paper 3a: cost accounting chapter 6 ca. dharmendra … · 2014-02-14 · work at site of contract ....
TRANSCRIPT
1 • Meaning & Features
2 • Costs & Expenses
3 • Work Certified & Work uncertified
4 • Treatment of Plant & Machineries
5 • Notional Profit & Its Recognition
6 • Format of Contract A/C & Balance Sheet
7 • Escalation Clause
8 • Estimated Total Profit & Recognition of Profit
Also called Terminal Costing
Usually adopted by Building Contractors
Large Job/ Assignment / Work order
Takes 2 or more Financial Years
Treatment of profit of Incomplete Contract
Fixed Price Contract Vs Cost Plus Contract
Applicable in Construction, Ship Building etc
Work at Site of Contract
Direct Expenses
Indirect Expenses
Separate Account
Number of Contracts
Cost Centre and Cost Unit
Two parties i.e. Contractor and Contractee
Recognition of Profit
Material
Labour
Direct expenses
Indirect Expenses
Sub-contract Costs
Cost of Extra work
Depreciation of Plant
Value of Work certified • Valued at Contract Price • Based on Technical Evaluation • Not based on Cost • May Include Profit or Loss
Cost of Work uncertified • Cost Basis • Work not Certified, or • Completed after Certification
Method I • Plant Shown In Debit Side at Cost • Plant Shown In Credit Side at WDV • Net Effect Being Depreciation • Applicable when Plant Used For Whole Year
Method II • Only Depreciation In Debit Side • Applicable When Plant used For Part of the year
Notional Profit • Excess of Credit Side on Debit Side
Notional Loss • Excess of Debit Side on Credit Side
Notional Loss • Taken to Profit & Loss A/C Fully Irrespective of Stage of
Completion
Share of Notional Profit taken to P & L A/C • Work Certified Less Than 25%
• No Share of Profit is Recognized in P & L A/C • Work Certified Less Than 50%
• 1/3 X Notional Profit X Cash Received/Work Certified • Work Certified More Than 50%-99%
• 2/3 X Notional Profit X Cash Received/Work Certified • Work Certified 100%
• Notional profit X Cash Received/Work Certified
Applicable in Fixed Price contract
Related To Increase in Prices Of Material, Labour etc
Contactee may agree to Share an Agreed Portion of The Excess Increase over a Specified Limit
Accounting Treatment
• Contractee Account Dr. • To Contract Account
Find the amount to be debited to Contractee? • A Contract has a clause if Material price increases by more than 2%, the
Contractee will Share 40% of the increase over 2%. • It was agreed that material price has increased by 10%. • Total Material consumed is Rs. 55000.
Solution • Price of material before increase = • Rs.55000/110% = Rs.50000 • 2% of 50000 = Rs. 1000 • Increase in the cost of material Rs. 5000 • Increase In excess of 2% = Rs. 5000 – 1000 = Rs. 4000 • Contractee’s Share = 40% of Rs. 4000 = Rs. 1600 • Contactee’s A/C will be debited & Contract A/C be credited
Supply From Stores
Direct Purchase
Tool Making Materials
Supply By Contractee
Transfer of material
Return of Excess Materials to stores
Sale of Surplus Material
Abnormal Loss of Materials
Estimated Total Costs (ETC) • Total Costs Till Date + Estimated Costs
To Complete The Contract
Estimated Total Profit (ETP) • Contract Price – Estimated Total Costs
Estimated Total Profit x Work Certified/contract Price
Estimated Total Profit x Work Certified/contract Price x cash Received/Work Certified
Estimated Total Profit x Cost till date/ Estimated Total Cost
Estimated Total Profit x Cost till date/ Estimated Total Cost x cash Received/Work Certified
Notional Profit x Work Certified/contract Price
2/3 x Notional Profit x Cash Received/ Work certified
Estimate the Share of Notional Profit to be taken to P & L A/c
• Total Costs Till Date Rs 9000 • Estimated Costs To Complete The Contract Rs. 575 • Notional Profit Rs.2800 • Work certified Rs. 11000 • Contract Price Rs. 12000 • Cash Payment Ratio 90%
Working Notes • Estimated Total Cost (ETC) =
• Rs. 9000+575= Rs. 9575 • Estimated Total Profit (ETP) =
• Rs. 12000 – 9575 =Rs. 2425
The Share of Notional Profit to be taken to P & L A/C will be Minimum of
1.Estimated Total Profit x Work Certified/contract Price
• Rs.2425 X 11000 /12000= Rs.2223
2.Estimated Total Profit x Work Certified/contract Price x cash Received/Work Certified
• Rs. 2425 X 11000 /12000 X 90 %= Rs.2000
3.Estimated Total Profit x Cost till date/ Estimated Total Cost
• Rs. 2425 X 9000 /9575 =Rs. 2279
4.Estimated Total Profit x Cost till date/ Estimated Total Cost x cash Received/Work Certified
• Rs. 2425 X9000 / 9575 X 90% = Rs. 2051
5.Notional Profit x Work Certified/contract Price
• Rs. 2800 X 11000/ 12000
6. 2/3 x Notional Profit x Cash Received/ Work certified
• 2/3 X2800 X90% = Rs.1680
Since Rs. 1680 is minimum, it should be taken to P & L A/C on Prudence Basis
Contract A/C Particulars Rs. Particulars Rs. To Materials To Wages To Direct Expenses To Indirect Expenses To Sub Contract work To Cost of Extra Work To Plant ( at Cost) To Notional Profit (Balancing Figure)
By Work in Progress Work Certified Work Uncertified By Balance c/d Plant (WDV) at site Material at Site
To Profit & Loss A/C (Profit recognized) To Reserve Profit (Balancing Figure)
By Notional Profit b/d
Contract A/c Particulars Rs. Particulars Rs. To Work in Progress b/d Work Certified Work Uncertified To Balance b/d Plant at site material at site
By Reserve Profit
Liabilities Rs. Assets Rs. CURRENT ASSETS: Contract Work-in-Progress Value of work certified Add: Cost of Work Uncertified Add: WDV of Plant at Site Add: Cost of Materials at Site Sub-Total Less: Reserve Profit Net Balance Less: balance in Contractee’s Personal A/c (Cash Received) Net Value Of Contract Work In Progress
} The following details relate to a Contract. } Contract Price Rs.7500 } Payment Ratio 90% } Particulars
Rs.
