molymoly credit suisse - global steel and mining … suisse - global steel and mining conference ......
TRANSCRIPT
0
MOLYMOLYMINESMINESLIMITEDLIMITED
Credit Suisse - Global Steel and Mining Conference24 -25 September 2008
Derek FisherChief Executive Officer
Credit Suisse - Global Steel and Mining Conference24 -25 September 2008
Derek FisherChief Executive Officer
MOLYMOLYMINESMINESLIMITEDLIMITED
1
MOLYMOLYMINESMINESLIMITEDLIMITED
Forward Looking StatementsForward Looking Statements
This presentation includes �forward-looking statements� as that term within the meaning of securities laws of applicable jurisdictions.
Forward-looking statements involve known and unknown risks, uncertainties and other factors that are in some cases beyond Moly Mines�
control. These forward-looking statements include, but are not limited to, all statements other than statements of historical facts
contained in this presentation, including, without limitation, those regarding Moly Mines� future expectations. Readers can identify
forward-looking statements by terminology such as �aim,� �anticipate,� �assume,� �believe,� �continue,� �could,� �estimate,� �expect,�
�forecast,� �intend,� �may,� �plan,� �potential,� �predict,� �project,� �risk,� �should,� �will� or �would� and other similar expressions.
Risks, uncertainties and other factors may cause Moly Mines� actual results, performance, production or achievements to differ materially
from those expressed or implied by the forward-looking statements (and from past results, performance or achievements). These factors
include the failure to complete and commission the mine facilities, processing plant and related infrastructure in the time frame and
within estimated costs currently planned; variations in global demand and price for molybdenum and copper; fluctuations in exchange
rates between the U.S. dollar and the Australian dollar; failure to recover the resource and reserve estimates of the Project; the failure
of Moly Mines� suppliers and service providers to fulfil their obligations under construction, supply and tolling agreements; unforeseen
geological, physical or meteorological conditions, natural disasters or cyclones; changes in the regulatory environment, industrial disputes,
labour shortages, political and other factors; the inability to obtain additional financing, if required, on commercially suitable terms; and
global and regional economic conditions. Readers are cautioned not to place undue reliance on forward-looking statements. We assume no
obligation to update such information.
2
MOLYMOLYMINESMINESLIMITEDLIMITED
MolybdenumMolybdenumSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Should You Be Interested?
MOLYMOLYThe Metal
MOLYMOLYThe Company
3
MOLYMOLYMINESMINESLIMITEDLIMITEDSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Mo Metal Price
+ $30per lb
$73,000per ton
OR
Moly Mines has 850,000,000 lbs of MoPlus
Copper, Tungsten and Iron
4
MOLYMOLYMINESMINESLIMITEDLIMITED
Molybdenum OxideMolybdenum Oxide
CopperCopper
NickelNickel
ZincZinc
Molybdenum � the metalMolybdenum � the metalSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Stable, non volatile price
Sept 2003 Sept 20080
2.50
US$
/lb
0.501.001.502.00
Sept 2003 Sept 20080
30
US$
/lb
6121824
Sept 2003 Sept 20080
5
US$
/lb
1234
Sept 2003 Sept 20080
20
40U
S$/lb
5
MOLYMOLYMINESMINESLIMITEDLIMITED
Why the High Mo Price?Why the High Mo Price?Spinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� World Mo economy is rapidly changing
� Accelerating growth in consumption ( 5 � 6%)
� Driven by;
! hydrocarbon industry
! construction industry
! automobiles
! 21st century issues
� global warming
� nuclear power
Rougher \ Scavengers Flotation
6
MOLYMOLYMINESMINESLIMITEDLIMITED
