p2 kirtling street sip
TRANSCRIPT
-
8/3/2019 P2 Kirtling Street SIP
1/32
-
8/3/2019 P2 Kirtling Street SIP
2/32
Kirtling Street
2
Section 1: Introduction and site informationWe are proposing to use land at Kirtling Street for this
construction work and to accommodate permanent
structures required to operate the main tunnel. The site
would be used to drive the main tunnel in two directions
to Chambers Wharf and to Carnwath Road Riverside.
The location of the site is shown in Figure 1A and extends
into the foreshore of the River Thames together with land
occupied by industrial warehousing, a depot, a concrete
batching works, former petrol filling station and office
buildings. Kirtling Street and Cringle Street run through
and around the site. The new residential development
(Riverlight) on the former Tideway Industrial Estate and
our existing Heathwall Pumping Station are situated to
the east of the site, with the River Thames located to the
north and Battersea Power Station to the west. Battersea
Park Road/Nine Elms Lane (A3205) is to the south of the
site. Two boat communities are located to the east of the
site. These are the Nine Elms Pier community (aroundNine Elms Pier) and Tideway Village in Tideway Dock.
This site information paper sets out our proposals at
Kirtling Street. We have also produced project information
papers, which cover overarching topics relating to the
project. Where we consider that a project information
paper is particularly relevant, we have highlighted this
in a related documents box. At the end of this site
information paper is a list of other documents, which maybe of interest and a glossary of terms.
Related documents:
Build
How we chose this site
What we proposed at phase one consultation
In addition to sites to intercept the existing local CSOs,
we require sites to build the main tunnel at:
each end of the main tunnel in west and east London
suitable intervals along the route of the main tunnel
locations where the type of geology that the main
tunnel goes through changes.
Prior to identifying the precise location of the main
tunnel sites, we established the broad areas within which
they would be needed. One of the main tunnel sites
is required in the Battersea area, where the geology
changes from clay to sands.
At phase one consultation, which was held betweenSeptember 2010 and January 2011, our preferred site
in this area was Tideway Walk where we would receive
the main tunnel from Barn Elms, drive the main tunnel
to Kings Stairs Gardens and intercept the Heathwall
Pumping Station CSO and South West Storm Relief CSO.
-
8/3/2019 P2 Kirtling Street SIP
3/32
Introduction
3
Figure 1A: Kirtling Street location plan
New CoventGarden Market
Royal MailSorting Office
Kirtling Street Nine Elms Pier
Battersea PowerStation
Batte
rseaP
arkRo
ad
CringleStreetNine
ElmsL
ane
N
CITY OF WESTMINSTER
WANDSWORTH
Local authority boundary
Draft limit of land tobe acquired or used
Proposed tunnelroute centreline
Heathwall PumpingStation site
-
8/3/2019 P2 Kirtling Street SIP
4/32
Kirtling Street
4
Why we amended our proposals
Since January 2011, we have considered the comments
from phase one consultation, feedback from ongoing
engagement and new information; and undertaken
further technical work. This work led us to review possible
sites and our tunnelling strategy, which considers how
sites might be linked together to construct the
main tunnel.
We have identified that the Tideway Walk site is no
longer available for use because planning permission
for residential development has been approved and
construction works have started on site. As a result, we
have re-assessed potential sites to drive the main tunnel
to Carnwath Road Riverside and Chambers Wharf, (ie a
double main tunnel drive site), in the Battersea area.
As part of our further technical work, we reviewed
whether it would be possible to reduce the size of our
main tunnel drive sites. Where the ground conditions are
clay and sands it was concluded that it was possible to
reduce the size of single and double main tunnel drive
sites. We therefore re-assessed what sites within the
Battersea area may be suitable as a main tunnel drive
site. One of the sites we identified was Kirtling Street; this
site is not located next to Heathwall Pumping Station
and South West Storm Relief CSOs, so a combined
main tunnel drive and CSO site would not be possible. A
separate site to intercept the CSOs would therefore be
required; our preferred site at phase two consultation tointercept both CSOs is Heathwall Pumping Station.
