© SSTL COMMERCIAL IN CONFIDENCE
P R O J E C T
Lunar Mission One
Lunar Mission One Request for Information (RFI)
W O R K P A C K A G E N U M B E R
RGPI
D O C U M E N T N U M B E R
0261758
C U S T O M E R I D N U M B E R
LM1-MT-001
R E V I S I O N
1
R E V I S I O N O R R E L E A S E D A T E
18 November 2015
S T A T U S
Issued
PREPARED BY SSTL ON BEHALF OF LUNAR MISSION ONE
Chris Saunders Susan Jason Jonathan Friend
R E V I E W E D B Y
LM1 Mission Team
C U S T O M E R A P P R O V A L Surrey Satellite Technology Limited Tycho House 20 Stephenson Road Surrey Research Park Guildford, Surrey GU2 7YE, UK Tel: +44 1483 803803 Fax: +44 1483 803804 Email: [email protected]
David Iron
THIS DOCUMENT IS THE PROPERTY OF SURREY SATELLITE TECHNOLOGY LIMITED AND MUST NOT BE COPIED OR USED FOR ANY PURPOSE OTHER THAN THAT FOR WHICH IT HAS BEEN SUPPLIED.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 2 of 16
© SSTL COMMERCIAL IN CONFIDENCE
TABLE OF CONTENTS
1 INTRODUCTION.................................................................................................................................................. 5
1.1 SCOPE ............................................................................................................................................................. 5 1.2 PROJECT BACKGROUND ................................................................................................................................... 5 1.3 REFERENCE DOCUMENTS ................................................................................................................................. 6 1.4 ACRONYMS AND ABBREVIATIONS ....................................................................................................................... 6
2 THE LUNAR MISSION ONE CONCEPT ............................................................................................................ 7
2.1 OVERVIEW ....................................................................................................................................................... 7 2.2 MISSION IMPLEMENTATION TIMELINE ................................................................................................................. 9 2.3 MISSION COST ............................................................................................................................................... 10 2.4 STRAWMAN PAYLOADS ................................................................................................................................... 10
3 REQUEST FOR INFORMATION ....................................................................................................................... 11
3.1 SPECIFIC ITEMS REQUESTED .......................................................................................................................... 11 3.2 SIZE OF SUBMISSION ...................................................................................................................................... 12 3.3 RESPONSE DEADLINES ................................................................................................................................... 12 3.4 OTHER ITEMS ................................................................................................................................................. 12 3.5 DISCLOSURE OF INFORMATION ........................................................................................................................ 12
APPENDIX A. DRILLING OBJECTIVES & ASSUMPTIONS ............................................................................... 13
APPENDIX B. STRAWMAN SCIENCE PAYLOAD .............................................................................................. 15
APPENDIX C. STRAWMAN ARCHIVE PAYLOAD ............................................................................................. 16
LIST OF FIGURES
Figure 1: Notional Lunar Mission One mission phases (assuming southern lunar pole landing) .......................... 7 Figure 2: Lunar Mission One Mission Phases (assuming southern Lunar Pole landing) ...................................... 8 Figure 3: High Level Lunar Mission One Product Tree .......................................................................................... 8 Figure 4: Preliminary Mission Implementation Schedule. ...................................................................................... 9
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 3 of 16
© SSTL COMMERCIAL IN CONFIDENCE
COPYRIGHT
COPYRIGHT AND LICENCE CONDITIONS
©SSTL THE COPYRIGHT IN THIS DOCUMENT IS THE PROPERTY OF SURREY SATELLITE TECHNOLOGY LIMITED. All rights reserved. No part of this documentation may be reproduced by any means in any material form (including photocopying or storing it in any electronic form) without the consent of the Copyright Owner, except in accordance with the Copyright, Designs and Patents Act, 1988, or under the terms of a licence and/or confidentiality agreement issued by the Copyright Owner, Surrey Satellite Technology Ltd. Applications for the copyright owners permission to reproduce any part of this documentation should be addressed to, The Chief Executive Officer, Surrey Satellite Technology Ltd., Tycho House, 20 Stephenson Road, Surrey Research Park, Guildford, Surrey, GU2 7YE, UK.
