    P3M3 v2.1 Sel-Assessment2

    P3M3 Project Management Sel-Assessment

    Contents

    Introduction 3

    User Guidance 4

    P3M3 Sel-Assessment Questionnaire 6

    P3M3 Model Answers 17

    Next Steps 20

    P3M3 a Registered Trade Mark o the Oce o Government CommerceThe OGC logo is a Registered Trade Mark o the Oce o Government Commerce in the United Kingdom

  • 8/22/2019 P3M3 Self Assess Project

    3/22

    P3M3 v2.1 Sel-Assessment 3

    P3M3 Project Management Sel-Assessment

    Introduction

    Sel-AssessmentP3M3 (Portolio, Programme and ProjectManagement Maturity Model) is an overarchingmodel containing three individual models:

    Portolio Management Maturity Model (PM3)Programme Management Maturity Model (PgM3)Project Management Maturity Model (PjM3)

    Although connected, there are no interdependenciesbetween these models which allows or independentassessment in any o the specic disciplines. For

    example, an organizations programme managementcapabilities may be more evolved than its projectmanagement capabilities, so the project managementmodel can be used as a stand-alone tool whenlooking to improve that area.

    Each model uses a ve-level maturity ramework andthe ve Maturity Levels are:

    Level 1 awareness o processLevel 2 repeatable processLevel 3 dened processLevel 4 managed processLevel 5 optimized process

    P3M3 ocuses on seven Process Perspectives,which exist in all three models and can be assessedagainst ve levels o maturity. The fexibility o P3M3allows organizations to review all seven ProcessPerspectives across all three models portolio,programme and project management but theycan also review just one (or several) o the ProcessPerspectives, whether across all three models or acrossonly one or two o them. This can be useul to gaina better understanding o an organizations overalleectiveness in, or example, risk management orresource management.

    This sel-assessment tool should be read in conjunctionwith the P3M3 version 2.1 standard itsel and the OGCGlossary o terms. These can be ound at:

    Sel assessment at www.p3m3-ofcialsite.comCommon Glossary at www.best-management-practice.com/Glossary-and-Acronyms

    Use o the P3M3 Sel-AssessmentThe P3M3 sel-assessment can be used in many ways,or example:

    to provide a basic introduction and overview o thescope o P3M3

    to gauge the current level o organizationalmaturity in respect o portolio, programme and/orproject management

    to gain an understanding o the key practicesin eective portolio, programme and projectmanagement processes

    to identiy the key practices that need to beembedded within an organization or it toimprove process capability and achieve thenext Maturity Level

    to understand and improve an organizationscapability to manage its portolio, programmes andprojects more eectively.

    The P3M3 sel-assessment questionnaire is one oa number o alternative ways or an organizationto begin to explore the P3M3 model. It introducessome o the core concepts such as the ve MaturityLevels and seven Process Perspectives that are theoundations o the P3M3.

    By completing the sel-assessment questionnaire,a relatively quick evaluation o the current

    organizational maturity with respect to portolio,programme and/or project management is obtained.Do remember though, that sel-assessments tendto introduce a degree o optimism bias that is otenremoved through a acilitated assessment conductedby a competent third party.

    The sel-assessment questionnaire may be usedas an introduction to the model and individuals incompleting the questionnaire are encouraged toexplore the P3M3 urther. It may also be used asperhaps a pre-cursor to seeking urther inormation,external consultancy, training or assistance on using

    P3M3. Further inormation, including details o ormalreviews, can be ound on the ocial P3M3 website.

    It should o course be recognised that the actualP3M3 model and in particular the Attributes -indicators o process and behavioural maturity,should be reerenced in drawing-up an improvementplan. The P3M3 model and knowledge o wherethe organization needs or wants to be positioned inuture, should underpin any subsequent improvementinitiatives and the P3M3 model and not simply thesel-assessment questionnaire should be the basis ocontinuous improvement initiatives.

  • 8/22/2019 P3M3 Self Assess Project

    4/22

    P3M3 v2.1 Sel-Assessment4

    P3M3 Project Management Sel-Assessment

    User Guidance

    The sel-assessment consists o nine questions andalthough the sel-assessment is based on a ewquestions, it remains a powerul tool addressingboth process capability and providing insight into anorganizations Maturity Levels in respect o portolio,programme and project management.