In our review, we identified Kirtling Street as a potentially
suitable shortlisted site. In August 2011 we held drop-in
sessions for the community around the site to understand
any local issues they may have in relation to this possible
site. Since the drop-in sessions, we have continued to
refine our proposals for this site and have added in
adjacent land off Cringle Street to improve the logistics
for the site. We held a further drop-in sessions to present
our revised proposals in October 2011. We have reviewedall the comments we received from both rounds of drop-in
sessions and took these into account as part of the site
selection process.
What we are proposing at phase two consultation
We have identified eight shortlisted sites for a main
tunnel drive site, as shown on Figure 1B. The sites are:
Battersea Park (site 1)
Battersea Power Station (site 2)
Part of Battersea Power Station (site 3)
Heathwall Pumping Station and Middle Wharf (site 4)
Post Office, Nine Elms Lane (site 5)
Post Office Way (west of US Embassy site) (site 6)
Depots, Ponton Road (east of US Embassy site) (site 7)
Kirtling Street with Cringle Street (our preferred site).
Kirtling Street with Cringle Street is our preferred site
because it is brownfield land in a mainly industrial area
and has more space to accommodate tunnelling activities
associated with a main tunnel double drive site. Including
the land at Cringle Street means that there is more river
frontage. This would provide better arrangements forjetties and barges and may result in less impact on the
nearby houseboats. There is also good vehicular access
directly from Nine Elms Lane (A3205) and unlike a
number of the shortlisted sites, using this site would avoid
needing to cross Nine Elms Lane (A3205) in to access the
River Thames to transport excavated material by barge.
The site would not affect the early stages of the Battersea
Power Station redevelopment.
-
8/3/2019 P2 Kirtling Street SIP
5/32
Introduction
5
Figure 1B: Preferred and shortlisted sites
Site 1
Site 2
Site 5
Site 4Site 3ChelseaBridge
BatterseaPark
GrosvenorBridge
New CoventGardenMarket
Site 7Site 6
N
WANDSWORTH
LAMBETH
CITY OF WESTMINSTER
KENSINGTON &CHELSEA
Preferred site Kirtling Street
Other shortlisted site locations
Local authority boundary
Phase one consultationpreferred site Tideway Walk
-
8/3/2019 P2 Kirtling Street SIP
6/32
Kirtling Street
6
Site 1 Battersea Park is a shortlisted site and is
considered less suitable than our preferred site because
it is a Grade II* registered park and garden, which would
be affected by development. The loss of open space,potential adverse effects on heritage features, landscape,
townscape and archaeology and the need for permanent
above ground structures make this location less suitable.
Site 2 Battersea Power Station is a shortlisted site
and is considered less suitable than our preferred site
because using this site would affect the appearance and
setting of the listed power station. Access to this site is
also restricted. Beneath the site are service tunnels, whichwould restrict where we could construct the shaft. The use
of this site could result in a delay to the Battersea Power
Station redevelopment, which has planning consent.
Site 3 Part of Battersea Power Station is a shortlisted
site and is considered less suitable than our preferred site
because the site is occupied by an existing district heating
plant serving buildings in the Pimlico area, to the north
of the River Thames, which would need to be relocated.Use of the river for transportation of materials by barge
may also be constrained by the Battersea Power Station
redevelopment and the adjacent Waste Transfer station
barge operations. The shape of the site would constrain
how we could undertake our works. The use of this site
could also affect the existing Grade II listed pumping
station, which is situated in the central area of the site.
Site 4 Heathwall Pumping Station and Middle Wharfis a shortlisted site, which we considered in conjunction
with the Tideway Walk site at phase one consultation.
By itself it is too small for a single or double main drive
site However, this site contains the two local CSOs known
as Heathwall Pumping Station and South West Storm
Relief that we need to intercept. We would prefer to use
it as a CSO site. For more information please refer to the
Heathwall Pumping Station site information paper.
Site 5 Post Office, Nine Elms Lane is a shortlisted
site and is considered less suitable than our preferred
site because it is distant from the River Thames, which
means that the main tunnel would have the potentialto affect buildings. As the site does not have direct
river access excavated materials would need to be
transported on overhead conveyors over the Nine Elms
Lane (A3205). There is also a strong likelihood that the
site is contaminated as it used to be part of Nine Elms
Gas Works.
