part 2 – transmission and distribution - · pdf filepart 2 – transmission and...
TRANSCRIPT
1
Swanton Village Electric Department
Integrated Resource Plan
2015 - 2034
Part 2 – Transmission and Distribution
Presented to the Vermont Public Service Board
June 20, 2016
Submitted by:
Vermont Public Power Supply Authority
2
Swanton Village Electric Department
2015 Integrated Resource Plan
Transmission and Distribution Section
INTRODUCTION
This component of the Integrated Resource Plan (“IRP”) of the Swanton Village
Electric Department (“Swanton”) addresses the transmission and distribution
components of Swanton’s electric system. Consistent with collaboration
between Swanton, Vermont Public Power Supply Authority (“VPPSA”) and the
Vermont Public Service Department (“PSD”), the format of this Transmission
and Distribution (“T&D”) section of the IRP follows the key topics contained
within the addendum to the PSD’s 2011 Vermont Electric Plan.
Swanton’s Electric Department was incorporated in 1894. Like most of
Vermont’s smaller municipal utilities, many of its utility functions, such as
office staffing, are carried out by employees who also have responsibilities in
other aspects of village municipal operations. Swanton remains guided by the
Vermont Public Service Board (“PSB”) rules as well as by the American Public
Power Association’s (“APPA”) safety manual. Well-established practices keep
Swanton operating efficiently.
Swanton’s service territory is located in Franklin County in northwest Vermont,
in an area where weather events- especially in recent years- have been both
challenging and at times highly localized. Its 56 square mile service territory
can be seen on the Vermont Utility Service Territory map found below, and it
encompasses the Village of Swanton Village as well as portions of three of the
surrounding towns: Swanton, Highgate, and St. Albans. About 70% of
Swanton’s customers are served within the village and town portions of
Swanton. Swanton serves approximately 3,632 retail customers. In addition to
the retail customer load served within its service territory, Swanton provides
3
transmission service to an island of customers in Highgate, which is in
Vermont Electric Cooperative’s (“VEC”) retail franchise territory.
In 2014 Swanton’s peak demand in the winter months was 9,611 KW and
10,356 KW during the summer and shoulder months. Annual energy sales for
2014 were 56,758,783 kWh (pulse load at system boundary) and the annual
load factor for 2014 was 62.6%.
4
SERVICE TERRITORY
SWANTON VILLAGE ELECTRIC DEPARTMENT
Swanton Village
Electric Department
Service Territory
5
SWANTON VILLAGE ELECTRIC DEPARTMENT
SYSTEM OVERVIEW
Swanton-owned Generation:
Unit Nameplate Rating (kW)
2014 Annual Generation (kWh)
Unit #1 1,170 4,562,200
Unit #2 1,012 2,037,800
Unit #3 3,420 16,830,500
Unit #4 6,500 16,912,700
Unit #5 585 1,813,690
History of the Orman Croft Hydroelectric Plant – Highgate Falls:
The Highgate Falls power dam has been a dependable source of power for the
evolving energy needs of northwestern Vermont since 1797. By the early
1900’s, the facility played an important role in providing electricity to the
2011 2012 2013 2014 2011 2012 2013 2014
Residential sales (440) 3,136 3,137 3,150 3,139 24,551,885 24,414,839 24,276,736 24,507,293
Rural sales 66 57 58 63 2,153,244 2,168,808 2,141,236 2,077,879Small commercial and industrial sales
(442) 1000 Kw or less 425 432 429 418 24,868,379 25,926,939 25,874,589 25,903,550Large commercial and industrial sales
(442) above 1,000 Kw 0 0 0 0 0 0 0 0
Public street and highway lighting (444) 0 3 3 3 365,891 258,036 248,774 223,484
Other sales to public authorities (445) 0 0 0 0 0 0 0 0
Interdepartmental sales (448) 11 10 9 9 1,185,373 1,102,089 900,123 997,776
Total 3,638 3,639 3,649 3,632 53,124,772 53,870,711 53,441,458 53,709,982
Y/Y 0% 0% 0% 1% -1% 1%
Number of Retail Customers Retail Sales (kWh)
2011 2012 2013 2014
Peak Demand kW 10,317 10,576 10,657 10,356
Peak Demand Date 07/21/11 06/21/12 07/19/13 07/01/14
Peak Demand Hour 18 15 16 13
Annual System Peak Demand
6
citizens of Swanton and Highgate, and through regular maintenance and
equipment upgrading, has retained that position.
