p2 kirtling street sip

Upload: thamestunnel

Post on 07-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 P2 Kirtling Street SIP

    1/32

  • 8/3/2019 P2 Kirtling Street SIP

    2/32

    Kirtling Street

    2

    Section 1: Introduction and site informationWe are proposing to use land at Kirtling Street for this

    construction work and to accommodate permanent

    structures required to operate the main tunnel. The site

    would be used to drive the main tunnel in two directions

    to Chambers Wharf and to Carnwath Road Riverside.

    The location of the site is shown in Figure 1A and extends

    into the foreshore of the River Thames together with land

    occupied by industrial warehousing, a depot, a concrete

    batching works, former petrol filling station and office

    buildings. Kirtling Street and Cringle Street run through

    and around the site. The new residential development

    (Riverlight) on the former Tideway Industrial Estate and

    our existing Heathwall Pumping Station are situated to

    the east of the site, with the River Thames located to the

    north and Battersea Power Station to the west. Battersea

    Park Road/Nine Elms Lane (A3205) is to the south of the

    site. Two boat communities are located to the east of the

    site. These are the Nine Elms Pier community (aroundNine Elms Pier) and Tideway Village in Tideway Dock.

    This site information paper sets out our proposals at

    Kirtling Street. We have also produced project information

    papers, which cover overarching topics relating to the

    project. Where we consider that a project information

    paper is particularly relevant, we have highlighted this

    in a related documents box. At the end of this site

    information paper is a list of other documents, which maybe of interest and a glossary of terms.

    Related documents:

    Build

    How we chose this site

    What we proposed at phase one consultation

    In addition to sites to intercept the existing local CSOs,

    we require sites to build the main tunnel at:

    each end of the main tunnel in west and east London

    suitable intervals along the route of the main tunnel

    locations where the type of geology that the main

    tunnel goes through changes.

    Prior to identifying the precise location of the main

    tunnel sites, we established the broad areas within which

    they would be needed. One of the main tunnel sites

    is required in the Battersea area, where the geology

    changes from clay to sands.

    At phase one consultation, which was held betweenSeptember 2010 and January 2011, our preferred site

    in this area was Tideway Walk where we would receive

    the main tunnel from Barn Elms, drive the main tunnel

    to Kings Stairs Gardens and intercept the Heathwall

    Pumping Station CSO and South West Storm Relief CSO.

  • 8/3/2019 P2 Kirtling Street SIP

    3/32

    Introduction

    3

    Figure 1A: Kirtling Street location plan

    New CoventGarden Market

    Royal MailSorting Office

    Kirtling Street Nine Elms Pier

    Battersea PowerStation

    Batte

    rseaP

    arkRo

    ad

    CringleStreetNine

    ElmsL

    ane

    N

    CITY OF WESTMINSTER

    WANDSWORTH

    Local authority boundary

    Draft limit of land tobe acquired or used

    Proposed tunnelroute centreline

    Heathwall PumpingStation site

  • 8/3/2019 P2 Kirtling Street SIP

    4/32

    Kirtling Street

    4

    Why we amended our proposals

    Since January 2011, we have considered the comments

    from phase one consultation, feedback from ongoing

    engagement and new information; and undertaken

    further technical work. This work led us to review possible

    sites and our tunnelling strategy, which considers how

    sites might be linked together to construct the

    main tunnel.

    We have identified that the Tideway Walk site is no

    longer available for use because planning permission

    for residential development has been approved and

    construction works have started on site. As a result, we

    have re-assessed potential sites to drive the main tunnel

    to Carnwath Road Riverside and Chambers Wharf, (ie a

    double main tunnel drive site), in the Battersea area.

    As part of our further technical work, we reviewed

    whether it would be possible to reduce the size of our

    main tunnel drive sites. Where the ground conditions are

    clay and sands it was concluded that it was possible to

    reduce the size of single and double main tunnel drive

    sites. We therefore re-assessed what sites within the

    Battersea area may be suitable as a main tunnel drive

    site. One of the sites we identified was Kirtling Street; this

    site is not located next to Heathwall Pumping Station

    and South West Storm Relief CSOs, so a combined

    main tunnel drive and CSO site would not be possible. A

    separate site to intercept the CSOs would therefore be

    required; our preferred site at phase two consultation tointercept both CSOs is Heathwall Pumping Station.

