performance year 2 m&v report - esbnyc.com€¦ · empire state building py 2 m&v report ....

102
Empire State Building PY 2 M&V Report Empire State Building Performance Year 2 M&V Report March 1, 2013 Rev.1 (August 15, 2013)

Upload: others

Post on 20-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Empire State Building PY 2 M&V Report

Empire State Building

Performance Year 2 M&V Report

March 1, 2013 Rev.1 (August 15, 2013)

Page 2: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

i

Table of Contents Table of Contents .............................................................................................................i Glossary ........................................................................................................................... v

Executive Summary....................................................................................................... 1

Project Overview ............................................................................................................ 6

EPC Guaranteed Savings (2007) .......................................................................... 9

EPC 2012 Target Savings ...................................................................................... 9

2012 ECM Savings .................................................................................................. 9

Model Build.............................................................................................................. 10

1. ECM 1: Window Retrofit ...................................................................................... 11

1.1 ECM 1: Window Retrofit ................................................................................ 11

1.1.1 ECM Description......................................................................................... 11

1.1.2 Pre-Installation System Conditions ......................................................... 11

1.1.3 Post-Installation System Conditions........................................................ 11

1.1.4 ECM M&V Methodology ............................................................................ 12

1.1.5 PY ECM Performance Savings ................................................................ 13

2. ECM 2: Radiator Insulation and Steam Trap Retrofit .................................. 14

2.1 ECM 2.1: Radiator Insulation ....................................................................... 14

2.1.1 ECM Description......................................................................................... 14

2.1.2 Pre-Installation System Conditions ......................................................... 14

2.1.3 Post-Installation System Conditions........................................................ 14

2.1.4 ECM M&V Methodology ............................................................................ 14

2.2 ECM 2.2: Steam Trap Retrofit ...................................................................... 16

2.2.1 ECM Description......................................................................................... 16

2.2.2 Pre-Installation System Conditions ......................................................... 16

2.2.3 Post-Installation System Conditions........................................................ 16

2.2.4 ECM M&V Methodology ............................................................................ 16

2.2.5 PY ECM Performance Savings ................................................................ 17

3. ECM 3: BAS Retrofit ............................................................................................. 18

3.1 ECM 3.1: BAS Damper Retrofit and Demand Controlled Ventilation 18

3.1.1 ECM Description......................................................................................... 18

Page 3: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ii

3.1.2 Pre-Installation System Conditions ......................................................... 18

3.1.3 Post-Installation System Conditions........................................................ 18

3.1.4 ECM M&V Methodology ............................................................................ 19

3.2 ECM 3.3: Fan Scheduling.............................................................................. 20

3.2.1 ECM Description......................................................................................... 20

3.2.2 Pre-Installation System Conditions ......................................................... 20

3.2.3 Post-Installation System Conditions........................................................ 20

3.2.4 ECM M&V Methodology ............................................................................ 21

3.2.5 PY ECM Performance Savings ................................................................ 21

4. ECM 4: Chiller Plant Retrofit .............................................................................. 22

4.1 ECM 4.1: Chiller Tubes and Chiller VFD Retrofit .................................... 22

4.1.1 ECM Description......................................................................................... 22

4.1.2 Pre-Installation System Conditions ......................................................... 22

4.1.3 Post-Installation System Conditions........................................................ 22

4.1.4 ECM M&V Methodology ............................................................................ 22

4.2 ECM 4.2: CHW Supply Temperature Reset .............................................. 24

4.2.1 ECM Description......................................................................................... 24

4.2.2 Pre-Installation System Conditions ......................................................... 24

4.2.3 Post-Installation System Conditions........................................................ 24

4.2.4 ECM M&V Methodology ............................................................................ 24

