February 17, 2016
Oversight Committee
![Page 2: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/2.jpg)
AGENDA
As required, please be advised that a copy of the rules of the Open Meeting Act as amended by LB898 is located in the folder on the north wall of Jesse Lowe Conference Room and assistance will be provided for anyone needing help.
● Call to Order - Deb Sander
● Approval of Minutes from the January 20, 2016 Oversight Meeting - Deb Sander
● Standing Business
○ IT Service Management - Julie Stangl
○ Projects - Tracy Svevad
○ Capital Improvement Plan - Bob Nord
○ Operations - Bob Nord
○ Applications - Tom Olson/Vijay Badal
○ Security - Greg Andersen
○ Financials - Tracy Svevad
○ Organization - Derek Kruse
○ Innovation Topic - Investment Updates (SQL and SCCM)
● New Business
● Public Comments
● Next Regular Meeting - April 20, 2016 at 2:30-4:00 in Jesse Lowe Conference Room, Civic Center - No March Meeting
● Adjournment
● Executive Session (as needed) for the purpose of discussing personnel and legal issues in conformance with Nebraska Rev. Stat. 84-1410(d)
February 17, 2016
![Page 3: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/3.jpg)
IT Service Management(Julie Stangl)
![Page 4: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/4.jpg)
February 17, 2016
2016 Hours by Category
DOTComm began tracking all hours in January.
![Page 5: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/5.jpg)
The breakout of Incidents and Service Requests between the City and County was 44% / 56%
Direct Support Hours Allocation
City - 44%
County - 56%
* vs. the 2015 cost model split of 46% City / 54% County
![Page 6: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/6.jpg)
February 17, 2016
Projects Update
The project bucket hour forecast for 2016 uses the 2015 cost model for allocation between the City, County and Shared Services
33,698
![Page 7: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/7.jpg)
Projects Update
County Shared City
2016 Total Bucket Hours: 9,302 11,865 12,531
YTD Bucket Hour Actuals: 787 736 786
% Bucket Hour Actuals: 8% 6% 7%
Project Bucket Hour Summary by Portfolio January 2016
![Page 8: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/8.jpg)
February 17, 2016
Projects Update
Project Bucket Hour Summary by Portfolio 2015 Actual Hours Used
County = 25 Projects
GTL = 315 BOE = 81 Sheriff Records Mgmt System = 64 ROD Land Book Records = 57
Enterprise = 17 Projects AWS Migration = 381 Oracle OBIEE Reporting = 144 Filebound 7 upgrade = 61 CMS NE eFiling = 51
City = 24 Projects Finance Budget Web App = 146 Planning EPA Superfund = 128 Fire ePCR= 81
2,309 (7%)
![Page 9: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/9.jpg)
Total Direct Support Hours Allocation
City - 47%
County - 53%
* vs. the 2015 cost model split of 46% City / 54% County
![Page 10: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/10.jpg)
Projects(Tracy Svevad)
![Page 11: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/11.jpg)
February 17, 2016
Project Status
Total City CountyEnterprise / DOTComm
Feb Jan Feb Jan Feb Jan Feb Jan
Active 70 66 23 19 27 25 20 22
Pending(1) 39 30 10 6 22 18 7 6
Estimation 39 30 13 13 15 12 11(2) 5
Total 148 126 46 38 62 55 38 33
New Project Requests
25 2 8 1 8 1 9(2) 0
(1) Pending = Pending Initiation which is generally due to resource constraints (excludes Pending Request)(2) Includes 7 Windows 2003 Upgrade Sub-Projects
Projects - Summary
![Page 12: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/12.jpg)
February 17, 2016
Projects - Closed Project Metrics
● What data is being evaluated?○ Hours: planned vs. actual○ Schedule: planned vs. actual○ Included in “planned” are Project Change Requests
● Projects - Closed projects from Sept. to January○ Exceptions: 2 large, multi-year projects were not graphed due
to extreme variances (both missed on schedule)■ ENT-Managed Print Services■ ENT-Microsoft WinXP Upgrade
● Current Chart - Nothing but the Facts (not good, not bad)
● What will we gain from reporting this information?○ Increased focus by PMs to report issues quickly○ Improve estimating capabilities for hours and schedules○ Improve start date planning for new projects
![Page 13: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/13.jpg)
February 17, 2016
Projects - Closed Project Metrics
![Page 14: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/14.jpg)
February 17, 2016
Projects Update - Enterprise PortfolioActive Phase Highlights Status
2017 Service Cost Model & Reports
Closing Project acceptance document signed and project closed.