    In our review, we identified Kirtling Street as a potentially

    suitable shortlisted site. In August 2011 we held drop-in

    sessions for the community around the site to understand

    any local issues they may have in relation to this possible

    site. Since the drop-in sessions, we have continued to

    refine our proposals for this site and have added in

    adjacent land off Cringle Street to improve the logistics

    for the site. We held a further drop-in sessions to present

    our revised proposals in October 2011. We have reviewedall the comments we received from both rounds of drop-in

    sessions and took these into account as part of the site

    selection process.

    What we are proposing at phase two consultation

    We have identified eight shortlisted sites for a main

    tunnel drive site, as shown on Figure 1B. The sites are:

    Battersea Park (site 1)

    Battersea Power Station (site 2)

    Part of Battersea Power Station (site 3)

    Heathwall Pumping Station and Middle Wharf (site 4)

    Post Office, Nine Elms Lane (site 5)

    Post Office Way (west of US Embassy site) (site 6)

    Depots, Ponton Road (east of US Embassy site) (site 7)

    Kirtling Street with Cringle Street (our preferred site).

    Kirtling Street with Cringle Street is our preferred site

    because it is brownfield land in a mainly industrial area

    and has more space to accommodate tunnelling activities

    associated with a main tunnel double drive site. Including

    the land at Cringle Street means that there is more river

    frontage. This would provide better arrangements forjetties and barges and may result in less impact on the

    nearby houseboats. There is also good vehicular access

    directly from Nine Elms Lane (A3205) and unlike a

    number of the shortlisted sites, using this site would avoid

    needing to cross Nine Elms Lane (A3205) in to access the

    River Thames to transport excavated material by barge.

    The site would not affect the early stages of the Battersea

    Power Station redevelopment.

  • 8/3/2019 P2 Kirtling Street SIP

    5/32

    Introduction

    5

    Figure 1B: Preferred and shortlisted sites

    Site 1

    Site 2

    Site 5

    Site 4Site 3ChelseaBridge

    BatterseaPark

    GrosvenorBridge

    New CoventGardenMarket

    Site 7Site 6

    N

    WANDSWORTH

    LAMBETH

    CITY OF WESTMINSTER

    KENSINGTON &CHELSEA

    Preferred site Kirtling Street

    Other shortlisted site locations

    Local authority boundary

    Phase one consultationpreferred site Tideway Walk

  • 8/3/2019 P2 Kirtling Street SIP

    6/32

    Kirtling Street

    6

    Site 1 Battersea Park is a shortlisted site and is

    considered less suitable than our preferred site because

    it is a Grade II* registered park and garden, which would

    be affected by development. The loss of open space,potential adverse effects on heritage features, landscape,

    townscape and archaeology and the need for permanent

    above ground structures make this location less suitable.

    Site 2 Battersea Power Station is a shortlisted site

    and is considered less suitable than our preferred site

    because using this site would affect the appearance and

    setting of the listed power station. Access to this site is

    also restricted. Beneath the site are service tunnels, whichwould restrict where we could construct the shaft. The use

    of this site could result in a delay to the Battersea Power

    Station redevelopment, which has planning consent.

    Site 3 Part of Battersea Power Station is a shortlisted

    site and is considered less suitable than our preferred site

    because the site is occupied by an existing district heating

    plant serving buildings in the Pimlico area, to the north

    of the River Thames, which would need to be relocated.Use of the river for transportation of materials by barge

    may also be constrained by the Battersea Power Station

    redevelopment and the adjacent Waste Transfer station

    barge operations. The shape of the site would constrain

    how we could undertake our works. The use of this site

    could also affect the existing Grade II listed pumping

    station, which is situated in the central area of the site.

    Site 4 Heathwall Pumping Station and Middle Wharfis a shortlisted site, which we considered in conjunction

    with the Tideway Walk site at phase one consultation.

    By itself it is too small for a single or double main drive

    site However, this site contains the two local CSOs known

    as Heathwall Pumping Station and South West Storm

    Relief that we need to intercept. We would prefer to use

    it as a CSO site. For more information please refer to the

    Heathwall Pumping Station site information paper.

    Site 5 Post Office, Nine Elms Lane is a shortlisted

    site and is considered less suitable than our preferred

    site because it is distant from the River Thames, which

    means that the main tunnel would have the potentialto affect buildings. As the site does not have direct

    river access excavated materials would need to be

    transported on overhead conveyors over the Nine Elms

    Lane (A3205). There is also a strong likelihood that the

    site is contaminated as it used to be part of Nine Elms

    Gas Works.

