Owners- How to contract for BIM deliverables and actually get what you want Birgitta Foster & Cindy Baldwin

Upload: phamnhu

Post on 27-Mar-2018

240 views

Category:

Documents


0 download

TRANSCRIPT

Owners- How to contract for BIM deliverables and actually get what you

want

Birgitta Foster & Cindy Baldwin

#BIMForumED

Check us out at …….. VDCOtech.com

Intr

od

uct

ion

VirtualDesign

Construction Operations

Owner BIM representative

@BirgittaFoster @CindyWBaldwin

#BIMForumED

OVERVIEWAligning organizational goals with BIM Deliverables

Dictating platform-

specific BIM

deliverables

Keeping your Eye on the

data deliverables

Practical and

achievable BIM

deliverables

“To Do or Not to do”

Record Model

deliverables

OwnersHow to contract for BIM deliverables and

actually get what you want

@BirgittaFoster @CindyWBaldwin

#BIMForumED

Unsatisfactory experience : oRequiring BIM without defining why or how their BIM

deliverables

oResults unsure why they are doing BIM.

Best chance at successoBusiness BIM Uses - Business reasons to use BIM

oNot a one time savings but the ANNUALIZED savings

oContracting for the BIM deliverables you can use

BIM Deliverables andOrganizational goals

@BirgittaFoster @CindyWBaldwin

Expectations

#BIMForumED @BirgittaFoster @CindyWBaldwin

BusinessBIM Uses

ESTA

BLI

SH

Geometry

Data

Schedule

File Formats

CO

NTR

AC

T

BIMPxP

DEV

ELO

P

Deliverable RequirementsContracts

Requirements

CAD PDF

CMMS

Space Mgt

EHS Requirements

2D 3D

Excel

Geometry - MP Spec/LOD Spec/M3

DEF

INE

User Requirements

Data - Facility Data Spec/COBie/LOD Attributes

File Format

Data Schedules

Sheet Views

Naming Conventions

BIM Guidelines

ContractorDesign Team

BIM Uses

CD Package

Software

Submittals

Commissioning

Programming

Equip Schedules

Emergency Mgt

Documents

Commissioning report

Word

Submittals

CD Record

Digital Deliverable Guide

Facility Data Spec

Geometry - MP Spec

File Formats

Contractor deliverables

Design Team Deliverables

Documents

Schedule BIM Uses

Software

#BIMForumED

Assessment based on

1- Current need2- short term need3- long term need

BIM Deliverables andOrganizational goals

@BirgittaFoster @CindyWBaldwin

Business BIM Uses

Begin your BIM roadmap

Start here

#BIMForumED @BirgittaFoster @CindyWBaldwin

Uncover most common organizational “Pain Points”

A pain point

o is a problem, real or perceived.

o creates opportunities for themselves by creating

solutions.

o Solutions create value for everyone.

BIM Deliverables andOrganizational goals

Business Value

#BIMForumED

What data can we get?

@BirgittaFoster @CindyWBaldwin

8

What data do we need?Keeping your Eye on the

data deliverables

#BIMForumED @BirgittaFoster @CindyWBaldwin

9

“KISS” principal : Data we need

Keeping your Eye on the

data deliverables

#BIMForumED

Go beyond COBie withdata deliverables

@BirgittaFoster @CindyWBaldwin

Keeping your Eye on the

data deliverables

#BIMForumED @BirgittaFoster @CindyWBaldwin

Keeping your Eye on the

data deliverables

Reformat the dataforOwner data schedules

EHS check : Equipment Utilities = Room Utilities

Missing FMS System – Data set for upload

#BIMForumED

Pros and Cons

@BirgittaFoster @CindyWBaldwin

Dictating platform-

specific BIM

deliverables

#BIMForumED @BirgittaFoster @CindyWBaldwin

September 2016

Owner ( Year released)Design Software Construction Software 3D viewer IFC requirements Record - Design As-built - GC

Broward County Aviation

Department - BCAD ( 2013)

