DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39 1 A. SURVEY Detailed Survey of the route has already been carried out. Check survey will be based on the tentative Alignment Plan of the route attached with this bid document. Detailed survey and Forest survey of a portion of the route may be felt necessary during check survey, and that shall be conducted by the Contractor as per route alignment approved by DVC. A.01 DETAILED SURVEY: The object of carrying out detailed survey is to prepare longitudinal and cross section profiles on the approved alignment to prepare the route plan showing details of deviation angles, important objects coming within the right of way. Work of detailed survey is distinctly done in two stages: 1. Actual field observations taking level readings and calculating distances, level differences, deflection angles, offset distances etc. 2. Plotting of profiles on graphed tracing papers. TOWER SPOTTING: The work of tower spotting is clearly divided into the following five operations : 1. Sag tension calculations. 2. Preparation of Sag Template. 3. Application of Sag Template to decide optimum tower position on Survey Chart. 4. Preparation of Structure Limitation Charts. 5. Deciding tower type and preparation of Tower Schedule. SAG TEMPLATE Sag Template drawing for AAA Conductor on DVC designed towers shall be prepared by the Contractor and get approved from DVC. Inputs required for preparation of Sag Template will be furnished by DVC to the Contractor. Based on the above drawing the Contractor has to prepare Sag Template on rigid acrylic transparent plastic sheet and provide two sets of the same to the owner for checking purposes. With the help of Sag Template and tower spotting data, tower locations shall be marked on the profiles. A.02 CHECK SURVEY: Check survey is carried out for the following: 1. To reconfirm the work carried out during detailed survey.

Upload: arogya-raju-pudhota

Post on 21-Jul-2016

73 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

1

A. SURVEY Detailed Survey of the route has already been carried out. Check survey will be based on the tentative Alignment Plan of the route attached with this bid document. Detailed survey and Forest survey of a portion of the route may be felt necessary during check survey, and that shall be conducted by the Contractor as per route alignment approved by DVC. A.01 DETAILED SURVEY: The object of carrying out detailed survey is to prepare longitudinal and cross section profiles on the approved alignment to prepare the route plan showing details of deviation angles, important objects coming within the right of way. Work of detailed survey is distinctly done in two stages: 1. Actual field observations taking level readings and calculating distances, level differences, deflection angles, offset distances etc. 2. Plotting of profiles on graphed tracing papers. TOWER SPOTTING: The work of tower spotting is clearly divided into the following five operations : 1. Sag tension calculations. 2. Preparation of Sag Template. 3. Application of Sag Template to decide optimum tower position on Survey Chart. 4. Preparation of Structure Limitation Charts. 5. Deciding tower type and preparation of Tower Schedule. SAG TEMPLATE Sag Template drawing for AAA Conductor on DVC designed towers shall be prepared by the Contractor and get approved from DVC. Inputs required for preparation of Sag Template will be furnished by DVC to the Contractor. Based on the above drawing the Contractor has to prepare Sag Template on rigid acrylic transparent plastic sheet and provide two sets of the same to the owner for checking purposes. With the help of Sag Template and tower spotting data, tower locations shall be marked on the profiles. A.02 CHECK SURVEY: Check survey is carried out for the following: 1. To reconfirm the work carried out during detailed survey.

Page 2: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

2

2. To locate and peg mark the tower position on ground controlling to the route profiles. 3. To give direction pegs. Check survey should be conducted to make rough check on detailed survey and to locate and peg mark the tower position on ground conforming to the survey chart. Position of Tower shall be kept on high places and good soil as far as practicable. Any deviation of the actual tower position from the route profile drawing shall have to be corrected by the contractor accordingly in the drawing. After check survey route profile, tower spotting, line chart etc shall be prepared and submitted for approval of DVC. A.03 FOREST SURVEY 1) Identification & survey of forest area & Jungle Jhari area. A statement of Forest area and Jungle-Jhari area to be prepared. Demarcation of forest boundary is to be done. Co-ordination & interaction with Forest Authority and collection of Mouja map, necessary for survey work will be done by DVC. Collection of Topo sheet is Contractor’s responsibility. The Contractor’s responsibility is to do the field survey work and align the route on Mouja map and Topo sheet. All interaction and co-ordination with State Forest Department will be done by DVC.

The tree-cutting shall be the responsibility of the Contractor. Contractor may please note that owner shall not pay any compensation for any loss or damage to the properties or for tree cutting due to Contractor’s work. However, if any statutory compensation is required to be paid for getting necessary forest clearance, it will be paid by DVC at actual.

Contractor shall count, mark and put proper numbers with suitable quality of paint at his own cost on all the trees that are to be cut (after obtaining forest clearance) at the time of actual execution of the work. 2) To evaluate and tabulate the trees and bushes coming within 17.5 meters on either side of the centre line of alignment, the trees will be numbered and marked with quality paint serially from angle point-1 onwards and the corresponding number will be painted on the stem of the trees at height of 1 meter from ground level. 3) The contractor shall be responsible for tree enumeration for the purpose of initiating proposal for obtaining forest clearance from Ministry of Environment and Forest. The contractor shall submit 2 copies of the complete proposal to be moved for forest clearance to the satisfaction of the Engineer-in-charge of the work.

Page 3: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

3

A.04 PAYMENTS:

Separate payment shall be made for survey which the contractor should quote separately for the same as indicated in the price schedule. B. GEO-TECHNICAL INVESTIGATION B.01 GENERAL The Transmission tower foundation shall be classified based on the soil conditions. Optimization of foundation design and their safety mainly depend on correctness of soil and their analysis. The scope of work includes detailed soil investigations at various locations such as railway crossings, major road, crossing, power line crossings, river crossings and wherever soil strata differs. However, the soil investigation activities shall be completed before the commencement of main erection activities. Soil investigation may not be needed for all the locations of the line. The required locations will be at the discretion of DVC. B.02 NORMAL LOCATIONS : One bore hole of 150 mm dia shall be drilled at the centre point of the tower. Standard penetration test (S.P.T) shall be carried out at 1.5 meter interval or change of strata upto the required depth of 2.5 times below the depth of foundation below existing surface elevation or refusal whichever occurs earlier. (By refusal it shall mean that a standard penetration below count ‘N’ of 100 is recorded for 30 cm penetration). Bore details and water table upto required depth below existing surface elevation or refusal whichever occurs earlier shall be furnished in the report. B.03 SPECIAL LOCATIONS: At certain locations such as river banks, river beds or midstream of river and at other places, special soil investigation shall be carried out by drilling two holes each of 150 mm diameter at each tower location on the diagonally opposite legs of the tower, considering the base width of tower as 20 meter. Standard penetration tests shall be carried out at every 1.5 meter interval or change of strata till refusal is met subject to maximum of 40 meter below the existing surface elevation. Undisturbed samples of soils shall be collected at every 2.5 meter interval or change of strata whichever occurs earlier. In the hard rock the bore drilling shall be continued at least 5.0 meter to ascertain its sufficient thickness. B.04 SALIENT TEST REQUIREMENTS:

Page 4: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

4

The following covers the technical requirements for a detailed Geo-Technical Investigation & submission of a detail geotechnical report :

1. Mobilization of all necessary equipment, men & materials to the

project site for carrying out geotechnical investigation and demobilization of the same after completion.