Chindia, ChindiaChindia, ChindiaSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� 25% of world Mo production
� +35% of world steel
� +25% of world specialty steel �expanding
� Mo exports severely restricted
� Urbanisation, infrastructure
China
India et al
Secondary Crusher
7
MOLYMOLYMINESMINESLIMITEDLIMITED
World Mo Industry � STAGNANT !!!World Mo Industry � STAGNANT !!!Spinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� 25 years of low, flat Mo prices
�Little or no exploration
�Last new large Mo mine � 1982
�World consumption � 460m lbs pa, 5% growth pa
The world needs a �Spinifex Ridge�every year to satisfy expanding
consumptionGrinding
8
MOLYMOLYMINESMINESLIMITEDLIMITEDIndustry OverviewIndustry Overview
Growing Supply Defecit Growing Supply Defecit
Highlights
� Estimated committed supply growth includes plannedexpansions of existing primary and by-product mines
� Moly consumption is expected to grow at 5-6% CAGR through 2015
� Cumulative supply deficit of 70-100Mlb expected by 2012, growing to 230-300Mlb by 2015
� Short fall in future supply can only be met by NEW production from NEW mines
� Only 4 major new primary mines under consideration to help fill this deficit
9
MOLYMOLYMINESMINESLIMITEDLIMITED
Why Moly Mines?Why Moly Mines?Spinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� The World�s most advanced large Mo resource
� Significant Copper, Iron, Tungsten, Silver
� All permitting in place, Stage 1 development commenced
� Capex, Opex largely de-risked
� Located close to Asian market in the Pilbara, WA
� Long life resource, can supply 5% of World consumption for +25 years
� Off-take with ThyssenKruppFlotation Copper Cleaning
10
MOLYMOLYMINESMINESLIMITEDLIMITED
Mt Newman (Fe)Mt Newman (Fe)
Woodie Woodie(Mn)
Woodie Woodie(Mn)
Telfer(Au, Cu)Telfer
(Au, Cu)
Paraburdoo (Fe)Paraburdoo (Fe)
Tom Price (Fe)Tom Price (Fe)
Marble Bar
Nifty (Cu)Nifty (Cu)
Port Hedland
Dampier
Broome
Spinifex RidgeSpinifex RidgeYarrie (Fe)Yarrie (Fe)
100kms
KarrathaKarratha
W e s t e r n
A u s t r a l i a
Chichester Range (Fe)Chichester Range (Fe)
Major RoadRailMajor Port
EASTASIAEASTASIA
Commodity
Iron OreManganeseChromiteCopperSaltCondensateLNGLPGAmmonia
Current
2641.10.30.26.83.312.51.50.7
Future
8001.50.50.48.34.517.02.00.8
Production � Mt pa
Pilbara Exporters 2006 / 2007
4,000kms4,000kms
10,000kms
13,000kms
18,000kms
Pilbara Region, Australia � Location, Location !Pilbara Region, Australia � Location, Location !Spinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
11
MOLYMOLYMINESMINESLIMITEDLIMITED
Construction ReadyConstruction ReadySpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Services corridorServices corridor
Secondary CrusherSecondary Crusher
StockpileStockpile
Ball & SAG MillsBall & SAG Mills
HPGR MillHPGR Mill
Power StationPower Station
AdministrationAdministrationTailings ThickenerTailings Thickener
Mo / Cu Regrind & FlotationMo / Cu Regrind & Flotation
Waste 3Waste 3
Waste 2Waste 2
Waste 1Waste 1
PitPit
ROMROM Plant &AdministrationPlant &Administration
Dry Stack TailingsDry Stack Tailings
CampCamp
Pit Office/WorkshopsPit Office/Workshops
Port Hedland (160kms)
NorthNorth
TunnelTunnel
23 Year Reserve+ Resource tail
10 Year
20 Mtpa Open pit mine140,000 tonnes / day (average)Pre-strip � 34 Million tonnesStrip ratio � 1.1 to 1
(includes pre-strip, excludes low grade)
First 10 year pit� 1.3 kms x 1.1kms� 400m deep, Pit angle 43°
12
MOLYMOLYMINESMINESLIMITEDLIMITED
Mineral / Ore Reserves & Mineral ResourcesMineral / Ore Reserves & Mineral ResourcesSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
JORC/NI43-101 classification Mt Mo% Cu% Ag g/t Proven reserves 199.7 0.06 0.10 1.5 Probable reserves 251.1 0.04 0.07 1.1 Total 450.8 0.05 0.08 1.3
