partnership to advance clean energy deployment (pace-d 2.0) … · 2019. 9. 2. · output of demand...
TRANSCRIPT
Partnership to Advance Clean Energy Deployment (PACE-D 2.0)
Technical Assistance Program : Technical Workshop
Strategic Energy Planning for Renewable Deployment
18 September 2019, Ranchi, Jharkhand
•2/18/2019 FOOTER GOES HERE 1
Mr. Sumedh Agarwal | Dr. Nagaraja R
Agenda
Resource Planning - States
❑Strategic Resource Planning (SRP) - What & Why?
❑Current Practices
❑Case Studies from Rajasthan and Karnataka
❑PACE-D 2.0 Program Approach for Jharkhand Power
Sector Planning
• Renewable is cheaper compared to conventional
• Time is not far that soon with the thrust on RE
– RE will no longer enjoy must run status
– Permissible variation limit will shrink
• However challenge remains, RE is uncertain and
unpredictable and hence require a better
understanding of load curve to support
integration.
RE to play a big role in India’s Power Sector
Resource Planning - States
RE Installed
78 GW(22% of Installed Cap. May’19)
RE Target by Y2022
175 GWAiming for 225GW
Falling RE Prices
Wind ₹ 2.5 -2.85/kWh
Solar ₹ 2.4 -2.65/kWh
Discoms’ Avg. Procurement
Cost
₹ 3.6/kWh(APPC FY18-19)
2223
10 5 3
27
18 12 9
0%
20%
40%
60%
80%
100%
2015 2016 2017 2018 2019
Thermal & Hydro (GW) RE (GW)
1. Capacity Constraints – Power Shortage during Peak Times
2. High AT&C Losses
3. Unforeseen Shortages of Fuel and Existing planning practices –
lead to steep rise in power purchase cost.
4. Power procurement cost is 70-80% of the total cost of supply.
5. Discoms needs to be better equipped to deal with new
challenges of RE dominated power portfolio.
Current Challenges Faced by Distribution Utilities
Resource Planning - States
0
200
400
600
800
1000
1200
1400
1600
1800
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
200
400
600
800
1000
1200
1400
1600
1800
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fill Peak with PeakersBackdown TP
Average
Peak
Resource Planning - Conventional Approach
• Thermal Resource fairly a base load, predictable and stable.
• The peak requirements were attended through Peaker’s
• Demand was considered uncontrollable.
• Demand was higher than supply. Load control was through load shedding.
Now Supply Curve also Varies with time (RE)
Resource Planning - States
600
800
1000
1200
1400
1600
DEM
AN
D (
MW
)
Typical Demand Curve
0
200
400
600
800
1000
1200
1400
1600
Typical Resource Curve
RESO
UR
CE (
MW
)
Resource Planning - States
0
200
400
600
800
1000
1200
1400
1600
1800D
EM
AN
D
Matching Supply and Demand Curve- Possibility of Higher
RE Share without External Support
• Substantial efforts are on for RE (Wind, Solar, Storage) forecasting
• Requirement is to predict a better and granular demand curve.
• Demand can be controlled by DR and time of the day tariff.
Dispatch on Dec. 14, 2018
• PLF of TPPs – 71%
• RE Generation Share –
15%
• Avg. Power Cost – Rs
4.88/u
How Supply and Demand Curve Matching Helps Higher RE Uptake ? –
A Simulation Study for Rajasthan
Resource Planning - States
Capacity Add.
2x Solar
2.5x Wind
Others-Nil
0
2000
4000
6000
8000
10000
12000
14000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Actual Dispatch on December 14, 2018Nuclear
Coal
Gas
Hydro
Wind
Solar
ST Market
Demand (FY2019)
0
2000
4000
6000
8000
10000
12000
14000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
Simulation for December 14, 2022
Demand FY2018
Demand FY2022
With better Demand Forecast & Resource Planning, RE Share can Get Doubled
Simulation for Dec. 14, 2022
• PLF of TPPs – 72%
• RE Generation Share – 30%
• Avg. Power Cost– Rs 4.63/u
(Decrease of about 5.2%)
Resource Planning - States
Karnataka : Resources Optimization using Simulation Tool
2019
No stranded asset created
No system level grid security issues
Savings of 1500 Crs/annum
Peak Demand : 11245 MW
Resources : Thermal + Hydro + RE (W+S)(55%) (14%) (31%)
Business As Usual (+) RE Scenario (+)
New Thermal 4500 MW 2400 MW
RE 0 MW 6400 MW
Storage - 2000 MW
Cost 18,500 Cr. 17000 Cr.