Amazon Web Migration Executing & Controlling
City Landmark was completed and moved to production. Crime Stoppers and DC Treasurer continue on-schedule. EPA Superfund data was moved as additional scope was identified.
Oracle US Bank Integration Executing & Controlling
Production issue found in early February but fix has been applied. Customer continues to test.
Oracle OBIEE Reporting Executing & Controlling
Two tasks remain. Once completed (in February), project will be closed.
SQL/Infrastructure Upgrade Executing & Controlling
Planning continues to get a full schedule. City HCM/Payroll (SQL and Win2003 upgrade) moved from “hold” and is now active. Also active is the upgrade to the Synergy Datamart.
Filebound Upgrade to v7 Executing & Controlling
Project plan signed and approved. Test environment is in progress. Customer interviews are completed. Discussions regarding interfaces is in progress.
![Page 15: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/15.jpg)
February 17, 2016
Amazon Web Migration (2015-2018)Project Manager: Bavitha Govindarajulu
![Page 16: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/16.jpg)
CIP Project Updates - SQL UpgradeProject Manager: Kelly Gray
No ChangeNo Change
No Change
![Page 17: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/17.jpg)
CIP Project Updates - Cox Fiber Upgrades
Sites Completed Last Month0
![Page 18: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/18.jpg)
February 17, 2016
Projects Update - Douglas County PortfolioActive Phase Highlights Status
GTL Implementation Executing & Controlling
Reviewed schedule with Corrections management and GTL key personnel. Training plan is in process with tentative go-live scheduled for August 2016.
ECM - Land Book Scan & Store
Executing & Controlling
Continuing to work on “Lands” data and images for premium services. Working through duplicate image issue.
Health Data Website Phase 2 (DCHD)
Executing & Controlling
2nd demo was completed. Project meeting customer expectations, but additional testing is in progress.
DCHC-EHR - MSite Connectivity
Executing & Controlling
Dell changed circuit vendor to Cox. Cox delivered a circuit that did not meet customer requirement. Working with vendor to meet customer requirements.
DCTres - Rebuild Website Executing & Controlling
Customer requirements have been added to the website. Work is progressing on the JAVA applications.
DCSO-Records Mgmt Planning Action plan is in process which will allow for completion of the overall project plan and schedule. Initial draft of plan and schedule is due Feb.12th.
DCROD-Landmark Implementation
Planning Significant planning has been completed in advance of vendor discovery sessions scheduled for early March. Project charter and plan are in progress.
DC Env Services - VOIP Implementation
Planning Charter signed and approved. Project plan provided to customer for review and signature. Once plan is signed, chargebacks will be completed.
Additional Active Projects Various Phases
Includes several year-end projects, DCCDC Support Scanning, BOE 2015, JailTV, ACA Reporting, 2016 Open Enrollment, and HD File Server Replacement.
![Page 19: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/19.jpg)
February 17, 2016
Projects Update - City of Omaha PortfolioActive Phase Highlights Status
CIOFD-Electronic Patient Care Reporting
Closing Lessons learned with customer completed on 2/11/16. Closing/acceptance documents provided to customer for signature.
CIPW - VoIP Street Maint & Construction
Closing Project completed and all closing documents signed.
CIHR&R CC1 Online Form Submission
Executing & Controlling
Project has a technical issue that is being worked by staff and vendors. The issue is critical to go-live and impacts the SEB enhancement project.