4.3 ECM 4.3: CHW Loop Delta-T Enhancement ............................................. 26

4.3.1 ECM Description......................................................................................... 26

4.3.2 Pre-Installation System Conditions ......................................................... 26

4.3.3 Post-Installation System Conditions........................................................ 26

4.3.4 ECM M&V Methodology ............................................................................ 27

4.4 ECM 4.4: CHW Pump VFD Automation ..................................................... 27

4.4.1 ECM Description......................................................................................... 27

4.4.2 Pre-Installation System Conditions ......................................................... 28

4.4.3 Post-Installation System Conditions........................................................ 28

4.4.4 ECM M&V Methodology ............................................................................ 29

4.5 ECM 4.5: CW Supply Temperature Reset ................................................. 29

4.5.1 ECM Description......................................................................................... 29

4.5.2 Pre-Installation System Conditions ......................................................... 30

Page 4: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

iii

4.5.3 Post-Installation System Conditions........................................................ 30

4.5.4 ECM M&V Methodology ............................................................................ 30

4.6 ECM 4.6: Cooling Tower Fan VFD Automation ....................................... 30

4.6.1 ECM Description......................................................................................... 30

4.6.2 Pre-Installation System Conditions ......................................................... 31

4.6.3 Post-Installation System Conditions........................................................ 31

4.6.4 ECM M&V Methodology ............................................................................ 32

4.7 ECM 4.7: CW Pump VFD Automation ........................................................ 32

4.7.1 ECM Description......................................................................................... 32

4.7.2 Pre-Installation System Conditions ......................................................... 33

4.7.3 Post-Installation System Conditions........................................................ 33

4.7.4 ECM M&V Methodology ............................................................................ 33

4.7.5 PY ECM Performance Savings ................................................................ 34

5. ECM 5: TEM Portal ................................................................................................ 35

5.1 ECM 5: TEM Portal .......................................................................................... 35

5.1.1 ECM Description......................................................................................... 35

5.1.2 Pre-Installation System Conditions ......................................................... 35

5.1.3 Post-Installation System Conditions........................................................ 35

5.1.4 ECM M&V Methodology ............................................................................ 36

5.1.5 PY ECM Performance Savings ................................................................ 37

Appendix List ................................................................................................................ 38

Appendix 1: BAS Retrofit Data Analysis .......................................................... 39

Data Analysis ............................................................................................................ 39

Damper Retrofit and DCV ..................................................................................... 39

Fan Scheduling ....................................................................................................... 42

Appendix 2: Chiller Retrofit Data Analysis ...................................................... 46

Appendix 3: Chiller Plant Retrofit Data Analysis ........................................... 52

3.1 CHWST Reset.................................................................................................. 52

3.2 CHW Loop Delta-T Enhancement ................................................................ 56

3.3 CHW Pump VFD Automation ........................................................................ 63

3.4 CW Supply Temperature Reset .................................................................... 64

3.5 Cooling Tower Fan VFD Automation............................................................ 66

3.6 CW Pump VFD Automation ........................................................................... 67

Page 5: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

iv

Appendix 4: Steam Chiller Usage Data Analysis ........................................... 71

Appendix 5: Occupancy Modeling Methodology ........................................... 74

Appendix 6: ESB eQUEST Model Inputs and Outputs ................................... 77

Appendix 7: Utility Analysis ................................................................................. 88

Appendix 8: FPI ........................................................................................................ 93

Page 6: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

v

Glossary

Definition ADX Application and Data Server

AHU Air-Handling Unit

ARI Air-Conditioning and Refrigeration Institute

ASHRAE American Society of Heating, Refrigerating, and Air-Conditioning Engineers

ASTM American Society for Testing and Materials

ATI Architectural Testing, Inc.