JORC/NI43-101 classification Mt Mo% Cu% Ag g/t Measured resources 206.8 0.06 0.10 1.5 Indicated resources 445.4 0.04 0.07 1.1 Total 652.2 0.05 0.08 1.3 Inferred resources 399.0 0.04 0.07 1.1
Reserves
Resources
13
MOLYMOLYMINESMINESLIMITEDLIMITED
0.09% Mo HighGrade Core
0.02% Mo Resource(~1 billion tonnes)
10 Year Pit Shell
10 Year Plan10 Year PlanSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
14
MOLYMOLYMINESMINESLIMITEDLIMITED
2020 and Beyond2020 and BeyondSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� Ore :
� Mo %:
� Strip Ratio
Initial 10 Years (DFS)Initial 10 Years (DFS)
197Mt
0.065
1.3 :1
� Ore :
� Mo %:
� Strip Ratio
2020 & Beyond2020 & Beyond
935Mt
0.044
1.1 :1
15
MOLYMOLYMINESMINESLIMITEDLIMITEDSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Expansion Scenario �2015Expansion Scenario �2015
DFS 20mtpa � Pre Tax NPV - A$855M IRR - 21.5%
30mtpa - (3 year Av Mo)1 A$2,215M 23.2%- (Spot Mo)2 A$3,313M 29.9%
� In-pit crusher, mill expansion to 30-33mtpa
� Stockpiled, lower-grade ore processed from 2015
1. US $28.50 / lb � per Ryans Notes
2. US $33.50 / lb � per Ryans Notes
Flotation Mo Cleaners
16
MOLYMOLYMINESMINESLIMITEDLIMITED
Project ExecutionProject ExecutionSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� All mining leases "
� Native title agreement "� Environmental approvals
� State "
� Commonwealth "
� Key construction contracts "
� Mining contract awarded � A$1.1 billion over 7 years "
� Engineering / construction team "
� EPCM "
� Offtake � ThyssenKrupp "
� Long lead equipment "Milling
17
MOLYMOLYMINESMINESLIMITEDLIMITED
Project UpdateProject UpdateSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
� 70% Project capital cost contracted or tendered
� Engineering and procurement of process plant
� 35% complete
� 463,000 man hours
� $150m Interim Financing negotiated and being documented
� funds expected mid October
� continues Critical Path activities - long lead items, construction
camp, access, airport
� Full project funding � negotiating with Strategic Investors
Milling
18
MOLYMOLYMINESMINESLIMITEDLIMITED
Execution & Development TimetableExecution & Development TimetableSpinifex Ridge Molybdenum ProjectSpinifex Ridge Molybdenum Project
Q1
20072007
Q2 Q3 Q4 Q1
20082008
Q2 Q3 Q4 Q1
20092009
Q2 Q3 Q4 Q1
20102010
Q2 Q3 Q4
� Long Lead Items Ordered
� Feasibility Study Completed
� Capital Cost Control Est.
� Key Contract Completion
� Environmental Approvals
� Project Funding
� Site Construction Activities
� Commissioning
� Production
19
MOLYMOLYMINESMINESLIMITEDLIMITED
GalifreyPlanned
Spinifex Ridge Molybdenum \
Copper Pit
PlannedSpinifex Ridge Molybdenum \
Copper Pit
Planned Waste DumpPlanned Waste Dump
PlannedSpinifex Ridge
Processing Plant
Plan
ned
Tunn
el
500m
Auton
Dalek
Surface Fe Mineralisation Outcrop
Fe Prospect
North
I R O N
F O R M A T I O N
Iron Ore At Spinifex Ridge Iron Ore At Spinifex Ridge
20
MOLYMOLYMINESMINESLIMITEDLIMITEDSpinifex Ridge
- Iron OreSpinifex Ridge- Iron Ore
ResultsConceptual Model
Dalek Prospect� 72 metres @ 60.7% Fe from 0m including
� 42 metres @ 66.2% Fe and� 9 metres @ 60.2% Fe
� 106 metres @ 52.8% Fe from 0m including
� 3 metres @ 65.4% Fe and� 47 metres @ 65.8% Fe
Auton Prospect� 55 metres @ 64.3% Fe from 0m
� 19 metres 61.6% Fe from 3m
Galifrey Prospect (rockchips)
� SXF42119 � 67.1% Fe� SXF42124 � 65.6% Fe� SXF42118 � 65.5% Fe
� Targeting a 10 Million tonne resource
� 6 year mine, 1- 2 Million tonne pa
� Drill & blast, crush, screen, truck to Port Hedland - $50/t
� Minimal capital cost, established infrastructure
� Complementary to Spinifex Ridge Mo\Cu operations
� $360m Net Cashflow (50:50 lump/fines, 60% Fe)
or
� A$2-3/lb in Mo cost credits
21
MOLYMOLYMINESMINESLIMITEDLIMITEDMolybdenum � �a metal for our time�Molybdenum � �a metal for our time�
What is Molybdenum?What is Molybdenum?
