ALABANG TOWN CENTER BPO 1Alabang Town Center, Brgy, Ayala Alabang, Muntinlupa City May 5, 2014

PROJECT EXECUTION PLAN Rev. 00Makati Development Corporation16 Pt. Project Execution Plan

Project Information

Risk Management

EHS Plan

QA Plan

Program & Planning

Design Production

Value Engineering & Innovation

Construction Methods

Temporary Works & Site Logistics

Table of Organization

Procurement

Asset Management

Contract Management

Operating Budget

Sustainability, CSR & Environment

Project Close - OutMakati Development CorporationProject Information

OPCEN Head : Napoleon P. Micaller Project Manager : Jodel M. Ebero Project-in-Charge : Dennis I. TomanengResource Assignment Contract Package : Fixed Lump Sum Contract Amount : Php 956,170,901.47 Start Date : Completion Date : Duration : 16 monthsContract Details Structural : TandeM Engineering & Consultancy Architectural : Aidea Architects Mechanical : Westrim Electrical : EB Cruz Plumbing/Sanitary : NBF Consulting Inc. Fire Pro : NBF Consulting Inc.

Design ConsultantsMakati Development CorporationProject DescriptionProject Name : Alabang Town Center BPO 1Project Location : Alabang Town Center, Brgy. Ayala Alabang, Muntinlupa CityBuilding Type : Retail & Typical Office floorsNature of Project : BPO Building BUILDING CONFIGURATION:No. of FloorsDESCRIPTION11 - Lower Ground Floor (Parking + Utility rooms) with provision for future tunnel connection to proposed adjacent retail expansion11 Ground floor (Retail)11 - 2nd Floor (Parking + Admin office) with bridgeway connection to existing mall11 - 3rd Floor (Parking)77 - 4th to 10th Floor (Office)Total = 11 FloorsTotal CFA: 33,083.82 sq.m.Total GFA: 24,665.18 sq.m.Makati Development Corporation

ALABANG TOWN CENTER BPO - 1ATC BPO 1ALABANG TOWN CENTER BPO is a 10 storey with roofdeck building located along Madrigal Avenue and supermarket drive. This composed of retail stores at ground floor, parking floor levels and an office rental spaces. Makati Development Corporation

PROGRAM AND PLANNINGVICINITY MAPMakati Development CorporationPROJECT HIGHLIGHTS

PARKING AREA CFA = 3,229.5 sqm.Total No. of Slots = 266 slotsLEASABLE (RETAIL)LEASABLE (BPO)COMMON AREASERVICE AREA CFA = 1,576.74 sqm.Total No. of Spaces = 10 retail , 1 convenience store & 1 Bank spaces CFA = 15,943.83 sqm.Total No. of Office = 6 offices CFA = 8,737.94 sqm. CFA = 3,035.22 sqm.Makati Development CorporationLOCATION MAP

MADRIGAL AVENUESUPERMARKET DRIVEATC BPO1ATC MALL PARKINGEXISTING MALLMakati Development CorporationPROJECT MILESTONESGROUND BREAKING:05 APRIL 2014 GENCON AWARD DATE: 21 APRIL 2014 START OF BULK EXCAVATION: START OF STRUCTL EXCAVATION:FIRST POURING:TOPPING - OFF:WATERTIGHNESS : ENERGIZATION:TESTING AND COMMISSIONING: 15 PROJECT COMPLETION:HANDOVER TO SBU : START OF TENANT FIT-OUT :Pre-requisites:STRUCTURAL, ARCHITECTURAL AND MEPFS FCD :Contract awarding must be on orbefore:

Makati Development CorporationTEMPORARY FACILITIES LAY-OUT

PUMPCRETE STN. 2PUMPCRETE STN. 1FORMWORKS FABRICATION AND STAGING AREAGate 1Gate 3MC (160 TONNER)TRANSLAB FABRICATION AREATRANSLAB STOCKPILE AREA (Zone 1)Gate 2SATELLITE OFFICETRANSLAB STOCKPILE AREA (Zone 2 & 3)REBARS STOCKPILE AREASTRUCTURAL FILL HOLDING AREACONSTRUCTION ACCESSGENSETMakati Development Corporation3. CONSTRUCTION METHODS AND TEMPORARY WORKSBulk Excavation Sequence

Legend:Subject for excavation4,511.86cu. m

All excavated materials shall be hauled out a total of 376 truck loads Start = May 19, 2014 End = June 18, 2014

Stockpile AreaItem No.DescriptionNo. Of Units1Backhoe (PC 200)12Bulldozer1Equipment Needed:Exit PointMakati Development CorporationTOWER CRANE

TOWER CRANE FOUNDATIONTOWER CRANE MASTTOWER CRANE FOUNDATIONTOWER CRANE LOCATION30 MTS. 6.3T40 MTS. 5.0T50 MTS. 3.6TMakati Development CorporationPROGRAM AND PLANNING

TOWER CRANE FOUNDATION SECTION

TOWER CRANE FOUNDATION PLANTOWER CRANE FOUNDATION SECTION SHOWING DISTANCE FROM LOWER GROUND FLOORMakati Development CorporationTOWER CRANE UTILIZATION

ELEVATION SHOWING TOWER CRANETC UTILIZATION SCHEDULEACTIVITIES7AMto8AMRebar8AMto9AMRebar9AMto10AMPRECAST TRANSLAB (STRIPPING)10AMto11AMFORMWORKS (Loose Forms)11AMto12NNFORMWORKS (Loose Forms)12NNto13PMBREAK TIME13PMto14PMREBARS14PMto15PMFORMWORKS (Gang Forms)15PMto16PMFORMWORKS (Gang Forms)16PMto17PMFORMWORKS (Gang Forms)17PMto18PMFORMWORKS (Gang Forms)18PMto19PMMEPFS19PMto20PMPRECAST WALL INSTALLATION20PMto21PMPRECAST WALL INSTALLATION21PMto22PMPRECAST WALL INSTALLATION22PMto23PMPRECAST WALL INSTALLATION23PMto24AMCONCRETE POURING24PMto1AMBREAK TIME1AMto2AMCONCRETE POURING2AMto3AMCONCRETE POURING3AMto4AMCONCRETE POURING4AMto5AMCONCRETE POURINGMakati Development CorporationEquipment Utilization ScheduleITEMMAJOR EQUIPMENTDURATION (mos.)STARTFINISHPEAK20142015MayJunJulAugSeptOctNovDecJanFebMarAprMayJunJulyAug1Tower Crane - Luffer Type 50m Radius (TC-1)9.519-Jul-1430-Apr-15111111111114Genset 300KVA 440/220V 3PH9.519-Jul-1430-Apr-15111111111115Genset 150KVA 230V 3PH - Construction Power Source)12.519-Jun-1430-Jun-15111111111111116Genset 100KVA 230V 3PH - Off Site Temporary Power Source)7.019-Jun-1415-Jan-151111111117Backhoe (PC 100)1.019-Jun-1419-Jul-141117Backhoe (PC 100)1.010-Feb-1512-Mar-151118Stake Truck4.019-Sep-1417-Jan-151111119Mini-Dumptruck 3.019-Jun-1418-Sep-14111119Mini-Dumptruck 1.010-Feb-1512-Mar-1511110Skid Loader 3.019-Jun-1418-Sep-141111111Submersible Pump10.05-Jul-1430-Apr-1522222222222212Gondola (rental)4.115-Apr-1515-Aug-1533333313Air Compressor 185CFM8.124-Jul-1424-Mar-151111111111Makati Development CorporationConcreting ScheduleMayJunJulAugSeptOctNovDecJanFebMar779.21358135818851554188520991677197.4Makati Development CorporationTRANSLAB FABRICATION AREA (ON-SITE)TRANSLAB FABRICATION OUTPUT