Any person, other than the authorised holder, who finds or otherwise obtains possession of the document, should post it together with his name
and address to the Chief Executive Officer, Surrey Satellite Technology Ltd., TYCHO HOUSE, 20 STEPHENSON ROAD, SURREY RESEARCH PARK,
Guildford, Surrey, GU2 7YE, UK.
Postage will be refunded.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 4 of 16
© SSTL COMMERCIAL IN CONFIDENCE
DOCUMENT REVISION STATUS
Last Edited Date
Revision / Release Number
Status Edited By Pages / Paragraphs Affected
Change Ref
17 /11/ 2015 1 Issued LM1 Mission Team
All (first issue)
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 5 of 16
© SSTL COMMERCIAL IN CONFIDENCE
1 INTRODUCTION
1.1 Scope This document is a statement of work for a Request for Information (RFI) issued by Lunar Mission One, in order to facilitate initial discussions with interested industrial partners. The document includes the following:
An overview of the Lunar Mission One main mission objectives.
The associated programmatic and procurement approach planned by Lunar Mission One. Lunar Mission One has issued this RFI in order to better understand possibilities for industrial management and implementation for the mission. In particular, the following are of high interest to the Lunar Mission One team:
The proposed industrial consortia that could be put together to deliver the mission
Preliminary mission architecture(s) which could meet the main mission objectives
Non-binding, indicative price(s) for the mission architectures
High-level delivery schedule
Innovative ideas for cost reduction, schedule acceleration, and/ or increased value The Lunar Mission One concept is still in a relatively early stage of its planning (pre-Phase A), and therefore the mission concept and mission requirements are not fully developed and consolidated. As such, Lunar Mission One does not expect a firm fixed price or a fully formed and detail technical proposal. The RFI is intended to capture early ideas and preliminary concepts for the management and delivery of the mission architecture, which will be refined though a formal Request for Proposals (RFP) which is planned for the second half of 2016 (see Figure 4). Lunar Mission One welcomes innovative solutions that will deliver the mission objectives. This document is structured as follows:
Section 1.2 covers general project background.
Section 2 provides an overview of the Lunar Mission One concept, the mission objectives and requirements, and the baseline implementation schedule
Section 3 details the specific items to be addressed by any organisation responding to this Request for Information
Appendix A outlines the preliminary drilling objectives and definitions.
Appendix B outlines the preliminary strawman science payload for the mission.
Appendix C outlines the preliminary strawman archive payload.
1.2 Project Background Lunar Mission One is a plan for landing a vehicle on the Moon, expected to be near to the Southern Lunar pole, to use this vehicle to drill a deep borehole into the Moon’s surface, and then to place inside the borehole an enduring time capsule – an archive payload consisting of digital media and DNA samples from Earth. In addition, the mission is required to enable highly valuable new science by performing detailed analyses of core samples returned to the lunar surface during the drilling process. Investigations to support manned lunar bases are also desirable. The mission has an innovative funding structure, based on self-financing through payments from members of the public in return for an allocation of the archive payload. More information on the Lunar Mission One concept is available on the mission website (https://lunarmissionone.com). RD-2 links to a full list of project documents including the business case and market studies. Specifically, RD-1 can be consulted to obtain background information on the preliminary feasibility
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 6 of 16
© SSTL COMMERCIAL IN CONFIDENCE
study performed in 2013 on the Lunar Mission One concept. It should be noted since that time some aspects of the mission concept may have changed, and therefore the information in this document should take preference in terms of a response to the questions in this RFI. Lunar Mission One is also seeking to form a Public Private Partnership (PPP) between a Government agency, which will act as the political authority for the mission, and an industrial consortium with a lead company as the contracting authority for the mission’s implementation. The objectives of the PPP will be expressed in terms of the transport, placement and servicing of the archive and science payloads. The industrial consortium would manage the programme for the selection and development of the technical solution and the subsequent space operations. The industrial consortium is expected to draw on a wide range of international capabilities.