Spinifex Ridge Copper/Molybdenum Producer
Crushing, Grinding, Flotation
Crushing, Grinding, Flotation
Lubricants, Chemicals, Mo Metal
Bags, Drums, Cans
Bags, Drums
Low Cu Concentrate
High Cu Concentrate
TechnicalMolybdenum Oxide
Pure Oxide Oxide Powder and Briquettes
FeMo
LeachingRoasting
Sublimation and Further Processing
Converting
Molybdenum Output Flow-Chart Highlights
� Moly is primarily used as an alloying agent in steel or as a catalyst in chemicals
� Moly offers very attractive properties� Fourth highest melting point of any metal
on the periodic table� Anti-corrosive� Weldability� Flexibility� Hardness
� Low substitution risk� Unique properties that satisfy increasing
performance requirements� Potential substitutes are more costly
and/or follow same commodity cycle
22
MOLYMOLYMINESMINESLIMITEDLIMITED
Diversified End-Use Diversified End-Use Molybdenum � �a metal for our time�Molybdenum � �a metal for our time�
28%
40%11%
6%
4%4%
5% 2%
StainlessSteel
Low Alloy Steels
Chemicals
Moly Metal
Castings
Superalloys
High-speed & tool steels OtherGlobal economies demanding more molybdenum
� Stainless and low alloy steels will continue to
grow supporting molybdenum�s traditional
applications.
� BUT�.
� The Energy Industry to emerge as a major end
user of molybdenum products
Energy IndustryEnergy Industry Global WarmingGlobal Warming Nuclear PowerNuclear Power
� Desalination� Automobile Industry� Desalination� Automobile Industry
� Piping� Shells & tubes� Piping� Shells & tubes
ULSDULSD
� Ultra low sulphur diesel� Catalysts� Ultra low sulphur diesel� Catalysts
� Pipelines� Sour oils & gases
(high sulphur)
� Pipelines� Sour oils & gases
(high sulphur)
Energy Industry accounts for 35-40% of global Moly demandEnergy Industry accounts for 35-40% of global Moly demand
23
MOLYMOLYMINESMINESLIMITEDLIMITED
Market HighlightsMarket HighlightsMolybdenum � �a metal for our time�Molybdenum � �a metal for our time�
� Sept 2008 Spot Price
� US$33.50 /lb
� 3 Year Average
� US$30.00 /lb
� 5 Year Average
� US$26.10 /lb
� Long Term Estimate
� US$20.00+ /lb
PricingSupply and Demand
CAGR Demand Estimates: 5 � 6%
Existing Production Sources Are At Capacity � Primary mines require capital intensive expansions
� By-product producers have high graded & production stagnant
� Chinese industry consolidating, export quota�s & tariffs applied
� No significant new supply before 2011
� Production costs are rising, energy intensive industry
� New projects are capital intensive
24
MOLYMOLYMINESMINESLIMITEDLIMITED
China Growth Supported by Stability from WestChina Growth Supported by Stability from WestIndustry OverviewIndustry Overview
� Western Europe, USA and Japan accounted for 62% of total consumption in 2007, China consumed 17%
� World CAGR of 6.6% since 2002� China CAGR of 24% since 2002� Strong global demand growth since the early 2000s