    Site 6 Post Office Way site (west of proposed US

    Embassy site) is a shortlisted site and is considered lesssuitable than our preferred site because it is too small to

    accommodate a double main tunnel drive site. There is a

    strong likelihood that the site is contaminated as it used

    to be part of Nine Elms Gas Works. Construction activities

    could also affect the proposed US Embassy site, given

    its close proximity. The site does not have direct river

    access, therefore excavated materials would need to be

    transported on overhead conveyors over the Nine Elms

    Lane (A3205).

    Site 7 Depots, Ponton Road (east of US Embassy

    site) is a shortlisted site and is considered less suitable

    than our preferred site because of the potential effects of

    construction activities on the proposed US Embassy site,

    given its close proximity. There is also no direct access to

    the River Thames. The lack of direct access means that an

    overhead conveyor belt across Nine Elms Lane (A3205)

    and between the residential properties Elm Quay andRiverside Court would be required to transport materials

    by barge.

  • 8/3/2019 P2 Kirtling Street SIP

    7/32

    Introduction

    7

    Related documents:

    Changes

    Q&A Consultation

    Site selection

    Carnwath Road Riverside

    Chambers Wharf

    Heathwall Pumping StationHePS

    CRR

    CW

  • 8/3/2019 P2 Kirtling Street SIP

    8/32

    Kirtling Street

    8

  • 8/3/2019 P2 Kirtling Street SIP

    9/32

    Construction

    Construction

    9

    Section 2: Construction

    Construction activitiesConstruction activities are required to construct themain tunnel. We would construct a shaft with an internal

    diameter of approximately 30m. Once completed

    tunnel boring machines would be lowered into the shaft

    (approximately 48m deep) and would drive the main

    tunnel to Carnwath Road Riverside and Chambers Wharf.

    Excavated material from the tunnel drives would be

    removed from the shaft and taken off site. The shaft

    would also be used to install the secondary lining intothe main tunnel. Figure 2A illustrates the below ground

    infrastructure proposed.

    Figure 2A: Illustration showing typical elements of below ground infrastructure

    These activities would take place within the area

    indicated by the red line in Figure 1A, in six main phases,

    lasting approximately five to five and a half years. Works

    carried out in advance of the main construction, such as

    connection a power supply, and the nature of the site as

    a main tunnel drive site means that the overall period of

    construction is likely to be approximately six years. The

    main construction activities associated with these phases

    are set out in Table 2.1.

    Related documents:

    Build

    Managing construction

    Main tunnel

    Shaft

  • 8/3/2019 P2 Kirtling Street SIP

    10/32

    Kirtling Street

    10

    Advance works

    Phase 1

    Site setup

    Figure reference Figure 2C

    Typical working hours Varies Standard

    Mainconstruct

    ionactivities

    Utilities connected

    Site cleared

    Temporary works in the River Thames constructed

    Site facilities and access set up

    Shaft excavated and built

    Tunnel boring machine delivered to site and assembled

    Tunnel excavated and built

    Internal (secondary) tunnel lining constructed

    Above and below ground structures constructed

    Mechanical and electrical equipment installed

    Temporary works in the River Thames removed

    Site restored and landscaped

    Temporary site facilities removed

    Table 2.1: Main activities during construction phases

    Our typical working hours are expected to be:

    Standard: 8am-6pm weekdays, 8am-1pm Saturday*

    Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays

    Continuous: 24 hours a day, seven days a week**

    Varies: Working hours for advanced works will depend on the nature of the works and will be agreed

    with the local authority

  • 8/3/2019 P2 Kirtling Street SIP

    11/32

    Construction

    11

    Phase 2

    Shaft construction

    Phase 3

    Tunnelling

    Phase 4

    Secondary

    lining

    Phase 5

    Construction of

    other structures

    Phase 6

    Completion of

    works and siterestoration

    Figure 2C Figure 2D Figure 2E Figure 2E

    Standard with occasional

    extended standardContinuous Continuous Standard Standard

    * Standard working hours would also include, subject to agreement with the local authority:

    a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site.

    equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday.