Neutral- Native & IFC compliant

Acceptable : ArchiCAD; Bentley

Ach V8i, Bentley Building, Revit

Neutral- Native & IFC compliant

Acceptable : ArchiCAD; Bentley

Ach V8i, Bentley Building, Revit

N/A YES - compliant 2x3 for

Record & As builtYES_ Design -Native/IFC YES- Native and IFC

Broward Health - FLA ( 2013) Revit Revit N/AYES - IFC compliance for file

transfer & Solibri checker

YES_ A/S/MEPF Models must reflect as-built

geometry & Data. Native- Navisworks/IFC/RVT

YES_ A/S/MEPF Models;2D PDF; BIM-Native-

Navisworks/RVT/IFC

Denver Airport ( 2013) Revit Revit Navisworks/Revit N/A N/A YES_ Navisworks/Revit Record AS-built

Department of Defense’ Military

Health System - DOD-MHS ( 2011)Neutral- Native- IFC certified Neutral- Native- IFC certified

Navisworks

/Navigator/

Adobe/Google earth

YES - certified 2x3 or better

for Coord view for all

deliverable

N/AYES_Design & Contractor - As-built conditions and

updated parameters

Federal Aviation Administration-

FAA (2012)

Neutral- IFC Compliant -

Arch/Struct: Revit Architecture,

Bentley Architecture(Triforma),

Tekla MEPF Revit MEP, AutoCAD

MEP, Bentley BIM

Neutral- IFC Compliant - Revit

MEP, AutoCAD MEP, Bentley BIM,

CAD-Duct, CAD-Pipe,AutoSprink,

PipeDesigner 3D

Navisworks

/Navigator/

Adobe/Google earth

YES - certified 2x3 or better

for Coord view for all

deliverable

N/A YES -Record models

Florida International Unv (2014) Revit Revit/Navisworks NavisworksYes- at close out for record

keeping and interoperabilityNO_ See as-built

YES_ Design update Arch & Struct through construction/

Contractor MEPF

Massport ( 2015) Revit Revit N/A

YES- IFC file may be required

on some projects for model

quality review at handover

YES_The Record Model is the Design Intent

Model updated to show the as-built locations of

the elements within this model and does not

reflect all As Built components’ geometry. will

contain accurate attribute data on major

equipment and systems for FM. Typically updated

by the Designer from information provided by the

Constructor (digital mark-ups, photography, laser

scans). It may be used by Commissioning

YES_The As-Built Model (.nwd) is submitted to MPA by

the Contractor. The As-Built Model is typically an

Autodesk® Navisworks® file that includes shop models

and drawing information from trades and fabricators

with detail of the as-built conditions. This model may

also include laser scan data. It is used as a detailed

reference document of all as-built conditions, but is not

the basis of FM.

University California San Francisco

Medical Ctr (2015)Revit Revit Navisworks

NO deliverables - Only when

used for coordinationN/A YES- By Contractor Called Record for LOD 500

Univ Southern California (USC)

Design Bid Build (2012)Revit Neutral- Not specified- Native Navisworks

YES -May be required- all

subs have capability to save

into most recent version

YES_ As Constructed YES_ As Constructed - Native

USC GMP Contracts (2012) Revit Revit Navisworks/ Revit N/A YES YES_ Revit or Native

USC PRevitXP (2015) Revit Revit N/A N/A YES- with shared parameters & COBie data YES_ Revit/Native(trade models)

University South Florida- USF

(2015)Revit Revit Navisworks N/A See as-builts

YES_Construction updates by Contractor then sent to

Design team for final As built -Revit/Navisworks

Veterans Administration - VA -

(2010)

Neutral- IFC Compliant -

Arch/Struct: Revit, Bentley BIM,

ArchiCAD, Tekla, Vectorworks;

MEPF: ArchiCAD MEP, Revit,

AutoCAD MEP, Bentley BIM,

Neutral- IFC Compliant - ArchiCAD

MEP, Revit, AutoCAD MEP, Bentley

BIM, CAD-Duct, CAD-Pipe,

AutoSprink, PipeDesigner 3D

N/A

YES_- IFC file format of the

consolidated building

systems models -

Coordination view

YES- Native file format(s) of Design Model -

“Design Intent model” remains current with all

approved bulletins for overall scope. It is NOT

expected that product specific information will be

added to this model.