2. Sinking of 150 mm nominal diameter bore hole in all types of soil,

sand including laterite, at various locations up to a maximum depth of 20.0m– 25.0m below ground level or upto rock level, whichever is earlier, using suitable approved method of boring including chiseling, cleaning, providing casing pipe as required :

a) Performing SPT at every meter interval, at change of strata and at

depths wherever undisturbed soil samples could not be collected, b) Collection of undisturbed soil samples at every meter and at

change of strata, c) Collection of disturbed soil samples and water samples, d) Observation such as ground water table, rock level etc. e) Transportation of collected samples to the laboratory, f) Backfilling of bore holes with sand on completion. Borehole to be properly stabilized with Bentonite.

Conducting laboratory test on soil samples including preparation of soil samples to determine the following properties etc. &/or as per specifications:

a) Bulk density & moisture content b) Sieve analysis c) Liquid limit and plastic limit d) Triaxial shear test e) Unconfined compressive strength.

B.05 PREPARATION OF TEST REPORTS:

The geotechnical investigation report shall include but not be limited to the following:

i) Location & reduced levels of bore holes, ii) A true cross section of all bore holes showing the

classification & thickness of individual stratum, position of G.W.T., rock stratum if met with etc.,

iii) Water level & rock level contours,

Page 5: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

5

iv) Plot of SPT ‘N’ values (both corrected & uncorrected) with depth,

v) Results of all tests in tabular as well as graphical forms, vi) Values of cohesion, angle of internal friction, skin friction. vii) High flood level of the area.

The report should contain specific recommendation for the type of foundation. In case the soil parameters obtained from the soil investigation report for a particular tower location, differ from the ones considered during design, a fresh design has to be developed for such locations.

B.06 RECOMMENDATIONS:

Recommendation shall include but not be limited to the following:

a) Type of foundation to be adopted for Transmission Towers duly considering the sub-strata characteristics, G.W.T.

b) For shallow foundation the following shall be furnished : Net safe bearing capacity for isolated square footing of size 4.0 m & 5.0 m at different founding depths of 3.0m, 4.0m & 5.0m below G.L. considering shear & differential settlement criteria

c) If piling is envisaged the following shall be furnished with comprehensive supporting calculations :

i) Type of pile & reasons for recommendation. ii) Suitable founding strata for the pile. iii) Estimated length of 600/800 dia pile considering end

bearing and frictional resistances. iv) Safe lateral & tensile load carrying capacity of pile. v) Magnitude of negative skin friction considering Scour

Depth.

All work shall be carried out as per relevant I.S. code & standards etc. C. EARTHWORK IN EXCAVATION: C.01 GENERAL Each tower shall have four footings; the excavation of the pits for the four footings shall be of same type unless otherwise approved by the Engineer. The four pits shall be marked by the contractor at his cost as such the tower is open in the direction of the line or the line bisecting the angle of deviation for angle location. The levels up and down of each pit centre with respect to the centre of the tower location shall be noted by the contractor & approved by the Engineer or his

Page 6: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

6

authorised representatives before the excavation is started. The surfaces of the excavated pits shall be made full dimensions required and as per drawings. All the excavated materials shall be dumped away from the pits at a distance not exceeding 50 meters preferably in diagonal directions keeping the space along the centre line free for foundation work. Care shall be taken that no moving vehicles or heavy equipments are drawn too near the foundation excavation.

C.02 CLASSIFICATION OF SOIL:

The classification of various types of soil will be as under:

Ordinary soil: The ordinary soil will mean all types of soil excluding all kind of rocks and wet soil. Hard soil: Hard soil will mean soil mixed with moorum, kankor etc. but not soft rock.

Slushy soil: Slushy soil will mean the soil below water level. Soft rock: This will mean decomposed rock, hard gravel, kankor, lime-stone, laterite or any other soil which cannot be easily excavated with pick axe or spade. Hard rock: Hard rock will be that which requires chiseling or drilling and blasting. The cost of drilling and blasting are to be included in the quoted rate. The contractor shall supply requisite blasting material and be responsible for the purpose of the storage and use of the material. Blasting shall be done so that pits are as near to the designed dimension as practicable. Fully/Partially submerged soil: Fully/Partially submerged soil means locations where water is met within 1.5 meter / 0.75 meter from ground respectively. It should be avoided as far as possible.

Filled up soil: It should be avoided. Sandy soil: Soil mixed with Sand (or fully Sandy location).

The contractor will be required to submit at his own cost to the Engineer his report about the water-logging, if any, sub soil water-table and type of soil encountered at the locations along with his proposal for type of foundation. He should also be satisfied that the allowable bearing pressure of the soil as mentioned in the drawing will be available at the locations. The approval of the Engineer should be obtained regarding type of foundation to be used.

C.03 CLASSIFICATION OF FOUNDATION:

Classification of soil shall be made according to I.S. 200 (Part-I) for footing cast in open pits. Depending upon the ground water table and type of soil / rock and presence of surface water the foundations can be classified as follows:

Page 7: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

7

a) Normal Dry Soil Foundations When water table is below foundation level and when soil is normal, dry, cohesive and homogeneous upto the full depth having clay content of 10- 15%. (b) Wet Soil Foundations When water table is above foundation level and up to 1.5 meter below ground level. The foundations in the soils which have standing surface water for a long period with water penetration not exceeding 1.5 meter below ground level (e.g. paddy fields) are also classified as wet foundations. (c) Partially Submerged Foundations When water table is at a depth between 1.5 meter and 0.75 meter below ground level and when the soil is normal and cohesive. (d) Fully Submerged Foundations When water table is within 0.75 meter below ground level and the soil is normal and cohesive. (e) Black Cotton Soil Foundations When the soil is cohesive having inorganic clay exceeding 15% and shrinks when dry, swells when wet, (need not be always black in colour) resulting in differential movement extending upto a depth of about 3.5 meter below ground level. (f) Soft Rock/Fissured Rock Foundations When decomposed or fissured rock, hard gravel or any other soil of similar nature is met which can be executed without blasting. Under cut & Rock Anchor type foundation can be used at these locations. In case of fissured rock locations where water table is met at 1.5 meter or more below ground level, submerged fissured rock foundation shall be adopted. When the water table in such location is met within 1.5 meter from ground level, fully submerged fissured rock type foundations shall be adopted. (g) Hard Rock Foundations Where chiseling, drilling and blasting is required for excavation hard rock type foundation are to be used. Rock anchoring is to be provided to resist uplift forces. The above categorizations has been done for economizing the foundations, as uplift resistance of foundation is a critical design factor which is greatly affected by the location of water table and the soil surrounding the foundation. In addition to the above, depending on the site conditions other types of foundations may also be developed for :