� Continued strong demand growth from BRIC markets driven by urbanization, development in stainless, carbon and alloy steels
� China to lead world growth at estimated 12 � 15% CAGR through 2015� Developing steel industries key growth driver (2006-2012 CAGR of 17%)
� 8-9% growth expected for low alloy steels and chemicals
� Western Europe: Estimated 3 � 4% CAGR through 2015� Stainless steel represents ~50% of total moly demand
� Automotive industry (low alloy steels) also important contributor to demand
� Moly bearing grades becoming increasingly popular
� USA: Estimated 2 � 3% CAGR through 2015� Comparatively even distribution between end segments
� Strong environmental regulations driving growth (chemicals)
HighlightsMoly Consumption Dominated by the Big Four
China is Expected to Drive Demand Growth
17%
15%
21%29%
18%USA
W Europe
Other
Japan
China
30%
11%
20% 25%
14%USA
W EuropeOther
Japan
China
~ 2015
2007
25
MOLYMOLYMINESMINESLIMITEDLIMITED
Iron Ore At Spinifex Ridge Iron Ore At Spinifex Ridge
Iron Ore Drilling
Tungsten Drilling
Iron Formation
Waste
Mo Pit
Waste
Process Plant
0 1500metres
Mine Village
Airstrip
Tailings
Fe Area 2Fe Area 2 Fe Area 1Fe Area 1
S p i n i f e xR i d g e
Mining Leases
� 55 metres @ 64.3% Fe from 0m� 19 metres @ 61.6% Fe from 3m� 29 metres @ 58.3% Fe from 0m including
� 4 metres @ 63.1% Fe from 0m and� 11 metres @ 61.2% Fe from 17m
� 18 metres @ 58.3% Fe from 7m including� 8 metres @ 61.4% Fe from 11m
� 14 metres @ 55.6% Fe from 2m� 16 metres @ 56.0% Fe from 0m� 18 metres @ 54.3% Fe from 0m� 7 metres @ 55.0% Fe from 1m� 106 metres @ 52.8% Fe from 0m including
� 3 metres @ 65.4% Fe and� 47 metres @ 65.8% Fe
� 72 metres @ 60.7% Fe from 0m including� 42 metres @ 66.2% Fe and� 9 metres @ 60.2% Fe
� Major synergies for the Spinifex Ridge operation
� Potential credits to molybdenum production
� Resource delineation drilling required
Highlights Results
June
200
8 R
esul
ts
General / Misc. Leases
26
MOLYMOLYMINESMINESLIMITEDLIMITED
Corporate StructureCorporate StructureMoly Mines LimitedMoly Mines Limited
Shares on issue: 86,191,677
� ASX Listed: 54M
� TSX Listed: 32M
Options: 15,425,000
Fully diluted issued capital: 101,616,677
Board/Staff (inc all options) : 16%
Cash on hand: A$26M
Major Shareholders:� 19.9% - Harbinger Capital� 7.2% - CIBC Mellon� 5.8% - Oppenheimer Funds
Broker Coverage:� Paradigm Capital Inc.� Haywood Securities Inc. � Wellington West Capital Markets
Inc.Trading Symbols:
� ASX: MOL, TSX: MOL, FWB: HJ1
27
MOLYMOLYMINESMINESLIMITEDLIMITED
� 50 Kings Park Rd, West Perth, WA, 6005, AUSTRALIA� Telephone: +61 8 9429 3300 Fax: +61 8 9429 3399
Contact informationContact information
� Suite 1801, Level 18, 80 Richmond St West, Toronto, Ontario, CANADA
� Telephone: +1 416 777 1801 Fax: +1 416 777 1802
� Email: [email protected]� Website: http://www.molymines.com� Stock market codes: ASX: MOL, TSX: MOL, FWB: HJ1
Moly Mines LimitedMoly Mines Limited