YES_ Contractor—Native file formats of the final

consolidated as-built Model(s) for building systems used

in the multi-discipline coordination process . The

Model(s) shall be fully coordinated and align with the

Design Model for architecture and structure;

General Services Admin -GSA

Series 8 FM (2012)

Neutral- IFC Compliant - should

create IFCs in compliance with

the coordination view, spatial

program validation view and

COBie

Neutral- IFC Compliant - should

create IFCs in compliance with the

coordination view, spatial program

validation view and COBie

N/A

YES- Design Intent BIMs:

Record BIMs deliverable --

not required for

Construction or Coordination

BIMs

YES_ Native and IFC - represent the final as-

constructed building and components

configuration, including Architectural

Supplemental

Instructions, Change Notices, and field changes

YES_Native and IFC, Editable copy of the Record BIM that

is constantly updated to represent the current

completed state of the building and systems

configuration.

United States Army Corp of

Engineers- USACE ( 2012)Neutral-Revit or AECOsim Neutral-Revit or AECOsim N/A IFC coord view - archive n/a YES -Record models

Birgitta Foster/VDCO Tech 2016

DELIVERABLES

Dictating platform-

specific BIM

deliverables

Reviewed Fifteen (15)Standards

#BIMForumED

Pros oHealthier competition – no software requirements to limit the set of bidders

o The team members work with their own software platforms

oDo not use unfamiliar software

oOr pay a third party to produce the BIMs.

@BirgittaFoster @CindyWBaldwin

Dictating platform-

specific BIM

deliverables

ConsOwners may have

oLess control of the final software selection

oRisk receiving a less desirable platform.

oSupport multiple software platforms

oDifficultly hiring experienced staff in the multiple platforms

oA platform not compatible downstream applications.

#BIMForumED

Record vs As-Built

@BirgittaFoster @CindyWBaldwin

“To Do or Not to do”

Record Model

deliverables

“Record” should be reserved for models being provided by the designers of record.

“As-built” is associated with contractor provided as-installed building models.

#BIMForumED

Wide range Record BIM deliverables

oStrategiesoArch/Struct CD BIMs with Contractor MEPF modelsoDesign intent models to incorporate as-constructed conditions oDesign record models use As-built model elements with

product data

OWNER Example : “Design Intent model” remains current with all approved bulletins for overall scope. It is NOT expected that product specific information will be added to this model.”

oTerminology – mix and matching = confusingoAs-built RecordoRecord As-builtoDesign As-builtoContractor RecordoContractor Record As-built

@BirgittaFoster @CindyWBaldwin

“To Do or Not to do”

Record Model

deliverables

#BIMForumED

ContractorsAs-Built Deliverables

oMost consistent owner BIM requirement.

oNative common deliverable file formats.

oSome cases IFC and Navisworks files.

oHybrid – mix of BIM/3D CAD/2D CAD

oFederated Models- A trend to merge into a single deliverable o limits the number of BIMs the owner ultimately stores,

manages and updates

@BirgittaFoster @CindyWBaldwin

“To Do or Not to do”

Record Model

deliverables

#BIMForumED

Design Teams Deliverable Record BIMs

@BirgittaFoster @CindyWBaldwin

“To Do or Not to do”

Record Model

deliverables

PROS- Provides “record” models of changes

recorded by the Design Team- More accurate starting point for

renovations- Better investment than 2D record drawing

from Contactor redlines- Reuse of Contractor models to capture

undocumented changes

CONS- Perceived risk will come with a price tag- Hard to identify level of effort for each

project- No industry-wide best

practice/guidelines/standards available

#BIMForumED

Ensure practical and achievable

oProven

oBest Practice examples

oResource Model

oValidation Tools

@BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverables

#BIMForumED

Proven to be achievable

@BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverables

All required deliverables testedo As acceptable for intended use by End Usero Produced with existing project softwareo Workflows are possible and practical

#BIMForumED @BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverablesBuilding Systems

YARD SALE!