The first dam at Highgate Falls was built during the late 1700’s by private
entrepreneurs to power the saws, mill stones, and forges of the various
businesses occupying the Highgate Falls site. In 1894, Swanton Village
purchased the rights to develop the site for hydroelectric power.
In 1915, the Vermont General Assembly authorized Swanton Village to develop
its water power at Highgate Falls and for that purpose to build, construct, and
maintain a suitable power plant or improve its present plant with all buildings,
dams, flumes, and other equipment necessary and to borrow money or issue
bonds for that purpose. Numerous improvements were made to the project and
by 1920, the project structures included a concrete dam, woodstave penstock,
concrete surge tank, and powerhouse. The powerhouse contained two 900 kw
generating units, necessary switchgear, and transmission terminal equipment.
The original dam was constructed to elevation 164.8 feet above sea level and
had provisions for five feet of flashboards, giving the dam the potential for a
maximum power pool at elevation 169.8 ft asl.
The flood of November, 1927 brought waters 17 feet over the dam. There came
a period of modification and refurbishment which began with the installation of
a 900 kW Westinghouse generator (initially operated in 1928) in the unit # 2
position. During the early thirties, a steel surge tank was built inside the
existing tank, and butterfly valves were installed between the generating units
and the surge tank. The addition of a General Electric 900 kW generator
(initially operated in 1932) in the powerhouse unit # 1 position completed the
configuration until the 1950’s.
The 1952-1954 changes included reshaping the dam cross section, raising the
pond level from elevation 169.8 ft. (above sea level) to 170.8, construction of a
new intake facility and conduit system, raising the height of the steel surge
tank and expanding the powerhouse to enable the 1954 installation of a
Westinghouse 2,800 kW generating unit.
In 1986, the three generating units went through a major overhaul to improve
their generating performance. In 1990, another phase of powerhouse
improvement was completed. The powerhouse was once again increased in size
7
and a National Industrial generating unit with a capacity to produce 5,800 kW
was installed in the new area, as well as new switchgear, and computerized
controls. This phase of the project was dedicated to Orman E. Croft who, at the
time, was the Village Manager for the Village of Swanton, VT. A few years later,
another major change at the dam site would take place. In 1994, the most
recent phase of improvement was completed. The intake structure was raised
to elevation 193 ft. also, a new trash rake was installed, a new dam site
powerhouse was built, and as for the dam; the elevation of concrete was
brought up to elevation 175 ft. and an inflatable rubber dam provided by
Bridgestone was installed on top of the concrete. The addition of the rubber
dam would bring the pond level up to elevation 190 ft. as it remains today.
In 2011, a 5th turbine and generator was installed into the overflow power
house. The installation of this unit was the final step of the upgrades started in
1994, but was halted due to budget restrictions. The 5th turbine went into
production in March 13, 2012.
About the Orman Croft Hydroelectric Plant:
The Orman Croft Hydroelectric Plant consists of five hydroelectric generators with the
following characteristics as a combined operating system:
Capacity: 9.85 Megawatts (total of all units generating simultaneously).
2014 Annual Production: 41,783 MWH.
Water Flow: 1800 cubic feet of water per second.
Minimum Flow at bypass: 35 cfs, 200 cfs at the tailrace
Head Water Elevation: 190 feet above sea level.
Tailwater Elevation: 105 feet above sea level.
The whole is less than the sum of its parts. In other words, when the units are
generating simultaneously, the maximum total output is lower than that
maximum total output of each unit if each unit were generating separately.
Output Capacity for each Generator:
“Rated kW” signifies the actual output kW capacity of the generator, not the kW
nameplate rating.
Unit # 1: General Electric AC Generator installed in 1930. Excitation is
provided by a Basler static exciter. Voltage: 7200 volts, Speed: 360 revolutions
8
per minute, Cycles: 60hz., Phase: 3,Power Factor: 0.8, rated kW: 1,170
Kilowatts. The Turbine unit is a Francais type, Rated Horsepower: 1,340 hp,
Discharge: 224 cubic feet of water per second.
Unit # 2: Westinghouse AC Generator installed in 1928. Excitation is provided
by a Basler static exciter.