Site 6 Post Office Way site (west of proposed US
Embassy site) is a shortlisted site and is considered lesssuitable than our preferred site because it is too small to
accommodate a double main tunnel drive site. There is a
strong likelihood that the site is contaminated as it used
to be part of Nine Elms Gas Works. Construction activities
could also affect the proposed US Embassy site, given
its close proximity. The site does not have direct river
access, therefore excavated materials would need to be
transported on overhead conveyors over the Nine Elms
Lane (A3205).
Site 7 Depots, Ponton Road (east of US Embassy
site) is a shortlisted site and is considered less suitable
than our preferred site because of the potential effects of
construction activities on the proposed US Embassy site,
given its close proximity. There is also no direct access to
the River Thames. The lack of direct access means that an
overhead conveyor belt across Nine Elms Lane (A3205)
and between the residential properties Elm Quay andRiverside Court would be required to transport materials
by barge.
-
8/3/2019 P2 Kirtling Street SIP
7/32
Introduction
7
Related documents:
Changes
Q&A Consultation
Site selection
Carnwath Road Riverside
Chambers Wharf
Heathwall Pumping StationHePS
CRR
CW
-
8/3/2019 P2 Kirtling Street SIP
8/32
Kirtling Street
8
-
8/3/2019 P2 Kirtling Street SIP
9/32
Construction
Construction
9
Section 2: Construction
Construction activitiesConstruction activities are required to construct themain tunnel. We would construct a shaft with an internal
diameter of approximately 30m. Once completed
tunnel boring machines would be lowered into the shaft
(approximately 48m deep) and would drive the main
tunnel to Carnwath Road Riverside and Chambers Wharf.
Excavated material from the tunnel drives would be
removed from the shaft and taken off site. The shaft
would also be used to install the secondary lining intothe main tunnel. Figure 2A illustrates the below ground
infrastructure proposed.
Figure 2A: Illustration showing typical elements of below ground infrastructure
These activities would take place within the area
indicated by the red line in Figure 1A, in six main phases,
lasting approximately five to five and a half years. Works
carried out in advance of the main construction, such as
connection a power supply, and the nature of the site as
a main tunnel drive site means that the overall period of
construction is likely to be approximately six years. The
main construction activities associated with these phases
are set out in Table 2.1.
Related documents:
Build
Managing construction
Main tunnel
Shaft
-
8/3/2019 P2 Kirtling Street SIP
10/32
Kirtling Street
10
Advance works
Phase 1
Site setup
Figure reference Figure 2C
Typical working hours Varies Standard
Mainconstruct
ionactivities
Utilities connected
Site cleared
Temporary works in the River Thames constructed
Site facilities and access set up
Shaft excavated and built
Tunnel boring machine delivered to site and assembled
Tunnel excavated and built
Internal (secondary) tunnel lining constructed
Above and below ground structures constructed
Mechanical and electrical equipment installed
Temporary works in the River Thames removed
Site restored and landscaped
Temporary site facilities removed
Table 2.1: Main activities during construction phases
Our typical working hours are expected to be:
Standard: 8am-6pm weekdays, 8am-1pm Saturday*
Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays
Continuous: 24 hours a day, seven days a week**
Varies: Working hours for advanced works will depend on the nature of the works and will be agreed
with the local authority
-
8/3/2019 P2 Kirtling Street SIP
11/32
Construction
11
Phase 2
Shaft construction
Phase 3
Tunnelling
Phase 4
Secondary
lining
Phase 5
Construction of
other structures
Phase 6
Completion of
works and siterestoration
Figure 2C Figure 2D Figure 2E Figure 2E
Standard with occasional
extended standardContinuous Continuous Standard Standard
* Standard working hours would also include, subject to agreement with the local authority:
a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.
equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.