    ** The main activities taking place 24 hours a day are below ground or within an enclosure.

  • 8/3/2019 P2 Kirtling Street SIP

    12/32

    Kirtling Street

    12

    Site layout and construction phases

    Figures 2C, 2D and 2E show how the site might be laid

    out during the construction phases, which are set outin Table 2.1 and Figure 2B. These layouts have been

    informed by the size of the infrastructure proposed,

    the construction methods required and the location

    of neighbouring buildings and structures. These have

    also been developed to minimise effects on the local

    community and environment. Particular factors at this site

    that have influenced the layout are as follows:

    Consideration has been given to the relationshipwith neighbouring developments, effects on the local

    highway network and river access to nearby wharves.

    The site layout would permit the continued use of the

    concrete batching works or its removal.

    The site layouts are indicative only, and the contractor

    may arrange the site in a different way, depending onthe chosen construction methods, provided that any

    environmental effects are appropriately managed and

    that the main construction activities are undertaken

    within the red line shown in Figure 1A.

    P1

    P2

    P3

    P4

    P5

    P6

    Year 1 Year 2 Year 3 Year 4 Year 5

    Advan

    ce

    works

    Figure 2B: Construction timeline showing approximate duration of works in phases (P)

  • 8/3/2019 P2 Kirtling Street SIP

    13/32

    Construction

    13

    Figure 2C: Illustrative phases 1 and 2 construction plan

    Jack up bargeservicing piling

    operations

    Cranes

    Piling rig

    Conveyor

    Shaft

    N

    Maximum extent ofconstruction site for

    phases 1 and 2Site hoarding

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing Thames Path

    Thames Path diversion

  • 8/3/2019 P2 Kirtling Street SIP

    14/32

    Kirtling Street

    14

    Figure 2D: Illustrative phase 3 construction plan

    Shaft

    Barges

    Gantry crane

    N

    Maximum extent ofconstruction site forphase 3

    Site hoarding

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing Thames Path

    Thames Path diversion

    Noise enclosure overshaft and gantry crane

    Crane

    Conveyor

  • 8/3/2019 P2 Kirtling Street SIP

    15/32

    Construction

    15

    Figure 2E: Illustrative phases 4 and 5 construction plan

    N

    Shaft

    Gantry crane

    Conveyor

    Maximum extent ofconstruction site forphases 4 and 5

    Site hoarding

    Site support/welfare

    Excavated materialstorage and processing

    Maintenance workshopand storage

    Construction support

    Internal site road

    Site access

    Existing Thames Path

    Thames Path diversion

    Noise enclosure overshaft and gantry crane

    Ki tli St t

  • 8/3/2019 P2 Kirtling Street SIP

    16/32

    Kirtling Street

    16

    Additional works and activities

    The main construction activities at this site are set out in

    Table 2.1. We would also need to undertake additionalworks and activities, some of which may be located

    outside of the area indicated by the red line in Figure 1A.

    The anticipated additional works and activities are set

    out in Table 2.2.

    When Type of works What we would do

    Required for

    construction

    phase

    Installation of equipment

    to monitor environmental

    matters such as noise,

    vibration and dust.

    The locations of monitoring equipment would be agreed with the local

    authority and relevant landowners.

    Protection works to third

    party structures (such as

    buildings, bridges and

    tunnels).

    We would undertake studies to identify any effects our construction

    work may have on third party structures. The studies may recommend

    particular construction methods or, in very limited instances, protection

    works.

    Temporary connection to

    utilities (such as water,

    sewer, phone and electricity

    supply).

    We expect to connect to water, sewer and phone supplies in Cringle

    Street or Kirtling Street.

    A major new electricity supply would be required at this site to provide

    power during construction. We expect to connect to a cable tunnel at

    Kirtling Street, running cables along Cringle Street and Kirtling Street.

    Traffic management works.These may need to extend beyond our site and could include relocating

    kerb lines, repainting road lines and modifying traffic signals.

    Dredging.There is a possibility that as the detailed design is developed we may

    need to undertake dredging to allow barges to get to and from our site.

    Required for

    operational

    phase

    Permanent connection

    to utilities (such as water,

    phone and electricity supply)

    for the operational tunnel.

    We expect to connect to utilities in Cringle Street or Kirtling Street.

    Table 2.2: Additional works and activities

  • 8/3/2019 P2 Kirtling Street SIP

    17/32

    Construction

    17

    Construction transport and access

    We propose to use barges to transport the majority of

    excavated material from the tunnel. It is not generally

    practical and cost effective to transport all materials

    to and from the site by barge so we would still need to

    transport some materials by road. We would however

    give the contractor the flexibility to determine the most

    practical and cost-effective means of transporting other

    materials and equipment.