Makati Development CorporationTRANSLAB FABRICATION AREA (ON-SITE)TRANSLAB PRODUCTION CYCLE

TRANSLAB CASTING BED SECTIONTRANSLAB CASTING BED PLANTURN-AROUND CYCLEACTIVITIES7AMto8AMRebar Fabrication8AMto9AMRebar Fabrication9AMto10AMRebar Fabrication/Formwork Installation/Stripping10AMto11AMRebar Fabrication/Formwork Installation11AMto12NNRebar Fabrication/Formwork Installation12NNto13PMBREAK TIME13PMto14PMFormworks/Rebar Fabrication14PMto15PMRebar Fabrication/ MEPFS Insert15PMto16PMRebar Fabrication/ MEPFS Insert16PMto17PMClean - Up17PMto18PMInspection18PMto19PMConcrete Pouring19PMto20PMConcrete Pouring20PMto21PMCuring Time21PMto22PMCuring Time22PMto23PMCuring Time23PMto24AMCuring Time24PMto1AMCuring Time1AMto2AMCuring Time2AMto3AMCuring Time3AMto4AMCuring Time4AMto5AMCuring Time5AMto6AMCuring Time6AMto7AMCuring TimeMakati Development Corporation

reStructural Excavation Sequence3. CONSTRUCTION METHODS AND TEMPORARY WORKS4For formworks fabrication and staging AreaFor structural backfill holding AreaEXCAVATION TRAFFIC SCHEMEEXIT POINTGATE 2ZONE 4 ( Nov. 14 Nov. 21, 2014)ZONE 1June 19 July 03, 2014ZONE 2July 04 July 14, 2014ZONE 3July 05 July 18, 2014123Vol = 3408.21cumVol = 1747.35 cumVol = 319.01 cumMakati Development Corporation++++++++++++++++++++++++++++

19

reFoundation Concreting Sequence3. CONSTRUCTION METHODS AND TEMPORARY WORKS4ZONE 4 ( Nov. 21 Nov. 28, 2014)ZONE 1July 05 July 23, 2014ZONE 2July 16 July 31, 2014ZONE 3July 24 August 08, 2014123Makati Development Corporation++++++++++++++++++++++++++++

20

Cover SlabZONE 1Aug. 20 Aug. 29, 2014ZONE 2Aug. 22 Sept. 03, 2014ZONE 3Aug. 27 Sept. 08, 2014Slab on Grade Concreting Sequence123* Imported Fill (for structural backfill) volume = 5474.57cumMakati Development CorporationSTRUCTURAL MILESTONESSTRUCTURAL (BELOW GROUND)ZONE 1ZONE 2ZONE 3StartEndStartEndStartEnd1EXCAVATION19-Jun-143-Jul-144-Jul-1414-Jul-145-Jul-1418-Jul-142FDN3Footing5-Jul-1423-Jul-1416-Jul-1431-Jul-1424-Jul-148-Aug-144Pedestal24-Jul-1429-Jul-1427-Jul-141-Aug-1430-Jul-144-Aug-145Column 1st Lift30-Jul-143-Aug-142-Aug-146-Aug-145-Aug-149-Aug-146Retaining Wall 1st Liftn/an/a31-Jul-144-Aug-149-Aug-1413-Aug-147Underground Tanks24-Jul-147-Aug-148Cover Slab9-Aug-1416-Aug-149Backfilling17-Aug-1427-Aug-1424-Aug-141-Sep-1429-Aug-146-Sep-1410SOG/Underground Utilities20-Aug-1429-Aug-1422-Aug-143-Sep-1427-Aug-148-Sep-1411Retaining Wall 2nd Lift30-Aug-146-Sep-144-Sep-1411-Sep-149-Sep-1416-Sep-1412Column 2nd Lift30-Aug-146-Sep-144-Sep-1411-Sep-149-Sep-1416-Sep-14Makati Development Corporation