** The main activities taking place 24 hours a day are below ground or within an enclosure.
-
8/3/2019 P2 Kirtling Street SIP
12/32
Kirtling Street
12
Site layout and construction phases
Figures 2C, 2D and 2E show how the site might be laid
out during the construction phases, which are set outin Table 2.1 and Figure 2B. These layouts have been
informed by the size of the infrastructure proposed,
the construction methods required and the location
of neighbouring buildings and structures. These have
also been developed to minimise effects on the local
community and environment. Particular factors at this site
that have influenced the layout are as follows:
Consideration has been given to the relationshipwith neighbouring developments, effects on the local
highway network and river access to nearby wharves.
The site layout would permit the continued use of the
concrete batching works or its removal.
The site layouts are indicative only, and the contractor
may arrange the site in a different way, depending onthe chosen construction methods, provided that any
environmental effects are appropriately managed and
that the main construction activities are undertaken
within the red line shown in Figure 1A.
P1
P2
P3
P4
P5
P6
Year 1 Year 2 Year 3 Year 4 Year 5
Advan
ce
works
Figure 2B: Construction timeline showing approximate duration of works in phases (P)
-
8/3/2019 P2 Kirtling Street SIP
13/32
Construction
13
Figure 2C: Illustrative phases 1 and 2 construction plan
Jack up bargeservicing piling
operations
Cranes
Piling rig
Conveyor
Shaft
N
Maximum extent ofconstruction site for
phases 1 and 2Site hoarding
Site support/welfare
Excavated materialstorage and processing
Maintenance workshopand storage
Construction support
Internal site road
Site access
Existing Thames Path
Thames Path diversion
-
8/3/2019 P2 Kirtling Street SIP
14/32
Kirtling Street
14
Figure 2D: Illustrative phase 3 construction plan
Shaft
Barges
Gantry crane
N
Maximum extent ofconstruction site forphase 3
Site hoarding
Site support/welfare
Excavated materialstorage and processing
Maintenance workshopand storage
Construction support
Internal site road
Site access
Existing Thames Path
Thames Path diversion
Noise enclosure overshaft and gantry crane
Crane
Conveyor
-
8/3/2019 P2 Kirtling Street SIP
15/32
Construction
15
Figure 2E: Illustrative phases 4 and 5 construction plan
N
Shaft
Gantry crane
Conveyor
Maximum extent ofconstruction site forphases 4 and 5
Site hoarding
Site support/welfare
Excavated materialstorage and processing
Maintenance workshopand storage
Construction support
Internal site road
Site access
Existing Thames Path
Thames Path diversion
Noise enclosure overshaft and gantry crane
Ki tli St t
-
8/3/2019 P2 Kirtling Street SIP
16/32
Kirtling Street
16
Additional works and activities
The main construction activities at this site are set out in
Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located
outside of the area indicated by the red line in Figure 1A.
The anticipated additional works and activities are set
out in Table 2.2.
When Type of works What we would do
Required for
construction
phase
Installation of equipment
to monitor environmental
matters such as noise,
vibration and dust.
The locations of monitoring equipment would be agreed with the local
authority and relevant landowners.
Protection works to third
party structures (such as
buildings, bridges and
tunnels).
We would undertake studies to identify any effects our construction
work may have on third party structures. The studies may recommend
particular construction methods or, in very limited instances, protection
works.
Temporary connection to
utilities (such as water,
sewer, phone and electricity
supply).
We expect to connect to water, sewer and phone supplies in Cringle
Street or Kirtling Street.
A major new electricity supply would be required at this site to provide
power during construction. We expect to connect to a cable tunnel at
Kirtling Street, running cables along Cringle Street and Kirtling Street.
Traffic management works.These may need to extend beyond our site and could include relocating
kerb lines, repainting road lines and modifying traffic signals.
Dredging.There is a possibility that as the detailed design is developed we may
need to undertake dredging to allow barges to get to and from our site.
Required for
operational
phase
Permanent connection
to utilities (such as water,
phone and electricity supply)
for the operational tunnel.
We expect to connect to utilities in Cringle Street or Kirtling Street.