Page 8: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

8

1. Intermediate conditions under the above classifications to effect more economy or 2. For locations where special foundations (well type or piles) are necessitated. While classifying foundations of Wet, Partially submerged, Fully submerged foundations mentioned above, the worst conditions should be considered and not necessarily the conditions prevailing at the time of inspection. For instance, there are area where sub-soil water rises when canal water let-out in the fields raising sub-soil water to a considerable degree. Similarly, the effect of monsoon or when the nearby reservoirs are full should also be considered and not the conditions prevailing in open season or summer when work is carried out normally. C.04 DEWATERING: Dewatering, if required, shall be done at the cost of the contractor either manually or by mechanical pumps or power driven pumps to facilitate excavation and during excavation. The pumps shall be suitable for handling mud water. The pits shall also be kept water free during concreting and till 24 hours of concreting the foundation. No backfilling should be done till pits are dewatered fully. C.05 SHORING AND STRUTTING: Shoring and strutting shall be used in pits excavated in sandy soil or in water bearing strata if directed by the Engineer, where there is every likelihood of pit collapsing. Shoring and strutting shall be made out of timber planks or steel frame and struts of adequate strength to suit the requirement as directed by the Engineer-in-Charge. Separate unit price per square meter shall be quoted for this item. Shoring and strutting may be necessary during excavation or during concreting or during excavation and concreting both. However, payment for shoring and strutting will be made once and not for the second time even if shoring and strutting are required to be provided during excavation and concreting both. C.06 MEASUREMENT: The payment for excavation of pits will be made on the basis of pre-work ground level and post work ground level measurement of the tower pits. No payment will be made for the excavation made in excess to the quantity of excavation shown in the approved drawings. In case it is required to excavate more than what is mentioned in such drawings, then approval of the Engineer should be obtained specifically for such cases and in that case, payment will be made for the total excavated quantity certified by the Engineer as per rate quoted by the contractor. If the different types of soil are encountered within a pit while excavating, then payment will be made as per volume measured for different types soil therein. No

Page 9: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

9

payment for dewatering will be made for any type of soil. The rate of excavation for different types of soil should include the cost of dewatering, if required and also the cost of pit-marking.

Before starting the excavation of pits, the contractor or his representative should inform the Engineer or his representatives. The contractor or his representative should also inform the Engineer or his representative after the excavation is completed but before backfilling to enable the Engineer to take measurement of the quantity of earth excavated and type of soil encountered.

In case of the excavated pits being ready for backfilling after stub setting where contractor has filed a statement protesting the measurement taken regarding the quantity and nature of earthwork excavated for which payment is to be made, the contractor shall delay back-filling work until the Engineer-in-Charge is able to verify the necessary measurement or to secure such an additional data as may be necessary for the proper consideration to the contractor’s protest, which shall be done by the Engineer-in-Charge of the work within 10 days from the date of receipt of such protest. Such delay shall be considered incidental to the work and no additional compensation will be granted to the contractor thereof. Failure of the contractor to permit such re-examination before back-filling shall be considered as waiver of all claims. C.07 PAYMENT: Payment for excavation for tower foundation shall be made for unit price per cubic meter. If, during the progress of excavation or after excavation is completed, it is found necessary or desirable to change the type of footings or to change the dimension of excavation for the footings from those shown in the drawings or prescribed by the Engineer, payment for such change or allocation of cost thereof shall be as follows :

i) Where the change in the type of footing or change in the dimension of the excavation for a footing are the result of the faults on the part of contractor e.g. defects in pit marking, improper excavation method or means of supporting excavation or of taking inadequate means of protection of the excavation from weathering or of the contractor’s delaying between the excavation of footings and placing of concrete etc., the cost of all additional excavation, reinforcement, cement concreting and back-filling shall be borne by the contractor.

ii) Where the type of footing or excavation is changed for no fault of the

contractor, but it is felt so necessary by DVC and done accordingly, payment for excavation, back-filling etc. so performed shall be made by DVC at the unit price for the items. No additional rate above the unit price for the work shall be allowed to the contractor.

Page 10: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

10

D. EARTHWORK IN BACKFILLING:

The backfilling of the excavation pits shall be carried out after the concrete work is over, form work is opened, shoring and strutting, if any, are removed. The backfilling shall be done by the contractor only after the receipt of approval from the Engineer or his representative. Unless special instruction given in any specific case, no backfilling work shall be carried out if the repair & finishing work is not complete. Finishing of coping (the top of the foundation above ground) may be done after the completion of backfilling. Backfilling shall be done with excavated soil if the excavated soil is free from decomposed soft rock and gravels not more than 50 mm and also free from organic and other foreign materials. In case the excavated soil is not of such specifications backfilling should be done with normal soil from suitable borrow pits.

The backfill should be compacted with special care. Good thorough compaction is to be made for ensuring uplift resistance and development of passive earth resistance. The backfill should be deposited in layers of thickness of not more than 200mm after compaction. The back filling operation should be such that the materials when compacted will be blended sufficiently to secure the best practicable degree of compaction. The backfilling is to be carried out to an elevation up to concrete level and with a size equal to maximum plan dimensions of excavated pits at ground level. Volume of backfilling shall be considered equal to that of excavation to account for the extra backfilling above ground level. The backfill material shall have optimum practicable moisture content requiring for the purpose of compaction and curing as determined by the Engineer and the moisture content shall be uniform throughout the layers. The moistening shall be made by sprinkling of water at the site of compaction. The backfill shall be compacted by tamping or by such means or equipments as approved by the Engineer. Care shall be taken that backfilling is started from inner end of the pits, towards the outer end. The stub template may be struck and removed only after getting clearance from Engineer or his representatives.

The backfilling of foundation shall be carried out so that after one / two monsoon the level of backfilled earth does not go below the surrounding ground level. On completion of the backfilling as per above requirements and completion of curing period, proper grading should be carried out to drain out the water. Separate rate shall be quoted by the contractor for backfilling work (I) with soil obtained from excavation of foundation and (II) with soil from borrow pits. In case of backfilling being done with normal soil from borrow pits no separate payment for excavation of such soil from borrow pits including its carriage to the place of backfilling will be paid.

Page 11: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

11

E. SUB-BASE:

A lean concrete sub-base shall be provided if required and directed by the Engineer-in-Charge. The work should be done as per instruction of the Engineer-in-Charge. Payment for supplying and placing lean concrete sub-base will be made at unit price per cubic meter.

F. STUB-SETTING: F.01 SETTING OF STUB WITH TEMPLATE:

The Stubs are set with the help of the Stub-setting Templates, which are supplied loose, ready to be assembled at site. All four excavated pits are to be lean concreted to correct level sighted through level and the stubs are to be placed on the lean concrete pad. Correct alignment is carried out by 0.9 Kg. Plumb bob 4 in numbers hung from centre of horizontal bracings. Following is the procedure for Stub-setting at Site: 1. Assemble the Template as per the drawing along with the supply. 2. Set the Template as per the drawing at site. 3. Place the Stub-setting Jacks below the Template. 4. Align Template, along with the line and centre it over the centre peg of the location. 5. Fix up the stub to the Template and with the help of a dumpy level, level the Template corners to the required level. 6. Ensure that all the four stubs are at the same level. 7. Check the alignment and centering of the Template again.

8. By placing on 8 to `12 screw jacks according to the length of Template, with a leveling instrument fine adjustment can be made by lifting / lowering the screw jacks, and the stubs can be perfectly levelled. This ensures accurate verticality of the tower. For ensuring all towers in one line and cross-arms at right angle to it, 4 plumb bobs should be dropped from the centre of the horizontal members of the Template to correspond to the cross pegs and alignment pegs given during the line alignment survey for the tower location.

The contractor shall be fully responsible for correct setting of stub in accordance with the drawing supplied, at the exact locations and alignments and precisely at correct level. The stubs are to be set with the help of stub setting templates supplied by DVC & the contractor wherever necessary. F.02 SETTING OF STUBS WITH SECTION METHOD:

There may be occasions when templates may not be available from DVC. In such special and exceptional cases DVC may permit setting of the stubs by first section method i.e. lowest section of the tower body complete with bracings may be used as template.