    In completing the sel-assessment, a decision needsto be taken on whether the scope will be limitedto a particular combination o portolio, and/or programme and/or project management. Forexample, an organization may wish to assess just

    project management, or programme and projectmanagement. A second decision on scope is todetermine the boundary o the organization that isto be reviewed i.e. is it the whole organization or aparticular division or department alone?

    The rst question relates to the overall organizationalmaturity levels. The aim in answering this questionis to ascertain which o the ve Maturity Leveldescriptions best describes the portolio, programmeand/or project management processes within theorganization. In answering this question, users areencouraged not only to amiliarize themselves with

    the denitions o portolio, programme and/or projectmanagement within Chapters 3, 4, and 5 o theP3M3 respectively, but to amiliarize themselves withthe characteristics which constitute best practice.

    The questionnaire then contains seven questions,one or each o the Perspectives contained withinP3M3 covering:

    Management ControlBenets ManagementFinancial ManagementStakeholder Engagement

    Risk ManagementOrganizational GovernanceResource Management

    In completing the sel-assessment questionnaire,a user may elect to answer questions on a subseto perspectives that are perhaps o particular interestto the organization or refect the particular usersknowledge o the organizations processesand practices.

    A description is presented or each perspectivecovering ve levels o maturity or portolio and/orprogramme and/or project management.

    The user needs to simply decide which o theve descriptions most adequately refects theorganizations current capability.

    In reading the descriptions, the user may concludethat the organization could be positioned withinperhaps two o the Levels. In such circumstances, theuser should review the specic Attributes associatedwith the Perspective Level descriptions within P3M3.There are usually c.10 attributes associated with eachPerspective Level and the user should review each othe specic Attributes in turn or the two Levels and

    consider whether the specic attribute is true or alsein respect to current practice within the organization.By simply counting the number o armative specicAttributes within two Levels, a decision can be takenbased on the greater number o armative Attributes.In the unlikely case that the count is the samebetween two levels, then the organization shouldselect the lower Perspective Level.

    The nal question, provides a cross-check on thestructural components i.e. between the individualperspectives and the overall maturity level orportolio, programme and/or project management.

    It should be remembered that sel-assessment has atendency to result in some optimism bias and thatalthough by completing the questionnaire, one willhave indicative values o process capability and theoverall organizational maturity in relation to portolio,and/or programme and/or project management, itcannot be relied upon to the same extent as a detailedacilitated assessment carried out by a qualied,registered consultant.

    Step-by-Step GuideThe ollowing steps provide a simple guide toaccomplishing a P3M3 sel-assessment.

    The rst step, ater amiliarizing onesel with thegeneral scope o P3M3, is to decide on the intento the sel-assessment, the range o areas to becovered and the parts o the overall organizationto be included. For example, it may be the intentto limit the assessment to programme and/orproject management, or perhaps to look at (say)organizational governance and risk managementacross portolio, programme and projectmanagement, or to limit the scope to onedivision alone.

  • 8/22/2019 P3M3 Self Assess Project

    5/22

    P3M3 v2.1 Sel-Assessment 5

    P3M3 Project Management Sel-Assessment

    The next step, having determined the scope o theassessment is to determine the most appropriateindividual(s) to complete the exercise. The sel-

    assessment may be undertaken by: an individual, with knowledge o theorganizations portolio, programme and/orproject management processes and practices,as applicable

    a group o people, either individually, or as ateam to arrive at a consensus

    an internal or external acilitator, to identiykey individuals, e.g. Project Director, ProgrammeManagers, collating answers rom key personneleither individually or in groups and analysing the

    response(s).Having decided upon the assessment scope, anddetermined the approach and who will contributeto answering the questionnaire, the assessment canbe completed, by reerring to the model answerssupplied. The most appropriate response rom themodel answer specication should be selected thatrefects the current process / practices within theorganization. Where a group o individuals haveprovided their answers, the leader o the review willneed to determine and agree a process or combiningthe individual scores. This might be the minimum

    score, or some orm o averaging.

    The penultimate step is to analyze the results o theassessment in the context o the organizations goalsor intent. For example, the sel-assessment may havebeen undertaken to provide a current baseline romwhich the ecacy o process improvement can bejudged; alternatively it may be used to help justiy thecase or investment in (say) programme managementmethods training.

