1 POWER CORE
ARIES-AT ARIES-ACT1
Major radius 5.5 m 6.25 m
IB Blanket LiPb cooled SiC/SiC structure LiPb cooled SiC/SiC structure
1st OB Blanket LiPb cooled SiC/SiC structure LiPb cooled SiC/SiC structure
2nd OB Blanket LiPb cooled SiC/SiC structure LiPb cooled SiC/SiC structure
HT Shield LiPb cooled SiC/SiC structure and B-
FS filler
He-cooled ODS steel structure
Upper/Lower Divertors LiPb cooled SiC/SiC structure He-cooled W-based divertor and
ODS steel cartridge
Vacuum vessel Water-cooled FS structure and WC He-cooled Bainitic FS
(3Cr-3WV)
LT shield Water-cooled Bainitic FS and WC
3
REPLACEMENT UNITS FOR THE QUICK SECTOR
MAINTENANCE
4
All the in-vessel components have a limited lifetime and
require replacement. Our design approach is to integrate
all the in-vessel components into replacement units to
minimize the number of the coolant access pipe
connections and time–consuming handling inside the
plasma chamber.
The integrated replacement unit must maintain a
constant distance in radial direction, and no welds are
used for the connections between the different
components of the replacement units and between the
units and the VV.
The replacement units are supported at the bottom only
through the VV by external vertical pillars, and can
expand freely in all directions without interaction with
the VV.
The unit can be inserted and withdrawn by straight
movement in radial direction during installation and
maintenance.
Replacement unit (1/16)
OVERALL LAYOUT OF THE ARIES-ACT1
POWER CORE
5
All the coolant access pipes to the sector are
connected to the structural ring close to its
bottom plate.
Cutting/Reconnection of all the access pipes
is located in the port, and all the pipes and
shield blocks would be removed for sector
maintenance.
Control coils are supported by the structural
ring and be removed to the upper corner of
the VV for the sector removal.
Shield blocks are arranged in the VV port to
protect the coils, and they would be cooled by
helium.
The saddle coil can be attached to the upper
shield block and removed together during
maintenance.
Maintenance ports are arranged between the
TF coils, and there is only one vacuum door
located at the end of the port for each sector.
Cross section of the ACT1 power core
(1/16 sector)
T-SHAPED ATTACHMENT AND RAIL SYSTEM
UTILIZED FOR SECTOR ALIGNMENT
6
During the installation, a rail system with 2 or
3 vertical pistons would be inserted and the
sector will be supported by the rail system for
the vertical and horizontal alignment.
There are wide gaps in the wedge allowing the
precise alignment of the sector in all
directions.
After the alignment, the grooves of the
attachment have to be filled with a suitable
liquid metal (possibly a Cu-alloy) and fixed in
the position by freezing the liquid metal the
attachment grooves. Then, the rail system will
be withdrawn.
T-shaped attachment for sector support
Cross-section of T-shaped attachment
and rail system
MAIN FEATURES OF THE SECTOR
MAINTENANCE
7
A transfer flask with the rail system and fresh
sector can be docked to the port to avoid any spread
of radioactivity during maintenance.
After all access pipes disconnected, and the shield
blocks, saddle coil, control coils and access pipes
removed, the rail system would be inserted into the
space between the structural ring and the VV.
Using the rail system, the sector is supported by
pressurizing the pistons and separated from the
VV by melting the metal inside the T-shaped
attachment grooves.
Then, the sector can be pulled in straight way out
the plasma chamber into the transfer flask. After
that, the new sector can be installed in reverse
order without moving the flask away from the port.
Design and Optimization of the First Wall and
Blanket Modules
Major objective of the blanket design is
to achieve high performance while
keeping attractive features, feasible
fabrication, credible maintenance
schemes and reasonable design margin
on the operating temperature and stress
limits.
Design iterations were made to
determine and optimize all the
parameters of all the blanket segments,
including:
curvature of the FW/BW,
thickness of the FW/SW/BW,
width and depth of FW cooling
channels,
number of the ribs per duct,
number of modules per sector.
8
ARIES-AT-type SiC/SiC blanket modules
Cross-section of one OB-I module
Outer
duct
FW Center duct
with ribs
Scope Structural Analyses for Optimizing the
Geometry and Reducing SiC Volume Fraction
Stress limits for using in FEM analysis: Conventional stress limits (3 Sm) can not be directly applied to ceramics.