Voltage: 7200 volts, Speed: 360 revolutions per minute,
Cycles: 60 hz., Phase: 3, Power Factor: 0.8, rated kW: 1,012 Kilowatts. The
Turbine unit is a Francais type.
Rated Horsepower: 1,340 hp, Discharge: 224 cubic feet of water per second.
Unit # 3: Westinghouse AC Generator installed in 1954. Excitation is provided
by a Basler static exciter.
Voltage: 7200 volts, Speed: 257 revolutions per minute.
Cycles: 60 hz., Phase: 3, Power Factor: 0.8, rated kW: 3,420 Kilowatts. The
Turbine unit is a Francais type,
Rated Horsepower: 4,070 hp, Discharge: 558 cubic feet of water per second.
Unit # 4: National Industrial AC Generator installed in 1990. Excitation is
provided by a Basler static exciter.
Voltage: 7200 volts, Speed: 211.8 revolutions per minute, Cycles: 60hz, Phase:
3, Power Factor: 1.0, performed kW: 4,994 Kilowatts. The Turbine unit is a
Francais type, Rated Horsepower: 7,600 hp, Discharge: 900 cubic feet of water
per second.
Unit #5: OSSBERGER turbine, Hitzinger generator: construction and
installation into minimum flow building in September 2011, and in production
in March 13, 2012. Unit is a horizontal intake, horizontal shaft double cell,
cross flow design impulse type turbine, with draft tube effect. Rated at static
Head =44.6ft=13.6m. Full flow= 200cfs, partial flow= 35cfs. Normal speed 900
rpm with an over speed of 2010 rpm. Tp parent power is 650KVA at full flow
with a frequency of 60Hz. Rated kW: 484 Kilowatts.
Transmission System:
Swanton owns approximately 6.4 miles of 46KV transmission line. This line
connects Highgate substation, Elm Street substation, and Leader substation
and has a feed to the Swanton Peaking generator unit. This line connects the
Highgate substation and the Elm Street substation to the VELCO Highgate
9
substation at the east end, and can also make a connection to the VEC Island
circuit at the western end. The Swanton system can also be configured and
split up so that the Elm Street substation can be on the VEC Island circuit,
and the Highgate substation can be connected to the VELCO substation. This
dual feed into the Swanton System creates the ability for Swanton to have two
different sources feed these substations. The transmission line is located in the
towns of Highgate and Swanton. The circuit consists of 4 miles of 336 ACSR
conductor with an additional 0.4 miles of 336 ACSR conductor connecting the
Swanton Peaker generating project’s transformer. There is also 1.8 miles of
4/0 ACSR conductor connecting the 46kV lines on Route 78 to the Leader
substation mainly via a cross-country path.
Swanton has a SCADA (“Supervisory Control and Data Acquisition”) control over both the transmission switches and the substation reclosers.
Distribution System General:
The distribution system includes approximately 120 miles of line operating at 12.5 KV located in the towns of Swanton, Highgate, and St. Albans.
Substation name and description:
Swanton currently operates three substations. Each substation is briefly
described below.
SWANTON SUBSTATIONS
Elm Street Substation
The Elm Street substation consists of a 10,000 KVA step down transformer
from 46 KV primary to 12,470/7,200 volt grounded secondary. There are three
reclosers that feed the load normally fed from this substation. The reclosers are
ABB vacuum units that also have potential transformers tied to them to take
advantage of their microprocessors for data gathering. Swanton downloads the
load data monthly to see what the load balance is as well as what the system
power factor on each circuit is. This allows for the correct sizing of capacitor
banks for each circuit. Swanton presently maintains each circuit power factor
range between 92 and 97 percent. As stated before, the controls of these
reclosers are self-standing but also are operated by remote control by SCADA.
10
Highgate Substation
Highgate substation is located at the Orman Croft generating station. The
transformer at this site is a 15,000 KVA step down with a 46 KV primary and
12,470/7200 volt grounded secondary. There are three load circuits there as
well. These circuits are also remotely controlled as well. The load data is
recorded from this location as well. In addition to these three load circuits, the
power plant generation is connected to this bus by way of an underground
circuit that goes to a 10,000 KVA transformer with a primary voltage of
12,470/7,200 volt grounded primary with a 7,200 volt delta secondary. The
operational voltage for the four hydro generators at this location is 7,200 volts
delta.