    The nal step, having analyzed the results o the sel-assessment is to consider and plan the next steps and

    perhaps continue to improve portolio, programmeand/or project management within the organizationleading to improved eciency, quality and successuldelivery o the organizations initiatives.

    Generic Approach to P3M3 Sel-Assessment

    Decide Assessment Scope

    Decide Approach

    Determine Suitable Assessors

    Complete Assessment

    Analyze Assessment Results

    Consider Next Steps

  • 8/22/2019 P3M3 Self Assess Project

    6/22

    P3M3 v2.1 Sel-Assessment6

    P3M3 Project Management Sel-Assessment

    P3M3 uses a ve-level maturity ramework and theve Maturity Levels are:

    Level 1 awareness o processLevel 2 repeatable processLevel 3 dened processLevel 4 managed processLevel 5 optimized process

    The descriptions and characteristics o the veMaturity Levels apply equally to each o the threesub-models Portolio, Programme and Project

    Management. P3M3 recognizes that organizationsmay excel at project management without havingembraced programme management, or indeed viceversa. Similarly, an organization may be accomplishedin portolio management but immature in programmemanagement. P3M3 thereore allows an organizationto assess its eectiveness against any one or more othe sub-models independently. Although an overallP3M3 maturity rating cannot be given, since eachmodel is independent rom the others, gauging theoverall maturity o an organization is still possible byundertaking assessments under all three sub-models.

    The rst question relates to the overall organizationalmaturity levels. The aim in answering this questionis to ascertain which o the ve descriptions givenbelow is the most accurate refection o the portolio,programme and/or project management processes.

    P3M3 Sel-Assessment Questionnaire

  • 8/22/2019 P3M3 Self Assess Project

    7/22

    P3M3 v2.1 Sel-Assessment 7

    P3M3 Project Management Sel-Assessment

    a

    b

    c

    Organisation description

    Processes are not usually documented; there are no, or only a ew, process descriptions.Actual practice is determined by events or individual preerences, and perormance is variable.

    Successul initiatives are oten based on key individuals competencies rather than organization-

    wide knowledge and capability and the organization is unable to repeat past successesconsistently. Such successes are oten achieved with budget and/or schedule overruns.

    Processes are undeveloped or incomplete. There is little, i any, guidance or supportingdocumentation, and even terminology may not be standardized across the organization e.g. business case, risk, issues, etc. may not be interpreted in the same way by all managers

    and team members.

    The organization is able to demonstrate that basic management practices have been established

    e.g. tracking expenditure and scheduling resources and that processes are developing. Thereare key individuals who have had suitable training and who can demonstrate a successul trackrecord and through them, the organization is capable o repeating earlier successes in the uture.

    Initiatives are perormed and managed according to their documented plans; project status anddelivery is visible to management at dened points, such as on reaching major milestones.

    The organization may still have inadequate measures o success; unclear responsibilities or achievement;ambiguity and inconsistency in business objectives; lack o ully integrated risk management; limited

    experience in change management; and inadequacies in communications strategy.

    Management and technical processes are documented, standardized and integrated tosome extent with other business processes. There is likely to be process ownership and an

    established process group with responsibility or maintaining consistency and delivering processimprovements across the organization.

    Senior management are engaged consistently and provide active and inormed support.

    There is likely to be an established training programme to develop the skills and knowledgeo individuals so they can more readily perorm their designated roles. A key aspect o qualitymanagement will be the widespread use o peer reviews o identied products, to betterunderstand how processes can be improved and thereby eliminate possible weaknesses.

    A key distinction between this and the previous level description is the scope o standards, process

    descriptions and procedures. Processes will be managed more proactively and the standard processescan be tailored to suit specic circumstances, in accordance with explicit guidelines.

    Tick the mostappropriate

    description

    Question 1: Our organization can be best characterised as having:

  • 8/22/2019 P3M3 Self Assess Project

    8/22

    P3M3 v2.1 Sel-Assessment8

    P3M3 Project Management Sel-Assessment

    P3M3 contains seven process perspectivesthat identiy the key characteristics o matureorganizations using portolio, programme and/orproject management to successully achieve strategicobjectives and priorities. The processes and practicesthat characterise a particular level o maturity withineach perspective are described.