1.3 Reference Documents
RD-1 https://lunarmissionone.com/lunar-mission-one/the-business-case-technical-review RD-2 https://lunarmissionone.com/lunar-mission-one/business-case
1.4 Acronyms and Abbreviations The following abbreviations are used within this document:
COSPAR Committee on Space Research DNA Deoxyribonucleic Acid FRR Flight Readiness Review ITAR International Traffic in Arms Regulations PPP RFI
Public Private Partnership Request for Information
RFP Request for Proposal TBC To be Confirmed TBD To be Determined ΔV Delta-Velocity
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 7 of 16
© SSTL COMMERCIAL IN CONFIDENCE
2 The Lunar Mission One Concept
2.1 Overview Lunar Mission One is a UK-originated idea for an international robotic lunar drilling mission to land and drill a near-vertical borehole of a minimum 20 meters on the Moon. The project embodies a number of unique features, including:
The first deep drilling mission on a solar system body other than Earth
A commercial payload, contained in the archive, that enables the self-financing of the project
Potential for unique science and exploration knowledge returns, as well as engineering technology demonstrations
The prime mission objective for Lunar Mission One is:
Land a vehicle safely on the surface of the Moon, expected to be in the southern lunar polar region, and use this vehicle to drill a deep vertical borehole into the lunar surface. The vehicle shall place an archive consisting of
digital and DNA information into the hole that shall be able to survive undamaged on the Moon for one billion years. In addition the vehicle shall perform scientific analysis of lunar rock samples obtained during the drilling of the
archival borehole and take measurements of the local surface environment.
This includes the following considerations:
The mission shall comply with all aspects of the Committee on Space Research (COSPAR) Category II Planetary Protection Requirements
The minimum surface lifetime for drilling and archive deployment is expected to be 6 months, based upon current understanding of the drilling capabilities.
The minimum mission lifetime for potential extended science operations should exceed the lunar polar day.
A non-polar site can be proposed. This will be evaluated in the same way as polar sites - in terms of the balance of cost, value and risks.
The mission will be split into several different phases, as illustrated at Figure 1 and outlined in more detail in Figure 2. The phases are shown in a nominally chronological order although scientific analysis may continue after the placement of the archive into the bore hole.
Figure 1: Notional Lunar Mission One mission phases (assuming southern lunar pole landing)
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 8 of 16
© SSTL COMMERCIAL IN CONFIDENCE
Figure 2: Lunar Mission One Mission Phases (assuming southern Lunar Pole landing)
Figure 3: High Level Lunar Mission One Product Tree
Mission Phase Name Description
1 Pre-launch The lunar lander vehicle is prepared for flight on the launch site, including its installation aboard
the launcher, and correct functioning of the whole system is checked before lift-off
2 Launch and Early Operations (LEOP)
Starting with launcher lift-off and ending when the lunar lander vehicle is acquired by the LM1
ground segment and is shown to be safe (from the power and thermal point of view) and stable
(from an attitude point of view)
3 Space Segment Commissioning Systems on-board the lunar lander are verified for correct functionality and operating behaviour
4 Lunar Transfer Orbit Injection
The lunar lander vehicle is placed on an orbital trajectory that is compatible with the desired lunar
parking orbit. This may come from the landers own propulsion, from an additional propulsion
module, or from the upper stage of the launch vehicle (TBC)
5 Lunar Cruise & ApproachThe lunar lander performs navigation updates and mid-course correction manoeuvres (if needed)
towards the intended lunar parking orbit
6 Lunar Parking Orbit Injection The lunar lander injects into a stable parking orbit around the Moon
7 Detailed Lunar Mapping OrbitThe lunar lander performs detailed surveillance of the Southern Lunar regions, for landing site
hazard identification, and landing site confirmation
8 Lunar Parking OrbitOnce the potential landing sites have been surveyed, the lander will wait whilst the landing site
imagery is checked and verified (on-ground)
9 Lunar Landing
Once the landing site suitability is confirmed, the vehicle orients itself to the desired attitude, uses
on-board propulsion and sensing equipment to navigate towards the preferred landing site (within
a defined error ellipsoid), performs course corrections and hazard avoidance manoeuvres as
needed, and finally descends towards the lunar surface, landing safely within the error ellipsoid
10Lunar Surface Operation
Commissioning
Once on the surface, the functionality of the lander, including the drilling mechanism(s) and any
science payloads shall be verified for correct functionality and operating behaviour
11Drilling of borehole and Scientific
Analysis
The lander shall employ a drilling device to dig the necessary borehole into the lunar surface. Core
samples shall be periodically removed from the hole and shall be placed onto a separate payload
on the lander for scientific analysis
12 Archive Placement into Borehole
Once the hole has been dug to the necessary depth, the lander shall place a DNA and Information
Archive into the hole. (Note, if mission resources allow it, this phase could be extended for
additional scientific measurements after the archive has been safely placed into the hole. This is
TBC.)
