parallel flow visualization and flowgate allocations equity concerns of non-market transmission...
TRANSCRIPT
Parallel Flow Visualization and
Flowgate Allocations
Parallel Flow Visualization and
Flowgate Allocations
Equity Concerns of
Non-Market
Transmission Owners
Equity Concerns of
Non-Market
Transmission Owners
Parallel Flow Visualization – For reliability
Parallel Flow Visualization – For reliability
• Objectives– Meet needs of Reliability Coordinator, RC– Observe impacts on congested flowgates– Provide IDC with current information– Increase accuracy of Gen to Load impacts
(timely updates)– Observe magnitude and source of all impacts
• Objectives– Meet needs of Reliability Coordinator, RC– Observe impacts on congested flowgates– Provide IDC with current information– Increase accuracy of Gen to Load impacts
(timely updates)– Observe magnitude and source of all impacts
Parallel Flow Visualization – Non-Market priorities
Parallel Flow Visualization – Non-Market priorities
• Objectives– Accurately prioritize certain non-market GtL
flows in real time that today may be inappropriately treated as firm, due to shortcomings in the IDC (e.g. Non-designated network resources)
• Objectives– Accurately prioritize certain non-market GtL
flows in real time that today may be inappropriately treated as firm, due to shortcomings in the IDC (e.g. Non-designated network resources)
Parallel Flow Visualization – Centralized calculationsParallel Flow Visualization – Centralized calculations
• Objectives– Perform impact calculation at a central location
for both the market flows as well as the non-market GtL flows
– Presently, the non-market BA GtL impact calculation is performed at a central location (IDC), whereas the market flow impact on flowgates is calculated by each market entity, then uploaded to the IDC.
• Objectives– Perform impact calculation at a central location
for both the market flows as well as the non-market GtL flows
– Presently, the non-market BA GtL impact calculation is performed at a central location (IDC), whereas the market flow impact on flowgates is calculated by each market entity, then uploaded to the IDC.
Parallel Flow Visualization - Equity Concerns
Parallel Flow Visualization - Equity Concerns
• This desire to have a centralized calculation seems to have been interpreted by some as a REQUIREMENT that the impact calculation and prioritization for the market flow and the non-market GtL flow must be the SAME.
• This has significant equity implications, and NAESB should consider this change carefully.
• This desire to have a centralized calculation seems to have been interpreted by some as a REQUIREMENT that the impact calculation and prioritization for the market flow and the non-market GtL flow must be the SAME.
• This has significant equity implications, and NAESB should consider this change carefully.
Concept being proposedConcept being proposed
• DNR designation is being proposed as the basis for determination of firm usage.
• Under this concept, what is designated as firm usage by the non-market BAs doesn’t conceptually change. Therefore, may be reasonable for non-market BAs.
• This would be a significant change from what is presently being done for prioritization of market flow. Is the DNR designation an equitable basis of firm usage for the market?
• DNR designation is being proposed as the basis for determination of firm usage.
• Under this concept, what is designated as firm usage by the non-market BAs doesn’t conceptually change. Therefore, may be reasonable for non-market BAs.
• This would be a significant change from what is presently being done for prioritization of market flow. Is the DNR designation an equitable basis of firm usage for the market?
How we got to where we are today..
(our view of history, and why it is relevant)
How we got to where we are today..
(our view of history, and why it is relevant)
• Section 28.3 Language obligates the Transmission Provider to;
…provide Firm Transmission Service over the Transmission System to the Network Customer for the delivery of Capacity and Energy from its designated Network Resources to service its Network Loads…[emphasis added]
• Section 28.3 Language obligates the Transmission Provider to;
…provide Firm Transmission Service over the Transmission System to the Network Customer for the delivery of Capacity and Energy from its designated Network Resources to service its Network Loads…[emphasis added]
Network Integration Transmission Service
(NITS)
Network Integration Transmission Service
(NITS)
Example: Historical “Tariff” Area
Example: Historical “Tariff” Area
Network Load
NetworkResource
Section 28.3 (NITS)Firm Transmission
RTO / Market AreasRTO / Market Areas
Historic Control (Tariff) Areas
Historic Control (Tariff) Areas
OTPMPMDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Example: Historical “Tariff” Area
Example: Historical “Tariff” Area
Network Load
NetworkResource
Section 28.3 (NITS)Firm Transmission
RTO / Market AreasRTO / Market Areas
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
RTO / Market AreasRTO / Market Areas
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
• Historically, the system was not planned nor built for firm deliveries between historic Control Areas
• Historically, the system was not planned nor built for firm deliveries between historic Control Areas
RTO / Market AreasRTO / Market Areas
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!If System Constra
ints -
Can all of th
is market
dispatch from DNRs be
firm?