Leader Substation
The Leader substation was originally built by Vermont Fasteners for their heat
treat hardening process of their product. It was later purchased by Swanton
Village from Leader Evaporator Co. when it purchased the building from
Vermont Fasteners. The transformer is rated at 49.2 kV delta to 13.8Y/7.968
kV with a 7,500 kVA base load capacity. The transformer was configured to
operate as close as possible to Swanton’s system requirements and three GE
VR1 voltage regulators were added to the step down side to maintain the proper
system voltage requirement. Located between the transformer step down
points and the regulators is an ABB vacuum recloser that provides fault
protection and data collection which is all accessible and remote controlled by
SCADA. This load circuit has a power factor range of 98 to 100 percent.
11
Circuit Description:
Circuit Name Description Length
(Miles)
# Customers
by Circuit
Outages by
Circuit 2014
1200 12.4 KV three-phase branching to 7,200 Volt single-phase
17.3 240 4
1201 12.4 KV three-phase branching to 7,200 Volt single-phase
16.8 867 4
1202 12.4 KV three-phase branching to 7200 Volt single-phase
4.3 783 3
1203 12.4 KV three-phase branching to 7,200 Volt single-phase
27.6 492 12
1204 12.4 KV three-phase branching to 7200 Volt single-phase
35.6 429 13
1205 12.4 KV three-phase branching to 7200 Volt single-phase
5.7 352 4
L50 12.4 KV three-phase branching to 7200 Volt single-phase
12.9 520 9
There are seven circuits in total. The voltage of the circuits is regulated at the
substation bus. Swanton does not consider any of its circuits as particularly
long. Circuit 1205, is single-phase right now, but Swanton has plans to move it
to three-phase soon.
As shown in the table (above), in 2014, circuits 1203 and 1204 had the
greatest number of outages. Both of those circuits are also the longest in length
as compared to the other circuits. There were twelve outages on circuit 1203
and thirteen outages on circuit 1204. For all circuits combined, there were a
total of forty-nine outages.
The following table (below) shows the outage details for circuit 1203. The
majority of the outages were caused by accidents.
Circuit
Name
Outage
Cause
Code
Outage Cause
Description
Outages
by Circuit
2014
1203 4 Equipment 3 1203 6 Accidents 7 1203 7 Animals 2 Total 12
12
The following table (below) shows the outage details for circuit 1204. The
outage causes were more varied on circuit 1204 than those on circuit 1203.
Animals caused five out of the thirteen total outages on this circuit.
Circuit
Name
Outage
Cause
Code
Outage Cause
Description
Outages
by Circuit
2014
1204 1 Trees 3 1204 2 Weather 1 1204 4 Equipment 1 1204 6 Accidents 3 1204 7 Animals 5 Total 13
To prevent future outages and maintain reliability, Swanton continues to trim
trees and add animal guards to equipment.
13
A One-Line Diagram of Utility System:
The following one line diagram of the system was updated on 11/19/2015.
ONE LINE DIAGRAM
14
The IRP should contain a detailed description of how and when the utility
evaluates individual T&D circuits to identify the optimum economic and
engineering configuration for each circuit, while meeting appropriate
reliability and safety criteria.
Swanton evaluates T&D circuits on an ongoing basis in order to identify the
optimum economic and engineering configuration for each circuit. Swanton
reviews the Rule 4.900 Outage Reports, system reviews, as well as annual
budgets in order to correct and/or prevent any issues that may materialize. A
copy of Swanton’s Rule 4.900 Overall Assessment of System Reliability report
can be found at the end of this document.
Page A-10 T&D System Evaluation
1) The current power factor of the system, and any plans for power factor correction; Swanton monitors the power factor on each individual circuit on a weekly basis. Swanton maintains a power factor of 95 percent or higher. There is no need for power factor correction at this point in time.
2) Distribution circuit configuration, phase balancing, voltage upgrades where appropriate, and opportunities for feeder back-up; Swanton is planning to change over the single-phase to three-phase on
the 1205 circuit in order to redistribute load, as was mentioned in the
previous “Circuit Description” section (above).
Swanton monitors each circuit’s neutral current and phase current and
also physically moves load from one phase to another.