13 End-of-Mission & PassivationOnce the archive has been placed into the hole, and all science observations have finished, the
lander shall be fully passivated, and left in a safe non-volatile state
Lunar Mission One: Mission Phases
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 9 of 16
© SSTL COMMERCIAL IN CONFIDENCE
Figure 3 shows the high level Lunar Mission One product tree, showing the key elements (the critical ‘building blocks’) of the mission.
2.2 Mission Implementation Timeline The mission is envisaged to be implemented as a PPP, split into two stages. This first phase is a set-up phase where the management structure is established, procurement approach and legal responsibilities are defined, and discussions with industry occur, all leading to a competitive PPP contract. The second stage (implementation) deals with the development and procurement of the mission hardware and the execution of the actual mission itself.
Figure 4: Preliminary Mission Implementation Schedule.
The preliminary mission delivery schedule is shown in Figure 4. This is subject to change but is based upon the following key stages:
Industry discussions – commencing with the issue of the Request for Information (RfI) Q4 2015 Competitive procurement – commencing with the issue of the formal Request for Proposal (RfP) Q3 2016 Contract negotiation – commencing with bid selection Q4 2017
Stage Mission Procurement Technology Development
2015 Q4 Initial expressions of
interest
Mission risk identification
2016 Q1 Initial industry discussions
& investment cases
Risk analysis
Q2 Initial formation of
consortiums
Preliminary mission
outlines
Q3 Procurement competition
plan with initial RfP
Risk reduction planning
Q4 Project planning, financial
investment assessments
First stage risk reduction
activity
2017 Q1 Candidate commercial
offers, developed RfP
Mission planning & cost
analysis
Q2 Investment optimisation &
contract development
Second stage risk
reduction activity
Q3 Best & final offers Refinements to mission
plan & cost analysis
Q4 Bid selection Negotiation support
2018 Q1 Contract decision &
financial close
Prep for Development
Stage
2018-
2022
Consortium sub-
contracting
Detailed technology
planning, design,
development and build
2023 Flight readiness review Assembly, integration &
test
2024
Spac
e
op
s Extended mission options
selection
Launch, spaceflight &
lunar operations
Mis
sio
n
dev
elo
pm
ent
Period
Ind
ust
ry d
iscu
ssio
ns
Co
mp
etit
ive
pro
cure
men
tC
on
trac
t
neg
oti
atio
ns
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 10 of 16
© SSTL COMMERCIAL IN CONFIDENCE
Mission development – commencing with the contract kick off Q1 2018 Space Operations – commencing 2024
2.3 Mission Cost Although the mission is not yet fully defined, a non-binding indicative mission price is requested as part of this RFI to support the high level trade-offs. This should highlight the high level mission architecture products that have been included such as the cost of the spacecraft, payload integration to spacecraft, launch vehicle, mission operations and provisions for launch services and which are not (refer to Figure 3).
2.4 Strawman Payloads The drilling and science payloads will be handled via a separate call for proposals from 2016. The drilling is expected to be within the scope of the PPP mission contract with the industrial consortium. The currently defined drilling objectives, science payloads and archive payloads for the Lunar Mission One lunar lander are shown in Appendix B and C respectively. These are preliminary definitions, and are subject to change, but should be used as the baseline for the payloads in terms of this RFI.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 11 of 16
© SSTL COMMERCIAL IN CONFIDENCE
3 Request for Information
3.1 Specific Items Requested The Lunar Mission One team has issued this RFI to begin the process of defining the industrial arrangements and implementation of the proposed mission concept. As such the Lunar Mission One team is interested in understanding the possible ways the mission development and implementation could be managed. Therefore Lunar Mission One specifically requests the responding organisation to address the questions shown below in their response
1:
The key questions to be addressed are:
1. What would be the core industrial consortium that could be put together to deliver the mission?
o This should include as a minimum the management teaming that would address the key aspects of the mission (e.g. the development and procurement of drilling, guidance navigation and control etc.) and an outline of the expertise and experience in the team.