New Status
CIHR&R-SEB Enhance Executing & Controlling
Initial customer testing completed. Issues being worked with database. Project is dependent on the CC1 project.
CIFIN Oracle Encumbrances
Executing & Controlling
Final report validation is in progress.
CIOPD - Data Processing Costs
Executing & Controlling
Final review meeting scheduled for 1/13/16.
CIFIN - Oracle AR Interface for Leases
Executing & Controlling
Final data validation and data clean-up is in progress.
CIPR - VoIP Park Maint. and Facilities
Executing & Controlling
Project plan completed with final schedule in discussion with vendor. Chargebacks signed and equipment order is in process.
CIOPD - Video Storage Planning Charter is signed and approved. Project plan is in progress. Equipment has been received and implementation is in progress.
![Page 20: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/20.jpg)
Capital Improvement ProjectsUpdate(Bob Nord)
![Page 21: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/21.jpg)
Capital Improvement Plan 2016/2017/2018
● Working to bring forth a three year capital plan○ Align with cost model budgeting cycles going forward○ Socialize 2016 needs in February
● Segmenting into priorities ○ Mandatory
■ Required to maintain operational stability; End of Life/Support replacement; Exceeded current hardware/software capacity
○ High■ Recommended to maintain operation performance;
approaching capacity or performance limitations within the year
○ Medium■ Not required in current year; approaching capacity or
performance limitations anticipated based on use trends ○ Low
■ Not required or will be proposed through individual business case; projected need in three years
![Page 22: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/22.jpg)
February 17, 2016
Operations Update(Bob Nord)
![Page 23: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/23.jpg)
Tech Center Hosting
Total Invoiceable: 7
Reciprocal Services:● Communication line to Lincoln● Hosting two cabinets in Lincoln
Operations Service Update
Storage ● Data backup devices have been moved
into the OCIO Lincoln Data Center○ Connected to the OCIO DC via a 10G
fiber link
MF Operations● Obsolete HW and Eliminate Physical Tape
○ Salvage old○ Use new shared services storage
● Move Shared Services Backups to Lincoln○ Test backup recovery annually
● Working Towards $0 Capital Outlay○ Targeting February for Extension
● Test MF backup recovery annually
![Page 24: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/24.jpg)
February 17, 2016
Mainframe Update
![Page 25: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/25.jpg)
February 17, 2016
![Page 26: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/26.jpg)
February 17, 2016
![Page 27: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/27.jpg)
February 17, 2016
IT Service Management Update
Incidentand
Service RequestSLAs
![Page 28: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/28.jpg)
Operations Service Update
January Priority 2Service Outages
Ticket Summary
➢ 156354 OPD NW Prec - Server Drive Failure
➢ 156622 OFD #21 - Cox Area Outage
➢ 156768 Main Library - Power Failure
![Page 29: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/29.jpg)
February 17, 2016
Incident Resolution Time
![Page 30: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/30.jpg)
February 17, 2016
Service Request Resolution Time
![Page 31: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/31.jpg)
February 17, 2016
January Ticket Summary - P3
![Page 32: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/32.jpg)
February 17, 2016
January Ticket Summary - P4
![Page 33: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/33.jpg)
February 17, 2016
January Ticket Summary - P5
![Page 34: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/34.jpg)
Tech Support Statistics and Customer Satisfaction Survey
Results
IT Service Management Update
![Page 35: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/35.jpg)
February 17, 2016
Tech Support Call Statistics
January
Average Speed of Answer 17 Seconds
Average Call Duration 5:37 (Min:Sec)
![Page 36: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/36.jpg)
February 17, 2016
Tech Support Call Statistics
Weekdays Monday 6PM - Friday 6AM
Calls Accepted
Calls Answered
Abandoned Calls
Longest Wait Time in Queue
Avg Duration of Calls
Longest Call
Avg Hold Time
121 119 2 8:23 4:39 3:48 1:58
Weekends Friday 6PM - Monday 6AM
Calls Accepted
Calls Answered
Abandoned Calls
Longest Wait Time in Queue
Avg Duration of Calls
Longest Call
Avg Hold Time
52 49 3 8:23 12:04 51:49 4:52
Extended Hours - January
![Page 37: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/37.jpg)
February 17, 2016
Customer Satisfaction Survey Results
January
Incident Survey Response Rate at 24.3%
Service Request Survey Response Rate at 26.4%
Industry Survey Response Rate 26.8%
![Page 38: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/38.jpg)
February 17, 2016
Applications Update(Vijay Badal / Tom Olson)
![Page 39: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/39.jpg)
February 17, 2016
No Update This Month
![Page 40: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/40.jpg)
February 17, 2016
IT Security
(Greg Andersen)
![Page 41: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/41.jpg)
February 17, 2016
PCI Compliance - Changes in obligations
Synopsis: The way some of our departments accept credit cards has changed. DOTComm is assisting finance staff by interpreting the IT requirements, working with vendors, outlining any compensating controls (risk mitigation), and drafting up a few long-term solutions.