    Each barge would remove approximately 55 lorries from

    the road. Using barges at this site would reduce the

    number of lorry visits to/from this site by approximately

    65% (saving 85,000 lorry visits over the construction

    period of approximately six years). Construction works

    at this site would support the works at our Heathwall

    Pumping Station site with welfare facilities, offices and

    site management for the two sites being located at

    Kirtling Street. Figure 1A shows the location of both sites.

    Table 2.3 sets out the anticipated average daily number

    of lorries and barges visiting (ie travelling to and from)the site during the peak months of each phase, based on

    moving excavated material from the tunnel by barge. We

    are also considering whether use could be made of the

    rail network.

    Table 2.3: Average daily lorry and barge visits during the peak months

    Construction traffic would access the site from Battersea

    Park Road (A3205), turning left into Kirtling Street and

    right into Cringle Street. Traffic leaving the site would turn

    left onto Nine Elms Lane (A3205) from Cringle Street.

    These access points are shown on Figure 2F. Beyond this,

    construction traffic would use the major road network to

    get to and from its final destination.

    The Thames Path runs past the proposed site access on

    Kirtling Street and through our construction site, so we

    would need to divert it during construction. We expect to

    divert it along Nine Elms Lane (A3205) and Kirtling Street

    to the east of the site, as shown on Figures 2C, 2D and 2E.

    As shown in the section on future use, the Thames Path

    may run along part of the riverfront after construction

    is completed. We would consider whether it would be

    possible to extend the Thames Path across the front of

    the whole site.

    We may also need to make modifications to the junction

    of Nine Elms Lane (A3205) and Kirtling Street and the

    junction of Nine Elms Lane (A3205) and Cringle Street

    in order to accommodate the movement of construction

    traffic. Based on our current design, we do not anticipate

    that any parking bay suspensions or bus stop relocations

    would be required.

    Phase 1Site setup

    Phase 2Shaft

    construction

    Phase 3Tunnelling

    Phase 4Secondary

    lining

    Phase 5Construction

    of otherstructures

    Phase 6Completion

    of worksand site

    restoration

    Average daily

    lorry visits26 lorries 64 lorries 67 lorries 35 lorries 30 lorries 9 lorries

    Average daily

    barge visits none none 4 barges none none none

    Kirtling Street

  • 8/3/2019 P2 Kirtling Street SIP

    18/32

    Kirtling Street

    18

    Figure 2F: Proposed access route to the site from the nearest major road

    KirtlingStreet

    Nine Elms Lane

    Cringle StreetKirtling Street

    Possible junctionmodifications

    CringleStreet

    A3035

    Battersea Park Road

    N

    WANDSWORTH

    CITY OF WESTMINSTER

    Draft limit of land tobe acquired or used

    Internal site road

    Site access

    Local authority boundary

    Transport for London(TfL) road network

    Proposed lorry access to

    TfL road network

    Related documents:

    Transport

    Construction

  • 8/3/2019 P2 Kirtling Street SIP

    19/32

    Construction

    19

    Management of construction works

    Our construction works would be managed in accordance

    with an agreed Code of construction practice (CoCP).For phase two consultation, we have produced a draft

    CoCP Part A: General requirements, informed by CoCPsfrom other major construction projects in London and

    consultation with the local authorities. Through the

    environmental impact assessment process, scheme-

    wide principles to address potential effects on the local

    environment have been identified and integrated into

    the design. The CoCP Part A sets out scheme-wide control

    measures that would be used to minimise potentialeffects during the construction process.

    Table 2.4 sets out what we consider to be the key issues

    for this site during construction, and how we are currently

    proposing to address them.

    Related documents:

    Environment

    Kirtling Street

  • 8/3/2019 P2 Kirtling Street SIP

    20/32

    Kirtling Street

    20

    Issue Our response

    Possible conflict with

    recent proposals for theredevelopment of Nine

    Elms Pier.

    We objected to the planning application for a new marina in summer 2011. However, asthe application has been amended, we would continue to work with the developers and the

    local authority to agree a phasing programme that allows construction of the main tunnel.

    Construction works may

    require the relocation of

    some of the 22 house

    boats from around Nine

    Elms Pier.

    We would investigate alternative mooring options for the houseboats as required.

    Possible conflict withpart of the consented

    redevelopment of

    Battersea Power Station.

    We are in contact with the owners/developers of this site and hope to negotiate an

    acceptable arrangement to both parties for use of this site before finalising our proposals.