Table 2.2: Additional works and activities
-
8/3/2019 P2 Kirtling Street SIP
17/32
Construction
17
Construction transport and access
We propose to use barges to transport the majority of
excavated material from the tunnel. It is not generally
practical and cost effective to transport all materials
to and from the site by barge so we would still need to
transport some materials by road. We would however
give the contractor the flexibility to determine the most
practical and cost-effective means of transporting other
materials and equipment.
Each barge would remove approximately 55 lorries from
the road. Using barges at this site would reduce the
number of lorry visits to/from this site by approximately
65% (saving 85,000 lorry visits over the construction
period of approximately six years). Construction works
at this site would support the works at our Heathwall
Pumping Station site with welfare facilities, offices and
site management for the two sites being located at
Kirtling Street. Figure 1A shows the location of both sites.
Table 2.3 sets out the anticipated average daily number
of lorries and barges visiting (ie travelling to and from)the site during the peak months of each phase, based on
moving excavated material from the tunnel by barge. We
are also considering whether use could be made of the
rail network.
Table 2.3: Average daily lorry and barge visits during the peak months
Construction traffic would access the site from Battersea
Park Road (A3205), turning left into Kirtling Street and
right into Cringle Street. Traffic leaving the site would turn
left onto Nine Elms Lane (A3205) from Cringle Street.
These access points are shown on Figure 2F. Beyond this,
construction traffic would use the major road network to
get to and from its final destination.
The Thames Path runs past the proposed site access on
Kirtling Street and through our construction site, so we
would need to divert it during construction. We expect to
divert it along Nine Elms Lane (A3205) and Kirtling Street
to the east of the site, as shown on Figures 2C, 2D and 2E.
As shown in the section on future use, the Thames Path
may run along part of the riverfront after construction
is completed. We would consider whether it would be
possible to extend the Thames Path across the front of
the whole site.
We may also need to make modifications to the junction
of Nine Elms Lane (A3205) and Kirtling Street and the
junction of Nine Elms Lane (A3205) and Cringle Street
in order to accommodate the movement of construction
traffic. Based on our current design, we do not anticipate
that any parking bay suspensions or bus stop relocations
would be required.
Phase 1Site setup
Phase 2Shaft
construction
Phase 3Tunnelling
Phase 4Secondary
lining
Phase 5Construction
of otherstructures
Phase 6Completion
of worksand site
restoration
Average daily
lorry visits26 lorries 64 lorries 67 lorries 35 lorries 30 lorries 9 lorries
Average daily
barge visits none none 4 barges none none none
Kirtling Street
-
8/3/2019 P2 Kirtling Street SIP
18/32
Kirtling Street
18
Figure 2F: Proposed access route to the site from the nearest major road
KirtlingStreet
Nine Elms Lane
Cringle StreetKirtling Street
Possible junctionmodifications
CringleStreet
A3035
Battersea Park Road
N
WANDSWORTH
CITY OF WESTMINSTER
Draft limit of land tobe acquired or used
Internal site road
Site access
Local authority boundary
Transport for London(TfL) road network
Proposed lorry access to
TfL road network
Related documents:
Transport
Construction
-
8/3/2019 P2 Kirtling Street SIP
19/32
Construction
19
Management of construction works
Our construction works would be managed in accordance
with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft
CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and
consultation with the local authorities. Through the
environmental impact assessment process, scheme-
wide principles to address potential effects on the local
environment have been identified and integrated into
the design. The CoCP Part A sets out scheme-wide control
measures that would be used to minimise potentialeffects during the construction process.
Table 2.4 sets out what we consider to be the key issues
for this site during construction, and how we are currently
proposing to address them.
Related documents:
Environment
Kirtling Street
-
8/3/2019 P2 Kirtling Street SIP
20/32
Kirtling Street
20
Issue Our response
Possible conflict with
recent proposals for theredevelopment of Nine
Elms Pier.
We objected to the planning application for a new marina in summer 2011. However, asthe application has been amended, we would continue to work with the developers and the
local authority to agree a phasing programme that allows construction of the main tunnel.
Construction works may
require the relocation of
some of the 22 house
boats from around Nine
Elms Pier.
We would investigate alternative mooring options for the houseboats as required.