    The ollowing set o questions is intended toexamine the maturity associated with eacho the seven perspectives.

    d

    e

    Organisation description

    The organization demonstrates mature behaviour through dened processes that arequantitatively managed i.e. controlled using metrics and quantitative techniques. There is goodevidence o quantitative objectives or quality and process perormance, and these are being

    used as criteria in managing processes. The measurement data collected is contributing towardsthe organizations overall perormance measurement ramework and acilitates portolio analysisand ascertaining the current capacity and capability constraints.

    Top management are proactively seeking out innovative ways to achieve goals.

    Using metrics, management can eectively control processes and identiy ways to adjust andadapt them to particular initiatives without loss o quality.

    The organization is ocused on optimization o its quantitatively managed processes to take into

    account changing business needs and external actors. It is able to anticipate uture capacity demandsand capability requirements to meet delivery challenges e.g. through portolio analysis.

    Top managers are seen as exemplars, reinorcing the need and potential or capability and

    perormance improvement.

    The knowledge gained by the organization rom its process and product metrics will enable it to

    understand causes o variation and thereore optimize its perormance. The organization will be ableto show that continuous process improvement is being enabled by quantitative eedback rom itsembedded processes and rom validating innovative ideas and technologies. The organization will be

    able to demonstrate strong alignment o organizational objectives with business plans, and this willbe cascaded down through scoping, sponsorship, commitment, planning, resource allocation, riskmanagement and benets realization.

    Tick the mostappropriate

    description

    Question 1: Our organization can be best characterised as having:

  • 8/22/2019 P3M3 Self Assess Project

    9/22

    P3M3 v2.1 Sel-Assessment 9

    P3M3 Project Management Sel-Assessment

    Management ControlThis covers the internal controls o the initiative andhow its direction o travel is maintained throughout

    its lie cycle, with appropriate break points to enableit to be stopped or redirected by a controlling bodyi necessary.

    Management control is characterized by clearevidence o leadership and direction, scope, stages,tranches and review processes during the course othe initiative. There will be regular checkpoints andclearly dened decision-making processes. There willbe ull and clear objectives and descriptions o whatthe initiative will deliver. Initiatives should have clearlydescribed outputs, a programme may have a blueprint

    (or target operating model) with dened outcomes,and a portolio may have an organizational blueprint(or target operating model).

    Internal structures will be aligned to achieve thesecharacteristics and the ocus o control will be onachieving them within the tolerance and boundariesset by the controlling body and based on the broaderorganizational requirements. Issues will be identiedand evaluated, and decisions on how to deal withthem will be made using a structured process withappropriate impact assessments.

    a

    b

    c

    d

    e

    Project Management

    Project management terminology is used by some members o the organization but not consistently and possibly notunderstood by all stakeholders. Projects are conducted and managed according to individual preerences.

    The concepts o project management will have been grasped by the organization, and there may be local experts,such as experienced project managers, working on key projects.

    There is a centrally dened and documented approach to a project management lie cycle and controls, and it is

    applied in all projects by capable sta who support project teams.

    Project management is seen as a key tool or the delivery mechanism o change. Within the project environment the

    ocus is on improvement o delivery through measurement and analysis o perormance.

    Management controls ensure that the project approach delivers the change objectives o the organization.Acceptance o project management as the optimal approach to change delivery is organization-wide. There isevidence o continual improvement.

    Question 2: Our management control is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    10/22

    P3M3 v2.1 Sel-Assessment10

    P3M3 Project Management Sel-Assessment

    Benefts ManagementBenets management is the process that ensures thatthe desired business change outcomes have been

    clearly dened are measurable and are ultimatelyrealized through a structured approach and with ullorganizational ownership.

    Benets should be assessed and approved by theorganizational areas that will deliver them. Benetdependencies and other requirements are clearlydened and understanding gained on how theoutputs o the initiative will meet those requirements.There should be evidence o suitable classicationo benets and a holistic view o the implicationsbeing considered. All benets should be owned,have realization plans and be actively managed to

    ensure that they are achieved. There will be a ocuson operational transition, coupled with ollow-upactivities to ensure that benets are being owned andrealized by the organization.

    There will be evidence o continual improvementbeing embedded in the way the organizationunctions. This process will identiy opportunities

    that can be delivered by initiatives and also takeownership o the exploitation o capabilities deliveredby programmes and projects. Change management,and the complexities this brings, will also be built intothe organizations approach.

    a

    b

    c

    d

    e

    Project Management

    There is some recognition that the concept o benets can be dierentiated rom project outputs.