3) Sub transmission and distribution system protection practices and
methodologies; Swanton’s sub transmission is protected by fuse protection. The three-phase main feeders are protected by reclosers and by the presence of down system protection fuses. If Swanton observes that load is growing in a specific area of the system, it monitors with load loggers and adjusts fuse sizes as necessary.
4) The utility’s planned or existing “smart grid” initiatives such as advanced metering infrastructure or distribution automation;
15
Swanton has and continues to explore the prospective installation of dual water and electric AMI systems. From Swanton’s recent attendance at multiple Smart Grid Summits, Swanton observed that many of the AMI vendors at the summit were startup companies that have gone out of business since the day of that summit. It is not clear that those vendors necessarily have the staying power to keep their companies viable, and Swanton does not want to overburden ratepayers with a product that will become obsolete soon after purchasing it. Swanton’s strategy is to wait for technology to mature so that prices become more economical, technology becomes more stable, and AMI vendor staying power becomes stronger. Swanton continues to explore the products of various vendors while maintaining its strategic analysis of full-village services.
Like the other VPPSA member electric utility systems, Swanton is part of the docket 7307 collaborative process that continues in both formal and informal means. The ongoing participation of Swanton and other VPPSA members in various facets of “smart grid” explorations has underscored both the challenges and the opportunities that lie ahead. On the challenge side, the cost effectiveness of AMI infrastructure is significantly less clear in small utilities like Swanton, where relatively limited savings around meter reading and other labor costs are combined with a terrain that challenges the efficacy of many wireless AMI systems. On the positive side, participation by VPPSA and member systems in municipal smart grid summits and other events have shown that prospective electric-water-sewer AMI applications may have efficiencies and synergies not available in electric only installations, though cost allocation in such situations must be done carefully to avoid subsidization issues. As we continue to collaborate with our Vermont utility colleagues regarding “lessons learned” from their experiences, Swanton will be in a good position to make technically and financially sound decisions regarding the timing and specifics of the smart grid applications that will be coming. Swanton is of course mindful of the many facets of the evolving grid, such as rapidly expanding net metering development, heat pump installations, and the advent of electric vehicles. Working with VPPSA, Efficiency Vermont, and other stakeholders, Swanton stays abreast of these developments and the strategies needed to maintain a safe, reliable, and economically viable distribution system.
While definitions of “smart grid” vary even within the industry, Swanton is also mindful of the increasing importance of cybersecurity concerns,
16
and the relationship of those concerns to technology selection and protection. While Swanton is not presently required to undertake NERC or NPCC registration, VPPSA is a registered entity, and the presence of the Swanton Village Manager on the VPPSA Board of Directors provides Swanton with knowledge and insight regarding ongoing cybersecurity developments and risks. On a more local level, Swanton endeavors to purchase and protect its IT systems (with assistance from VPPSA as needed), in a manner intended to minimize security risks to the system and its ratepayers. Swanton remains mindful of the balance between the levels of cybersecurity risk protection and the associated costs to its ratepayers.
5) Re-conductor lines with lower loss conductors; Swanton’s strategy for improving system efficiency involves monitoring actual system losses, and implementing system improvements to reduce system losses. After the ice storm of 1998, Swanton’s full system was re-conductored with lower loss conductors. When it comes to re-conductoring lines with lower loss conductors the advantages of the costs associated with lower loss conductors must be balanced against the higher costs associated with their purchase. Swanton assesses system performance vs. the cost of system reconductoring in making these equipment choices. Swanton’s load losses have decreased steadily over the past recent years. Swanton calculates load losses at the end of the year. Swanton’s load losses have fallen from 7.17% in 1997 to 4.36% in 2014.
6) Replacement of conventional transformers with higher efficiency transformers; Swanton replaced many of its transformers after the major ice storm of
1998. It is Swanton’s practice to always buy new transformers, rather
than used transformers. In its transformer purchase analysis, Swanton
compares the transformers of three manufacturing companies. Price is a
primary factor, efficiency is taken into account. Swanton tries to buy
U.S.A made transformers where possible.
7) Conservation voltage regulation;
17
Elm Street Substation and Leader Substation both have voltage
regulation equipment. The Highgate substation currently does not have
conservation voltage regulation equipment on it. Swanton has evaluated
the cost/benefit analysis of installing conservation voltage regulation in
the Highgate Substation, and it has determined that it would be cost
prohibitive to do so.
