overview of shelter implementation plan progress
DESCRIPTION
Overview of Shelter Implementation Plan Progress. Dennis K. Kreid Pacific Northwest National Laboratory January 22, 1998. Shelter Project Strategy Status as of February 1997 1997 Progress The Path Forward. Strategy of DOE Involvement at Shelter. Objective: - PowerPoint PPT PresentationTRANSCRIPT
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Overview of Shelter Implementation Plan Progress
Dennis K. Kreid
Pacific Northwest National Laboratory
January 22, 1998
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Shelter Project Strategy
Status as of February 1997
1997 Progress
The Path Forward
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Strategy of DOE Involvement at Shelter
Objective: To assist in international effort to convert Chornobyl Shelter and
destroyed reactor Unit 4 into a stable, environmentally safe, manageable system
Basis for U.S. assistance December 1995 Ukraine/G7 memorandum of understanding
Approach: Provide urgent operational safety improvements
Support international program
Avoid conflicts and duplication
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
February 1997 Status - Equipment Needs Project
Provide urgent operational safety improvement to upgrade shelter worker safety
Nuclear (criticality) safety
Dust suppression
Industrial safety
Equipment needs prioritized, specification preparation and purchasing initiated
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
February 1997 - Shelter Activities
European Commission Short and Long Term Measures, final report - November 1996
Approved by G7/Government of Ukraine
Established project framework
Lacked sufficient logic, cost, and schedule definition
G7 commissioned Shelter Implementation Plan
Draft due March 31, 1997
To provide additional definition to support initiation of Shelter project tendering
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
1997 Progress Report - Shelter Equipment Needs
Dose Reduction % in Purchasing Total $ % Delivered / Shipment
$5.9M 40 60
Electronic dosimeters; survey instruments; air sampling and monitoring; shielding/enclosures; calibration sources; radiological protection technician training; access control; databasing; shielding software; whole body counting; high-efficiency particulate air (HEPA) testing; excess radiation area clothing and respirators
Dust Suppression 0.4M 50 50
Decontamination methods survey; airless sprayers; dry and water vapor HEPA vacuum
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
1997 Progress Report - Shelter Equipment Needs
Nuclear (Criticality) Safety Monitoring
% in Purchasing Total $ % Delivered / Shipment
$1.3M 100% ---
8 pod detection system; power supplies; alarming readouts; archival and trending diagnostics
Industrial safety $1.85 70 30
Personal protective gear (hearing protection, hard hats, eye protection, gloves, respirators with internal communications); fall protection equipment; rescue gear; industrial hygiene test kits; first aid kits; concrete sawing and boring equipment; electrical generators; air compressor; jackhammer; two-way radios
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Dose reduction PD-3 self reading electronic dosimeters
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Water Vapor assisted surface HEPA-vac maintenance of good radiological conditions in frequently accessed areas of Shelter
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
BF3 & fission chamber detectors with gamma, temperature and humidity sensors.
Assess neutron count rate transients for criticality safety implications
System includes power supply, alarming readouts, data collection and trending capability, diagnostics
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Concrete drilling and sawing equipment
Replaces large, unreliable existing equipment
Support electrical/ventilation/access-way installations
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
1997 Progress Report - Unit 3/4 Ventilation Stack Repair
Issue Damaged in 1986 accident
Urgent and necessary action
G7 and Ukraine support “bilateral” repair project
Status Ukraine, Canada, U.S. establish $2.25M project
($4.5M Ukraine, $0.8M Canada, $1.0M U.S.)
Schedule Awaiting final design, project plan deliverables
Materials and equipment purchasing February-March 1998
Repairs April to May 1998 (subject to weather)
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
1997 Progress Report - Shelter Activity
Shelter Implementation Plan
Draft completed March 31, 1997
G7 and government of Ukraine approved May 1997
• Plan retains access to fuel-containing material (FCM)
• Develops removal strategies and technologies
• Does not include FCM removal
Sufficient to support international pledging
European Bank for Reconstruction and Development (EBRD) selected as funds administrator
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
1997 Progress Report - Shelter Activity
Denver Summit, June 1997G7 pledges $300M U.S. to Shelter funds
Ukraine pledges $50M, July 1997
International Donors Conference, New York, November 1997$37M U.S. additional pledges (other country donations)
G7/EBRD conclude sufficient commitment to initiate project