Possible conflict withpart of the consented
redevelopment of
Battersea Power Station.
We are in contact with the owners/developers of this site and hope to negotiate an
acceptable arrangement to both parties for use of this site before finalising our proposals.
Construction activities
may affect existing barge
operations from the
safeguarded wharves.
It is expected that current users of the waste transfer station would continue to operate
during construction. Arrangements would be discussed following completion of the
Navigational Risk Assessment that we have commissioned. Discussions are ongoing
with the concrete batching works owner regarding use of the site and associated wharf
during our construction works. The future use of the safeguarded wharf would not becompromised by our permanent works.
Construction works would
require the demolition
of six vacant offices in
Brooks Court.
We have sought to minimise the number of properties that must be removed and have an
established procedure for consulting with and providing appropriate compensation to site
owners. It is not expected that the properties would be reinstated following completion
of construction works, as the site is part of the wider Vauxhall and Nine Elms Opportunity
Area, which is expected to be comprehensively regenerated.
Possible effect of
construction vehicles on
the volume of traffic on
Nine Elms Lane (A3205).
Construction works at this site would generate large volumes of excavated material whichwould need to be transported off site.
We have sought to minimise disruption to the local road network through our site
layout and design. We would manage the effects of road transport through our traffic
management plans, which will seek to limit the number of vehicle movements and hours
of operation, identify the most suitable site access points and any necessary highway
management arrangements. As already set out, we also propose to use barges to transport
the majority of excavated material from the tunnel, which would reduce the number of
lorry movements from this site by approximately 65% over the construction period. We arealso considering whether use could be made of the rail network.
Construction
-
8/3/2019 P2 Kirtling Street SIP
21/32
Construction
21
Issue Our response
Temporary diversion ofthe Thames Path along
Kirtling Street.
The section of the Thames Path running past the proposed site access and through theconstruction site would be temporarily diverted via a safe alternative route to the east of
the site, along Nine Elms Lane (A3205) and Kirtling Street.
The proposed
construction site access
off Cringle Street is
shared with other sites
and businesses.
The road would be kept open during construction to maintain existing access to other sites
and businesses, including the waste transfer station and the public amenity site at Cringle
Dock, our existing water treatment works, Battersea Power Station and the new residential
development Riverlight.
Possible effect of
noise and vibration on
neighbouring areas.
The contractor would be required to implement noise and vibration control measures at
the worksite, which will be set out in the CoCP. We need to undertake continuous tunnelling
at this site for reasons of safety, cost and programme. While continuous tunnelling is
taking place, the working area would be enclosed in a temporary structure which would
significantly reduce noise levels. Materials needed to construct the tunnel at night would
also be loaded into the building during the day, to minimise machinery and vehicle
movements at night.
Possible effects on local
air quality and dust
nuisance in neighbouring
areas.
Preliminary findings indicate that while there is the potential for dust nuisance effects,
there are unlikely to be any significant local air quality effects at any of the sites. The
contractor would put in place air and dust control measures at the worksite, which will be
set out in the CoCP. This would include enclosing the working area whilst tunnelling works
are carried out to limit dust leaving the site.
Table 2.4: Key issues relating to construction
Related documents:
Managing construction
Transport
Kirtling Street
-
8/3/2019 P2 Kirtling Street SIP
22/32
Kirtling Street
22
Section 3: Future use
This section describes the site after the completion of the
construction work, ie when the main tunnel is in use the
operational phase.
Design
The design of the permanent use and appearance of
the structures at Kirtling Street follows our scheme-wide
principles and takes into account comments raised
during ongoing engagement with the London Borough ofWandsworth and other technical consultees.
Our permanent works need to incorporate functional
elements, which are required for the operation of thetunnel. These include:
Underground structures with ground level access covers
including: a main tunnel shaft with an internal diameter
of approximately 30m and a passive filter chamber.
One ventilation column up to 6m high.
Maintenance vehicle access.
An electrical and control kiosk.
Table 3.1 sets out the site specific issues that have
influenced our permanent design proposals and how we
have addressed them in our proposed design.