UG 4F 3F 2F 5F 6F 7F8F9F 10F RD RL ZONE 1ZONE 3ZONE 2LG Concrete Pouring SequenceNov. 27, 2014Nov. 20, 2014Nov. 13, 2014Oct. 8, 2014Oct. 15, 2014Oct. 22, 2014Oct. 26, 2014Dec. 17, 2014Dec. 8, 2014Dec. 1, 2014Jan. 16, 2015Dec. 28, 2015Dec.19, 2014Feb. 1, 2015Jan. 25, 2015 Jan. 18, 2015Feb. 12, 2015Feb. 5, 2015Jan. 29, 2015Mar. 02, 2015Feb. 23, 2015Feb. 16, 2015Mar. 20, 2015Mar. 13, 2015Mar. 6, 2015Apr. 7, 2015Mar. 31, 2015Mar. 24, 2015Apr. 25, 2015Apr. 18, 2015Apr. 11, 2015Apr. 23 , 2015Apr. 30, 2015Nov. 11, 2014Nov. 3, 2014FW1FW2FW3FW4FW5Makati Development Corporation23TABLE FORM FLY-OUT SCHEME

ZONE 1ZONE 2ZONE 31432Makati Development Corporation24STRUCTURAL MILESTONESSTRUCTURAL (ABOVE GROUND)ZONE 1ZONE 2ZONE 3StartEndStartEndStartEnd1UG30-Aug-1411-Sep-144-Sep-1416-Sep-149-Sep-1421-Sep-1422F14-Sep-1426-Sep-1419-Sep-141-Oct-1424-Sep-146-Oct-1433F29-Sep-1411-Oct-144-Oct-1416-Oct-149-Oct-1421-Oct-1444F14-Oct-1426-Oct-1419-Oct-1431-Oct-1424-Oct-146-Nov-1455F29-Oct-1411-Nov-145-Nov-1417-Nov-1410-Nov-1422-Nov-1466F13-Nov-1425-Nov-1418-Nov-1430-Nov-1423-Nov-145-Dec-1477F28-Nov-1410-Dec-143-Dec-1415-Dec-148-Dec-1420-Dec-1488F13-Dec-1427-Dec-1420-Dec-145-Jan-1529-Dec-1414-Jan-1599F28-Dec-1413-Jan-156-Jan-1518-Jan-1511-Jan-1523-Jan-15101016-Jan-1528-Jan-1521-Jan-152-Feb-1526-Jan-157-Feb-1511RD31-Jan-1512-Feb-155-Feb-1517-Feb-1510-Feb-1522-Feb-1512RL15-Feb-151-Mar-1522-Feb-158-Mar-15TOTAL SLAB FORMWORKS REQUIREMENTSMakati Development CorporationWORK CYCLE @ 12 DAYSDAY NO.ACTIVITIES1Survey and Lay-out2Installation of Column Rebars3Installation of Column Rebars/Column Formworks4Column Formworks/Column Concreting5Column Concreting/Preparation of Beam Bottom and Shoring6Preparation of Beam Bottom and Shoring/Beam Rebar Installation7Beam Rebar Installation/Installation of Translab8Installation of Translab/Beam Siding9Beam Siding/Installation of PC Wall10Installation of PC Wall/Installation of Top Bars11Installation of Top Bars/Electro-Mechanical Embedments12ConcretingWORK ACTIVITY SEQUENCE (PER ZONE)Makati Development CorporationACTIVITY DESCRIPTION Total Quantity UmeasActual ProductivityReqd MAN-HOURSWorking Hours per dayReqd MAN-DAYSTotal No. of DaysMANPOWERSTRUCTURAL WORKSMH/UmeasMHHRSMDdRequiredCurrentBalanceConcrete 13,283.86 m5.00 66,419.30 10 6,641.93 246.00 2727Formworks 65,472.35 m5.00 327,361.75 10 32,736.18 246.00 134134Rebars 2,967,765.02 kgs.0.07 207,743.55 10 20,774.36 246.00 8585Basis for Manpower Loading1. Program and PlanningMakati Development Corporation