2. What is the preliminary technical solution that could be envisaged by industry in order to meet the mission objectives of Lunar Mission One venture? This should include:
o The overall high-level mission architecture proposed, and the space and ground segment design concepts, including a proposed launch solution (prime and backup).
o Identification of mission drivers which have the capacity to be a particularly strong influence on the overall mission and project cost, complexity and risk. Highlight possible mitigation strategies and /or alternatives.
o Any aspects of the design with particular heritage or potential to de-risk the mission should be clearly identified.
3. What would be the proposed programmatic implementation for the mission? This should include:
o The proposed product and quality assurance approach and standards for the mission
o The indicative non-binding price for delivering the mission solution to Lunar Mission One
o The total mission schedule from kick-off to end-of-mission including any identified necessary critical technology pre-development or de-risking programmes
o The proposed relationship between the proposed industrial consortia and any other organisations in terms of delivering the mission (e.g. relationships with space agencies, national government programmes etc.)
o A first order assessment of the management of International Traffic in Arms Regulations (ITAR), or any other export or governmental restrictions that can be foreseen in terms of delivering the mission solution. This is particularly important given the expected international nature of the mission implementation.
4. What are considered the main risks to the project (both technical and programmatic)?
o If feasible this should also include any associated mitigation strategies to minimise these risks.
5. Are there any innovative ideas for cost reduction, schedule acceleration, or any other aspects, that could bring significant value without damaging the key mission objective?
1 Responding organisations are free to respond in which ever format they consider the most appropriate, e.g.
document, presentation slide pack etc.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 12 of 16
© SSTL COMMERCIAL IN CONFIDENCE
3.2 Size of Submission Lunar Mission One anticipates responses limited to a maximum of 20 pages in length, although this is not a strict requirement. However, responses significantly over this limit may not be read or acted upon.
3.3 Response Deadlines
3.3.1 Registration of Interest Potential respondents are asked to register their interest in this RFI by email by 09:00 GMT on 7
th
December 2015.
[email protected] Registration of interest does not create an obligation to respond to the RFI, but will allow the LM1 team to disseminate any additional details to the interested parties.
3.3.2 RFI Submissions RFI responses should be sent electronically (preferably in PDF format) to the following email address:
[email protected] The response should be contained within a single file, and should reach the stated email address by 17:00 GMT on the 25
th January 2016.
3.3.3 Questions Respondents may send questions to the LM1 team via the following email address:
[email protected] All questions and answers will be made available to those who register their interest. The source of the questions shall be held confidential. Questions and answers that contain information unique to a respondent’s proprietary approach will not be shared if they are identified as such.
3.4 Other Items The responding organisations are free to add any other information to their response if they feel it adds value to their proposal, and will be of benefit to Lunar Mission One (noting the target page count stated in section 3.2).
3.5 Disclosure of Information Any responses received by Lunar Mission One will be treated as commercially sensitive and treated as in-confidence information.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 13 of 16
© SSTL COMMERCIAL IN CONFIDENCE
APPENDIX A. DRILLING OBJECTIVES & ASSUMPTIONS
High Level Drilling Objectives: The drilling objectives should be phased. The following are recommended:
a) A cased 10 metre vertical borehole is the mission objective for success
b) 20 metres is the target depth, uncased hole below 10 metres
c) 100 metres is a stretch target based on uncased hole below 10 metres
Working Assumptions:
1. The lunar sub-surface shall be assumed to be a mix of basalt and breccia in a heterogeneous mix. See section on stratigraphy. This will require further iteration with the Science Team.
2. The diameter of the borehole will be optimised for drill performance, but is expected to be 0.045m. This will require iteration with the Drilling Team.
3. The lunar lander shall place the archive payload into the hole once the final hole depth has been reached. 4. The drilling system shall allow for the return to the lunar surface of core samples for scientific analysis. This
will require iteration with the Science and Mission Teams. 5. The arrangements and responsibilities for robotic sample handling will need co-ordination with the Science
Team. 6. Measurement While Down (MWD) – Critical engineering data on the drilling whilst drill is active in the hole
will be required but is still to be defined. 7. Logging While Down (LWD) - Mainly science data on the drilling whilst drill is active in the hole is desirable,
but is still to be defined.