The goal for end-of-line voltage is to stay within the bandwidth of 2.5%
on either side of the 120 Volts. It’s monitored by the regulators, LTC,
and by VELCO, and by taking voltage readings at different intervals.
8) Implementation of a distribution transformer load management (DTLM) or similar program (See Equipment Selection and Utilization Standards below); Swanton monitors distribution transformer load management via SCADA and makes changes as necessary.
9) A list of the locations of all substations that fall within the 100 and 500 year flood plains, and a plan for protection or relocation of these facilities. None of Swanton’s three substations fall within the 100 and 500 year flood plains.
10) A current copy of the utility underground Damage Prevention Plan (DPP) (or provide a plan to develop and implement a DPP; if none exists). The majority of Swanton’s lines are overhead lines. As the quantity of Swanton’s underground lines increase, Swanton will become increasingly more involved with the Damage Prevention Plan. Swanton requires inspection of all underground lines prior to burial. This will be performed by Swanton Village Electric Employees. Currently, Swanton does not have a Damage Prevention Plan in place. Swanton will collaborate with other VPPSA utilities to develop a more formal Damage Prevention Plan.
18
Discuss the utility’s process for selecting transmission and distribution
equipment (i.e., net present value of life cycle cost, evaluated on both a
societal and utility/ratepayer basis).
When replacing transmission and distribution equipment, Swanton solicits
three different quotes before making a purchase. Swanton installs equipment
that is tried-and-true. These purchases are based on pricing and reliability.
Set out program to maintain optimal T&D efficiency. Report program
progress.
Reliability
System reliability is important to Swanton’s customers. Swanton has a number of initiatives underway to improve reliability. Each of these initiatives is described below.
Automatic Reclosers
Swanton uses automatic reclosers to attempt to reestablish service after short-duration outages. Also, Swanton fuses all of its tap lines.
Animal Guards
Swanton believes that animal guards are a cost-effective means of reducing animal contact and the associated service interruptions. Swanton utilizes animal guards on its system to protect against outages. Animal guards are installed in all new installations, where appropriate and animal guards are retrofitted on existing equipment after an incident has occurred.
Fault Indicators
Swanton currently uses fault indicators in the industrial park underground.
Swanton typically utilizes them for developments where there is more than one
transformer. One of the benefits of fault indicators is a quicker response time
for trouble-shooting and repair. As a result, Swanton’s system reliability and
customer satisfaction improves.
Pole Inspection
Swanton has an informal pole inspection program to assure that poles in its
service territory are in good and reliable condition. Also, Swanton always
inspects poles that are in the vicinity of normal field work. Due to the size of
19
the system, Swanton has a good understanding of the age and condition of the
poles. Swanton has been planning to upgrade to a GIS system to help monitor
these types of items more formally.
Equipment
Swanton evaluates its equipment through inventory stock. Swanton looks at
trending and overall system performance.
Under Swanton’s procurement & purchase policy, as previously mentioned,
Swanton solicits three different quotes, before making a purchase. Also under
this policy, three different quotes are required before making any planned
purchase greater than ten thousand dollars.
System Maintenance
Swanton has an unwritten system maintenance program. Swanton performs
annual oil checks on transformers, weekly substation inspections, and has
thermal imaging devices in the field.
Energy Losses and System Efficiency
In order to reduce line losses, Swanton converted the system voltage of three
circuits in Village in early 2000.
As stated in the (above) “Re-conductor lines with lower loss conductors”
section, Swanton’s losses have been steadily decreasing over the years.
Does the utility use the NJUNS database to track transfer of utilities and
dual pole removal?
Swanton currently uses the NJUNS database to track transfer of utilities and
dual pole removal.
What is the utility’s philosophy regarding relocating cross-country lines
to road-side?
Swanton relocates cross-country lines to road-side locations, where cost-
effective, in order to reduce maintenance and outage costs as well as in order
to reduce impacts. It is Swanton’s plan to continue with this process.
20
Describe vegetation management plan, per page A-13, and complete the
table on page A-14.
Explain why it's a “least cost program” including details on tree species ,
annual growth rates of these species, and vegetation techniques,
including when, where, and how herbicides are used.
Swanton has a vegetative and brush management program with a
schedule to routinely clear under its distribution lines. Swanton will
undertake to review that program, utilizing inspections and feedback
from its outage reports, to assure that the program maintains the
vegetation and brush within its rights-of-way appropriately and to make
modifications to the management program in the event that the program
is not maintaining adequate clearances of brush from the lines.