BAS Building Automation System

CDD Cooling Degree Day

CHW Chilled Water

CTWLT Cooling Tower Water Leaving Temperature

CTWST Cooling Tower Water Supply Temperature

CW Condenser Water

DCV Demand Control Ventilation

DDC Direct Digital Control

DOE Department of Energy

ECM Energy Conservation Measures

EPA Environmental Protection Agency

EPC Energy Performance Contract

ESB Empire State Building

FPI Facil ity Performance Indexing

HDD Heating Degree Day

HZ High Zone

IG Insulated Glass

IPMVP International Performance Measurement and Verification Protocol

LZ Low Zone

Mlbs 1000 lbs. of Steam

MZ Mid Zone

NFRC National Fenestration Rating Council

OA Outside Air

PY Performance Year

SF Square Feet

SHGC Solar Heat Gain Coefficient

TEM Tenant Energy Management

VFD Variable Frequency Drive

VSD Variable Speed Drive

Page 7: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Executive Summary 1

Executive Summary Empire State Building (ESB) has committed to a major sustainability retrofit to become a leading example of economic and environmental revitalization. A Johnson Controls Energy Performance Contract (EPC) was developed to install five ECMs of the Sustainability Program at ESB. The project installation phase was completed in December 2010. The Performance Period started in January 2011. This report documents the project savings for Performance Year 2, ending December 2012.

Annual savings are calculated based on International Performance Measurement and Verification Protocol (IPMVP) Option D, which utilizes building performance simulation software (eQUEST®). Table 1.1 shows the contract guaranteed savings, the Performance Year (PY) target guaranteed savings and the ECM performance savings.

No. Energy Conservation Measure [A]

Contract Guaranteed Savings

(Unadjusted, from

2007 Contract) [B]

PY Target Guaranteed Savings

(After 2012 Baseline

Adjustment) [C]

PY ECM Performance Savings

(Using 2012

Measurements) [D]

1 Windows Retrofit $338,508 $361,629 $391,648

2 Radiator Insulation and Steam Traps $491,191 $496,887 $558,255

3 BAS Retrofit $774,388 $771,345 $929,871

4 Chil ler Plant Retrofit $611,641 $527,851 $446,904

5 Tenant Energy Management $25,000 $25,755 $0

TOTAL $2,240,728 $2,183,466 $2,326,678

Table 1.1: 2012 Project Savings For each PY, the target guaranteed savings is established using baseline adjustments including weather and occupancy factors. Performance of each ECM is then measured against the target guaranteed savings. For the 2012 performance year (January 1 to December 31), Johnson Controls ECM performance savings exceeds 2012 target guaranteed savings.

ECM Performance Accounts for the following:

1. The window testing is conducted every two years. The window testing showed that the Windows Retrofit ECM performed better than the contract for the performance period 2012.

2. The radiator insulation test uses the R values measured during the installation period (2010). The testing showed that the Radiator Insulation ECM performed better than the contract for all performance periods.

3. Steam trap savings are contracted to be non-measured savings. Steam trap surveying is used to support the annual maintenance program to identify and service leaking or failed traps.

Page 8: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Executive Summary 2

4. Trending analysis for 2012 indicates that the BAS Retrofit ECM savings exceeds contract savings for Year 2. The increase in savings is due to improve fan scheduling in 2012 when compared with the contract Post-Installation scheduling assumption.

5. Johnson Controls did not claim savings for CHW Reset Controls. Trending analysis showed that CHW Reset Controls were not fully utilized during the actual operation. Since the rest of the chiller ECMs were properly installed, Johnson Controls claimed savings for full ECM performance.

Figure 1.1: Reduction in ESB’s 2007 Baseline Electric Utility Consumption

during Performance Period Figure 1.1 illustrates that ESB’s Post-Installation electric utility consumption was reduced by 29% during base load conditions and was reduced by 34% during the hottest month.

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

0 50 100 150 200 250 300 350 400 450 500

Elec

tric

Con

sum

ptio

n(k

Wh)

CDD

Annual Electric Consumption Vs CDD

2007 Electric

2011 Electric

2012 Electric

Page 9: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Executive Summary 3

Figure 1.2: Reduction in ESB’s 2007 Baseline Steam Utility Consumption

during Performance Period Figure 1.2 illustrates that ESB’s Post-Installation winter steam consumption was reduced by 7% during the coldest month.

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

0 200 400 600 800 1000 1200

Stea

m C

onsu

mpt

ion

(mlb

s)

HDD

Winter Steam Consumption Vs HDD

2007 Winter Steam Usage

2011 Winter Steam Usage

2012 Winter Steam Usage

Page 10: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Executive Summary 4

Figure 1.3: Reduction in ESB’s 2007 Baseline Electric Utility Costs during Performance Period (Unadjusted)

Figure 1.3 illustrates that ESB’s unadjusted Year-Over-Year electric utility costs have decreased significantly. 2011 electric costs reduced by 35% when compared with the 2007 Baseline and the consumption reduced by 29% during the same period. These numbers represent actual realized savings and not modeled savings.