Stratigraphy
LM1 currently has three working scenarios for the drill site stratigraphy: a) Homogeneous anorthosite breccia scenario b) Homogeneous crystalline anorthosite scenario c) Heterogeneous scenario
a) Homogeneous anorthosite breccia scenario
A top layer of lunar soil up to a depth of 10 metres below which are anorthositic breccias to a depth of >100 metres.
b) Homogeneous crystalline anorthosite scenario
A top layer of lunar soil up to a depth of 10 metres below which are crystalline anorthosite to a depth of >100 metres.
c) Heterogeneous scenario
A top layer of lunar soil up to a depth of 5 meters followed by alternating layers of regolith breccia and crystalline anothosite separated by maximally compacted regolith (lunar soil) At circa 20 metres to circa 50 metres homogeneous anorthosite breccia. At circa 50 metres to > 100 metres, homogeneous crystalline anorthosite.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 14 of 16
© SSTL COMMERCIAL IN CONFIDENCE
Sources: Prof Ian Crawford & Mr Phil Bustin
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 15 of 16
© SSTL COMMERCIAL IN CONFIDENCE
APPENDIX B. STRAWMAN SCIENCE PAYLOAD
The following model payload is indicative of one that would achieve the proposed science goals within a notional 30 kg allocation. At present this is purely conceptual but is based on instrumentation that has an appropriate level of technical maturity. It will be refined as a result of future studies.
Descent Imager – part of landing system images of the landing site at various heights to place the landing
site into the local context. Some other instruments required for navigation/landing (e.g. landing LIDAR) may
also provide data of scientific value.
Landing Site Imager – multi-spectral imaging mineralogy for landing site characterisation. If possible,
obtaining images of Earth from the landing site will also be desirable for outreach purposes and for studies
using the Earth as an analogue for habitable exoplanets.
Infra-Red Imaging Spectrometer – to characterize the local mineralogy.
X-ray Diffraction/X-ray Fluorescence (XRF)/Gamma-ray spectrometer/Densitometer – to determine
elemental composition, mineralogy, trace elements and radio-nuclides. Note: It is important to ascertain the
thermal conductivity (e.g. via density) of the rock to accurately determine heat flow (a densitometer could
be incorporated within the drill).
Raman-LIBS (Laser Induced Breakdown Spectrometer) – to determine elemental composition and
mineralogy at the landing site and of drill samples.
Neutron spectrometer – for the determination of hydrogen concentrations in the local regolith for
comparison with orbital measurements.
Mass Spectrometer – for determination of the chemical composition of sampled materials, especially of
volatiles and (ideally) stable isotopes. This would give potential for K-Ar age dating (when combined with K
data from XRF or LIBS [8]), and characterization of volatiles trapped in the regolith. Requires a sample
handling system and a carousel of ovens.
Seismometer – for determination of internal lunar structure and characterization of natural moonquakes
(might also be used to monitor drilling activities). If a multi-year mission life proves possible this could
become a contribution to a future lunar geophysics network.
Heat Flow – to better characterize lunar thermal evolution; needs to measure temperature and thermal
conductivity as a function of depth.
Dust, radiation and charging package – to determine dust particle size and electrostatic charging; should
also include radiation monitor.
Sample imager – to image samples analysed by others to provide colour and context (may have
microscope capability).
Low-frequency (LF) radio-astronomy investigation package – to investigate the practicality of LF radio-
astronomy from the Moon (interference environment, etc); possible radio-frequency beacon to aid future
missions.
Proof of concept Magnetosphere Imager.
The above list is not exclusive and other instruments may be possible. This will be reviewed and consolidated as the project develops.
Lunar Mission One Request for Information (RFI)
Doc No: LM1-MT-001
Revision: 1 Status: Issued
Revision Release Date: 18/11/2015
Page 16 of 16
© SSTL COMMERCIAL IN CONFIDENCE
APPENDIX C. STRAWMAN ARCHIVE PAYLOAD
The following model payload is indicative of the archive currently anticipated. It will be refined as a result of future studies. In particular, the total length of capsules could be reduced in anticipation of a reduced expected minimum drilling depth.
Mass: 10 kg.
Volume: 10 litres.
Dimensions: 10 metres of cylinders of 3.5 cm diameter and 33 cm length.
Environmental requirements: TBD.