Best Practice - Example

Use the software to stop before it happens

Set systems with specific color –When placing - wrong color = wrong system

#BIMForumED @BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverables

Provide a Resource Model

Transfer using INSERT FROM FILE

Transfer as PROJECT INFO

Contains Owner Specific o Data Scheduleso Sheet Viewso Librarieso Shared Parameters

NOT A Model TEMPLATE

#BIMForumED @BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverables

Automate checking your staff doesn't have time to do thoroughly

“Data Clash detection”

Validation ToolsMore control of your

Data deliverables

Acceptable Manufactures ? Motor voltages?

Building SystemsPipe material correct ?System components assigned – no Yard Sale!Fire dampers in all Fire walls?

AV Equipment at required height ?

#BIMForumED

Record BIMs

@BirgittaFoster @CindyWBaldwin

Practical and

achievable BIM

deliverables

Leverage BIM deliverable software

o“Reverse” Clash detection

o Value-Add approach

“Reverse” Clash

Detection

= off by more than 12 ”

Design Intent Vs

As Constructed

@BirgittaFoster @CindyWBaldwin

#BIMForumED @BirgittaFoster @CindyWBaldwin

Contractor RoutingDesign Intent Routing

Contractor RoutingDesign Intent Routing

CHILLED WATER LINES

CHILLED WATER RISERS

Value Add to update??

#BIMForumED @BirgittaFoster @CindyWBaldwin

Contractor Location Design Intent Location

VAV & Duct

Contractor RoutingDesign Intent Routing

CHILLED WATER LINES

Ductwork

Value Add to update??

#BIMForumED @BirgittaFoster @CindyWBaldwin

Contractor Piping Design Intent Piping

Pumps

DuctworkContractor Routing Design Intent RoutingValue Add to update??

#BIMForumED

Record modeling

oMEANS… contains the same content and level of development as the Design Intent BIMs for Construction Documents.

oDoes NOT Mean…. to contain all the construction details in the trade models.

@BirgittaFoster @CindyWBaldwin

#BIMForumED

Owner example “Rules of thumb”

Design Intent Model updated when Contractor Models are either :

A) Location of element* deviates o 6” or more in any space

o 12” or more in any concealed spaces, mechanical spaces for MEP & other building systems.

o 12” or more by any slab openings, steel members greater than 10” in depth and other major structural elements.

B) Equipment* or system component* has been o Replaced by an owner-approved alternate or

o Added during the construction phase of the project.

*Vague= $$..…must define to what Equipment/system/component

@BirgittaFoster @CindyWBaldwin

#BIMForumED @BirgittaFoster @CindyWBaldwin

BusinessBIM Uses

ESTA

BLI

SH

Geometry

Data

Schedule

File Formats

CO

NTR

AC

T

BIMPxP

DEV

ELO

P

Deliverable RequirementsContracts

Requirements

CAD PDF

CMMS

Space Mgt

EHS Requirements

2D 3D

Excel

Geometry - MP Spec/LOD Spec/M3

DEF

INE

User Requirements

Data - Facility Data Spec/COBie/LOD Attributes

File Format

Data Schedules

Sheet Views

Naming Conventions

BIM Guidelines

ContractorDesign Team

BIM Uses

CD Package

Software

Submittals

Commissioning

Programming

Equip Schedules

Emergency Mgt

Documents

Commissioning report

Word

Submittals

CD Record

Digital Deliverable Guide

Facility Data Spec

Geometry - MP Spec

Best Practices

Contractor deliverables

Design Team Deliverables

Documents

Schedule BIM Uses

Software

Owners –How to contract for BIM

deliverables and actually get what you want

Birgitta Foster Cindy Baldwin

THANK YOU!