First and foremost, Swanton visually inspects the system to determine
the problem areas that need immediate attention. Swanton monitors its
vegetation along the distribution and transmission lines annually.
Swanton trims along its transmission lines approximately every three to
five years and trims along the distribution lines about every five to seven
years. Swanton has a spreadsheet that lists where and when it trims.
Swanton’s outage reports show that the trimming plans have been
working successfully.
All lines are trimmed to the edge of the legal right-of-way. The trimming
width on either side of the line is fifty feet.
Swanton has a firm budget on trimming, which is approximately one-
hundred thousand dollars per year; the miles of trimming are determined
during the inspections and are dependent on growth due to climate
conditions. Eighty percent of the system is road side, so monitoring is
fairly simple. The other twenty percent is monitored on foot.
The trimming cycle used to be much longer, but Swanton shorted it in
order to maintain adequate clearances of brush from the lines. Since the
ice storm of 1998, Swanton has become much more aggressive with its
tree trimming. Swanton’s ratepayers have also become more in favor of
tree-trimming, as it has seen first-hand the effects of what untrimmed
trees can do to reliability of the system during an ice storm.
In addition to its vegetative and brush management program, Swanton
has a program to identify danger trees within its rights-of-way and to
21
either prune or remove those trees. Again, the success of this program is
measured by whether danger trees are a root cause of system outages.
Danger trees are identified by utility personnel while patrolling the lines,
reading meters, or inspecting the system. Once a danger tree is
identified, it is promptly removed if it is within Swanton’s right-of-way.
For danger trees outside of the right-of-way, Swanton contacts the
property owner, explains the hazard, and with the owner’s permission
removes them. Where permission is not granted, Swanton will
periodically follow up with the property owner to attempt to obtain
permission.
Occasionally, Swanton finds that some trees are out of its reach. In those
cases, Swanton hires a contractor to do the trimming work.
Total Miles Miles Needing Trimming Trimming Cycle
Transmission 6.2 0 3-5 year average
Distribution 120 20 5-7 year average
Distribution Lines Vegetative Management:
2012 2013 2014 2015 2016 2017
Amount
Budgeted
$74,000 $78,000 $80,000 $100,000 $110,000 $110,000
Amount
Spent
$60,072 $71,306 $82,556 $120,642 x x
Approx.
Miles
Trimmed
20 acres
(6 miles)
11.22 acres
(1.9 miles)
20.4 acres
(3.4 miles)
52.72 acres
(8.5 miles)
20 acres (3
miles)
20 acres (3
miles)
Transmission Lines Vegetative Management:
2012 2013 2014 2015 2016 2017
Amount
Budgeted
$5,000 $10,000 $10,000 $10,000 $0 $10,000
Amount
Spent
$22,694 $9,513 $7,500 $5,000 x x
Approx.
Miles
Trimmed
5 acres 21 acres 1 acre 1 acre 0 acres 1 acre
Swanton did not budget for trimming on its transmission lines for 2016 as all
of the trimming was done in 2015 so there was nothing left to be trimmed.
22
Utilities should monitor the # of tree-related outages as compared to the
total number of outages, and provide this information
2011 2012 2013 2014
Tree Related Outages 8 9 10 11
Total Outages 54 80 60 49
Tree-related outages as % of total outages 15% 11% 17% 22%
Swanton’s Public Service Board Rule 4.900 Electricity Outage Reports,
reflecting the last three years (2012-2014) in their entirety, can be found at the
end of this document.
One of the issues of significant concern in the operation of any distribution
system is reliability of service to its retail customers. As part of the recognition
of that concern, Swanton has committed to performance standards for
reliability that measure the frequency and duration of outages affecting its
customers. There are two measures for the frequency and duration of outages.
The Public Service Board’s Rule 4.900 defines them as:
System Average Interruption Frequency Index ("SAIFI"): Customers
Out, divided by Customers Served. SAIFI is a measure of the
average number of times that the average customer experienced an
Outage.
Customer Average Interruption Duration Index ("CAIDI"): Customer
Hours Out, divided by Customers Out. CAIDI is a measure of the
average length of time, in hours, that was required to restore
service to customers who experienced an Outage.
