glwa capital improvement...
TRANSCRIPT
THE FOSTER GROUP
TFG
GLWA Capital Improvement Program
Summary and Financing Observations
January 26, 2016
THE FOSTER GROUP
TFG
FY 2017 CIP Summary Definitions
2
• Two Separate CIP Plans
GLWA (Regional System)
DWSD-R (Local System)
• COMBINED CIP Financing
Requirements are still referenced
Programs for the Regional and Local
systems still need to be coordinated
Where not specified in this presentation,
figures refer to the COMBINED CIP
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP Recent CIP Financing Req’ts
3
• FY 2016 Approved CIP Approved by BOWC in March 2015
• POS Estimate Used for pursuit of bond consent and refunding
issue in December 2015
Reflects initial estimates from Master Plan Update (Water) and independent estimates in later years (Sewer)
• FY 2017 Preliminary CIP Presented today for review
Plan is for ultimate approval March 2016 as part of overall FY 2017 Financial Plan
THE FOSTER GROUP
TFG
FY 2017 COMBINED CIP Recent CIP Financing Req’ts
4
• We’ve been asked to review and provide
commentary on the PRELIMINARY
CIP’s, with specific focus on:
Alignment with / impact on existing financial
plans;
Comparisons to prior programs;
Alignment with cost of service categories;
Separation of distinct GLWA and DWSD-R
projects
THE FOSTER GROUP
TFG
FY 2017 COMBINED CIP Recent CIP Financing Req’ts
5
• In order to evaluate these overall CIP
plans, we have aligned the first 5 years
of these programs through FY 2020,
included an estimate for FY 2015, and
prepared resulting “6-year” programs for
comparative purposes
THE FOSTER GROUP
TFG
Water CIP Summary
THE FOSTER GROUP
TFG
FY 2017 GLWA Water CIP Total CIP Financing Requirements
7
• Six Year Financing Requirements for FY 2015* through FY 2020
FY 2016 Approved CIP = $587 million
POS Estimate = $674 million
FY 2017 Preliminary CIP = $697 million
• Increase is largely in “out” years, as short term financing requirements are actually lower
Increased Regional Transmission System projects
Additional Lake Huron Plant projects
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP 6-Year Financing Req’ts - $ millions
8
0
100
200
300
400
500
600
700
800
900
1,000
FY 2016 CIP Current Estimate FY 2017 Prelim CIP
GLWA Projects DWSD-R Projects
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP Comparison to Prior Plans - $ millions
9
0
50
100
150
200
250
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 GLWA Water CIP Comparison to Prior Plans - $ millions
10
0
20
40
60
80
100
120
140
160
180
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 DWSD-R Water CIP Comparison to Prior Plans - $ millions
11
0
5
10
15
20
25
30
35
40
45
50
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP Major Category Breakdown
12
Springwells
Water Works Park
Lake Huron
NE & SW
Transmission Mains
Pumping Stations &
ReservoirsGeneral & Other
DWSD-R Local
THE FOSTER GROUP
TFG
FY 2017 GLWA Water CIP Potential Financial Plan Impact
13
• GLWA CIP will continue to be financed by a combination of bond proceeds and revenues
• The overall plan continues to focus on increasing the amount of CIP funded by revenues (and less through debt)
• The Preliminary 2017 CIP identifies a “preferred funding source”
Not intended to be definitive as future financing plans need to consider market and other conditions
THE FOSTER GROUP
TFG
FY 2017 GLWA Water CIP Preferred Funding Source Summary - $ millions
14
0
20
40
60
80
100
120
140
160
180
2016 2017 2018 2019 2020 2021
Debt Eligible
Preferred Revenue Funded
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP Potential Financial Plan Impact