Page 12: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

12

F.03 PAYMENTS:

When stubs are set by using first section methods the contractor shall be entitled to no additional payment over the unit price bid for setting of stub. Payment for erection of first section with bracings, excluding weight of stubs, will be made at the unit rate quoted for tower erection and will be included in the item “Erection of tower.” However, if the contractor quote separate rate for setting of stubs by using first section method, the same will be paid accordingly.

G. CONCRETE: G.01 GENERAL:

All reinforced concrete will be either with M-15, M-20 or M-25 concrete. Nominal Mix proportion 1:2:4, 1:1.5:3 & 1:1:2 by volume shall be taken as equivalent to M-15, M-20 and M-25 respectively. Characteristic compressive strength of 15 cm cube at 28 days for M-15, M-20 and M-25 mix is 15 N / Sq.mm , 20 N / Sq.mm and 25 N / Sq.mm respectively. All concrete work shall fully comply with the latest edition of Indian Standard Specification IS : 456, "Code of Practice for Plain and Reinforced Concrete".

Cement, sand and stone chips (Coarse aggregate) shall be used for concreting with 20 mm and down stone chips for chimney and pyramid portion. Approved mechanical vibration for all structural and reinforced concrete shall be mandatory. Immersion type vibrators (65 mm and / or 75 mm dia and 500 mm to 600 mm long) with a minimum vibration of 8000 revolutions / minute shall be used. Use of pneumatic and / or electrical vibrators are mandatory. Sample of cement, stone chips and sand to be used for construction works by the contractor must got approved by the Engineer before use. Cement, Stone chips and sand are to be supplied by the contractor at his own cost. Specification for the materials are given below. G.02 MATERIALS: a) Cement: Cement shall be ordinary cement conforming to IS: 269 / IS: 455. Cement shall be kept in clean dry, moisture-proof covered stores. It shall be adequately protected from condensation, rising damp and atmospheric moisture. Sufficient cement shall be stored at all times to ensure continuity of work. Not more than ten bags shall be stacked in any tier. The Engineer-in-charge if consider any cement defective, then irrespective of its origin and / or manufacturer’s test certificates, such cement shall be tested immediately at DVC’s laboratory or any Laboratory approved by DVC,

Page 13: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

13

and until the results of such tests are found satisfactory it shall not be used in any work. The Contractor shall not be entitled to any claim of any nature on this account. The cement supplied by contractor should be purchased directly from the approved manufacturer and should be supported by matching challans of the manufacturer. b) Fine Aggregates: Fine aggregates (Sand) shall be clean, sharp coarse, gritty to the touch and free from elongated and flaky particles with a fineness modulus between 2.8 and 3.2 and shall pass through sieve no. 16. It shall be clear and free from any mixture of clay, dust, vegetable matter, mica, shale, loam, salts and organic matter, or other impurities, which may be considered by the Engineer-in-Charge as harmful. Sand containing clay shall be thoroughly washed by the contractor at his own expenses before use. Unless otherwise specified fine sand may be used for sand filling and for mixing with cement for mortar and plaster. c) Coarse Aggregates: Coarse aggregates, whether crushed stone or washed and graded gravel shall conform to sieve analysis presented in Table-II of IS : 383 and when tested shall conform to IS : 2386 ( Pt.I to VIII )

Stone aggregates (20 mm. & down ) shall consist of good, hard and broken stone of the gauge specified and approximately cubicle in shape. It shall be free from dirt, clay, heaves or any organic matter of admixture of soft or decayed stone. Different sizes shall be stacked sufficiently apart or separated with approved wooden bulk heads. The Engineer-in-Charge if consider any aggregate defective or of poor quality, then irrespective of any previous approval or tests, samples of such materials shall be immediately tested and until the result of such tests prove the materials to be satisfactory, it shall not be used in any work. The contractor shall not be entitled to any claim of any nature on this account.

d) Water: Water shall be clean, transparent, tasteless and free from organic or deleterious matter in solution or suspension in quantities which may impair the strength or durability of the concrete. Contractor shall provide his own arrangements and at his own cost for distribution, store, filtration and / or treatment, as necessary of the required quantity of water. The water should be reasonably clear and of turbidity limit 2000 ppm.

e) Reinforcement:

All reinforcement shall be of tested quality strictly in conformity with the relevant Indian Standards. Steel reinforcement shall comply with the requirement of the latest

Page 14: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

14

edition of IS-1786. All reinforcement shall be HYSD bars of Grade Fe-415. The Engineer-in-charge shall check and ensure that appropriate test certificates of materials are available to his satisfaction. If demanded by DVC the contractor shall submit the manufacturer’s test certificate for steel. Otherwise, necessary tests shall be made by the Contractor at his own cost to ensure that the quality and physical properties of the materials used conform to the specification. No complaints or claims shall be entertained on this account.

All reinforcement materials, before its final use, shall be free from loose mill scales, loose rust, oily or bituminous coating or injurious adherents. Pitted and otherwise defective rods shall not be used. The binding wire (18 SWG) shall be included in the cost of reinforcement rod binding and shall be borne by the contractor. All bars shall be rigidly held in position before concreting as per requirements of the latest edition of IS:2502. No welding of rod shall be allowed. Laying of Reinforcement bars shall be in accordance with relevant I. S. specifications unless otherwise specified. Lap lengths shall not be less than the minimum values specified in the relevant codes of practice. The laps shall be staggered. Dowel bars shall be provided wherever required or as directed by the Engineer or as shown in the approved drawings. The Contractor shall check, ensure and procure in time, as necessary, the reinforcement materials required for the continuous scheduled progress of the work till completion. All reinforcement steel shall be suitably stacked and stored by the Contractor to protect it from damage by corrosion, and to prevent distortion of section in long lengths. The horizontal distance between parallel reinforcement bars in row shall not be less than the greatest of the following:

a) The larger diameter if the diameter be unequal. b) Diameter, if the diameters are equal. c) 6 mm. more than the nominal maximum size of coarse

aggregate.

The vertical distance between two rows of reinforcement bars shall be not less than 12 mm unless they are cross reinforced or lapped. No reinforcement shall be bent when in position in the work without approval whether or not this is partially embedded in concrete. Reinforcement shall be accurately fixed and maintained in position by approved means. Placing of reinforcement shall be completed well in advance of concreting. In case reinforcement bars are in coil form, straightening of the same shall be done by the contractor at his own cost.

Page 15: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

15

G.03 MAINTENANCE OF LOG BOOK FOR CONCRETING WORK:

While all efforts shall have to be made by the contractor to achieve rapid progress in construction in all sector and to avoid deterioration in the quality of concrete work, it is necessary that for every tower a log book should be maintained showing –

a) The date and time of commencement of pouring of concrete. b) The date and time of completion of pouring of concrete. c) The quantity of cement used in concreting foundation.

The log book shall have to be signed by both the representative of the contractor and DVC.

G.04 CONSISTENCY:

The amount of water used in concrete shall be regulated as required to secure concrete of proper consistency and to adjust for any variation in the moisture content of grading of the sand and aggregates as they enter the mixture. Addition of water to compensate stiffening of the concrete before placing will not be permitted. Uniformity in concrete consistency from batch to batch will be required. The slump of concrete after deposition but before it has been consolidated shall not exceed 76.2 mm. DVC reserves the right to require a lesser slump whenever concrete of such lesser slumps are required. DVC also reserves the right to make the slump test in accordance with the latest practice. The concrete mix has to be used within half an hour of the mixing. The proportions of nominal mix concrete & amount of water may be estimated in accordance with Table-4, Table-5 & Table-9 of IS: 456.

