Page 1: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

OVERVIEW : MITCHELLS PLAIN HOSPITAL

Page 2: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

A state of the art 270 bedded hospital

Page 3: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Executive Summary

The new 270 bedded hospital will provide district hospital and general specialist services and support to the primary health care platform within the Mitchells Plain sub-district.

Patients requiring higher level specialist and sub-specialist care will be referred to Groote Schuur Hospital and Red Cross Hospital.

G F Jooste Hospital (located in the Klipfontein sub-district), will be rebuilt on the same site between 2014 and 2017.

Some emergency services will be rendered at the Heideveld CDC, in order to retain access to care for patients living in the Klipfontein sub-district.

A new 30 bedded 72 hour observation ward will be build on the MPH site and will open in March 2014

Mitchells Plain Hospital Commissioning Brief 3

Page 4: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Overview

Mitchells Plain Hospital Commissioning Brief 4

1. Introduction

2. Current Status of Project

3. “Go Live”

3.1 Phase 1: 15 June 2012 – 31January 2013

3.2 Phase 2: 31 January 2013 - 30 April 2013

3.3 Phase 3: 30 April 2013 – 31 May 2013

3.4 Phase 4: 31 May 2013 – 15 November 2013

4. EC with 30 overnight beds at Heideveld CDC: May

2013 – March 2014

5. 30 bedded 72 hour observation ward: May 2013 -

March 2014

Page 5: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

“Go Live”

5Mitchells Plain Hospital Commissioning Brief

Mitchells Plain Hospital to be commissioned in 4 phases

Page 6: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 1: Completion and hand-over of building

6Mitchells Plain Hospital Commissioning Brief

Marker

Staff

Ambulance

Service delivery

Pharmacydelivery

Public Parking

Public transport drop off area

VisitorsVehicles

Towards AZ Berman

NORTH

Staff parking area

Page 7: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 1 Continued�������������������A��B�CD�E���F�����FA���F���A������������������E�

7Mitchells Plain Hospital Commissioning Brief

Key Deliverables: Delivery Date: Key Activity:

Practical Completion 18 February 2013 Contractor hands over the main building.

Handover of keys to the Department of

Health.

Award Security , Catering

and Cleaning Tender

April – May 2013 Security Company on site.

SLA to employ local Employment

Appointment of staff May 2013 –

October 2013

Phased approach.

Communication On-going Formally signed off departmental

communication strategy.

Hospital Board May-June 2013 Appointment of hospital facility board by

MEC office

Page 8: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 2: Installation of equipment and provisioning of supplies

8Mitchells Plain Hospital Commissioning Brief

Marker

Staff

Ambulance

Service delivery

Pharmacydelivery

Public Parking

Public transport drop off area

VisitorsVehicles

Towards AZ Berman

NORTH

Staff parking area

Page 9: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 | 9Mitchells Plain Hospital Commissioning Brief

Key Deliverables: Delivery Date:

Utility Services 18 February 2013

Works Completion 31 May 2013

Finance, SCM, HRM and Registry 31 May 2013

Linen and Laundry 31 May 2013

Award Non Core Service Tenders 30 April 2013

End User SOP’s and documentation 31 May 2013

End user equipment 31 May 2013

End user consumables 30 April 2013

Pharmacy Store 30 April 2013

PACS/RIS, ECM, HIS 31 May 2013

AB�C��D�E�F�����������D�F��� ��������D�F�

�����������E�������������B�C������� !��"����������

C���������"��C�� �������C�������C�����C��

Page 10: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 3: Initiating patient care activities

10Mitchells Plain Hospital Commissioning Brief

Marker

Staff

Ambulance

Service delivery

Pharmacydelivery

Public Parking

Public transport drop off area

Visitors

Vehicles

Towards AZ Berman

NORTH

Staff parking area

Page 11: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 3 July – November 2013Key activity: Phased activation of clinical/ancillary services

11Mitchells Plain Hospital Commissioning Brief

Key Deliverables: Delivery Date:

Transitional management plan for the hub and

hospital

1 July 2013

Patient Registration and Switchboard 1 July 2013

Drainage mapping and shifts 1 July 2013

“Medical Service Cluster” 1 July 2013

Community Based Services 1 July 2013

EMS 1 July 2013

CSSD 1 July 2013

NHLS and Bloodbank 1 July 2013

PAM’s 1 July 2013

Pharmacy Service 1 July 2013

“Women and Child Health Service Cluster” 15 November 2013

“Surgical Service Cluster” 1 October 2013

Quality On-going

Page 12: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 4: De-commission services at GF Jooste

12Mitchells Plain Hospital Commissioning Brief

Marker

Staff

Ambulance

Service delivery

Pharmacydelivery

Public Parking

Public transport drop off area

Visitors

Vehicles

Towards AZ Berman

NORTH

Staff parking area

Page 13: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Phase 4: Key timelines

13Mitchells Plain Hospital Commissioning Brief

Key Deliverables: Delivery Date:

Admin and support services move to MPH Mid June 2013

First patients from MP Hub move to MPH 1 July 2013

Open EC Services at MPH 1 October

Move patients from GJ Jooste 1 October 2013

Open paediatric, obstetrics and gynaecology

services

1 November 2013

Open EC in Klipfontein 1 March 2014

Open 72 hour observation ward at MPH April 2014

Page 14: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Mitchell’s Plain Hospital – Eastern View

Page 15: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Mitchell’s Plain Hospital – Mosaic

Page 16: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Mitchell’s Plain Hospital – Nurse Station

Page 17: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

© Western Cape Government

2012 |

Mitchell’s Plain Hospital – Staff Entrance

Page 18: OVERVIEW : MITCHELLS PLAIN HOSPITAL Plain000.pdf · Phase 3 July – November 2013 Key activity: Phased activation of clinical/ancillary services Mitchells Plain Hospital Commissioning

Thank you