overview flue gas desulphurization …soxnox2017.missionenergy.org/presentations/samik...
TRANSCRIPT
CONFIDENTIALRESTRICTEDPUBLIC INTERNAL
OVERVIEWFLUE GAS DESULPHURIZATION
TECHNOLOGIES FOR INDIAN MARKET
1
Samik GuptaNew Delhi22/9/2017
CONTENTS
MoEF & CC Regulations & Implication
Overview of Mature DeSOx Technologies
Important Technical Factors for Consideration
Part 2
Part 3
Part 1
Way Forward for ImplementationPart 4
Part 5
ConclusionPart 6
Indicative Cost Comparison
225-Sep-17
MoEF & CC Regulations & Implication
Part 1
325-Sep-17
MoEF&CC Environmental Norms - Dec 7, 2015
Category 1 Category 2 Category 3WORLD BANK EMMISSION NORMS FOR SOLID FUEL PLANT RATING ≥ 600 MW
PARAMETER (mg/NM3)
PREVIOUS NORMS
TPPs installed before 31 Dec 2003
TPPs installed after1 Jan 2003 up to 31 Dec 2016
TPPs to be installed from 1 Jan 2017
NDA DA
< 500 MW
> 500 MW
< 500 MW
> 500 MW
For all Units
Particulate Matter 150/50 100 50 30 50 30
Sulphur Dioxide (SO2) None 600 200 600 200 100 200-850 200
NOx None 600 300 100 510-1100 200
Mercury None NA 0.03 0.03 0.03
Timeline for compliance
• Category 1 & 2 Projects: to comply within 2 years form the date of Notification
• Category 3 Projects have to comply prior to Commissioning
MoEF & CC norms more stringent than World Bank
425-Sep-17
Applicability of New Technologies
150 GW of existing market plus
new installations
525-Sep-17
SOx Gap Analysis
ParameterFlue gas SOx range
(mg/NM3)
Required Limit(mg/NM3)
Sulfur Dioxide (SO2) 1058 - 2858 100
Notes:• Data for a 660 MW supercritical unit• The SOx data represents the range of SOx levels obtained due to the combustion process burning the range of “design”,
“best” and “worst” coal at TMCR and BMCR load conditions. • Coal sulphur content 0.26 – 0.7 %• Dry, 6% oxygen basis• SO3 ~ 1%
Reduction efficiency ~ 96.5%
625-Sep-17
Overview of Mature DeSOx Technologies
Part 2
725-Sep-17
FGD
WetDry
LSFO Sea Water SDA
Spray TowerJBR
CDS
Overview of Mature FGD Technologies
Legend:
LSFO: Limestone Forced Oxidation
JBR: Jet Bubbling Reactor
SDA: Spray Dryer Absorber
CDS: Circulating Dry Scrubber
Other types -• Dry sorbent injection• REACT Multipollutant
825-Sep-17
Attribute Limestone Wet FGD Spray Tower Sea Water Spray TowerDry FGD Spray Dryer Absorber (SDA)/
Circulating Dry Scrubber(CDS)
Commercial StatusUnits with single absorber modules are in
operation up to 900 MW unit capacity
(largest population > 85%)
Units with single absorber modules are
in operation up to 1000 MW unit capacity
Units are in operation in facilities up to 500 MW.
Multiple absorber modules are required for
units above 350 -400 MW range.