G.05 BATCHING:

The contractor shall provide equipment and shall maintain and operate the equipment as required to accurately determine and control the amount of each separate ingredient entering the concrete. The amount of cement, sand, stone chips and water entering each batch of concrete shall be determined by the volumetric measurement.

G.06 MIXING:

The concrete ingredients shall be mixed in a batch in right proportions in mixing drum & shall be kept rotating for not less than two minutes after all the ingredients except full amount of water are in the mixer. The Engineer reserves the right to increase mixing time when charging and mixing operation fails to produce a concrete batch whose consistency is not uniform. The concrete as discharged from the mixture shall be uniform in composition except where changes in composition or consistency are required. Excessive over mixing requiring addition of water to preserve the required concrete

Page 16: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

16

consistency will not be permitted. Any mixer when produce unsatisfactory results shall be repaired promptly and effectively for controlling the mixing time. Hand mixing as per standard practice will be allowed only when concrete mixer fails during concreting. Hand mixing may also be allowed at the discretion of DVC’s representative in-charge of the work as also for the location where mixer machine is not accessible.

When hand mixing is adopted it shall be carried out on a water tight platform such as 1.8 mm galvanised iron plain sheets properly overlapped and placed upon level ground. The coarse aggregates shall be spread out first evenly over the sheets. The fine aggregate shall be evenly spread out over the coarse aggregate. The aggregates shall then thoroughly be mixed together and leveled. The required amount of cement shall now be spread evenly over the mixed aggregates and wet mixing shall start from one end with required amount of water using shovels. The whole lot shall not be wetted, instead, mixing shall proceed progressively. The whole operation shall not be taken more than 15 minutes. If moist sand is used allowance for bulking shall be made.

In case of such hand mixing being permitted, 10% extra cement on this account will be added at Contractors expense.

For mixing in mechanical mixers, the same order of placing ingredient in the loader/drum shall be adopted, that is coarse aggregates shall be put in first followed by sand, cement & water.

G.07 FORMS (Form boxes or Muff box):

Form boxes made of steel will be used to confine the concrete and shape it to the required line. The inner side of the forms shall be cleaned and oiled before concreting (quality of oil to be approved by Engineer or his representatives). Immediately before the concrete is placed, precaution shall be taken so that forms are in proper alignment and tight to prevent any loss of mortar and forming of honey combing in the concrete and also its supports are thoroughly secured and tight. Steel Form Boxes which will be supplied to the contractor have to be returned in good condition to DVC stores on completion of work, failing which cost of form boxes (muff boxes) will be recovered by DVC from the contractor at the rate decided by DVC, which in no case will be less than the rates paid to the contractor for supply of this item. Steel form-boxes (muff-boxes) shall not be galvanized, instead they will be painted with 2(two) coats of red-oxide primer paint.

Page 17: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

17

G.08 PLACING / DEPOSITING THE CONCRETE:

The contractor shall keep the Engineer or his representatives intimated at least 7 (seven) days in advance as to when placing of concrete will be performed. The contractor should try to follow his programming in this regard. Incase of abnormal situation or emergency condition, intimation shall be given to the Engineer or his representative at least 24 hours before the starting of the work. Unless inspection is waived out in any specific case, placing of concrete shall be performed only presence of Engineer or his authorized representative. Contractor will arrange for transport for the Engineer for inspection, if Engineer so desires. The concrete must be used while fresh and shall be laid (not thrown) in layers not exceeding 150 mm and consolidated well. The concrete shall be placed and compacted before setting commences and should not be subsequently disturbed. The placing should be such that no segregation takes place. Concrete shall be thoroughly compacted during the placing operation and thoroughly worked around reinforcements, embedded fixtures and into corners of form work by means of 16 mm dia poking bars pointed at the ends so that no honey-combing is left in the concrete. After concreting the chimney portion to the required height, the top surface should be finished smooth, with slight slope towards the outer edge to drain off the rain water falling on the coping. Concreting shall be done continuously so that their subsequent layers are laid before the initial setting of the bottom layer begins. The time from starting of mixing to ramming in final position shall not take more than 30 minutes. If fresh concrete is to be laid on the old concrete which is less that 10 days old, the surface of old concrete should be cleaned with wire brush and washed with a layer of thick cement slurry before new concrete is laid. But if the concrete is 10 days or more old, then the top of the set concrete should be chipped and cleaned thoroughly with wire brush and fresh water, and layer of 12 mm thick cement mortar (1:2) shall be laid evenly after giving a coat of cement slurry as specified above to ensure proper bonding between old and new concrete, for which no extra payment over the unit price for reinforced cement concrete work will be made. G.09 CURING:

The concrete after setting for 24 hours shall be cured by keeping the concrete wet continuously for a period of 14 days after laying. The pit may be back filled with selected earth sprinkled with necessary amount of water and well consolidated in layers not exceeding 200mm after a minimum period of 24 hours and thereafter both the back filled earth and exposed chimney top shall be kept wet for the remainder of the prescribed time of 14 days. The uncovered concrete chimney above the back filled earth shall be kept wet by providing empty cement bags dipped in water fully wrapped around the concrete chimney for curing and ensuring that the bags be kept wet by frequent pouring of water on them.

Page 18: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

18

No separate payment shall be made for curing. The rate for concrete should include the curing charges. G.10 REMOVING OF FORM WORK:

All form work shall be removed without such shock or vibration as would damage the concrete or forms. Under fair weather conditions (generally where average daily temperature is 25°C or above) and where ordinary cement is used, forms may be struck after 24 hours of the placing of concrete. In dull weather (such as rainy periods) and very cold temperature, the forms shall be struck after 48 hours of the placing of concrete. The consequences arising during the removal of the shuttering shall be contractor’s entire responsibilities. Before reuse all forms shall be thoroughly cleaned as specified earlier & may be used after repair, if any, with the approval of the Engineer. G.11 FINISHING OF CONCRETE:

If after the form work has been struck, the concrete surfaces are found to have defects, all the damaged surface shall be repaired with mortar application composed of cement and sand in the same proportion as the cement and sand in the concrete mix. Such repairs shall be carried out within 24 hours after removal of forms and before the foundation pits are backfilled. The form work is to be struck and repairing if required is to be done in presence of the Engineer or his representative. The cost of materials, labour and equipment, required in the repair of concrete shall be borne by the contractor. In case of salty / saltish soil, special type of bituminous paint shall be applied over the finished concrete surface. The paint shall be supplied by DVC, but no payment for painting will be made by DVC. Exposed surface of the chimney portion of the foundation above the ground level shall be brought to uniform surface by plastering. Finishing shall be neatly done with cement punning. The top surface of the foundation shall be sloped towards the outer edge to provide drainage from the steel stub angle. 12 mm thick cement mortar in 1:6 ratio shall be used.