    Construction activities

    may affect existing barge

    operations from the

    safeguarded wharves.

    It is expected that current users of the waste transfer station would continue to operate

    during construction. Arrangements would be discussed following completion of the

    Navigational Risk Assessment that we have commissioned. Discussions are ongoing

    with the concrete batching works owner regarding use of the site and associated wharf

    during our construction works. The future use of the safeguarded wharf would not becompromised by our permanent works.

    Construction works would

    require the demolition

    of six vacant offices in

    Brooks Court.

    We have sought to minimise the number of properties that must be removed and have an

    established procedure for consulting with and providing appropriate compensation to site

    owners. It is not expected that the properties would be reinstated following completion

    of construction works, as the site is part of the wider Vauxhall and Nine Elms Opportunity

    Area, which is expected to be comprehensively regenerated.

    Possible effect of

    construction vehicles on

    the volume of traffic on

    Nine Elms Lane (A3205).

    Construction works at this site would generate large volumes of excavated material whichwould need to be transported off site.

    We have sought to minimise disruption to the local road network through our site

    layout and design. We would manage the effects of road transport through our traffic

    management plans, which will seek to limit the number of vehicle movements and hours

    of operation, identify the most suitable site access points and any necessary highway

    management arrangements. As already set out, we also propose to use barges to transport

    the majority of excavated material from the tunnel, which would reduce the number of

    lorry movements from this site by approximately 65% over the construction period. We arealso considering whether use could be made of the rail network.

    Construction

  • 8/3/2019 P2 Kirtling Street SIP

    21/32

    Construction

    21

    Issue Our response

    Temporary diversion ofthe Thames Path along

    Kirtling Street.

    The section of the Thames Path running past the proposed site access and through theconstruction site would be temporarily diverted via a safe alternative route to the east of

    the site, along Nine Elms Lane (A3205) and Kirtling Street.

    The proposed

    construction site access

    off Cringle Street is

    shared with other sites

    and businesses.

    The road would be kept open during construction to maintain existing access to other sites

    and businesses, including the waste transfer station and the public amenity site at Cringle

    Dock, our existing water treatment works, Battersea Power Station and the new residential

    development Riverlight.

    Possible effect of

    noise and vibration on

    neighbouring areas.

    The contractor would be required to implement noise and vibration control measures at

    the worksite, which will be set out in the CoCP. We need to undertake continuous tunnelling

    at this site for reasons of safety, cost and programme. While continuous tunnelling is

    taking place, the working area would be enclosed in a temporary structure which would

    significantly reduce noise levels. Materials needed to construct the tunnel at night would

    also be loaded into the building during the day, to minimise machinery and vehicle

    movements at night.

    Possible effects on local

    air quality and dust

    nuisance in neighbouring

    areas.

    Preliminary findings indicate that while there is the potential for dust nuisance effects,

    there are unlikely to be any significant local air quality effects at any of the sites. The

    contractor would put in place air and dust control measures at the worksite, which will be

    set out in the CoCP. This would include enclosing the working area whilst tunnelling works

    are carried out to limit dust leaving the site.

    Table 2.4: Key issues relating to construction

    Related documents:

    Managing construction

    Transport

    Kirtling Street

  • 8/3/2019 P2 Kirtling Street SIP

    22/32

    Kirtling Street

    22

    Section 3: Future use

    This section describes the site after the completion of the

    construction work, ie when the main tunnel is in use the

    operational phase.

    Design

    The design of the permanent use and appearance of

    the structures at Kirtling Street follows our scheme-wide

    principles and takes into account comments raised

    during ongoing engagement with the London Borough ofWandsworth and other technical consultees.

    Our permanent works need to incorporate functional

    elements, which are required for the operation of thetunnel. These include:

    Underground structures with ground level access covers

    including: a main tunnel shaft with an internal diameter

    of approximately 30m and a passive filter chamber.

    One ventilation column up to 6m high.

    Maintenance vehicle access.

    An electrical and control kiosk.

    Table 3.1 sets out the site specific issues that have

    influenced our permanent design proposals and how we

    have addressed them in our proposed design.

    Future use

  • 8/3/2019 P2 Kirtling Street SIP

    23/32

    Future

    use

    23

    Issue Our response

    Effects on the future development

    of the site and area.

    We have located the main tunnel site to optimise critical engineering

    requirements and avoid compromising the future development of the site.