    Benets are recognized as an element within project business cases. There may be some documentation regarding who

    is responsible or particular benets and their realization, but this is unlikely to be ollowed through or consistent.

    There is a centrally managed and consistent ramework or dening and tracking the realization o benets arising romproject outputs.

    Benets management is embedded within the project management approach and there is a ocus on delivery o businessperormance rom project outputs. Project perormance metrics are collected and analyzed.

    Benets management is embedded within the organizational approach to change and is assessed as part o the

    development o organizational strategy. Business perormance metrics are linked to, and underpin, the recognition obenets realization. There is evidence o continual improvement.

    Question 3: Our benefts management is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    11/22

    P3M3 v2.1 Sel-Assessment 11

    P3M3 Project Management Sel-Assessment

    Financial ManagementFinance is an essential resource that should be a keyocus or initiating and controlling initiatives. Financial

    management ensures that the likely costs o theinitiative are captured and evaluated within a ormalbusiness case and that costs are categorized andmanaged over the investment lie cycle.

    There should be evidence o the appropriateinvolvement o the organizations nancial unctions,with approvals being embedded in the broaderorganizational hierarchy. The business case, orequivalent, should dene the value o the initiativeto the business and contain a nancial appraisal othe possible options. The business case will be atthe core o decision-making during the initiatives

    lie cycle, and may be linked to ormal review stagesand evaluation o the cost and benets associatedwith alternative actions. Financial management willschedule the availability o unds to support theinvestment decisions.

    a

    b

    c

    d

    e

    Project Management

    There is little or no nancial control at project level. There is a lack o accountability and monitoring o project expenditure.

    Project business cases are produced in various orms and the better and more ormal cases will present the rationale on

    which to obtain organizational commitment to the project. Overall cost o the project is not monitored or ully accounted or.

    There are centrally established standards or the preparation o business cases and processes or their managementthroughout the project lie cycle. Project managers monitor costs and expenditure in accordance with organizational

    guidelines and procedures, with dened interaces with other nancial unctions within the organization.

    The organization is able to prioritize investment opportunities eectively in relation to the availability o unds and other

    resources. Project budgets are managed eectively and project perormance against cost is monitored and compared.

    Project nancial controls are ully integrated with those o the organization. Cost estimation techniques used atthe project level are continually reviewed in terms o actual versus estimate comparisons to improve estimationthroughout the organization. There is evidence o continual improvement.

    Question 4: Our fnancial management is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    12/22

    P3M3 v2.1 Sel-Assessment12

    P3M3 Project Management Sel-Assessment

    Stakeholder EngagementStakeholders are key to the success o anyinitiative. Stakeholders at dierent levels, both

    within and outside the organization, will needto be analyzed and engaged with eectively inorder to achieve objectives in terms o support andengagement. Stakeholder engagement includescommunications planning, the eective identicationand use o dierent communications channels, andtechniques to enable objectives to be achieved.Stakeholder engagement should be seen as anongoing process across all initiatives and one thatis inherently linked to the initiatives lie cycle andgovernance controls.

    a

    b

    c

    d

    e

    Project Management

    Stakeholder engagement and communication is rarely used by projects as an element o the delivery toolkit.

    Some projects will be communicated to stakeholders, but this is linked more to the personal initiative o project managersthan to a structured approach being deployed by the organization.

    There is a centrally managed and consistent approach to stakeholder engagement and communications used by all projects.

    Sophisticated techniques are used to analyze and engage the project stakeholder environment eectively, and quantitativeinormation is used to underpin the assessment o eectiveness.

    Communications are being optimized rom extensive knowledge o the stakeholder environment, to enable the projects toachieve their objectives. There is evidence o continual improvement.

    Question 5: Our approach to stakeholder engagement is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    13/22

    P3M3 v2.1 Sel-Assessment 13

    P3M3 Project Management Sel-Assessment

    Risk ManagementThis views the way in which the organizationmanages threats to, and opportunities presented

    by, the initiative. Risk management maintains abalance o ocus on threats and opportunities, withappropriate management actions to minimize oreliminate the likelihood o any identied threatoccurring, or to minimize its impact i it does occur,and maximize opportunities. It will look at a variety orisk types, both internal and external, that aect theinitiative and will ocus on tracking the triggers thatcreate risks.