Underground Tanks3. CONSTRUCTION METHODS AND TEMPORARY WORKSZONE 1STARTEND5-Jul-1416-Aug-14Concrete Vol= 569.30cum

Formworks: 2168.25sqm Rebars: 129,714.48kgsMakati Development Corporation++++++++++++++++++++++++++++

28

re3. CONSTRUCTION METHODS AND TEMPORARY WORKSZONE 1STARTEND5-Jul-1423-Jul-14Concrete Vol= 286.40 cum

FoundationZONE 2ZONE 3STARTEND16-Jul-1431-Jul-14Concrete Vol= 492.83 cum

STARTEND24-Jul-148-Aug-14Concrete Vol= 285.4 cum

Formworks: 344.9sqm Rebars: 65256.24kgsFormworks: 323.28sqm Rebars: 112291.6kgsFormworks: 313.5sqm Rebars: 65,028.39kgsMakati Development Corporation++++++++++++++++++++++++++++

29

Slab on GradeZONE 1STARTEND20-Aug-1429-Aug-14Concrete Vol= 87.47cumZONE 2ZONE 3STARTEND22-Aug-143-Sep-14Concrete Vol= 122.63cumSTARTEND27-Aug-148-Sep-14Concrete Vol= 122.46cum

Cover SlabRebars: 19931.09kgsRebars:27,942.26kgsRebars: 27,902.35kgsMakati Development CorporationPROJECT SCHEDULE (STRUCTURAL)

Concrete Vol= Concrete Vol=

ZONE 1STARTEND30-Aug-1411-Sep-14Concrete Vol= 404.86cumGround FloorZONE 2ZONE 3STARTEND4-Sep-1416-Sep-14Concrete Vol= 540.80cumSTARTEND9-Sep-1421-Sep-14Concrete Vol= 483.21cum

Formworks: 2336.25sqm Rebars: 92,248.13kgsFormworks: 2892.3sqm Rebars: 123,220.72kgsFormworks: 2673.37sqm Rebars: 110,099.39kgsMakati Development Corporation

ZONE 1STARTEND14-Sep-1426-Sep-14Concrete Vol= 372.50cumSecond FloorZONE 2ZONE 3STARTEND19-Sep-141-Oct-14Concrete Vol= 390.72cumSTARTEND24-Sep-146-Oct-14Concrete Vol= 296.98cum

PROJECT SCHEDULE (STRUCTURAL)Formworks: 2122.11sqm Rebars: 84,873.24kgsFormworks: 2148.54sqm Rebars: 89,025.81kgsFormworks: 1666.25sqm Rebars: 67,666.39kgsre4ZONE 4 STARTEND28-Nov-1412-20-14Concrete Vol= 142.81cumFormworks: 929.85sqm Rebars: 32,538.57kgsMakati Development Corporation

ZONE 1STARTEND29-Sep-1411-Oct-14Concrete Vol= 256.58cumThird FloorZONE 2ZONE 3STARTEND4-Oct-1416-Oct-14Concrete Vol= 380.68cumSTARTEND9-Oct-1421-Oct-14Concrete Vol= 254.46cum

PROJECT SCHEDULE (STRUCTURAL)Formworks: 1499sqm Rebars: 58,461.47kgsFormworks: 1898.07sqm Rebars: 86,738.67kgsFormworks: 1493.91sqm Rebars: 59,979.78kgsMakati Development Corporation