2030
Peak Demand : 19127 MW
0
5000
10000
15000
20000
0
5000
10000
15000
20000
25000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Peak d
em
an
d (
MW
)
Gen
era
tio
n D
isp
atc
h i
n M
W
Generation Dispatch on 25-03-2030
Solar Wind Thermal Hydro Firm Storage Demand
Ge
ne
rati
on
Dis
patc
hG
en
era
tio
n D
isp
atc
h
Pe
ak
De
man
d (
MW
)
How Karnataka Exceeded RPO Target ?
Resource Planning - States
0
2000
4000
6000
8000
10000
12000
14000
1:0
0
2:0
0
3:0
0
4:0
0
5:0
0
6:0
0
7:0
0
8:0
0
9:0
0
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
0:0
0
De
man
d (
MW
)
Actual Load Curve of - April-2018
Demand Solar
0
2000
4000
6000
8000
10000
12000
14000
1:00
3:00
5:00
7:00
9:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
De
man
d (
MW
)
Actual Load Curve April-2019
Demand Solar
Due to shifting of part of
Irrigation pump sets to Solar
generation time. Total irrigation
contributes to 1/3rd of State
Energy
Approach for Power Sector Planning for Jharkhand
Scaling & OutreachProcurement
Plan Software Design &
Development
Study
Current Practices
v/s Best Practices
Develop Design Scale
Develop Methodology and
design tool in 3 modules
(demand forecasting,
resource planning and least
cost procurement)
Undertake study to assess
utility demand forecasting,
resource planning and least
cost power procurement
practices.
• Build Capacity of
planners,
• Disseminate
Knowledge and
• Replicate for
national adoption.
• Deploy Tool and
develop procurement
plan,
• Model guidelines and
regulation
Support and Engagement with Stakeholders in Jharkhand
Management Steering
Committee
Steering Committee
Project Committee
USAID/ MNRE
Secretary, Power (E) Dept. –Chairman
MD, JBVNL,
MD, JUSNL ; MD, JUVNL
Director, JREDA
Secretary, JSERC
Representative USAID
Representative Tetra Tech
ED, C&R, JBVNL - Chairman
ED, O&M, JBVNL; GM, IT, JBVNL
Chief Eng, C&R, JBVNL,
SE, Commercial, JBVNL
SE, C&R, EE C&R, EE-Comm. JBVNL
Representative USAID
Tetra Tech
Approach for Power Sector Planning in Jharkhand
Resource Planning - States
PPO D – G Mapping
Approach❑Demand Forecast Module
❑Generation Mapping Module
❑Power Procurement Optimization Module
Demand Forecast Module
Resource Planning - States
• Dependent variable: Category-wise historical annual
energy & peak power.
• Independent
Variables: Historical and predicted GDP,
population, per capita
income, policies, etc.
• Energy forecast up to 20 years on
yearly basis
• Peak demand estimations as per load
factor
• Forecast values of dependent variable
i.e. monthly energy in MU and load
(MW) for up to 3 years with hourly
resolution.
Output of demand
forecasting is used in
demand-generation
mapping & SRP
Long Term
Load
Forecast
Medium
Term Load
Forecast
•Multiple regression analysis
•Time series methods like
ARIMA
•Artificial Neural Networks
•Adaptive methods.
• Dependent variable: Historical monthly energy & peak
power with hourly resolution.
• Independent Variables: Historical and predicted
weather parameters,
seasonality, locality
Generation Mapping Module
Resource Planning - States
• Projected demand
• Available generation sources
• Planned and forced outages
• Signed contracts
• Generation Adequacy up to 20 years
• Surplus / Deficit status and quantum
• Application will generate the optimal
plan to meet demand at the lowest
cost, considering the available
resources up to 3 years
Power
Procurement
Optimization
Demand
Generation
Mapping
Strategic
Resource
Planning
•Mapping = ∑ Total available generation
- Projected demand for each year
•MILP optimization techniques aligns
variations in IRP with variations in REs
• Generation
• Uncertainty
• Hourly demand profiles
• DSM and Energy Efficiency
policies
Power Procurement Optimization
Resource Planning - States
•Projected demand & available
generation.