Future use
-
8/3/2019 P2 Kirtling Street SIP
23/32
Future
use
23
Issue Our response
Effects on the future development
of the site and area.
We have located the main tunnel site to optimise critical engineering
requirements and avoid compromising the future development of the site.
Visual effect of the permanent
works.
As a result of the modified scheme-wide ventilation strategy, the need for a
ventilation building at this location has been eliminated, with passive ventilation
only required.
Effect on the Thames Path.
After the completion of construction, the Thames Path may extend along the
eastern part of the Kirtling Street site to facilitate future access and connectivity
in the area following completion of development by the developer. We would
consider whether it would be possible to extend the Thames Path across the frontof the whole site.
Table 3.1: Site specific issues that have influenced our permanent design
Kirtling Street
-
8/3/2019 P2 Kirtling Street SIP
24/32
Kirtling Street
24
Figure 3A: Aerial view of the completed works
Figures 3A and 3B provide illustrations of our design
proposals. Further information on the development of our
design can be found in the Design development report.Related documents:
Design
Future use
-
8/3/2019 P2 Kirtling Street SIP
25/32
25
Figure 3B: Layout of site once construction works complete
Permanentaccess for
maintenance
Combinedventilation
structure andequipment kiosk
SafeguardedWharf jetty
retained
Temporaryhoardingaround site fordevelopmentby others
Riverlightdevelopment
Nine Elms pier
Kirtling Street
resurfaced
Thames Pathwayfinding
signage
KirtlingStreet
CringleStreet
Nin
eEl
msLan
e
N
New fence toboundary of concrete
batching works site
Kirtling Street
-
8/3/2019 P2 Kirtling Street SIP
26/32
t g St eet
26
Operation and maintenance
Once the tunnel is operational, we would need access
to the site occasionally for inspection and maintenance
purposes. We expect to visit the site approximately onceevery three to six months to carry out inspections and
maintenance of the ventilation equipment. This is likely
to involve a visit by staff in a small van, and may take
several hours.
Once every ten years, we expect to carry out a major
internal inspection of the tunnel and underground
structures. This is likely to involve a small team of
inspection staff, a small team of support crew and twomobile cranes to lower the team and inspection vehicle
into the shaft. This is likely to take several weeks, and
would require temporary fencing around the shaft for
safety and security while the inspection takes place.
We may also need to make visits to the site for unplanned
maintenance or repairs, for example if there is a blockage
or equipment failure. This may require the use of mobile
cranes and vans.
Permanent vehicular access would be from Kirtling Street.
Management of operational effects
We have undertaken technical work, including stakeholder
engagement, to assess and identify the key issues
associated with this site once it is operational. Table3.2 summarises these issues and how we are currently
proposing to address them.
Future use
-
8/3/2019 P2 Kirtling Street SIP
27/32
27
Issue Our response
Possible odour effects during
the operation of the tunnel.
Odour effects at this site are expected to be negligible because we have developed
anAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at this site
includes the use of passive below ground carbon filters that will remove possible odour
before air leaves the ventilation equipment.
Disturbance from future
maintenance access.
Permanent access would be required for maintenance and servicing purposes to the
shaft and ventilation equipment. Any planned maintenance visits would be undertaken
during normal working hours and all visits managed to avoid disruption to local
residents, businesses and users of affected public areas as far as possible.
Table 3.2: Key issues relating to site operation
Related documents:
Odour
Further information
-
8/3/2019 P2 Kirtling Street SIP
28/32
28
This section sets out documents which may be of particular interest. Further information on our proposals can be
found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre
on 0800 0721 086).
Phase two public consultation material
Project information papers include general information about the Thames Tunnel project. There are 17 project
information papers, which cover various aspects of the project. Those project information papers that may be of
particular interest are set out below.
Icon Title Details
Build
Provides information on the different types of sites required for the Thames Tunnel
project and the typical construction activities that will be undertaken at each site.
Changes
Explains how the scheme has changed compared to that presented at phase one
consultation, including changes to the tunnelling strategy for the main tunnel and
changes to sites.
