HARGA JUMLAH No SATUAN HARGA
( Rp) ( Rp)
1 3 4 5
A PEK. PERSIAPAN1 Galian tanah 1575,83 M 30.000,00Rp. 47.274.900,00Rp. 2 Pemindahan tanah ex galian 93,62 M 20.000,00Rp. 1.872.400,00Rp. 3 Buang tanah keluar lokasi 1482,22 M 25.000,00Rp. 37.055.500,00Rp. 4 Urug pasir t = 5 cm 97,51 M 100.000,00Rp. 9.751.000,00Rp.
5 Pemadatan tanah / badan jalan 1950,20 M 8.000,00Rp. 15.601.600,00Rp.
TOTAL A 111.555.400,00Rp. B PEKERJAAN JALAN PAVING
1 Paving t = 8 cm; K 400; ex PT Focon Indonesia 1311,00 M 35.000,00Rp. 45.885.000,00Rp.
2 Sp + Ps K 15.25.40 396,30 M 30.000,00Rp. 11.889.000,00Rp.
TOTAL B 57.774.000,00Rp. C PEKERJAAN JALAN BETON
1 Jalan Beton t = 15 cm- Ready Mix K 250 95,88 M 1.200.000,00Rp. 115.056.000,00Rp. - Wiremesh M 8 639,20 M 75.000,00Rp. 47.940.000,00Rp. - Dowel 16 (L = 500 mm - 50 cm) 149,30 Kg 20.000,00Rp. 2.986.000,00Rp. - Bekisting 37,86 M' 35.000,00Rp. 1.325.100,00Rp. - Plastik Cor 639,20 M' 3.000,00Rp. 1.917.600,00Rp. - Pasangan Batu Gunung M 600.000,00Rp. -Rp.
- Plesteran M 65.000,00Rp. -Rp.
TOTAL C 169.224.700,00Rp.
338.554.100,00Rp. 33.855.410,00Rp.
372.409.510,00Rp.
372.409.000,00Rp.
Terbilang : Tiga ratus tujuh puluh dua juta empat ratus sembilan ribu rupiah.
TOTAL HARGA (A+B+C)PPN 10%JUMLAH KESELURUHAN
DIBULATKAN
2
RENCANA ANGGARAN BIAYA
Penawaran Pekerjaan STP CIOMAS Banjarmasin
VOLUMESATUANURAIAN