    Responses to risk will be innovative and proactive,using a number o options to minimize threats andmaximise opportunities. The review o risk will be

    embedded within the initiatives lie cycle and havea supporting process and structures to ensure thatthe appropriate levels o rigour are being applied,with evidence o interventions and changes made tomanage risks.

    a

    b

    c

    d

    e

    Project Management

    There is minimal evidence o risk management being used to any benecial eect on projects. There may be evidenceo risks being documented but little evidence o active management.

    Risk management is recognized and used on projects, but there are inconsistent approaches which result in dierent levels

    o commitment and eectiveness.

    Project risk management is based on a centrally dened process that is cognizant o the organizations policy or themanagement o risks and is used consistently.

    Project risk management is working eectively, is embedded, and the value o risk management can be demonstrated.

    There is evidence o opportunity management and management o risk aggregation.

    Risk management is embedded in the organizational culture and underpins all decision-making within projects.There is evidence o continual improvement.

    Question 6: Our risk management is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    14/22

    P3M3 v2.1 Sel-Assessment14

    P3M3 Project Management Sel-Assessment

    Organizational GovernanceThis looks at how the delivery o initiatives is alignedto the strategic direction o the organization. It

    considers how start-up and closure controls areapplied to initiatives and how alignment is maintainedduring an initiatives lie cycle. This diers rommanagement control, which views how control oinitiatives is maintained internally, as this perspectivelooks at how external actors that impact on initiativesare controlled (where possible, or mitigated i not)and used to maximize the nal result. Eectivesponsorship should enable this.

    Organizational governance also looks at how arange o other organizational controls are deployedand standards achieved, including legislative and

    regulatory rameworks. It also considers the levels oanalysis o stakeholder engagement and how theirrequirements are actored into the design and deliveryo outputs and outcomes.

    a

    b

    c

    d

    e

    Project Management

    Some inormal governance o projects exists but has undened links to broader organizational controls. Roles are unlikelyto be ormally dened.

    Project management rom an organizational perspective is beginning to take shape but with ad hoc controls and no clear

    strategic control. Roles and responsibilities will be inconsistent, as will reporting lines.

    Centrally dened organizational controls are applied consistently to all projects, with decision-making structures in place

    and linked to organizational governance.

    There will be clearly aligned project decision-making processes that adopt and integrate with broader organizational

    governance and which are transparent to those involved. Project management responsibilities are embedded withinbroader role descriptions.

    The governance arrangements or projects are a core aspect o organizational control, with demonstrable reporting linesto Executive Board level and with clear ownership and control responsibilities embedded within the organization. There is

    evidence o continual improvement.

    Question 7: We deliver organizational governance by:

  • 8/22/2019 P3M3 Self Assess Project

    15/22

    P3M3 v2.1 Sel-Assessment 15

    P3M3 Project Management Sel-Assessment

    Resource ManagementResource management covers management o alltypes o resources required or delivery. These include

    human resources, buildings, equipment, supplies,inormation, tools and supporting teams. A keyelement o resource management is the process oracquiring resources and how supply chains are utilizedto maximize eective use o resources. There will beevidence o capacity planning and prioritization toenable eective resource management. This will alsoinclude perormance management and exploitationo opportunities or greater utilization. Resourcecapacity considerations will be extended to thecapacity o the operational groups to resourcethe implications o change.

    a

    b

    c

    d

    e

    Project Management

    There is some recognition within the organization o the need to manage resources eectively to enable successul deliveryo projects, but little evidence o resource acquisition, planning or management.

    Resources are being deployed across the organization and individual projects have an approach to resource acquisition,

    planning or management. However there is little evidence o consistency o approach.

    The organization has a centrally dened and adopted set o procedures and management processes or acquiring, planningand managing project resources.

    Resource management or projects is considered at a strategic level within the organization. There is evidence o resource

    capacity management, through capacity planning, in order to meet project delivery needs.

    Resources are deployed optimally. There is clear evidence o load balancing and the eective use o both internal and

    external resources across all projects. There is evidence o continual improvement.

    Question 8: Our resource management is best described by:

  • 8/22/2019 P3M3 Self Assess Project

    16/22

    P3M3 v2.1 Sel-Assessment16

    P3M3 Project Management Sel-Assessment

    a

    b

    c

    d

    e

    Project Management

    Recognize projects and run them dierently rom its ongoing business. (Projects may be run inormally with no standard

    process or tracking system).