ZONE 1STARTEND14-Oct-1426-Oct-14Concrete Vol= 295.13cum4th FloorZONE 2ZONE 3STARTEND19-Oct-1431-Oct-14Concrete Vol= 394cumSTARTEND24-Oct-146-Nov-14Concrete Vol= 265.91cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1687.83sqm Rebars: 64,678.87kgsFormworks: 1892.65sqm Rebars: 86,207.18kgsFormworks: 1502.71sqm Rebars: 58,436.50kgsMakati Development Corporation

ZONE 1STARTEND29-Oct-1411-Nov-14Concrete Vol= 306.15cum5th FloorZONE 2ZONE 3STARTEND5-Nov-1417-Nov-14Concrete Vol= 359.49cumSTARTEND10-Nov-1422-Nov-14Concrete Vol= 275.03cum

PROJECT SCHEDULE (STRUCTURAL)Formworks: 1744.88sqm Rebars: 67,192.66kgsFormworks: 1967.44sqm Rebars: 78,178.53kgsFormworks: 1549.32sqm Rebars: 60,518.39kgsMakati Development Corporation

ZONE 1STARTEND13-Nov-1425-Nov-14Concrete Vol= 306.58cum

6th FloorZONE 2ZONE 3STARTEND18-Nov-1430-Nov-14Concrete Vol= 359.78cum

STARTEND23-Nov-145-Dec-14Concrete Vol= 275.46cum

PROJECT SCHEDULE (STRUCTURAL)Formworks: 1747.22sqm Rebars: 67,288.36kgsFormworks: 1968.79sqm Rebars: 78,242.97kgsFormworks: 1551.66sqm Rebars: 60,614.08kgsMakati Development Corporation

ZONE 1STARTEND28-Nov-1410-Dec-14Concrete Vol= 306.58cum7th FloorZONE 2ZONE 3STARTEND3-Dec-1415-Dec-14Concrete Vol= 359.78cumSTARTEND8-Dec-1420-Dec-14Concrete Vol= 275.46cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1747.22sqm Rebars: 67,288.36kgsFormworks: 1968.79sqm Rebars: 78,242.97kgsFormworks: 1551.66sqm Rebars: 60,614.08kgsMakati Development Corporation

ZONE 1STARTEND13-Dec-1427-Dec-14Concrete Vol= 306.58cum8th FloorZONE 2ZONE 3STARTEND20-Dec-145-Jan-15Concrete Vol= 359.78cumSTARTEND29-Dec-1414-Jan-15Concrete Vol= 275.46cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1747.22sqm Rebars: 67,288.36kgsFormworks: 1968.79sqm Rebars: 78,242.97kgsFormworks: 1551.66sqm Rebars: 60,614.08kgsMakati Development Corporation

ZONE 1STARTEND28-Dec-1413-Jan-15Concrete Vol= 306.73cum9th FloorZONE 2ZONE 3STARTEND6-Jan-1518-Jan-15Concrete Vol= 359.92cumSTARTEND11-Jan-1523-Jan-15Concrete Vol= 275.46cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1747.64Rebars: 67,320.83kgsFormworks: 1969.22sqm Rebars: 78,275.43kgsFormworks: 1551.66sqm Rebars: 60,614.08kgsMakati Development Corporation

ZONE 1STARTEND16-Jan-1528-Jan-15Concrete Vol= 308.03cum10th FloorZONE 2ZONE 3STARTEND21-Jan-152-Feb-15Concrete Vol= 364.18cumSTARTEND26-Jan-157-Feb-15Concrete Vol= 275.38cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1751.82sqm Rebars: 67618.52kgsFormworks: 1986.24sqm Rebars: 79,246.3kgsFormworks: 1549.53sqm Rebars: 60,595.58kgsMakati Development Corporation