Reagent Limestone (CaCO3) Sea Water Lime (CaO) /Hydrated lime Ca(OH)2
Byproduct Saleable gypsum (CaSO4) or landfill Treated sea water
Calcium sulfite (CaSO3) and calcium sulfate
(CaSO4) along with some fly ash
Mostly used in landfill
Sulfur in coal <6% (high flexibility) < 2% <2.5%
SO2 Removal Efficiency
~98-99% ~98-99% 90-95%, up to 98% in CDS
SO3 Removal Does not efficiently capture SO3 Efficiently removes SO3 as well as HCl, HF, Hg
Comparison of Mature FGD Technologies
925-Sep-17
Attribute Limestone Wet FGD Spray Tower Sea Water Spray TowerDry FGD
Spray Dryer Absorber (SDA)
Operating temperatureFlue gas at outlet is saturated with water ~ 55 deg C Flue gas at outlet is unsaturated (typically
15 - 30 deg C above dew point)
Footprint Small in power island and, large overall Relatively smaller than wet FGD
Pros/Cons
Acid corrosion potential downstream
Higher Capital Cost
High power consumption
Waste water needs treatment for reuse/disposal
No corrosion potential
downstream
Lowest Capital Cost
Dry byproduct/no waste water
High power consumption
High maintenance cost
High cost reagent
Byproduct use limited
Comparison of Mature FGD Technologies
1025-Sep-17
Wet Limestone Forced Oxidation ProcessSpray Tower
JBR
1125-Sep-17
Parameter Unit Value RemarksLimestone consumption rate Ton/h 8.2 Per absorber @ 85% purity
Gypsum generation Ton/h 11 Per absorber on dry basis, purity >
85%, moisture < 15%
Flue gas temperature at stack inlet Deg C ~ 55 ~85 with gas to gas heater
Pressure drop on flue path due to FGD
mmwg 385 Including absorber and GGH
Auxiliary power consumption kW 14000 Both units with GGH
Noise level dBA < 85
Make up water requirement M3/h 220 (max) Both units
Effluent water generation M3/h 42 (max) Both units
Effluent qualityChloride ppm 10,000
Temperature Deg C 37 - 65
pH 5-6
LSFO Typical Operating Parameters (Spray Tower)
Note: Representative data for a 2 x 660MW plant. Above parameters are calculated based on max S coal & BMCR basis. The numbers are indicative and supplier specific.
1225-Sep-17
Sea Water FGD Process
SEA WATER FROM CONDENSER
1325-Sep-17
Dry FGD Processes
SDA CDS
• Additional capture of SO3, HCl, HF, Hg• Improved efficiency of CDS ~ 1-2%• Particulate emission guarantee
1425-Sep-17
Simple Dry Systems
• Suitable for small units• Ca(OH)2 powdered reagent• Can be retrofitted with existing ESP• Cost effective
Bag Filter
1525-Sep-17
Parameter Unit Value Remarks
Lime (CaO) consumption rate Ton/h 8 Per unit @ 90% purity
Flue gas temperature at reactor
Deg C ~ 65 - 70
Auxiliary power consumption kW 15000 Both units
Noise level dBA < 85
Make up water requirement M3/h 210 (max) Both units (CT blowdown
grade)
CDS (NID) Typical Operating Parameters
Note: Representative data for 2 x 660 MW plant. Above parameters are calculated based on max S coal & BMCR basis. The numbers are indicative and supplier specific.
1625-Sep-17
Important Technical Factors for Consideration
Part 3
1725-Sep-17
Coastal
Type of Condenser cooling system > sea water open cycle
First choice in favour of sea water FGD may be considered
Rethinking needed on use of cooling tower on coastal plants as per new MoEFCC regulation. Result in prohibitively high cost for independent sea water pumping for FGD (~ INR 250 Cr/unit) + Cooling Tower (~INR 250 Cr/unit).
Location of Plant
1825-Sep-17
LSFO largest space due to many ancillaries • Absorber Area/slurry pumps/booster fan/GGH• Buildings (air blowers, bleed pumps, dewatering equipment,
control & electrical room)
• Limestone Storage & handling • Limestone milling/product tanks/pumps
• Gypsum storage area• FGD waste water treatment
Sea Water FGD requires large treatment basin
Dry FGD most compact
Space & Layout
172 ft
125
ft
600 MW
500x150 ft
1925-Sep-17
10-12 Million Tons of lime stone per year (for existing capacity)
Purity Impacts saleability of gypsum, preferred 85% or more Limestone mines located in Rajasthan, MP, Gujarat, AP, Telengana, Karnataka, Tamil Nadu, Orissa
Lime is obtained from chemical suppliers mostly in powdered or pebble form
Availability of Reagents
Limestone analysis Unit Range
Calcium as Cao % by mass 50-54
Magnesium as MgO % by mass 1.0-2.0
CO2 % 41-42
Sulphur (as S) % 0.1
Alumina ( Al2O3) % 0.5-1.5
Silica+ Al2O3+ Fe2O3 % 3.0
Bond Grindability g/rev 2.65
Powder Gravity g/cm2 2.65
Limestone sample obtained from mine located in MP
2025-Sep-17
By-product offtake
Possible gypsum useso Building industry: plaster, blocks & boardo Cement industryo Agricultural soil conditionerMinimum by product gypsum purity requirement 85-90%o Achievable saleable grade gypsum purity 90%o Lower grade gypsum used in manufacture of port land
cemento Plant Owner tie ups with cement and building material
industries nearby o Policy mandate for use of byproduct gypsum in
cement/building industries
Dry FGD byproduct used as landfill
2125-Sep-17
Use of Gas to Gas Heater (wet FGD)
o Practical limit of gas reheating constrained by size/cost
o Typical reheat temperature 85 – 90 deg C
o Better dispersion from stack.