    Ensure that each project is run with its own processes and procedures to a minimum specied standard. (There may belimited consistency or coordination between projects).

    Have its own centrally controlled project processes and individual projects can fex within these processes to suit theparticular project.

    Obtain and retain specic measurements on its project management perormance and run a quality management

    organization to better predict uture perormance.

    Undertake continuous process improvement with proactive problem and technology management or projects in order

    to improve its ability to depict perormance over time and optimize processes.

    Question 9: Does the organization:

  • 8/22/2019 P3M3 Self Assess Project

    17/22

    P3M3 v2.1 Sel-Assessment 17

    P3M3 Project Management Sel-Assessment

    There are a number o possible answer permutationsto the nine sel-assessment questions presentedabove; the answer prole being dependent uponthe assessment scope and approach being adoptedby the organization.

    The matrix presented below may acilitate in thecollation o results or your sel-assessment.

    P3M3 Model Answers

    a b c d e

    1

    2

    3

    4

    5

    6

    7

    8

    9

    Question

    Our organization canbe best characterizedas having:

    Our managementcontrol is bestdescribed by

    Our benetsmanagement isbest described by:

    Our nancialmanagement is bestdescribed by:

    Our risk managementis best described by:

    Our approach tostakeholder managementis best described by:

    We deliver organizationalgovernance by:

    Our resource

    management is bestdescribed by:

    Does the organization:

    Focus

    Maturity

    Project

    Project

    Project

    Project

    Project

    Project

    Project

    Project

    ResultingLevel

    P3M3 Model Answers

  • 8/22/2019 P3M3 Self Assess Project

    18/22

    P3M3 v2.1 Sel-Assessment18

    P3M3 Project Management Sel-Assessment

    Sel-Evaluation TipsQuestion 1 is a general question relating to thelevel to which the processes have been dened and

    established within the organization. Higher levelso process maturity being demonstrated throughthe extent to which the processes are quantitativelymanaged and whether such management inormationis used to optimize the processes.

    I the overall judgement is that the model answer (a)best characterizes the current process maturity, thenthe organization would appear to have immatureprocesses and only partial awareness o the threePs. This means, in management terms, that theorganization may occasionally deliver individualinitiatives that produce excellent results; however,

    managers are likely to be working reactively, ocusingon solving immediate issues, rather than proactively.Schedules and budgets are likely to be exceededbecause o a lack o sound estimating techniques.I deadlines are imposed, the quality o deliverablesis likely to be compromised in order to meet theschedule. For example, verication and validationactivities, including reviews, may be skimped on, i aninitiative alls behind schedule.

    I the overall judgement is that the model answer (b),(c), (d) or (e) best characterizes the current processmaturity, then this is indicative o maturing processes,

    as shown below:

    (b) Level 2 - repeatable process

    (c) Level 3 - dened process

    (d) Level 4 - managed process

    (e) Level 5 - optimized process

    Levels 3 - 5 are representative o a matureorganization that has an organization-wide ability ormanaging initiatives based on standardized, denedmanagement processes. These processes can betailored to meet specic organizational needs and are

    increasingly likely to be updated whenever necessarywith improvements developed and implementedin accordance with a sound business case anddevelopment plan.

    At the higher Levels o maturity (Levels 4 and 5), theorganization will have the knowledge and quantitativeinormation against which to review perormance andevaluate schedules and budgets, ensuring that theseare realistic and achievable.

    Answers to Questions 2-8 can be collated on thematrix above. The number o answers will dependupon the scope o the assessment i.e. whether

    portolio and/or programme and/or projectmanagement has been included, and also the numbero perspectives that are being considered.

    It should be noted that the Level being attainedor each Perspective and within each model (PM3,PgM3, and PjM3) may be dierent, as shown in thediagram, below. Answers that are mainly (a) or aparticular Perspective represent Level 1, through tomainly (e) representing Level 5. Level 1 is the lowestlevel o maturity and this basic awareness o theimportance o a particular perspective is built upon inan incremental ashion as depicted in the P3M3 model

    answer specication.