Swanton has committed to achieve performance levels for its distribution
system below an index of 2.4 for SAIFI and 2.5 for CAIDI. Swanton maintains a
record of and reports on all its system outages, including the root cause of an
outage. While some outages cannot be prevented, there are a number of
specific, cost-effective steps that can be taken to maintain or improve system
reliability by working to eliminate the potential for some outages to occur and
making changes that will promote reduced outage times when an unavoidable
outage does occur.
Baseline 2011 2012 2013 2014
SAIFI 2.4 1.6 1.9 0.8 0.4
CAIDI 2.5 2.2 2.4 2.1 2.0
23
Describe storm/emergency procedures, such as securing contract crews,
dispatch center, participating in utility conference calls, updating
vtoutages.com.
Like other Vermont municipal electric utilities, Swanton is an active participant
in the Northeast Public Power Association (“NEPPA”) mutual aid system, which
allows Swanton to coordinate not only with public power systems in Vermont,
but with those throughout New England. A Swanton representative is also on
the state emergency preparedness conference calls, which facilitate in-state
coordination between utilities, state regulators and other interested parties.
Swanton uses the www.vtoutages.com site during major storms especially if it
experiences a large outage that is expected to have a long duration. Swanton
believes it is beneficial to inform the Public Service Department if it is
experiencing these types of outages.
Discuss last T&D studies, and plans for future studies.
Two twenty-year system studies have been conducted for Swanton. The first
study was done in 1968, by Burns and Roe, Inc., and the second was done in
1996, by PLM Electric Power Engineering. The content of these two studies is
available upon request.
At this point, Swanton does not have any system study plans. However, when
renewable projects are proposed, a system study may be initiated to determine
the impact. Any future studies will depend on growth resulting from additional
loads and from generation projects.
Has a fuse coordination study been conducted, and has it been
implemented?
In 2008, John Askew of L.N. Consulting, Inc. assisted Swanton Village Electric
in the coordination of their electric circuit feeders and fusing. Final reporting
was informal and correspondence was carried out using email. Technical one-
line diagrams and associated fault curves as well as recommended recloser
control settings were included within the correspondence. Some fine
adjustments have been made to recloser response settings, since the major
coordination effort, to satisfy FERC, NERC, and ISO-NE requirements. Copies
of the emails (12 pages) and technical drawings (13pages) are available if
desired.
24
Historical Capital Projects over last three years (2012-2014):
Historical Capital Projects 2012-2014
2012 Hydro Plant Plant upgrades $496,358 New turbine $1,342,909 Total: $1,839,267 Distribution Plant New transformer $468,477 Plant upgrades $90,605 Total: $559,082 Transportation $0 Total: $0
2012 Total: $2,398,349
2013 Hydro Plant Plant upgrades $237,147
Total: $237,147 Distribution Plant Plant upgrades $33,847
Total: $33,847 Transportation $0 Total: $0
2013 Total: $270,994
2014 Hydro Plant Plan upgrades $164,948 Total: $164,984 Distribution Plant Plant upgrades $52,351
Total: $52,351 Transportation Dump cart $6,134 Total: $6,134
2014 Total: $223,469
25
Future Capital Projects for next three years (2015-2017):
Future Capital Projects 2015-2017
2015 Hydro Plant Repair of Unit #1 Butterfly Valve $90,857 Replacement of Unit #4 Governor $90,000 Total: $180,857 Distribution Plant Gore Road Upgrade $3,263 South River Street Upgrade $8,241 Canada Street Upgrade $12,161 King Street Upgrade $3,309 Total: $26,974 Transportation Bucket Truck $296,990 Total: $296,990
2015 Total: $504,821
2016 Hydro Plant Fabrication of Wicket Gates
Bolts/Bushings $30,000 Replacement of Unit #1 Governor $90,000 Total: $120,000 Distribution Plant Tanner Memorial Drive $6,176 Brown Avenue $4,990 Taylor Drive $4,914 Bosworth Street $2,514 Total: $18,594
2016 Total: $138,594
2017 Hydro Plant Replacement of Unit #2 Governor $90,000 Total: $90,000 Distribution Plant Thibault Parkway $3,339 Winters Court $9,169 John Drive $4,611 Greenwich Street $8,215 Total: $25,334 Transportation
26
Bucket Truck $350,000 Total: $350,000
2017 Total: $465,334