•Penalty for unmet demand
•Contract obligations
•Variable RE generation
portfolio
•Power Markets data
Power
Procurement
Optimization
•Risk-based procurement
strategy assistance to
manage price and volume
risk associated with
procurement in the market
or by contracts applying
MILP optimization
techniques
Application provides the best possible
energy mix, considering power
procurement from contracts, including
the following:
• Strategy support, which includes all
types of contracts, for the forecast
horizon
• Surplus/shortfall optimization if
the quantum is to be absorbed
• Surplus / deficit in terms of MU
and MW with time slots.
• Seasonal power procurement
assessment.
• Revision of existing PPAs
• Cost benefit analysis by comparing
new PPAs/ existing PPAs / power
from markets
Demand Forecasting
• Multiple regression analysis
• Time series methods like ARIMA
• Artificial Neural Networks
• Adaptive methods.
Generation Resource Optimization focused on Minimized Cost using Stochastic modeling (using Monte-Carlo Simulation), MILP considering
• Thermal Constraints
• Hydro Constraints
• Renewable Constraints
• System Level constraints (demand & reserves)
Algorithms and Intricacies- For all three Modules
Key Benefits for Jharkhand
Resource Planning - States
Long & Medium
term forecasting
Optimization
RE Maximization
Procurement Planning
Reskilling of Planners
• Internal generation mix
• Existing medium & long term
contracts
• Considering technical
and economic
optimization of
conventional generation
Considering the uncertainty
from renewables
01
05
04
03
02
Equip Utility with better techniques of
planning - Using Merit Order Dispatch &
MILP
Features
Long term and medium term forecasting
considering econometric variables and scenario
analysis to accommodate for policy changes
Better Discom Power Planning Uptake lead to higher RE uptake at reduced Power Procurement Cost
Project Milestones
Resource Planning - States
Start
2 8
EndGap
Analysis
Beta
Software
Final
Software
Power
Procurement
Plan
Capacity
Planning
Scaling &
Outreach
9 12 13 14
Oct-19 April-20 July-20 Sep-20 Nov-20 Dec-20
▪ Current
practices across
globe
▪ Requirements
from DISCOM
▪ Develop frame
work
▪ Functional,
Technical
requirement
document
▪ Development
of Beta
software
▪ Factory
Acceptance
Test
▪ Customizations
▪ Deployment of
Final SW
▪ Site Acceptance
Test
▪ Data collection
& Modeling
▪ Demand
Forecasting
▪ Generation
Mapping
▪ Power Plan
Development
▪ Training/Video
calls
▪ Reskilling of
Utility members
▪ Building
analytical skills
to maximize
utilization of
SW
▪ Development of
Strategy
▪ Support
Documents
▪ workshops/train
ing for other
DISCOMs in
India
Project Milestones
Resource Planning - States
Start
1
Gap
Analysis
Oct-19
▪ Current
practices across
globe
▪ Requirements
from DISCOM
▪ Develop frame
work
Current Planning
Practices v/s Best
Practices
Data collection complete
Report presentation to Project committee by 1st Week
of October.
Demand
Forecasting
Module
Development
Data Collection Started
System Parameter requirements
Development of Algorithms
Development of Use Cases and Test Cases and Steering
committee approval
Development and Testing of Module
Deployment of Module
2
DF
Module
Power Purchase
Quantum*
(MUs)
Power Purchase
Cost*
(Rs Crore)
Average Cost of
Power*
(FY19-20)
13,448.22 5,524.90 Rs 4.11/kWh
Jharkhand: Energy Portfolio
Resource Planning - States
RE Source Potential (MW)
Wind -
Solar 18,180
S-Hydro 228
Source: CSO ES Report 2018
Type State Private Central Total
Thermal 1,190 900 315 2,405
Hydro 130 0 71 201
RE 4 16 0 20
% RE
Addition
PPC with
ES
(Crores)
PPC
without ES
(Crores)
Savings
(Crores)
%
Savings
5 5518 5417 101 2%
10 5510 5309 202 4%
15 5503 5200 303 5%
20 5496 5092 403 7%
Source: Power for All for Jharkhand
Installed Capacity (MW)
*JBVNL
0
200
400
600
800
1000
3000
3500
4000
4500
5000
5500
6000
5 10 15 20 25 30 35 40
Savi
ngs
(C
rore
s)
Pow
er
Purc
has
e C
ost
(C
rore
s)
% RE Addition
Power Purchase vs. RE Addition
PPC with Grid Integration PPC without Grid Integration Savings (Crores)
RE @2.5 Rs/unit
22Resource Planning - States
Questions and Comments
Thank You!