In our design, we try to maintain the primary stress to <~100 MPa and limit the total combined stress to ~190 MPa.
Assumed the MHD pressure drop through
the FW and blanket ∆P MHD=~0.2 MPa
ARIES-AT blanket
ARIES-ACT1 blanket
9
(Inboard blanket of the ARIES-ACT1)
Phydrostatic=~0.8 MPa
(Inboard blanket)
Example of Definition, Dimensions of the OB
Blanket Modules
Total number of the module for each blanket sector=16, 14
inner modules with pressure balance on side walls and 2
outer modules without pressure balance on the outer side
wall. (same number for OB-II)
The FW/SW/BW thickness of the outer/inner ducts =5 mm
(7 mm for OB-II)
The fluid thickness of the annular gap=10 mm
(same for OB-II)
Rib thickness at 4 corners=6 mm (same for OB-II)
Rib thickness on both sides=2 mm (same for OB-II)
Diameter of the curvature for the FW and back wall=30 cm
(45 cm for OB-II)
Inner modules of the OB-I and OB-II
Outer module of the OB-I and OB-II
Inner and Outer Modules of OB Blanket
45 cm
10
Increase the thickness of the outer SW from 5 mm to 15 mm
(22 mm for OB-II)
Increase the thickness of the rib at the outer SW from 2 to 5 mm
(6 mm for OB-II)
Increase the numbers of the rib at the outer SW from 2 to 5
(9 for OB-II)
Inner
modules
Outer module
30 cm
Thermal Stress Results indicate the Design Limits
Are Satisfied
B.C. and loads: Free expansion, and allowing for free bending Pressure load at the bottom: 1.95 MPa at annular ducts and 1.65 MPa at the center duct Pressure load at the top: 0.95 MPa at the annular ducts and 0.85 MPa at the center duct
Thermal stress distribution of the inboard blanket module
Max. thermal stress =~91 MPa
Pressure stress<~50 MPa
Total stresses=~141 MPa
11
Max. combined primary and thermal stresses are ~141 MPa at the bottom (higher primary stress, lower thermal stresses) and ~142 MPa at the top (higher thermal stresses, lower primary stress)
INTEGRATION OF THE HE-COOLED W-BASED
DIVERTOR IN THE ACT1 POWER CORE Fingers arranged over the entire plate Imping-jet cooling, Tin/Texit=700/800 ᵒC Allowable heat flux up to~14 MW/m2
Avoiding joints between W and ODS steel at the high heat flux region
~550,000 units for a power plant
T-Tube divertor: ~1.5 cm dia. X 10 cm long Impinging-jet cooling, Tin/Texit=700/800 ᵒC Allowable heat flux up to~11 MW/m2
~110,000 units for a power plant
Plate divertor: 20 cm x 100 cm Impinging-jet cooling, Tin/Texit=700/800 ᵒC
Allowable heat flux up to~9 MW/m2
~750 units for a power plant
Two zone divertor (any combination of the plate and finger and T-tube)
Fingers for q>~8 MW/m2, plate for q<~8 MW/m2
Decreased number of finger units
The selection of the divertor
depends on the peak heat flux
and heat flux profile of the
ACT1.
Plate-type divertor concept is
selected for the ARIES-ACT1
based on the peak-time average
heat flux of 10.6 MW/m2.
Tubular or T-Tube He-cooled SiC/SiC divertor
Impinging-jet cooling, Tin/Texit=600/700 ᵒC Allowable heat flux up to~5 MW/m2
Divertor region of the ARIES-ACT1
12
SUMMARY The power core configuration, system integration and maintenance scheme of the
ARIES-ACT1 have been re-examined, and major new design features are discussed
and highlighted.
The Pb-17Li SiC/SiC blankets including the IB, OB-I and OB-II segments have been
re-designed and optimized with the objective of achieving high performance (~58%
power conversion efficiency) while maintaining attractive safety features, feasible
fabrication process, credible maintenance scheme and reasonable design margin on
the temperature and stresses.
Design issues, uncertainties and R&D needs are discussed in separate presentation..
13