A CENTRALIZED APPROACH

TO DIGITAL SIGNAGE

Lessons Learned at Wayne State University

Internet2 Fall 2011 Member Meeting

David W. Fleig, PMP

Project Manager, Wayne State University

Patrick J. Gossman, Ph.D.

Deputy CIO, Wayne State University

Internet2 Fall 2011 Member Meeting

Wayne State Fast Facts

32,000 students

13 schools and colleges

400 degree and certificate programs

Most diverse university in Michigan:

students from 50 states and 70+ countries

Six extension centers throughout

Southeast Michigan

Tenth-largest Detroit employer

Internet2 Fall 2011 Member Meeting

Overview

Goals of the Project

Organization (People, Funding, Content)

Technology (Hardware, Software, Network)

Successes

Lessons Learned

Future

Internet2 Fall 2011 Member Meeting

Goal: From this…

Internet2 Fall 2011 Member Meeting

To this…

Internet2 Fall 2011 Member Meeting

Pretty simple, eh?

Launch digital signage as a . . .

University-wide collaborative,

Across schools and colleges,

Across multiple campuses,

Showcase important people, news

and events

Inform ourselves and visitors

Build unit recognition and the WSU brand

Internet2 Fall 2011 Member Meeting

A bit more complex… Project

Management

(C&IT)

President

VP

Chief of Staff

Budget Office

C&IT

CIO’s Office

Infrastructure & Operations

Enterprise Applications

Customer Service

Network Security

Telecom

Video & TV

Business Operations

Communications

Marketing

VP

Graphic Design

Content Development

News & Information

Services

Facilities

Project Managers

Architecture &

Engineering

Construction Trades

Inspection & Life Safety

Art Curator

Purchasing

Buyer Software

Buyer Hardware

Legal

Dept / College

(Customers)

Deans

Directors

Staff

Students

Extension Centers

Vendors

Software

Hardware

Training

Installation

Maintenance

Internet2 Fall 2011 Member Meeting

Here are the politics…

Lots of different players

Different wants and desires

Different content

Who will pay?

Who will have control?

Pressure for advertising

Internet2 Fall 2011 Member Meeting

Competing Goals

Goals

Image

Inform, Unify, and Market

Branding

Timeframe: Immediate vs. Planned

Content: Local vs. University

Control (Content and Look): Local vs. University

Funding and Resources

Internet2 Fall 2011 Member Meeting

Everyone wins

Internet2 Fall 2011 Member Meeting

Content/Image Control Model

Image and Design – Marketing and

Communications

Central Content – Marketing and

Communications

Local Content – Local School/College/Dept

Internet2 Fall 2011 Member Meeting

Funding Model

Central funding from President’s office

Central hardware and software

Signs in general purpose areas

Local funding from units

Local signs

Installation and replacement

Support from C&IT

Software

Central and remote support staff

Internet2 Fall 2011 Member Meeting

Just the University

Internet2 Fall 2011 Member Meeting

Shared Space

Internet2 Fall 2011 Member Meeting

Shared Time

Internet2 Fall 2011 Member Meeting

Shared Time

Internet2 Fall 2011 Member Meeting

Local, University, National

Internet2 Fall 2011 Member Meeting

How did we get here?

Project chartered in Fall 2008

Great team formed

Agreed to work toward the common goal

Architectural team understood value of

standardization, centralization

Multiple funding sources and multiple

ownership helped tie all together

Internet2 Fall 2011 Member Meeting

Successes

Great team!

It looks good!

We are “catching eyeballs”

Many positive comments about image of

WSU and reaction to postings

Love time and weather, CNN with captions

Central support great in eyes of customer

End result: It works!

Internet2 Fall 2011 Member Meeting

Lessons Learned

Top Support – policy and funding

Must have a clear goal and buy-in by

entire team

Easier to centralize BEFORE everyone

adopts their own standard

It’s all about the content

You can’t get everyone to play

It takes a long time

Internet2 Fall 2011 Member Meeting

Challenges

Bring all schools and colleges into the fold

Content creation limited by staffing, both

central and local

Create once, publish everywhere has

limitations

Not making use of extensive software

capabilities yet

What happens in 3 years?

Internet2 Fall 2011 Member Meeting

Future

Student channel

More signs

Get outliers in

More tailored content

Survey – What do customers like/dislike?