  • 8/22/2019 P3M3 Self Assess Project

    19/22

    P3M3 v2.1 Sel-Assessment 19

    P3M3 Project Management Sel-Assessment

    The answer to Question 9, provides an overallorganizational capability maturity evaluationor Portolio and/or Programme and/or ProjectManagement. I all o the Perspectives have beenassessed within a particular model (PM3, PgM3,PjM3) then the capability maturity evaluation is likelyto be a mean average o the maturity across the sevenperspectives. For example, the above assessment oProject Management resulted in the ollowing Levelscores: 3,2,3,2,4,3,4. The mean average or the seriesis 3 and thereore the overall project managementcapability maturity evaluation would be Level 3.

    However, do remember that the sel-assessmentis subject to a degree o optimism bias and thata acilitated assessment may result in a Level 2evaluation, although should not be any lower,i the sel-assessment has been conducted properly.

    A urther cross-check is recommended with the resultrom Question 1. I question 1 results in a Level that islower than Question 9, then it is likely that there is ahigh degree o variation in the maturity or dierentPerspectives. Under these circumstances, the overallcapability maturity evaluation should refect the lowerLevel score.

    Example Assessment o Process Perspectives

    ManagementControl

    Level 1

    Level 2

    Level 3

    BenetsManagement

    Level 1

    Level 2

    FinancialManagement

    Level 1

    Level 2

    Level 3

    StakeholderEngagement

    Level 1

    Level 2

    RiskManagement

    Level 1

    Level 2

    Level 3

    Level 4

    OrganizationalGovernance

    Level 1

    Level 2

    Level 3

    ResourceManagement

    Level 1

    Level 2

    Level 3

    Level 4

  • 8/22/2019 P3M3 Self Assess Project

    20/22

    P3M3 v2.1 Sel-Assessment20

    P3M3 Project Management Sel-Assessment

    The sel-assessment has enabled the organization togain an overall view o its Maturity Level or Portolioand/or Programme and/or Project Management.Process capability across seven perspectives applicableto all o the models (PM3, PgM3, and PjM3) will alsohave been obtained and can be used to prole thecurrent strengths and weaknesses.

    In interpreting the results, it is recommended thatthe detailed Attributes within the P3M3 model ora particular Level and Perspective are reviewed toveriy the accuracy o the sel-assessment. I the

    organization wants to use the sel-assessment resultsas the basis o an improvement initiative, then theassessment provides a valuable snapshot o where theorganization stands currently.

    The next step is to consider where the organizationwishes to be positioned in uture. It should berecognized that the optimal level may not be Level5 across all Perspectives or all three models, andbusiness needs in terms o the optimal level operormance, the business case or any processimprovement initiative and what the organizationeels able to achieve and sustain needs to be

    considered.

    Should improvement in capability with regard tocertain perspectives be deemed necessary, then inplanning an improvement initiative, the detailedAttributes or the next level above the currentassessed level should be reviewed and become anintegral part o the improvement plans.

    I the organization requires urther assistance or aormal review, additional inormation can be ound atwww.p3m3-ocialsite.com. Further inormation andassistance on using P3M3, including details o ormal

    reviews and consultancy services, can also be oundvia the ocial P3M3 website.

    Next Steps

  • 8/22/2019 P3M3 Self Assess Project

    21/22

    P3M3 v2.1 Sel-Assessment 21

    P3M3 Project Management Sel-Assessment

    Management Control

    Benets Management

    Financial Management

    Stakeholder Engagement

    Risk Management

    Organisational Governance

    Resource Management

    PortolioManagement

    Level

    ProgrammeManagement

    Level

    ProjectManagement

    Level

    Summary Table

  • 8/22/2019 P3M3 Self Assess Project

    22/22

    CP0254

    OGC 1 Horse Guards Road,London SW1A 2HQ

    About OGCThe Oce o Government

    Commerce is an independentoce o HM Treasury.

    The OGC logo is a registeredtrademark o the Oce oGovernment Commerce

    in the United Kingdom andother countries.

    OGC Service DeskOGC customers can contact

    the central OGC Service Deskabout all aspects oOGC business.

    The Service Desk will alsochannel queries to the

    appropriate second-linesupport. We look orwardto hearing rom you.

    You can contact the ServiceDesk 8am 6pm Monday

    to Friday:

    T: 0845 000 4999E: [email protected]

    Press enquiriesT: 020 7271 1318F: 020 7271 1345

    Thi i C i ht l dd d d t hi h

    Feedback concerning the model should be sent to

    [email protected]

    Feedback concerning the sel-assessment should be sent [email protected]