    Visual effect of the permanent

    works.

    As a result of the modified scheme-wide ventilation strategy, the need for a

    ventilation building at this location has been eliminated, with passive ventilation

    only required.

    Effect on the Thames Path.

    After the completion of construction, the Thames Path may extend along the

    eastern part of the Kirtling Street site to facilitate future access and connectivity

    in the area following completion of development by the developer. We would

    consider whether it would be possible to extend the Thames Path across the frontof the whole site.

    Table 3.1: Site specific issues that have influenced our permanent design

    Kirtling Street

  • 8/3/2019 P2 Kirtling Street SIP

    24/32

    Kirtling Street

    24

    Figure 3A: Aerial view of the completed works

    Figures 3A and 3B provide illustrations of our design

    proposals. Further information on the development of our

    design can be found in the Design development report.Related documents:

    Design

    Future use

  • 8/3/2019 P2 Kirtling Street SIP

    25/32

    25

    Figure 3B: Layout of site once construction works complete

    Permanentaccess for

    maintenance

    Combinedventilation

    structure andequipment kiosk

    SafeguardedWharf jetty

    retained

    Temporaryhoardingaround site fordevelopmentby others

    Riverlightdevelopment

    Nine Elms pier

    Kirtling Street

    resurfaced

    Thames Pathwayfinding

    signage

    KirtlingStreet

    CringleStreet

    Nin

    eEl

    msLan

    e

    N

    New fence toboundary of concrete

    batching works site

    Kirtling Street

  • 8/3/2019 P2 Kirtling Street SIP

    26/32

    t g St eet

    26

    Operation and maintenance

    Once the tunnel is operational, we would need access

    to the site occasionally for inspection and maintenance

    purposes. We expect to visit the site approximately onceevery three to six months to carry out inspections and

    maintenance of the ventilation equipment. This is likely

    to involve a visit by staff in a small van, and may take

    several hours.

    Once every ten years, we expect to carry out a major

    internal inspection of the tunnel and underground

    structures. This is likely to involve a small team of

    inspection staff, a small team of support crew and twomobile cranes to lower the team and inspection vehicle

    into the shaft. This is likely to take several weeks, and

    would require temporary fencing around the shaft for

    safety and security while the inspection takes place.

    We may also need to make visits to the site for unplanned

    maintenance or repairs, for example if there is a blockage

    or equipment failure. This may require the use of mobile

    cranes and vans.

    Permanent vehicular access would be from Kirtling Street.

    Management of operational effects

    We have undertaken technical work, including stakeholder

    engagement, to assess and identify the key issues

    associated with this site once it is operational. Table3.2 summarises these issues and how we are currently

    proposing to address them.

    Future use

  • 8/3/2019 P2 Kirtling Street SIP

    27/32

    27

    Issue Our response

    Possible odour effects during

    the operation of the tunnel.

    Odour effects at this site are expected to be negligible because we have developed

    anAir management plan to minimise possible odour and air quality effects arisingfrom the operation of the tunnel. The technology we are proposing to use at this site

    includes the use of passive below ground carbon filters that will remove possible odour

    before air leaves the ventilation equipment.

    Disturbance from future

    maintenance access.

    Permanent access would be required for maintenance and servicing purposes to the

    shaft and ventilation equipment. Any planned maintenance visits would be undertaken

    during normal working hours and all visits managed to avoid disruption to local

    residents, businesses and users of affected public areas as far as possible.

    Table 3.2: Key issues relating to site operation

    Related documents:

    Odour

    Further information

  • 8/3/2019 P2 Kirtling Street SIP

    28/32

    28

    This section sets out documents which may be of particular interest. Further information on our proposals can be

    found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre

    on 0800 0721 086).

    Phase two public consultation material

    Project information papers include general information about the Thames Tunnel project. There are 17 project

    information papers, which cover various aspects of the project. Those project information papers that may be of

    particular interest are set out below.

    Icon Title Details

    Build

    Provides information on the different types of sites required for the Thames Tunnel

    project and the typical construction activities that will be undertaken at each site.

    Changes

    Explains how the scheme has changed compared to that presented at phase one

    consultation, including changes to the tunnelling strategy for the main tunnel and

    changes to sites.

    Q&A Consultation

    Sets out the consultation we have undertaken to date on the project, the scope

    of this phase two consultation and how interested parties can respond to thisconsultation.

    DesignContains the design principles which have influenced the permanent appearance of

    our sites once construction work is complete.