RTO/Market AreasRTO/Market Areas
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
Constraints – Internal & External
Issue not just internal to the market
footprint
Issue not just internal to the market
footprint
Market Start-upMarket Start-up
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
Constraints – Internal & External• Central dispatch across the entire
market footprint (internal to and across historic CAs) without tagging.
• There wasn’t enough firm transmission to justify that “all market generation” was firm to “all market load”. (For example, generation in Indiana couldn’t service XCEL loads in Minnesota due to constraints)
• Central dispatch across the entire market footprint (internal to and across historic CAs) without tagging.
• There wasn’t enough firm transmission to justify that “all market generation” was firm to “all market load”. (For example, generation in Indiana couldn’t service XCEL loads in Minnesota due to constraints)
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• It was recognized that the non-markets
would be adversely and in-equitably impacted if markets didn’t constrain the centralized dispatch
• Some approach was needed to properly set the priority of the broader market footprint dispatch, while recognizing the transmission rights within the market
• It was recognized that the non-markets would be adversely and in-equitably impacted if markets didn’t constrain the centralized dispatch
• Some approach was needed to properly set the priority of the broader market footprint dispatch, while recognizing the transmission rights within the market
Equitable Prioritization – On Market Start-up??
Equitable Prioritization – On Market Start-up??
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• The “Markets” documented firm rights
on the system based on:• Firm GtL delivery internal to historic CAs• Existing historic Firm PtP between historic
CAs.
• An “Allocation” process was developed based on these historic firm rights to define limits for a firm centralized market dispatch
• The “Markets” documented firm rights on the system based on:• Firm GtL delivery internal to historic CAs• Existing historic Firm PtP between historic
CAs.
• An “Allocation” process was developed based on these historic firm rights to define limits for a firm centralized market dispatch
Allocation Process Allocation Process
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• Markets were allowed to dispatch centrally
(without tagging between historic CAs), but the market flow impact on flowgates was prioritized based on the historic firm usage
• The allocation process divides the market flow on a flowgate into three priorities (Firm-7, ED-6/NN-6, and ED-2/NH-2)
• Updating allocations for system changes/additions is necessary
• Markets were allowed to dispatch centrally (without tagging between historic CAs), but the market flow impact on flowgates was prioritized based on the historic firm usage
• The allocation process divides the market flow on a flowgate into three priorities (Firm-7, ED-6/NN-6, and ED-2/NH-2)
• Updating allocations for system changes/additions is necessary
Allocation Process (cont.)Allocation Process (cont.)
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• MISO has consolidated historic
CAs/BAs into one BA• No significant transmission additions
have occurred to span the historic CAs• The non-markets believe that there is
still NOT sufficient firm transmission available for any market gen to be delivered to any market load
• MISO has consolidated historic CAs/BAs into one BA
• No significant transmission additions have occurred to span the historic CAs
• The non-markets believe that there is still NOT sufficient firm transmission available for any market gen to be delivered to any market load
Since then ..Since then ..
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• The need for “Allocations” has not been eliminated
• The “desire to have the same GtL calculation” and “complexity in updating the allocations” are not sufficient justification to disregard the recognition that there was and still is limited firm transmission to transfer between the historic market CAs
• Use of DNR status only doesn’t properly reflect delivery capability across a broad market
• The need for “Allocations” has not been eliminated
• The “desire to have the same GtL calculation” and “complexity in updating the allocations” are not sufficient justification to disregard the recognition that there was and still is limited firm transmission to transfer between the historic market CAs
• Use of DNR status only doesn’t properly reflect delivery capability across a broad market
Since then .. (cont.)Since then .. (cont.)