$14,694,108

$12,853,869

$11,697,544

$11,710,160

$9,609,506 $9,874,215

0

10

20

30

40

50

60

70

80

90

$-

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

$16,000,000

2007 2008 2009 2010 2011 2012

Elec

tric

Cos

t ($)

Year

Year Over Year Electric Utility Costs

Electric energy cost

Occupancy Rate

Occ

upan

cyRa

te (%

)

Page 11: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Executive Summary 5

Figure 1.4: Reduction in ESB’s 2007 Baseline Steam Utility Costs during Performance Period (Unadjusted)

Figure 1.4 illustrates that ESB’s unadjusted Year-Over-Year annual steam utility costs. 2012 steam costs reduced by 35% when compared with the 2007 Baseline and the consumption reduced by 33% during the same period. These numbers represent actual realized savings and not modeled savings.

$2,783,031 $2,661,334

$2,523,295 $2,640,800

$2,268,641

$1,811,393

0

10

20

30

40

50

60

70

80

90

$-

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

2007 2008 2009 2010 2011 2012

Stea

m C

ost (

$)

Year

Year Over Year Steam Utility Cost Steam cost

Occupancy Rate

Occ

upan

cyRa

te (%

)

Page 12: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Project Overview 6

Project Overview

EMPIRE STATE BUILDING SUSTAINABILITY PROGRAM OVERVIEW The Empire State Building (ESB) has committed to a major sustainability retrofit program as an example for leading economic and environmental revitalization. ESB, in partnership with Clinton Climate Initiative, Johnson Controls Inc., Jones Lang LaSalle, NYSERDA, and Rocky Mountain Institute, project that the building can save 38% of its energy use and $4.4 million in annual utility costs.

A total of eight Energy Conservation Measures (ECMs) were selected for implementation as part of the ESB Sustainability Program. Each ECM, the responsible organization and associated contribution to savings is detailed below.

ENERGY PERFORMANCE CONTRACT OVERVIEW Johnson Controls developed an Energy Performance Contract (EPC) to install six ECMs of the Sustainability Program at ESB. The EPC consolidated the balance of Direct Digital Control (DDC) and Demand Control Ventilation (DCV) measures into one Building Automation System (BAS) Retrofit ECM. Therefore, five measures are documented in the EPC. The contract guaranteed savings for each ECM is listed below.

$491,191 - 11%

$338,508 - 8%

$858,305 - 20%

$675,714 - 15% $386,709 - 9%

$940,862 - 21%

$702,507 - 16%

Sustainability Program ECM Savings Total Savings $4,393,796

1 Radiator Insulation & Steam Trap Savings (JCI)

2 Windows Retrofit (JCI)

3+4 Direct Digital Controls and DCV (JCI)

5 Chiller Plant Retrofit (JCI)

6 Tenant Energy Mgmt (JCI)

7 Tenant Daylighting, Lighting, and Plugs (ESB)

8 VAV Air Handling Units (ESB)

Page 13: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Project Overview 7

To develop the energy savings guarantee, the EPC utilizes EPC Year 2007 baseline conditions. The EPC guarantees 90% of the projected energy savings, resulting in $2,240,728 in guaranteed energy savings (Table 2.1). The EPC includes a 15 year performance term.

No. Energy Conservation Measure [A]

Electric kWh Savings (2007

Contract) [B]

Electric kW Savings (2007

Contract) [C]

Steam Mlbs Savings

((2007 Contract)

[D]

Guaranteed Savings (2007 Contract)

[E]

1 Windows Retrofit 1,329,797 116 5,115 $338,508

2 Radiator Insulation and Steam Traps

14,870 $491,191

3 BAS Retrofit 1,621,091 138 16,744 $774,388

4 Chil ler Plant Retrofit 2,963,656 1,095 824 $611,641

5 Tenant Energy Management 160,256

$25,000

TOTAL 6,074,800 1,349 37,553 $2,240,728

Table 2.1: Shows the contract savings in kWh, kW, Mlbs and total guaranteed savings for each ECM.