G.12 PAYMENT:

Unit rate per cubic meter of reinforced cement concrete work including plastering and neat cement punning of the exposed surface of chimney portion should be quoted. In case of any special type of foundation and modification in the foundation design resulting in excess quantity of concrete, contractor will be paid as per quoted rate. No extra rate on this account will be entertained. However, if extra quantity of work is

Page 19: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

19

involved, then it will be paid as per original rate quoted by the contractor in the tender. G.13 INSPECTION OF CONCRETING WORK:

The Engineer-in-charge reserves the right to uncover and examine any foundation and if any foundation is found defective, the contractor shall be required to rectify or do new foundation, if required; at his own cost and put all these back in order. G.14 TOLERANCES:

The tolerances for various items connected to the foundation works of transmission line are as under. A) Stub-setting (Tower Footing)

All the stub angles for tower legs shall be set accurately to the grade and alignment shown on the drawings. The difference in elevation between identical parts of any two stub angles shall not exceed 1/1000 of the horizontal distance between the stubs, allowance being made for difference, if any, in the lengths of legs and extensions. The actual elevation of any stub angle shall not differ from the computed elevation by more than 1/100 of foundation depth. Stub angles shall be located horizontally so that each is within 6mm of its correct position, or by the amount of play as offered by the clearance between bolts and holes of the stub-setting template. To ensure greater accuracy, the hole clearance shall not be greater than 1.5mm on the punched side of the Template members. The following tolerances shall be applicable in case of position of foundations erected with reference to the tower position spotted on Survey Charts :

Type of Tower

Out of Alignment

From Centre Line of Route

From Transverse Centre line

Suspension 0.5 degree 25 mm +/-250 mm Tension 0.5 degree 25 mm +/-25 mm

(Set at bi-section of deviation angle) B) Concrete and Form Dimension: The maximum tolerance on the dimensions shall be +/-10 mm. All tolerances shall not be on the negative side.

Page 20: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

20

H. MISCELLANEOUS: H.01 ENCASING OF STUB: Encasing upto top of stub by mass concrete after erection of tower may be required to be done if desired by the Engineer. For that rate mentioned in the schedule for mass concrete shall be applied. H.02 EMBANKMENT: The contractor shall construct embankment for towers at the locations where embankment is to be made as directed by Engineer-in-Charge. The contractor should quote different rates for stone pitching, random stone masonry and brick masonry pitching. J. ERECTION OF TOWER: J.01 GENERAL The towers shall be erected on the foundations not less than 14 days after concreting or till such time that the concrete has acquired sufficient strength. The towers are erected as per the Structural / erection drawings furnished by DVC to facilitate erection. For the convenience of assembling the tower parts during erection operations, each member is marked in the factory to correspond with a number shown in the erection drawing. Any damage to the steel and injuring of galvanizing shall be avoided. No member shall be subjected to any undue overstress, during erection. Towers may be erected either by Built-up method or by Section method. Built-up Method This method consists of erecting the towers, member by member. The tower members are kept on ground serially according to erection sequence to avoid search or time loss. The erection progress from bottom upwards. The four main corner leg members of the first section of the tower are first erected and guyed off. The advantages of the built-up method are as follows: a) Tower materials can be supplied to site in knocked down condition which facilitates easier and cheaper transportation. b) It does not require any heavy machinery such as cranes etc. c) Tower erection activity can be done in any kind of terrain and mostly throughout the year. d) Availability of workmen at cheap rates.

Page 21: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

21

Section Method In the section method, major sections of the tower are assembled on the ground and the same are erected as units. Either a mobile crane or a gin pole is used. The gin pole used is approximately 10 m long and is held in place by means of guys by the side of the tower to be erected. The two opposite sides of the tower section of the tower are assembled on the ground. Each assembled side is then lifted clear of the ground with the gin or derrick and is lowered into position on bolts to stubs or anchor bolts. One side is held in place with props while the other side is being erected. The two opposite sides are then laced together with cross members and diagonals; and the assembled section is lined up, made square to the line. After completing the first section, gin pole is set on the top of the first section. The gin rests on a strut of the tower immediately below section. The gin rests on a strut of the tower immediately below the leg joint. The gin pole then has to be properly guyed into position. The first face of the second section is raised. To raise the second face of this section it is necessary to slide the foot of the gin on the strut of the opposite of the tower. After the two opposite faces are raised, the lacing on the other two sides is bolted up. The last lift raises the top of the towers. After the tower top is placed and all side lacings have been bolted up all the guyes are thrown off except one which is used to lower the gin pole. Sometimes whole on face of the tower is assembled on the ground, hoisted and supported in position. The opposite face is similarly assembled and hoisted and then the bracing angles connecting these two faces are lifted. J.02 TIGHTENING OF NUTS, PUNCHING OF THREADS AND TACK WELDING OF NUTS: All nuts shall be tightened properly using correct size spanners. Before tightening it is ensured that filler washers and plates are placed in relevant gaps between members, bolts of proper size and length are inserted and one spring washer is inserted under each nut. In case of step bolts, spring washer shall be placed under the outer nut. The tightening shall be carried on progressively from the top downwards, care being taken that all bolts at every level are tightened simultaneously. It may be better to employ four persons, each covering one leg and the face to his right. The threads of bolts shall be projected outside the nuts by one to two threads and shall be punched at three positions on the top inner periphery of the nut and bolt to ensure that the nuts are not loosened in course of time. If during tightening a nut is found to be slipping or running over the bolt threads, the bolt together with the nut shall be changed outright. The nuts upto Bottom Cross arm level shall be punched and tack-welded.

Page 22: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

22

J.03 PAINTING OF JOINTS: For galvanized towers in coastal or highly polluted areas, the joints shall be painted with zinc paints on all contact surfaces during the course of erection. J.04 CHECKING THE VERTICALITY OF ERECTED TOWERS: The finally erected tower shall be truly vertical after erection and no straining is permitted to bring in is alignment. Tolerance limit for vertical shall be 1 in 360 of the tower height. J.05 PAYMENTS: Payment for the erection of tower shall be made by DVC on the per Metric Ton basis. The rate quoted by the tenders for erection of tower shall include all works involved in the tower erection as per tower drawing, including transporting, storing and carriage of all materials to site from contractor’s stores and checking and punching and tack welding of bolts on the towers complete in all respect. For erection of the extension pieces of special towers, whenever necessary, payment will be made on Metric ton basis as per rate quoted for erection of towers and no additional rate over the unit price bid for erection of tower will be allowed for the above purpose. Measurement for payment of erecting the various types of steel towers will be made on the basis of weights computed by DVC and calculated in accordance with the bill of materials with variation sheets, if any. Final payments shall become due only after complete erection of tower and proper punching and tack welding.

K GROUNDING OF TOWERS:

At all locations the tower shall have to be grounded to bring down the lower footing resistance to 10 ohm and below. Measurement of the tower footing resistance as per directive of the engineer has to be done by the contractor at his own cost. Such measurement has to be done in dry weather in presence of the engineer or his representative before the stringing of earth wire. The two stubs which are in diagonally opposite direction are to be earthed. The earthing shall be done by G.I. Pipe connected with stub through GI flats and as per drawing supplied by the purchaser and as per instruction of the Engineer. One set of pipe earthing consists of 2 nos. of GI pipe and 50 x 6 mm GI flats. Where grounding of tower by GI pipe is not possible or the desired level of tower footing resistance not obtained the counter-poise earthing at the discretion of the site engineer should be done. The counterpoise earthing shall consist of four numbers 50 x 6 mm galvanised iron strip 30 M in length connected at four legs and buried radially at least at 600 mm depth below ground. In case counter poise earthing is required for 2 legs only that will be considered as half set. Similarly grounding of tower at one leg for pipe type earthing shall be treated as ½ (half) set.

Page 23: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

23

The contractor should submit statement mentioning the date of measurement

of tower footing resistance and tower footing resistance value and details of grounding adopted for each location.