Q&A Consultation
Sets out the consultation we have undertaken to date on the project, the scope
of this phase two consultation and how interested parties can respond to thisconsultation.
DesignContains the design principles which have influenced the permanent appearance of
our sites once construction work is complete.
EnvironmentSets out the process the project is following to assess potential environmental effects
of the Thames Tunnel project.
Managing
construction
Includes information on what measures our contractors will put in place at our sites
during construction.
Odour Sets out ourAir management plan and how it will work.
Options Outlines the various ways to deal with sewage overflows.
-
8/3/2019 P2 Kirtling Street SIP
29/32
29
Phase two public consultation material
Icon Title Details
OverflowSets out how Londons sewerage system works and why the capital has an overflow
problem.
Route and
tunnel
alignment
Sets out the preferred route of the main tunnel and the reasons for our preference.
Site selection Sets out the process we followed to find and select our preferred sites.
Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.
Site information papers provide information that relate to each preferred site along the route of the Thames Tunnel
project. The following site information papers may be of particular interest.
Carnwath Road Riverside
Chambers Wharf
Heathwall Pumping Station
CRR
CW
HePS
Further information
-
8/3/2019 P2 Kirtling Street SIP
30/32
30
Technical reports
Theme Icon Title Details
Interim
engagement
Interim engagement
report
Provides a summary of the public engagement we
have undertaken between phase one and phase two
consultations.
Phase one
consultation1
SUMMARY
Report on phase one
consultation:
summary report
Provides a summary of the comments made at phase one
consultation and our responses.
Phase two
construction
information
Code of construction
practice Part A:
General requirements
(CoCP)
Sets out control measures to be adopted during the project
construction period.
Phase twoenvironmental
information
Air management
plan
Outlines the methods which we will use to manage odour
from the main tunnel at all our preferred sites.
Preliminary
environmental
information report
(PEIR)
Contains initial assessments on the environmental effects of
the Thames Tunnel project based on information collected
to date. Please refer to volume 17 of the non-technical
summary and volume 17 of the PEIR for more information
on this site.
Phase two scheme
development
Design development
report
Provides a general overview of how the scheme design at
each site has evolved to date. Please refer to chapter 12 for
more information on this site.
2
Phase two scheme
development report
Provides an overview of the development of the Thames
Tunnel project and how each site was chosen. Please refer to
Appendix L for more information on this site.
Site glossary
-
8/3/2019 P2 Kirtling Street SIP
31/32
31
Term Definition
Carbon filters Filters that remove odours before the air is released from the tunnel.
Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.
Combined sewer
overflow (CSO)
A structure, or series of structures, that allows sewers to overflow into the river when they
are full as a result of increased rainfall. Without the overflows, the sewers would back up and
cause flooding in streets or houses.
Draft limit of land to
be acquired or used
The extent of land that we may need to use or acquire, or over which rights may be needed to
carry out works that are essential to the project.
Foreshore Ground uncovered by the river when the tide is low.
Main tunnel/connection tunnel
drive site
A site that would be used to construct the main tunnel or connection tunnel. The excavatedmaterial would be removed from the tunnel and the concrete tunnel lining segments would
be delivered to the tunnel at the main/connection tunnel drive site.
Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.
Operational phase After the completion of the construction work, when the main tunnel is in use.
Secondary lining A second, internal lining to the tunnel, giving it additional strength.
Thames Tunnel project
The Thames Tunnel project comprises a storage and transfer tunnel, from west London to
Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along theThames Tideway.
Transport for London
Road Network (TLRN)
The network of roads managed by Transport for London. These are the major or strategic
roads, which have high capacity.
Tunnel boring machine
(TBM)
A machine used to excavate tunnels through a variety of conditions, with a circular
cross-section.
-
8/3/2019 P2 Kirtling Street SIP
32/32
Phase two consultation: Kirtling Street
For further information or to comment on our
proposals see our website:
www.thamestunnelconsultation.co.uk
110-ED-PNC-00000-000088
Autumn 2011
It is very important that you understand theinformation we have provided. If you needfurther information in another language,
braille, large print or audio format pleasecontact us on 0800 0721 086.