$338,508 - 15%

$491,191 - 22%

$774,388 - 35%

$611,641 - 27%

$25,000 - 1%

1 Windows Retrofit2 Radiator Insulation & Steam Trap Savings3 BAS Retrofit4 Chiller Plant Retrofit5 Tenant Energy Mgmt

Page 14: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Project Overview 8

PROJECT GUARANTEED SAVINGS (UNADJUSTED) Table 2.2 below shows the unadjusted project guaranteed savings for the 15 year guarantee period.

Year Total Guaranteed Savings Windows Radiator

Insulation/Traps Chiller Plant BAS TEM

1 $2,240,728 $338,508 $491,191 $611,641 $774,388 $25,000

2 $2,310,490 $348,731 $506,025 $630,113 $799,866 $25,755

3 $2,382,427 $359,263 $521,307 $649,142 $826,183 $26,533

4 $2,456,608 $370,112 $537,050 $668,746 $853,365 $27,334

5 $2,533,102 $381,290 $553,269 $688,942 $881,441 $28,160

6 $2,611,983 $392,805 $569,978 $709,748 $910,442 $29,010

7 $2,693,324 $404,667 $587,191 $731,183 $940,396 $29,886

8 $2,777,202 $416,888 $604,925 $753,264 $971,336 $30,789

9 $2,863,697 $429,478 $623,193 $776,013 $1,003,294 $31,718

10 $2,952,891 $442,449 $642,014 $799,449 $1,036,303 $32,676

11 $3,044,867 $455,811 $661,403 $823,592 $1,070,399 $33,663

12 $3,139,713 $469,576 $681,377 $848,464 $1,105,616 $34,680

13 $3,237,519 $483,757 $701,954 $874,088 $1,141,992 $35,727

14 $3,338,376 $498,367 $723,154 $900,485 $1,179,564 $36,806

15 $3,442,381 $513,417 $744,993 $927,680 $1,218,373 $37,918

Totals $42,025,306 $6,305,119 $9,149,024 $11,392,550 $14,712,958 $465,655

Table 2.2: Unadjusted Project Guaranteed Savings.

2012 PERFORMANCE OVERVIEW Annual savings are calculated based on IPMVP Option D, utilizing building performance simulation software (eQUEST®). Table 2.3 shows the contract guaranteed savings, the PY target guaranteed savings and the PY ECM performance savings.

Page 15: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Project Overview 9

No.

Energy Conservation Measure [A]

Contract Guaranteed Savings

(Unadjusted, from

2007 Contract) [B]

PY Target Guaranteed Savings

(After 2012 Baseline

Adjustment) [C]

PY ECM Performance Savings

(Using 2012

Measurements) [D]

1 Windows Retrofit $338,508 $361,629 $391,648

2 Radiator Insulation and Steam Traps $491,191 $496,887 $558,255

3 BAS Retrofit $774,388 $771,345 $929,871

4 Chil ler Plant Retrofit $611,641 $527,851 $446,904

5 Tenant Energy Management $25,000 $25,755 $0

TOTAL $2,240,728 $2,183,466 $2,326,678

Table 2.3: 2012 Project Savings Note: (a) PY Target Guaranteed Savings and PY ECM performance savings were calculated using 2007 contract rates,

escalated by 3.02%. (b) PY target guarantee is shown after including the contract 8.07% average savings risk discount. (c) Johnson Controls confidence in the current eQUEST cooling tower fan VFD savings calculation is low due to

model l imitations. For all practical purposes, this does not affect the overall project savings level greatly, because the magnitude of this ECM savings is low (in the order of $25,000).

EPC Guaranteed Savings (2007) Using contract assumption for ECM performance, 2007 weather data, 2007 utility rates and 2007 vacancy data, the project guaranteed energy savings is $2,240,728.