K.01 PAYMENTS: Payments for grounding including excavation or backfilling of tower shall be made on per set basis. One set shall mean complete grounding of one tower at two legs for pipe type earthing and at four legs for counterpoise earthing. If more than one set of grounding is required for any tower, then payment for the additional set will be made at the rate quoted by the contractor. Pipe type earthing and counterpoise earthing shall be done as per IS-3040-1966 and IS-5613 (Part-II/Sec-2) 1976.

L. INSULATOR HOISTING AND POWER AND EARTH CONDUCTOR ERECTION INCLUDING FIXING OF TOWER ACCESSORIES: Work involves:

1) Hoisting of insulators and fixing on the towers and erection of hardware sets.

2) Jointing of conductors. 3) Running out (also called paying out) and stringing (pulling up) of

conductor. 4) Tensioning, sagging as per approved sag-tension (stringing) chart and

clipping in of the conductors (pulling up to proper tension, transferring of conductor to insulators).

5) Fixing of vibration dampers preformed armour rod and other tower

accessories. Viz. Number plate, Danger notice plate, Phase plate, Circuit plate, Bird Guard, Anticlimbing devices and step bolts etc.

6) Erection of jumpers at the section and angle towers and hoisting and

fixing of suspension insulator strings to restrict jumper swing.

Page 24: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

24

The contractor shall be entirely responsible for any damage to tower,

conductor or its accessories during wiring of lines. He shall also be responsible for proper distribution of the conductor drums to keep the number and lengths of cut pieces of conductor to a minimum. The following further precautions shall be observed.

a) There shall be not be any joint in conductor in Railway crossing,

main road crossing, power line crossing and river crossing.

b) No joints shall be less than 30 M away from adjacent towers.

c) There shall not be more than one joint in a span on each conductor.

d) Requisite and adequate precautionary measures are to be taken

while stringing & sagging power line, road, across Railway & other important crossing.

Rate of stringing & sagging of power conductor & earth wire quoted

against specific item of erection schedule of works should cover crossing of the power line, Railway line, small river, road etc. if any falling along the transmission line. For big river crossing separate rate for stringing the span between Anchor tower to Anchor tower as indicated may be quoted.

Requisite and adequate precautionary measures shall be taken

while stringing and sagging over power line, road, Railway and other important crossings.

L.01 HOISTING OF INSULATORS & FIXING ON THE TOWERS & ERECTION OF HARDWARE SETS:

The insulator string shall include shackles, yokes, clevises, dead end fittings, strain and suspension clamps etc. associated with fittings, except where otherwise specified. Single suspension insulator set of 09 nos disc shall be used in tangent location, single strain insulator set of 10 nos disc shall be used in angle location. For main road crossing, power line crossing etc. double insulator set of 2 x 09 disc (suspension) at tangent location and 2 x 10 disc (strain) at angle location shall be used. For Railway crossing 2 x 10 disc for suspension and 2 x 11 disc for tension point shall be used and latest Railway Regulation should be followed.

Insulator string shall be assembled on ground. These shall be cleaned

and examined before hoisting. All accessories shall be properly fitted

Page 25: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

25

according to approved drawing. It shall be ensured that all current carrying parts smooth and without dirt, grit, cuts, abrasions, projections etc. Insulators with hair cracks or chips or those having glazing defects exceeding half centimeter square will not be used. Security clips shall be in position for insulators before hoisting. Care should be taken that ‘W’ spring/security clips are in current position & all splits pins are opened.

L.02 JOINTING OF CONDUCTOR:

Jointing of conductor shall be done by splicing sleeves of compression type. All mid span joints or splices of conductor or earthwire which are subjected to the tension shall be of tension type and joints or splices of conductor used for jumper connection shall be of non-tension type. Both of the splices shall be in accordance with the recommendation of manufacturer. The contractor shall arrange the required compression jointing machine and dies and other necessary tools. Each part of the joints shall be cleaned by wire brush to make it free from rust or dirt etc. and proper non-oxide compound shall be placed before final compression is done with compressors. Jointing shall be to the satisfaction of the Engineer.

The contractor shall be entirely responsible for the proper handling of

conductor, earthwire and accessories in the Site. Handling and transporting of conductor and accessories shall be carried out in such a manner so to minimise the possibility of damage from abrasion, through rough handling or dirt and grit getting into reel and on the conductor causing injury to conductor etc. Particular care shall be taken at all time to ensure that conductors do not become kinked, twisted or abraded, bird caged in any manner.

If the conductor during operation got damaged, compression type

repair sleeves shall be used with the approval of the Engineer or his representative to repair minor damage to the conductor provided that

a) At the location on the damage on the conductor to be repaired

nor more than 1 or 2 or the aluminum strand are damaged over a length of not more than 102 mm.

b) Not more than 2 Aluminum strands in the outer layer are

broken and cross sectional area of any other of the damaged Aluminum strands is not reduced by more than 25 percent. All joints or splices or repair sleeves shall be made at least 30 meters away from the structure. No joints or splices shall be made in span crossing over main roads, Railway, river. Nor more than one joints or repair sleeve shall be allowed in one span per conductor.

Page 26: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

26

L.03 RUNNING OUT (PAYING OUT) & STRINGING (PULLING UP) OF CONDUCTOR:

The reels on which the conductors are wound are to be raised from

ground so that they are free to rotate. The conductors are then to be pulled out. Care must taken by the contractor to avoid any damage to the conductor which are prone to become scratched. The conductor must be prevented from ‘paying’ too fast and becoming tangled. Suitable methods, proper scaffolding are to be adopted by the contractor for crossing obstructions or roads or existing power or Telephone line. Turn table may also be used depending on suitability of work for running out of conductor.

As the conductors are reeled out they are to be hoisted up to the cross arms level and pass through the travellers comprising of aerial rollers and ground rollers. The travellers shall have a size and shape most suitable for the type of stringing and size of conductor involved and as recommended by the conductor manufacturer and DVC. The travellers contact surface with conductor shall be coated with such materials e.g. neoprene rubber that conductor is not damaged during pulling up operation. These rollers shall be equipped with high quality ball or roller bearing for minimum friction. Proper approval regarding the travellers shall have to be obtained from the representative of the purchaser.

The aerial rollers shall be hung from cross arm of the tower by means of requisite wire rope slinging such a way that the conductor on the traveller will be at the same height as the suspension clamp to which it will be secured after final adjustment of tension. Sacking is to be wrapped over the steel work and under sling to avoid damage to the sling as well as to the protective surface finish of the steel work.

The pulling up of conductor through traveller shall be carried out in such a manner so that conductor is not damaged or contaminated with foreign substance and that it may not be rubbed with rough ground surface.

During pulling up operation the tension in each conductor and earthwire shall not exceed the design working tension of the conductor at the actual prevailing temperature. After being pulled the conductor & earthwire shall not be allowed to hang in the straining blocks for more than 96 hrs. Care should be taken in pulling up so that splices/joints and sleeves do not catch on cross arms or in the sleeves of travellers. Any catch of this sort may prevent the conductor from coming slip, as it should. Normally the joining of conductor shall be so made so that the joints are not required to pass through aerial roller.

Page 27: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

27

L.04 TENSIONING, SAGGING & CLIPPING IN OF THE CONDUCTOR:

The conductor and earthwire shall be sagged in accordance with erection sag tension chart supplied by the purchaser and as per instruction of the Engineer before they are finally attached to the tower through the earthwire clamps for earth wire and insulators strings and clamps for AAAC conductor.