    EnvironmentSets out the process the project is following to assess potential environmental effects

    of the Thames Tunnel project.

    Managing

    construction

    Includes information on what measures our contractors will put in place at our sites

    during construction.

    Odour Sets out ourAir management plan and how it will work.

    Options Outlines the various ways to deal with sewage overflows.

  • 8/3/2019 P2 Kirtling Street SIP

    29/32

    29

    Phase two public consultation material

    Icon Title Details

    OverflowSets out how Londons sewerage system works and why the capital has an overflow

    problem.

    Route and

    tunnel

    alignment

    Sets out the preferred route of the main tunnel and the reasons for our preference.

    Site selection Sets out the process we followed to find and select our preferred sites.

    Transport Contains information on the different transport options we have considered fordelivering and removing materials from our sites.

    Site information papers provide information that relate to each preferred site along the route of the Thames Tunnel

    project. The following site information papers may be of particular interest.

    Carnwath Road Riverside

    Chambers Wharf

    Heathwall Pumping Station

    CRR

    CW

    HePS

    Further information

  • 8/3/2019 P2 Kirtling Street SIP

    30/32

    30

    Technical reports

    Theme Icon Title Details

    Interim

    engagement

    Interim engagement

    report

    Provides a summary of the public engagement we

    have undertaken between phase one and phase two

    consultations.

    Phase one

    consultation1

    SUMMARY

    Report on phase one

    consultation:

    summary report

    Provides a summary of the comments made at phase one

    consultation and our responses.

    Phase two

    construction

    information

    Code of construction

    practice Part A:

    General requirements

    (CoCP)

    Sets out control measures to be adopted during the project

    construction period.

    Phase twoenvironmental

    information

    Air management

    plan

    Outlines the methods which we will use to manage odour

    from the main tunnel at all our preferred sites.

    Preliminary

    environmental

    information report

    (PEIR)

    Contains initial assessments on the environmental effects of

    the Thames Tunnel project based on information collected

    to date. Please refer to volume 17 of the non-technical

    summary and volume 17 of the PEIR for more information

    on this site.

    Phase two scheme

    development

    Design development

    report

    Provides a general overview of how the scheme design at

    each site has evolved to date. Please refer to chapter 12 for

    more information on this site.

    2

    Phase two scheme

    development report

    Provides an overview of the development of the Thames

    Tunnel project and how each site was chosen. Please refer to

    Appendix L for more information on this site.

    Site glossary

  • 8/3/2019 P2 Kirtling Street SIP

    31/32

    31

    Term Definition

    Carbon filters Filters that remove odours before the air is released from the tunnel.

    Combined sewer A single sewer system that takes both rainwater and domestic and industrial wastewater.

    Combined sewer

    overflow (CSO)

    A structure, or series of structures, that allows sewers to overflow into the river when they

    are full as a result of increased rainfall. Without the overflows, the sewers would back up and

    cause flooding in streets or houses.

    Draft limit of land to

    be acquired or used

    The extent of land that we may need to use or acquire, or over which rights may be needed to

    carry out works that are essential to the project.

    Foreshore Ground uncovered by the river when the tide is low.

    Main tunnel/connection tunnel

    drive site

    A site that would be used to construct the main tunnel or connection tunnel. The excavatedmaterial would be removed from the tunnel and the concrete tunnel lining segments would

    be delivered to the tunnel at the main/connection tunnel drive site.

    Main tunnel The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station.

    Operational phase After the completion of the construction work, when the main tunnel is in use.

    Secondary lining A second, internal lining to the tunnel, giving it additional strength.

    Thames Tunnel project

    The Thames Tunnel project comprises a storage and transfer tunnel, from west London to

    Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along theThames Tideway.

    Transport for London

    Road Network (TLRN)

    The network of roads managed by Transport for London. These are the major or strategic

    roads, which have high capacity.

    Tunnel boring machine

    (TBM)

    A machine used to excavate tunnels through a variety of conditions, with a circular

    cross-section.

  • 8/3/2019 P2 Kirtling Street SIP

    32/32

    Phase two consultation: Kirtling Street

    For further information or to comment on our

    proposals see our website:

    www.thamestunnelconsultation.co.uk

    110-ED-PNC-00000-000088

    Autumn 2011

    It is very important that you understand theinformation we have provided. If you needfurther information in another language,

    braille, large print or audio format pleasecontact us on 0800 0721 086.