15
• Current financing plan set forth in the consent pursuit / refunding bonds document
Projects a ~ $230 million bond sale Spring 2016
• Preliminary FY 2017 CIP does not significantly alter this plan
Next bond sale may be deferred a few months
Will not materially impact 2017 debt service projections
Will modify overall plan for subsequent bond sales
• Updated Financial Plan will have to reflect and accommodate separation of GLWA and DWSD-R financing requirements and sources
THE FOSTER GROUP
TFG
FY 2017 COMBINED Water CIP Potential Financial Plan Impact - $ millions
16
0
50
100
150
200
250
300
350
400
2016 2017 2018 2019 2020
FY 17 CIP
Revenue Transfers
Bond Proceeds
SRF Loans
Beginning Balance
Est CIP - POS
THE FOSTER GROUP
TFG
Sewer CIP Summary
THE FOSTER GROUP
TFG
FY 2017 GLWA Sewer CIP Total CIP Financing Requirements
18
• Six Year Financing Requirements for FY 2015* through FY 2020
FY 2016 Approved CIP = $587 million
Current Estimate = $674 million
FY 2017 Preliminary CIP = $697 million
• Increase is largely in “out” years, as short term financing requirements are actually lower
• Increased Regional Sewer System projects, including improvements to the NIEA
THE FOSTER GROUP
TFG
FY 2017 COMBINED Sewer CIP 6-Year Financing Req’ts - $ millions
19
0
100
200
300
400
500
600
700
800
900
1,000
FY 2016 CIP Current Estimate FY 2017 Prelim CIP
GLWA Projects DWSD-R Projects
THE FOSTER GROUP
TFG
FY 2017 COMBINED Sewer CIP Comparison to Prior Plans - $ millions
20
0
20
40
60
80
100
120
140
160
180
200
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 GLWA Sewer CIP Comparison to Prior Plans - $ millions
21
0
20
40
60
80
100
120
140
160
180
200
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 DWSD-R Sewer CIP Comparison to Prior Plans - $ millions
22
0
5
10
15
20
25
30
35
2015 2016 2017 2018 2019 2020
FY 2016 Approved CIP
Estimate for POS
FY 2017 CIP
THE FOSTER GROUP
TFG
FY 2017 COMBINED Sewer CIP Major Category Breakdown
23
WWTP
Regional Sewer System
Combined Sewer System
Sewer Lift Stations
General & Other
DWSD-R Local
THE FOSTER GROUP
TFG
FY 2017 GLWA Sewer CIP Potential Financial Plan Impact
24
• GLWA CIP will continue to be financed by a combination of bond proceeds and revenues
• A significant portion of the projected short term projects have SRF commitments
• The overall plan continues to focus on increasing the amount of CIP funded by revenues (and less through debt)
• The Preliminary 2017 CIP identifies a “preferred funding source”
Not intended to be definitive as future financing plans need to consider market and other conditions
THE FOSTER GROUP
TFG
FY 2017 GLWA Sewer CIP Preferred Funding Source Summary - $ millions
25
0
20
40
60
80
100
120
140
160
2016 2017 2018 2019 2020 2021
Debt Eligible
SRF Loans
Preferred Revenue Funded
THE FOSTER GROUP
TFG
FY 2017 COMBINED Sewer CIP Potential Financial Plan Impact
26
• Current financing plan set forth in the consent pursuit document
SRF Funding in short term defers any new “regular” bond issuances until at least FY 2019
• Preliminary FY 2017 CIP does not significantly alter this plan
Still no bond sale required in the short term
No change to 2017 debt service projections
Will modify overall plan for subsequent bond sales
• Updated Financial Plan will have to reflect and accommodate separation of GLWA and DWSD-R financing requirements and sources
THE FOSTER GROUP
TFG
FY 2017 COMBINED Sewer CIP Potential Financial Plan Impact - $ millions
27
0
50
100
150
200
250
300
2016 2017 2018 2019 2020
Prelim FY 2017 CIP
Revenue Transfers
Bond Proceeds
SRF Loans
Beginning Balance
Est CIP - POS