The sag shall be checked in the span which is nearly equal to the equivalent span of the stringing section. The contractor shall be responsible for any damage caused to towers or to the conductor through over stressing during stringing dynamometer and sag boards shall be used to measure tension and sag. The results are to be checked from the sag tension chart. Dynamometer shall be periodically checked with standard Dynamometer. The sag also to be checked when the conductor have been drawn up and transferred from travellers to the insulator clamps. The conductor shall be clamped within 36 hours or sagging in.

Sagging in operation shall not be carried out under wind, extremely low temperature or other adverse weather condition, which prevent satisfactory sagging. It should be carried out in the calm weather and when rapid changes in temperature are not likely to occur.

All conductors shall be temporarily earthed in an effective manner at every section point. Such temporary earth shall be removed after stringing of the entire line is over and before testing and commissioning of the line.

L.05 FIXING OF VIBRATION DAMPER AND OTHER ACCESSORIES:

Vibration dampers and/or armour rods for conductors shall also be

fitted according to the recommendation of the manufacturers and advised by the purchaser. Anti climbing devices shall be fitted on towers at a height approved by the Engineer. Danger plate & number plate etc shall have to be fitted on all locations and phase marking to be provided. The step bolts shall be provided on legs of tower and from height above ground level as specified by the Engineer. Fasteners on all fittings, tower, insulators and conductor accessories shall be secured in position, the security slips also properly opened and sprung into position.

Page 28: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

28

L.06 ERECTION OF JUMPERS AND SUSPENSION INSULATORS TO RESTRICT JUMPER SWING:

The jumper at the section & angle tower shall be erected as advised

by the Engineer. These shall be formed to parabolic shape to ensure minimum clearance requirements. Non-tension joints are to be made with the dead end tension clamps to ensure continuity of the line as directed by the Engineer or his authorised representative.

L.07 PAYMENTS:

Payments for the complete stringing work with 6 (six) Nos. AAAC conductor shall be made on per KM basis separately. Complete stringing works include all the above work and also the fitting of accessories as directed by the purchaser. The contractor shall quote separate rates for stringing of 6 Nos. AAAC conductor and 1 (one) No. earth wire each as two separate items on per KM basis. The rate shall be inclusive of handling, storage and carriage of all materials required for the purpose from contractors stores to work site.

M. FINAL CHECKING, TESTING & COMMISSIONING

After completion of the erection of line final checking shall be made by the contractor at his own cost with the representative of the purchaser and shall ensure that all the foundation work, tower erection and stringing has been done strictly according to the specifications given herein and as per IS & Electricity Act and rules. All works shall be thoroughly inspected keeping in view the following main points.

1) Finishing of coping with proper grading.

2) Sufficient back filling with proper grading.

3) Verticality of erected tower.

4) Proper placing, tightening and punching of bolt.

5) Normal position of the insulator string and clearance of conductor

from tower body.

6) Proper sag and tension of the conductor with proper ground clearance as per specification.

Page 29: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

29

7) No damage minor or major to the conductor earth wires, accessories and insulator string remain unattended. After final checking the line shall be tested for insulation in accordance with test prescribed by the purchaser and as per I.S. All arrangements for such testing shall be done by the contractor and necessary labor. Transport and equipment shall be provided by him at his own cost. Any defects found out as a result of such test, shall be rectified by the contractor forthwith without any extra charges to DVC. In addition to the above, the contractor shall be responsible for testing that the total and relative sags of the conductor and earth wires are within the specified tolerances. Such tests shall be carried out at selected points along the route as required by the Engineer and the contractor shall provide all necessary equipment and labour to enable the test to be carried out. After satisfactory tests on the line and on approval by the Engineer in writing. The line shall be energised at full operating voltages before handling over.

N. COLLECTION OF MATERIALS:

Materials will be supplied by the contractor at their own stores at site. Materials will be issued to the contractor by the purchaser for the execution of work either by paper transaction at contractor’s site stores for the materials under their scope of supply or from DVC’s departmental stores at Maithon/ Dhanbad/any other specified store. The cost involved in handling and transporting of stores and storing the materials and carriage of all materials to actual erection site and land/sheds for site storing of the materials by the successful tenderer shall be arranged at his own cost. The site stores shall be got approved by the purchaser before storing of the materials. The erection rate should also include the cost of security arrangement of the materials and tools and plants issued by DVC. The materials to be supplied and issued to the contractor in phased manner in conformity with the progress of erection work. The supply schedule would be fixed up by mutual agreement with the successful bidder after issuance of LOA.

O. SECURITY AGAINST MATERIALS TO BE SUPPLIED BY DVC:

For proper and safe custody of the line materials the contractor shall execute an indemnity bond for the total value of the materials supplied by DVC in approved proforma (enclosed in the specification) to the effect that in the event of loss and damages etc. during transit or from the site stores and erected line after the issuance of materials till the return of unutilized materials and handing over the line to DVC, the contractor shall indemnify DVC. The contractor shall execute the Indemnity Bond 15 days before drawal of materials from DVC.

Page 30: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

30

In the event of the theft/pilferage the contractor should immediately inform the matter to the law & order Authorities/District Administration and take further necessary action.

P. MATERIALS TO BE SUPPLIED BY THE CONTRACTOR:

The contractor shall supply all the materials such as cement, sand,

stone chips, gravels, non-oxide compound, M.S. rod, G.I. binding wire of 18 SWG etc which are not covered under supply schedule. The cost of these materials including transportation to site shall be included in the erection rate. The materials to be supplied by the contractor shall be approved by the site Engineer before use.

Q. RETURN OF MATERIALS:

All materials drawn by the contractor & supplied by DVC in excess

of those actually used shall be returned by him at his own cost to the purchaser’s stores at Maithon/ Dhanbad/any other specified store as per instruction of site Engineer.

Return of all the items as stated above shall be made within one month from the date of completion of particular work for which the materials were issued. For non-return of the same the purchaser shall realize the cost in full from the contractor at rates indicated in the schedule apart from taking any other action as per settled terms and conditions of contract.

R. APPROVAL FROM RESPECTIVE AUTHORITIES:

The contractor shall at his cost furnish well in advance before starting

erection of the line all necessary details and drawings as required for obtaining approval from P&T Department / Rly. & other utility or civil authorities etc. All these approval are to be liaisoned & to be arranged by the contractor.

S. MEASUREMENT OF WORK DONE:

Within 4 days from the date of completion of each item of work at

each location, measurement should be taken in the presence of the contractor whose signature should be obtained in the M.Bs as a token of his acceptance of the measurement. If the contractor fails to be present on the date of measurement as specified by the Engineer or the authorized representative, measurement taken by the purchaser shall be final and binding on the contractor, unless specific written objections thereto are filed with the Engineer within three days form the date of measurement.

Page 31: Overhead Transmission Line Survey & Erection

DVC, Electricity Dept., Spec. No. EDCON/EHV/L-39

31

T. TECHNICAL PARTICULARS:

Some essential particulars regarding the 132 kV D/C transmission line are given in Annexure –A for guidance.

U. COMPLETION OF DRAWINGS (AS EXCUTED):

On satisfactory completion of the work the contractor will supply to the Engineer free of cost “As executed” route profile of the line (one on good quality reproducible & ten copies of prints) showing therein the actual position and type of towers, double insulator points, forest, Rly, River, Telecom & Power lines, road crossing together with measured span on a scale of 25 meter to 1 cm horizontal and 2.5 meter to 1cm.vertical.