Internet2 Fall 2011 Member Meeting

Technology

Getting Started

Location

Architecture

Installation

Equipment

Construction

Challenges

Examples

Future

Lessons Learned

Internet2 Fall 2011 Member Meeting

Getting Started

Two Tech Teams

Hardware and software

Architecture and network design

Goal – Single Source

Accountability and coordination

Standard RFP Approach

Software

Hardware

Internet2 Fall 2011 Member Meeting

Getting Started

“No Dark Signs”

Key philosophy

Development Stations

Marketing

IT Customer Service

IT Enterprise Applications

Internet2 Fall 2011 Member Meeting

Present Day

45+ signs installed

25+ buildings

May be one or more sign per building

Internet2 Fall 2011 Member Meeting

Location, Location, Location

Goal – “Capture eyeballs”

Customer First

Environment

Heat

Ambient light

Security

Display size

Internet2 Fall 2011 Member Meeting

Architecture

How does it work?

No precedent

Centralized

Virtual

Production

Development

Common image

Internet2 Fall 2011 Member Meeting

Architecture

Internet2 Fall 2011 Member Meeting

Installation

More than “Just hang a display…”

“No Dark Signs” Buy it…

Hardware & Software

Build it…

Prepare walls or ceilings

Field conditions, historic buildings, etc.

IT

Program it…

Push content

Finally…Light up the sign!

Internet2 Fall 2011 Member Meeting

Equipment

Flat panel display

Computer

Software

Mount

Internet2 Fall 2011 Member Meeting

Equipment

Flat panel display

Computer

Software

Mount

Internet2 Fall 2011 Member Meeting

Equipment NEC 52” or 46” LCD displays

1920 x 1080p HDTV 16:9

Narrow bezel, Commercial

Players

Now Micro DMP-900

Small form factor computer

Fast and powerful as possible

“Keep it cool”

Software

Four Winds Interactive, Inc.

Content manager

Player application

Windows 7

Common Image

Internet2 Fall 2011 Member Meeting

Construction

Internet2 Fall 2011 Member Meeting

Let’s count the trades…

Construction

“No Dark Signs”

Coordination

Trades

Carpenters

Painters

Electricians

Communications

Technical staff

Audio-Visual

Internet2 Fall 2011 Member Meeting

Cost & Time

Construction

$500 - $5,000…depends

Equipment

$4,000 per sign…all in

Total

$7,500

Average per sign

Lead times

3 to 45 days

Internet2 Fall 2011 Member Meeting

AC Power

Internet2 Fall 2011 Member Meeting

Power failures

Significant challenge Players (computers)

OS (Windows 7)

Displays

Be Prepared… Random recovery

Solution Small, disposable UPS?

Not tried yet

Heat & Ventilation

Significant challenge

Content impact

Internet2 Fall 2011 Member Meeting

HOT

SPOT

Heat & Ventilation

Internet2 Fall 2011 Member Meeting

Heat & Ventilation

Internet2 Fall 2011 Member Meeting

Alternative

MUCH

COOLER

Heat & Ventilation

Internet2 Fall 2011 Member Meeting

College of Nursing

Ventilation Critical !!!

Examples

Internet2 Fall 2011 Member Meeting

Law School ceiling mount

Examples

Internet2 Fall 2011 Member Meeting

School of Business 2 x 2 array

Examples

Internet2 Fall 2011 Member Meeting

Near an elevator

Examples

Internet2 Fall 2011 Member Meeting

Recessed Mounts…careful…

Internet2 Fall 2011 Member Meeting

Real time monitoring

Audio, video and closed captioning

MPEG-4 AVC (Part 10)

H.264

HD 720p

6.5 Mbps

Multicast

VLC

Loudspeakers

CC text

Other Issues

Future

Interactivity – unlikely, but maybe…

Emergency messaging

Audio

Live streaming of special events

Enhanced remote management

Improved monitoring and QC

Additional signs

Internet2 Fall 2011 Member Meeting

Successes

Great teamwork

Great partners

Solid design

Centralized

Smooth integration

Satisfied customers

Internet2 Fall 2011 Member Meeting

Lessons Learned

Heat

AC power

Customer service and maintenance

Spares and warranties

Player computing power

Content impact

Networking

Centralized operations

Test and development facilities

Training

Codes and inspections

Internet2 Fall 2011 Member Meeting

Thanks!

Please feel free to give

us a call

Internet2 Fall 2011 Member Meeting

David W. Fleig, PMP

Project Manager, Wayne State University

[email protected]

(313) 577-0845

Internet2 Fall 2011 Member Meeting

For more info…