    Jacket Installation Methods –  Oil & Gas Trainings

    by Dr. Tofiqu Zaveri

    www.globalenergypanel.com

  • 8/17/2019 Overview of Jacket Installations

    2/20

    JACKET INSTALLATION

    • JACKET INSTALLATION

     – Vertical lift and set down

     – Two block upend in air/ water

     – launch

     – Lift and upend in water

  • 8/17/2019 Overview of Jacket Installations

    3/20

    Vertical lift and set down

    •Offshore time saving

  • 8/17/2019 Overview of Jacket Installations

    4/20

    Vertical lift and set down

  • 8/17/2019 Overview of Jacket Installations

    5/20

    Vertical lift and set down

  • 8/17/2019 Overview of Jacket Installations

    6/20

    Two Block upend in air/ water

  • 8/17/2019 Overview of Jacket Installations

    7/20

    Two Block upend in air/ water

  • 8/17/2019 Overview of Jacket Installations

    8/20

    Launch

    •Connected to the stern anchors of the DB

    •Pre rigged with the upending slings

  • 8/17/2019 Overview of Jacket Installations

    9/20

    Lift and upend

    Load out• Transport

    • Barge Alongside

    • Rig the main Block for Horizontal Lift

    • Cut Sea Fastening

    • Lift the jacket and move the material barge

    • Lower jacket to water

    • Rotate the jacket 

    • Rig the main block to upending slings

    • Upend the jacket and set down• Piling

  • 8/17/2019 Overview of Jacket Installations

    10/20

    Load out

    •Horizontal loadout

    Strand jack pull with crane assistance

  • 8/17/2019 Overview of Jacket Installations

    11/20

    Transportation

    •Tow Analysis: barge motion, transportation force, tug

    pull , sea fastening analysis

  • 8/17/2019 Overview of Jacket Installations

    12/20

    Barge Alongside

  • 8/17/2019 Overview of Jacket Installations

    13/20

    Rig Main Block

    •Rigging analysis

  • 8/17/2019 Overview of Jacket Installations

    14/20

    Cut Sea-Fastening

  • 8/17/2019 Overview of Jacket Installations

    15/20

    Lift Jacket and Move Material barge

  • 8/17/2019 Overview of Jacket Installations

    16/20

    Lower Jacket into Water

    •Buoyant ( Closure plate welded at the top and diaphragm at the bottom)

  • 8/17/2019 Overview of Jacket Installations

    17/20

    Rotate the Jacket

    •Rotate with tuggers, minimum clearance frm DB

  • 8/17/2019 Overview of Jacket Installations

    18/20

    Rig Main/ auxiliary block to Upending Slings

    Riggers transferred to jacket( boat/ man riding basket)•Main block derigged

    •Main block rigged with upending slings

    •Riggers are transferred back to DB

  • 8/17/2019 Overview of Jacket Installations

    19/20

    Upend jacket and Set Down

    •Lower jacket to 3m above sea bed

    •Survey the location / orientation

    •Rotate if required with the tuggers

    •Lower to sea bed and check location again

    •Flood the buoyant legs

    •Upending slings are derigged

  • 8/17/2019 Overview of Jacket Installations

    20/20

    20

    Disclaimer

    The information contained in these course/notes has been compiled from various sources and is

    believed to be reliable and to represent the best current knowledge and opinion relative to the

    subject.

    Global Energy Panel offers no warranty, guarantee or representation as to its absolute

    correctness or sufficiency.

    Global Energy Panel has no responsibility in connection therewith; nor should it be assumed

    that all acceptable safety and regulatory measures are contained herein, or that other or

    additional information may be required under particular or exceptional circumstances.

    www.globalenergypanel.com