How things were last year:
IT Security Program Update - PCI Compliance
![Page 42: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/42.jpg)
February 17, 2016
After -
Plan of Attack:1. Gather full inventory of products and processes used2. Work with vendors to make sure products are correct for our use3. Look at the PCI Self-Assessment Questionnaire Part D requirements, look for a
few different solutions to bring forward for City and County4. Work with finance and merchant departments to maintain compliance, select
products based on compliance needs
IT Security Program Update - PCI Compliance
![Page 43: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/43.jpg)
February 17, 2016
Metrics
IT Security Program Update
![Page 44: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/44.jpg)
February 17, 2016
Financials(Tracy Svevad)
![Page 45: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/45.jpg)
Financials - Operating Income Statement
![Page 46: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/46.jpg)
Financials - Funds Restricted for Capital
![Page 47: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/47.jpg)
Financials - Outstanding Receivables
.
![Page 48: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/48.jpg)
Financials - Cash Projections
![Page 49: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/49.jpg)
Financials - Chargebacks 2016 (as of 02/10/2016)
![Page 50: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/50.jpg)
Organizational Update
(Derek Kruse)
![Page 51: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/51.jpg)
I
Innovation TopicInvestment Update
SQL & SCCM
![Page 52: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/52.jpg)
SQL Upgrade Performance Improvement
![Page 53: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/53.jpg)
SQL Upgrade Performance Improvement
![Page 54: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/54.jpg)
SCCM Update
● Lower security risk due to consistent updates and patching of desktop, laptop, tablet○ Currently deployed to 3,863 clients
■ Outliers: OPD/Fire Mobile units, 911, Sheriff, Treasurer○ Devices receiving updates for Windows, Adobe Flash, Adobe Reader, and
Google Chrome.■ The deployment/update compliance is between 92% and 98%.
● Adobe Flash - 96% compliance● Adobe Reader - 92% compliance● Chrome - 98% compliance● Windows Updates - 92-95% compliance ● Java and Firefox - 98% compliance for both.
● Reduced deployment of new device images○ It now takes approximately 1 hour from start to finish for a new PC○ Currently testing a method to image an existing PC that will keep the user
profiles intact● Remote administration of device issues reducing resolution times
![Page 55: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/55.jpg)
Schedule Reminder
![Page 56: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/56.jpg)
New Business
![Page 57: Oversight Committee · Oracle OBIEE Reporting Executing & Controlling Two tasks remain. Once completed (in February), project will be closed. SQL/Infrastructure Upgrade Executing](https://reader034.vdocuments.net/reader034/viewer/2022042215/5ebb955c4bf4375c8d0e568e/html5/thumbnails/57.jpg)
▪ PUBLIC COMMENTS
▪ NEXT MEETING: April 20, 2016 @ 2:30 p.m. in Jesse Lowe Conference Room (No March Meeting)
▪ ADJOURN (to Executive Session as needed)