  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 1 of 11

    Good Day

    Introduction

    This is an exercise to calculate progress based on Client requirements for a typical EPC Project.

    Data used on this sample are referential and were created just for better understanding of this Progress Calculation exercise.

    This is open to anybody for comment or improvements.

    Client Requirements

    An EPC Project is required to be scheduled and follow up each of its phase and based on these following requirements:

    1. Project must start on Nov 1rst 2010 and must be done in 200 working days

    2. Working Time will be 8h/d; 40 hours a week (Standard Calendar to make simple the exercise)

    3. Phases must be weighted on cost except Engineering phase which will be weighted on man-hours to be expended (Effort)

    4. Resources and Cost have to be established for all phases

    5. The Weights of each Project phase must be:

    a. Engineering Design = 10%

    b. Procurement = 20%

    c. Construction = 70%

    6. Schedule must show Progress Earned Values against Planned Progress Values

    7. Schedule must show also a Graphical Baseline to evaluate future Project Performance and targets achievements

    8. Progress figures to be reported are Physical and Earned Values

    9. For Forecasting: Task endings dates will be given by using remaining durations

    Note: The main purpose of this exercise is to show Progress Calculations. So, no actual values on resources and cost expenditure are

    being given

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 2 of 11

    Execution by steps: Figure 01

    1. Define WBS, Activities, Resources and Cost (CTR)

    2. Create Baseline

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 3 of 11

    WBS

    Figure 02

    GROUP & SORT

    Figure 03

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 4 of 11

    Detail of Original Plan after assigning resources and cost

    Figure 04

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 5 of 11

    3. Weight Assignment

    a) Create three new user defined fields (Enterprise\User Defined Fields) given the following titles:

    % Progress Earn Value

    Planned % Complete

    Weight

    Figure 05

    Note: Once are created show

    them as on Figure 04 - Last 3

    columns

    b) Using Global Change (Tool\Global Change) create the following changes for each phase:

    ENGINEERING PHASE

    Note: Parameter/value

    number which divides BLU comes

    from Figure 04 (BLU Column)

    Weight for Engineering = 10%

    Figure 06

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 6 of 11

    PROCUREMENT PHASE

    Note: Parameter/value number

    which divides BTC comes

    from Figure 04 (BTC Column)

    Weight for Construction = 20%

    Figure 07

    CONSTRUCTION PHASE

    Note: Parameter/value number

    which divides BTC comes

    from Figure 04 (BTC Column)

    Weight for Construction = 70%

    Figure 08

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 7 of 11

    c) Apply Global Changes one by one and then we will get the committed changes or weights:

    Engineering = 10% Procurement = 20% Construction = 70%

    Figure 09

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 8 of 11

    4. Update the Schedule for: Figure 10

    Cut Off date = February 1rst 2011 (Data Date)

    Give % Physical Progress

    And Remaining Durations

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 9 of 11

    5. Create and apply a Global Change to calculate

    % Progress Earn Value and % Planned Progress

    Figure 11

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 10 of 11

    6. Check Progress results

    Figure 12

  • Gustavo Paolini

    Using Primavera P6.7 - Technical Notes

    12/10/2010 Page 11 of 11

    FINAL COMMENTS:

    1. If all the phases were weighted on cost only two global changes should be made

    2. Usually weights are being frozen by the client before project stars therefore the Global Changes which calculate activity

    weights are being applied or done only one time

    3. If there is any changes that affect Budgeted Labor Units (BLU) or Cost, weights have to be re calculated using again the

    Global Changes made for that purpose ( Advice: Always check the GC parameters/values field and update these values

    with those originated by the new changes to make sure you are weighting activities properly)

    4. Every time the schedule is updated base on physical progress and remaining durations it is required to re calculate

    progress values by applying last Global change made for it (GC No. 4)

    5. Weights can be calculate out of Primavera for example in Ms Excel and can be added to the Weight Column manually

    or using Primavera to import them from Excel Spreadsheet

    6. Feel free to make any comments or suggestions

    Additional information about this Project used as a sample