} Materials 900 } Labour 850 } Direct Expenses 35 } Indirect Expenses 15 } Work Certified to date 1750 } Work uncertified nil } Plant Issued 100 } WDV of Plant 80 } Prepare a Contract A/C and Show WIP in Balance Sheet
Stage of Work certified= • Work Certified / Contract Price • 1750/7500 • 23.33%
Since % of Completion is less than 25% • No Share of Notional Profit To Be Recognised
Loss in any Contract A/C is taken to P & L A/C
Contract A/C For the year ended….
Particulars Rs. Particulars Rs. To Materials To Wages To Direct Expenses To Indirect Expenses To Sub Contract work To Cost of Extra Work To Plant ( at Cost)
900 850 35 15
100
By Work in Progress Work Certified Work Uncertified By Balance c/d Plant (WDV) at site Material at Site By Loss ( balancing figure)
1750
80
70
1900 1900 By Loss b/d 70 To Profit & Loss A/C
70
70 70
} The following details relate to a Contract. } Contract Price Rs. 7500 } Payment Ratio 90% } Particulars Rs. } Materials 1100 } Labour 1150 } Direct Expenses 125 } Indirect Expenses 20 } Work Certified b/d 1750 } Work Certified c/d 5650 } Work uncertified c/d 100 } Plant 80 } WDV of Plant 50 } Prepare a Contract A/C and Show WIP in Balance Sheet
Stage of Work certified= • Work Certified / Contract Price • 5650/7500 • 75.33%
Since % of Completion is more than 50% • Share of Notional Profit To Be Recognised • 2/3 x Notional Profit x Cash Received/ Work certified • 2/3 X 1575 X 90% • Rs. 945
Contract A/C For the year ended….
Particulars Rs. Particulars Rs. To Work in Progress b/d Work Certified To Balance b/d Plant at site To Materials To Wages To Direct Expenses To Indirect Expenses To Notional Profit (Balancing Figure)
1750
80
1100 1150 125
20 1575
By Work in Progress Work Certified Work Uncertified By Balance c/d Plant (WDV) at site
5650
100
50
5800 5800 To Profit & Loss A/C To Reserve Profit
945 630
By Notional Profit b/d 1575
1575 1575
Balance Sheet Liabilities Rs
. Assets Rs.
CURRENT ASSETS: Contract Work-in-Progress Value of work certified Add: Cost of Work Uncertified Add: WDV of Plant at Site Add: Cost of Materials at Site Sub-Total Less: Reserve Profit Net Balance Less: balance in Contractee’s Personal A/c (Cash Received=90%of work certified) Net Value Of Contract Work In Progress
5650 100
50 ____ 5800 (630) 5170
(5085)
85
} The following details relate to a Contract. } Contract Price Rs. 7,500 } Payment Ratio 90% } Particulars Rs. } Materials 630 } Labour 850 } Direct Expenses 45 } Reserve profit b/d 630 } Work Certified b/d 5,650 } Work Certified c/d 7,500 } Work uncertified b/d 100 } Plant b/d 50 } WDV of Plant 20 } Prepare a Contract A/C and Show WIP in Balance Sheet
Stage of Work certified= • Work Certified / Contract Price • 7500/7500 • 100%
Since % of Completion 100% • Share of Notional Profit To Be Recognised • Notional Profit x Cash Received/ Work certified • 825x 90% • Rs. 742.5 • Contractee A/C is Debited in Contract A/C
Contract A/C For the year ended….
Particulars Rs. Particulars Rs. To Work in Progress b/d Work Certified Work Uncertified To Balance b/d Plant at site To Materials To Wages To Direct Expenses To Indirect Expenses To Notional Profit (Balancing Figure)
5650
100
50 630 850
45 -
825
By Reserve Profit By Contractee A/C By Balance c/d Plant (WDV) at site
630 7500
20
8150 8150 To Profit & Loss A/C To Reserve Profit
742.5 82.5
By Notional Profit b/d 825
825 825
Cost of The Project Rs. 1049000
Work Completed 2/3
Work Certified 50%
Find The Cost of Work Uncertified?
Since cost of Completing 2/3 Contact = • Rs. 1049000
So Cost of Completing The Whole Work = • Rs. 1049000/(2/3) • Rs. 1573500
Extent of Work uncertified = • 2/3-1/2=1/6
Then Cost of Work uncertified = • 1573500X(1/6) = Rs. 262250
1 • In our Discussion, We have discussed
2 • What is Contract and Types of Contracts
3 • Various Items of Income & Expenditure
4 • Format of Contract A/C in First & Next Year
5 • Balance Sheet representation of WIP
6 • Cost of Work Uncertified
7 • Recognition of Notional Profit and Loss
8 • Escalation Clause
9 • Concept of Estimated Total Profit
1 • What do you mean by contrast costing
2 • What are features of contrast costing
3 • Difference between Job & Contract Costing
4 • What is Cost plus and Fixed price contact
5 • What is the meaning of Escalation clause
6 • What is notional profit and Reserve Profit
7 • What is Estimated Total Profit
8 • What is Estimated Total Cost
9 • How Depreciation on Plant is recorded