o Prevents white plume
o Reduces water consumption by pre-cooling the flue gas minimizing evaporation loss.
But
o Does not entirely eliminate downstream corrosion due to SO3 in flue gas
o Ducting and stack still needs costly lining materials
o Adds to auxiliary power and OPEX
o Generally regenerative type heaters 10% of CAPEX
Gas to Gas Heater
2225-Sep-17
Dry FGD systems allow existing stack to be used as is
Wet systems need existing stack to be specially lined > duration 3-4 months > generation loss
Alternatively, a new shorter stack for FGD > old stack as is (only for FGD bypass operation)
Without GGH wet stack design to be adopted
Use of high efficiency mist eliminator to minimize droplet carry over
Condensate collection & draining system
Maintain proper gas velocity to eliminate droplet entrainment
Wet booster fan downstream of FGD
NDCT as stack
Stack Operation & Protection
2325-Sep-17
Chemical Resistance
Temperature Resistance deg C
Life Relative Cost Remarks
Borosilicate blocks on steel/concrete38 or 51 mm
Suitable for wet flue gas,
with high SO3 level
200 Long life /minor
maintenance
2 Can withstand higher temperature for short periods
Vinyl Ester FRP Do 150 Long life 2 Do
Glass flake vinyl ester on steel,2 mm
Do 140 Needs reapplication
/ maintenance in medium
term
1 (lowest) Do
Alloy cladding (C276 or Ti) steel,1.5 mm
Do 427 - 900 Long life 3 (highest) Suitable for all boiler upset conditions
Stack Operation & Protection Stack Lining Materials
2425-Sep-17
Major consumers:
o Cooling tower evaporation
o Wet FGD system (0.16-0.2 m3/MWh)
o Ash handling system
o Coal handling system
o Power cycle system
o HVAC system
Impact on Overall Water Balance
Case Plant water consumption without
FGDCOC=5
Plant water consumption with FGD
COC=5
Remarks
(m3/h)
(A)
m3/MWhr)
(B)
(m3/h)
(C)
(m3/MWhr)
(D)
1 3862 2.93 4036 3.06 FGD water 216 m3/h supplied from clarified water
2 2868 2.17 3091 2.34
Case 1: Both FA & BA Wet Disposal, with zero ash water recoveryCase 2: BA wet disposal & FA Dry Utilization, with 60% ash water recoveryThe figures shown in above table are indicative for a 2 x 660 MW plant with cooling tower
2525-Sep-17
Need for WFGD Waste Water Treatment
o Aggressive quality with very high TDS (Cl, heavy metals). Reuse within plant difficult
o Bled off to control chemistry in reaction chamber
o Schemes have been tried with conventional physical/chemical precipitation or biological treatment to target specific metal species.
o Slip stream flue gas heating u/s of APH to evaporate waste bleed.
o Stricter environmental regulations often call of zero liquid discharge which is complicated and costly.
FGD Waste Water Treatment
2625-Sep-17
Way Forward for Implementation
Part 4
2725-Sep-17
Schedule Realistic schedule - FGD project cycle 3 years (1 year planning and award + 2 year execution)
CEA/Regional Power Committees (RPCs) have published phasing plans starting 2020. More than 270 existing units (210 –660 MW range) ear marked for FGD installation in phasing plan
New plants under construction (planned COD after Jan 2017) to get suitable time extensions for concurrent FGD implementation.
Applicability CFBC boilers generally exempt
Partial capacity FGD in smaller (< 500 MW) plants – cost effective
Considered decision to retire old, non performing units (> 30 yrs) For larger plants (> 500 MW) wet FGD (limestone & sea water) are most suitable techno economically.