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
SIP Opportunity
The SIP is a logic-based program based on Shelter information, analyses, and assessments available to date. It features
Early Biddable Projects (EBPs) to develop the bases for optimizing and finalizing design decisions
• Also define and initiate balance of required infrastructure improvements
10 programmatic milestones (3 key) to integrate and drive final decisions
Long-term tasks to achieve safe confinement compatible with FCM removal strategy/decisions
Total estimated cost = $760M
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Work Breakdown Structure (WBS) Including the Grouping of Tasks
1RECOMMENDED COURSE OF ACTION
1.3.02CONTAINED WATER MANAGEMENT
1.4.03INTEGRATED MONITORING SYSTEM
1.4.04INTEGRATED DATABASE (CONFIGURATION MANAGEMENT)
1.1REDUCE COLLAPSE PROBABILITY -STRUCTURAL STABILISATION
1.2REDUCE COLLAPSE ACCIDENTCONSEQUENCES
1.3IMPROVE NUCLEAR SAFETY
1.4IMPROVE WORKER AND ENVIRONMENTAL SAFETY
1.5LONG TERM STRATEGY AND STUDY FOR CONVERSION TO ENVIRONMENTALY SAFE SITE
1.2.01EMERGENCY PREPAREDNESS
1.3.01CRITICALITY AND NUCLEAR SAFETY
1.5.01FCM REMOVAL AND WASTE MANAGEMENT STRATEGY & STUDY
1.1.02STABILISATION AND SHIELDING OF WESTERN SECTION
1.2.02DUST MANAGEMENT
1.3.03FUEL CONTAINING MATERIAL (FCM)CHARACTERISATION
1.5.02FCM REMOVAL TECHNOLOGY DEVELOPMENT
1.5.03SAFE CONFINEMENT STRATEGY
1.2.03EMERGENCY DUST SUPPRESSION SYSTEM
1.1.01STABILISATION AND SHIELDING DESIGN INTEGRATION & MOBILISATION
1.4.01RADIOLOGICAL PROTECTION PROGRAM
1.4.02INDUSTRIAL SAFETY; FIRE PROTECTION; INFRASTRUCTURE AND ACCESS CONTROLL
1.1.04STABILISATION AND SHIELDING OF THE EASTERN & NORTHERN SECTIONS
1.1.03STABILISATION AND SHIELDING OF MAMMOTH BEAM & SOUTHERN SECTION
1.1.05STABILISATION OF THE ROOF, ROOF SUPPORTS & COVERING
1.1.06STRUCTURAL INVESTIGATION AND MONITORING
1.1.07GEOTECHNICAL INVESTIGATION
1.1.08SEISMIC CHARACTERISATION AND MONITORING
1.5.04IMPLEMENTATION OF SAFE CONFINEMENT TO SUPPORT DECONSTRUCTION AND FCM REMOVAL
i:\dik-so\Hierar_2.sg
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Criteria for Selection and Specification of Early Biddable Projects
Urgent to risk management
Essential to improve levels of knowledge and engineering to support decision making
Critical path
Readily implementable
Created construction infrastructure
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Early Biddable Projects – See SIP Section 9 for Scope Descriptions of Early Biddable Projects
Civil Engineering
Structural stabilization, design integration and mobilization SIP Task 1
Structural investigation and monitoring Part of SIP Task 6
Geotechnical investigation SIP Task 7
Safe confinement strategy SIP task 21
Operations and Monitoring
Seismic characterization and monitoring Part of SIP Task 8
Radiological protection program Part of SIP Task 15
Industrial safety, fire protection, infrastructure Part of SIP Task 16 and access control
Integrated monitoring system Part of SIP Task 17
Integrated database/configuration management Part of SIP Task 18
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Early Biddable Projects – See SIP Section 9 for Scope Descriptions of Early Biddable Projects (contd)
Emergency Systems
Emergency preparedness SIP Task 9
Dust management Part of SIP Task 10
Emergency dust suppression system Part of SIP Task 11
Criticality control and nuclear safety Part of SIP Task 12
Contained water management Part of SIP Task 13
Fuel Containing Material
FCM initial characterization Part of SIP Task 14
FCM removal and waste management strategy Part of SIP Task 19
FCM removal technology development Part of SIP Task 20
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
The Path Forward
Activity Established
PMU/EBP expressions of interest 8/15 - 9/15/97
PMU RFPs 12/15/97 - 2/15/98
EBP RFPs12/15/97 - 3/15/98
EBP awards/performance 5/98 - 4/1/99
Key decision PI 2/99(stabilization & shielding strategy)
Long-term projects 4/99 - 3/06
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
SIP Project Structure
Donors
Fund Administration
Beneficiary
Executing Agency
Architect Engineers
Contractors/suppliers
PMU Ch NPP Consultant
EBRD
EBRDMonitor
InternationalAdvisory Group
NRALiaison Group
EPO1
EPO2
EPO3
G-7 Rest of World
Ch NPP
$ $
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
EBRD Procurement Policies
Open tendering required for >$200,000 ECU goods and services, >$5M ECU works
Process Pre-purchasing plan
Notification of opportunities for tendering(http://www.ebrd.com - 85£ UK subscription fee
Pre-qualification where appropriate
Invitation to tender/tender documents
• International competition encouraged
Receipt of tenders, evaluation and award• Objective evaluation criteria
Contract administration• Client (PMU-driven), bank oversight
C O N T R A C T O R I N F O R M A T I O N E X C H A N G EC O N T R A C T O R I N F O R M A T I O N E X C H A N G E
Shelter Activities - The Path Forward
Early Biddable Projects will initiate mid CY98 PMU and EPO subcontracting opportunities
Construction phase projects will initiate ~mid CY99 More subcontracting opportunities
Strong U.S. contractor support will help ensure implementation success