ZONE 1STARTEND31-Jan-1512-Feb-15Concrete Vol= 311.6cumRoof DeckZONE 2ZONE 3STARTEND5-Feb-1517-Feb-15Concrete Vol= 357.21cumSTARTEND10-Feb-1522-Feb-15Concrete Vol= 269.8cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 1839.47sqm Rebars: 70,998.75kgsFormworks: 2036.37sqm Rebars: 81,390.9kgsFormworks: 1569.31sqm Rebars: 61,474.75kgsMakati Development Corporation

ZONE 1STARTEND15-Feb-151-Mar-15Concrete Vol= 146.31cumRoof LevelZONE 2STARTEND22-Feb-158-Mar-15Concrete Vol= 97.98cumPROJECT SCHEDULE (STRUCTURAL)Formworks: 863.26sqm Rebars: 33337.68kgsFormworks: 576.54sqm Rebars: 22,325.26kgsMakati Development Corporation

ZONE 1ZONE 3ZONE 2Project Schedule (Construction Scheme)RDECK10TH9TH FLOOR8TH FLOOR4TH FLOOR3RD FLOOR2ND FLOORUG FLOOR5TH FLOOR6TH FLOOR7TH FLOORTOPPING OFF March 10, 2015Architectural Wet WorksBuilding EnvelopeArchitectural Dry WorksRubconInstln of Arty WallInstln of Steel DoorsWaterproofingConc. Topping/Tiling WorksInstln of Ceiling FrameInitial Paint ApplicationInstln of Perporated ACPInstln of Curtain Wall Drywall/Ceiling WorksMetalsTiling Works/GraniteSpecialty WorksFinal PaintingMakati Development Corporation

ZONE 1ZONE 3ZONE 2Project Schedule (Architectural Wet Works)RDECK Mar. 22 Apr. 21, 201510TH FLOOR Mar. 08 Apr. 07, 20159TH FLOOR Feb. 21 Mar. 23, 20158TH FLOOR Feb. 06 Mar. 08, 20154TH FLOOR Dec. 06 Jan. 13, 20153RD FLOOR Nov. 20 Dec. 30, 20142ND FLOOR Nov. 04 Dec. 26, 2014UG FLOOR Oct. 20 Dec. 01, 2014LG FLOOR Oct. 05 Nov. 14, 20145TH FLOOR Dec. 19, - Jan. 26, 20156TH FLOOR Jan. 03 Feb. 10, 20157TH FLOOR Jan. 28 Feb. 27, 2015Roof Deck Waterproofing (Apr. 21, 2015)Makati Development Corporation

ZONE 1ZONE 3ZONE 2Project Schedule (Building Envelope)RDECK May 04 May 18, 201510TH Apr. 23 May 07, 20159TH FLOOR Apr. 12 Apr. 26, 20158TH FLOOR Apr. 01 Apr. 15, 20154TH FLOOR Feb. 16 Mar. 02, 20153RD FLOOR Feb. 05 Feb. 19, 20152ND FLOOR Jan. 25 Feb. 08, 2015UG FLOOR Jan. 05 Jan. 28, 20155TH FLOOR Feb. 27 Mar. 13, 20156TH FLOOR Mar. 10 Mar. 24, 20157TH FLOOR Mar. 21 Apr. 4, 2015Building Watertightness (May 18, 2014)Makati Development Corporation

ZONE 1ZONE 3ZONE 2Project Schedule (Architectural Dry Works)RDECK Jul. 28 Aug. 21, 201510TH Jul. 14 Aug. 11, 20159TH FLOOR Jun. 30 July 28, 20158TH FLOOR June 16 Jul. 14, 20154TH FLOOR Apr. 21 May 19, 20153RD FLOOR Apr. 07 May 05, 20152ND FLOOR Mar. 24 Apr. 21, 2015UG FLOOR Mar. 10 Apr. 07, 2015LG Jul. 21 Aug. 21, 20155TH FLOOR May 05 June 2, 20156TH FLOOR May 19 Jun. 16, 20157TH FLOOR Jun. 02 Jun. 30, 2015Building Handover (Aug. 21, 2015)Makati Development Corporation