Space a critical constraint in older plants (pre 2003 COD). Dry technologies may be considered due to compactness/ease of retrofit, specially for < 500 MW.
FGD can bring a co-benefit in reduction of SPM (& Hg) - consider integrated approach with ESP modification
Way forward for Implementation
2825-Sep-17
Long term sourcing of 90% pure limestone. Ministry of mines to ensure ~10 Million tpy.
Policy mandate for use of by-product gypsum (rather than natural) with 90% quality met by plant.
Reduction of plant downtime during installation. New chimney versus existing chimney lining/modification (12-16 weeks or more). Leads to revenue loss ~ INR 7 lac/MW/week
Procurement readiness to meet installation deadlines starting 2020 – bulk orders by Dec 2017.
@ 30 GW per year and 3 units per supplier ~ at least 10 - 12 good suppliers are needed. Reputed technology suppliers globally available – US, Europe, Japan, South Korea, China – transfer of technology through
various collaborations/ventures/subsidiaries with Indian players to be accelerated to bring in more competition.
Way forward for Implementation
2925-Sep-17
Indicative Cost Comparison
Part 5
3025-Sep-17
Indicative Cost Comparison Wet & Dry FGD
Note: 1. This analysis does not include for LS WFGD:a) Cost of revenue loss due to shutdown for existing chimney
lining2. CAPEX of sea water FGD is marginally lower than LS WFGD
Assumptions:
The costs are based on budgetary estimates and indicated for reference onlyCost indicated is for 2 units of 660 MW each
Plant life is 25 yearsPlant capacity factor is considered 85%
Escalation rate is considered 3%
NPV discount rate is considered 10%O&M staff per shift is considered 4
O&M labor rate is considered INR 800 per dayFor semi dry FGD O&M includes filter bag and cage changes @ 15% of Capex every 4 years
FGD power consumption is considered 1% to 1.15% for LS WFGD and SD FGDPower cost is considered INR 4.67/KWh
Limestone consumption is considered 16.4 tons per hour for WFGD
Limestone (> 85% purity) cost is considered INR 2000 per ton Gypsum production is considered 22 tons per hour
Gypsum price is considered INR 700 per ton for saleLime consumption is considered 16 tons per hour for SDFGD
Lime (> 90% purity) cost is considered INR 6000 per ton
Repair/maintenance cost is considered 1% of FGD plant capital cost
Summary Cost Analysis for FGD 2 x 660 MW unitsLimestone Wet FGD Dry FGD (CDS) Remarks
FGD Plant Capital Cost (including civil & structural, erection, testing &commissioning)
INR Cr 550 370
Includes:Gas gas heater for WFGD
Excludes :a) reagent unloading/ crushing/ conveying for bulk storage areab) by product disposal system
Chimney lining INR Cr 80 Borosilicate for WFGDBulk Reagent handling INR Cr 15 5ZLD treatment package INR Cr 100Total installed cost INR Cr 745 375
INR Cr/MW 0.56 0.28
Total O&M Cost per year INR Cr/yr 68.61 136.74O&M labor 0.10 0.10Aux power 48.68 52.16
Reagent 23.83 71.48 Lime for CDS or limestone for WFGD
WWTS reagents 0.02Waste water treatment reagents for WFGD
Gypsum (marketable) -11.47 Revenue from selling gypsum. NA for CDS
Repair/maintenance 7.45 13.00includes annualized filter bag change for CDS every 4 years
O&M 25 yr NPV INR Cr 814.47 1623.18
Plant 25 yr lifecycle cost INR Cr 1559.47 1998.18
3125-Sep-17
Conclusions
Part 6
3225-Sep-17
Major boost in AQCS market in India
Mature FGD technologies proven worldwide are ready to be adopted for Indian market
Qualified, global FGD technology suppliers to collaborate with Indian suppliers for critical design & supply.
Choice of best technology to be made after detailed analysis covering all aspects of plant life, interfaces, emission gap, sustainable operation and cost.
All stakeholders (plant operators, policy makers, regulators) should work together to address remaining concerns (mostly related to investment and cost recovery) to clear the path to speedy implementation. .
Conclusions
3325-Sep-17
tractebel-engie.comShaping our world
Let’s keep in touch – T +91 1244698500