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• Before the “DNR designation” be allowed as the basis of firm usage of the market, the market needs to demonstrate to NAESB that they have sufficient firm transmission to deliver from their market gen to their market load across their entire footprint on a comparable basis to the non-markets.– This wasn’t the case on market start-up– What has changed that would allow this use of
footprint-wide DNR designation in markets?• There is a Significant equity issue on all market
impacted flowgates, if market flow is prioritized as firm solely based upon DNR status, if firm transmission really doesn’t exist.
• Before the “DNR designation” be allowed as the basis of firm usage of the market, the market needs to demonstrate to NAESB that they have sufficient firm transmission to deliver from their market gen to their market load across their entire footprint on a comparable basis to the non-markets.– This wasn’t the case on market start-up– What has changed that would allow this use of
footprint-wide DNR designation in markets?• There is a Significant equity issue on all market
impacted flowgates, if market flow is prioritized as firm solely based upon DNR status, if firm transmission really doesn’t exist.
NAESB / Need to ensure Equity
NAESB / Need to ensure Equity
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & External• Assuming the allocations are maintained, MISO has argued that the non-market GtL flow should be prioritized based on allocations during congestion, just like the market flow… However;– For the non-market, transmission service
priority (for GtL and PtP) is set based on the service that has been demonstrated and granted. Priority should be based upon that TP designation.
– For the non-market, the allocations are considered during the granting of such firm service.
• Assuming the allocations are maintained, MISO has argued that the non-market GtL flow should be prioritized based on allocations during congestion, just like the market flow… However;– For the non-market, transmission service
priority (for GtL and PtP) is set based on the service that has been demonstrated and granted. Priority should be based upon that TP designation.
– For the non-market, the allocations are considered during the granting of such firm service.
Allocations – Impact to non-markets
Allocations – Impact to non-markets
OTPMP
MDU
NSP
SMP
MEC IES
WPLWEP
UE
IP IPL
MECS
PSIDQE
DPLCGE
MH
GRE
PSI
Network Load
NetworkResource
CONSTRAINTS..!!
Constraints – Internal & ExternalAlso; other equity concerns..– Markets have documented to NERC that they do
not currently achieve their assigned curtailment obligations – that transfers the impact to the non-market uses (equity concern as well as reliability)
– The non-markets are required to meet their curtailment obligations, or they are found non-compliant. The non-markets cannot avoid a curtailment due to it being too large.
– Non-markets have not disagreed that non-firm resources should be prioritized as non-firm during congestion, and presumed that those uses of the system will be prioritized correctly during congestion based upon IDC improvements.
Also; other equity concerns..– Markets have documented to NERC that they do
not currently achieve their assigned curtailment obligations – that transfers the impact to the non-market uses (equity concern as well as reliability)
– The non-markets are required to meet their curtailment obligations, or they are found non-compliant. The non-markets cannot avoid a curtailment due to it being too large.
– Non-markets have not disagreed that non-firm resources should be prioritized as non-firm during congestion, and presumed that those uses of the system will be prioritized correctly during congestion based upon IDC improvements.
Allocations – Impact to non-markets
Allocations – Impact to non-markets
Non-market requests to NAESB
Non-market requests to NAESB
• NAESB ensure that any change to the prioritization of the market flow consider whether it is equitable to both market/non-market to make such change.– Use of DNRs in the market to set market flow priority
would adversely and in-equitably impact the non-markets.
• NAESB not recommend or endorse elimination of allocations to set the market flow priorities until such time as the markets have clearly demonstrated that allocations are no longer needed.
• NAESB consider the parallel operation/test mode (existing IDC versus Parallel Visualization effort) before implementing changes that impact equity
• NAESB ensure that any change to the prioritization of the market flow consider whether it is equitable to both market/non-market to make such change.– Use of DNRs in the market to set market flow priority
would adversely and in-equitably impact the non-markets.
• NAESB not recommend or endorse elimination of allocations to set the market flow priorities until such time as the markets have clearly demonstrated that allocations are no longer needed.
• NAESB consider the parallel operation/test mode (existing IDC versus Parallel Visualization effort) before implementing changes that impact equity