EPC 2012 Target Savings Using measured ECM performance, actual 2012 weather data, contract utility rates and actual 2012 vacancy data, projected energy savings would be $2,183,466.

2012 ECM Savings Based on actual measured ECM performance, 2012 weather data, contract utility rates and 2012 vacancy data, the PY ECM performance savings is $2,326,678.

Page 16: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Project Overview 10

EQUEST MODEL SETUP OVERVIEW Modeling Software

eQUEST v3.64, build 7130

Model Author

Quest Energy Group, LLC

1620 W Fountainhead Pkwy #303 Tempe, AZ 85282 +1 480 467 2480

Model Build • A detailed architectural model of the building was

created based on archive drawings, photos taken at the site, and site inspections. Site inspections included verifying wall and roof constructions, external shading, and glass types.

• Schedules based on building operation were used in the model.

• Lighting demand and energy (schedules) were put into the model based on the lighting information provided by JLL.

• Representative internal equipment loads by space type (office, corridor, etc.) were incorporated into the model.

• Heating, Ventilating, and Air-Conditioning (HVAC) equipment and efficiencies were added and each zone was assigned to the appropriate HVAC system. Zoning was determined by the base building core areas including elevator shafts, restrooms, corridors, etc. and the tenant occupy-able areas, which were zoned using perimeter/core areas by orientation. HVAC equipment efficiencies were based on field measurements, nameplate data, or mechanical plans as available (this would tie in to your report's description of field measured data, etc.).

• Vacancy rates for the building were included in the model.

Page 17: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 1 11

1. ECM 1: WINDOW RETROFIT

1.1 ECM 1: WINDOW RETROFIT

1.1.1 ECM Description This ECM upgraded the existing Insulated Glass (IG) for 6,514 double-hung windows to Suspended Coated Film AlpenGlass. This “re-manufacturing” of the (2 x 6,514 =) 13,028 IG units was done on-site at ESB. IG units were removed, delivered to a production area located on the 5th Floor and picked up for reinstallation by ESB’s window contractor. Alpenglass TC88 or SC75 was used as the suspended film based on window orientation. A mix of krypton/argon gas was used between the glass and suspended film. This ECM improved the thermal resistance of the glass from R-2 to R-6 and cut the heat gain by more than half. As an additional contribution to sustainability, all existing glass removed from the windows was recycled.

1.1.2 Pre-Installation System Conditions Pre-Installation double pane windows were estimated (not measured at that time) to have 0.48 U-Value and 0.645 Solar Heat GainCoefficient (SHGC). After testing, it was found that Pre-Installation window performance was 0.58 in U-Value and there would be more savings than previously estimated.

1.1.3 Post-Installation System Conditions North windows were targeted to attain 0.365 U-Value and 0.448 SHGC through Krypton/Argon gas fill and TC88 suspended film. S-E-W windows were targeted to attain 0.384 U-Value and 0.325 SHGC through Krypton gas fill and SC75 suspended film.

In 2010, the post-Installation North windows were tested to attain 0.344 U-Value and 0.448 SHGC. Post-Installation S-E-W windows were tested to attain 0.397 U-Value and 0.325 SHGC. All Post-Installation windows in the exterior envelope of the building were assumed to reduce heat loss and solar heat gain.

Page 18: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 1 12

1.1.4 ECM M&V Methodology

Figure 1.1.4.1: ESB Windows when tested at ATI (left);

Schematic of ATI’s window testing chamber (right) IG units were sent to an independent testing agency (Architectural Testing, Inc. [ATI]) for evaluation of several window performance indices including the ones used as eQUEST inputs (Whole window U-Value and SHGC).

ATI, located in York, PA, is a premier window testing company that possesses extensive experience and testing in the field of window testing. ATI is accredited with several agencies including the National Fenestration Rating Council (NFRC), American National Standards Institute, Insulating Glass Certification Council, American Architectural Manufacturers Association, Window and the Door Manufacturers Association. Extensive information about ATI, ATI’s work, testing facility and certificate of accreditations is given in the attached test report.

A total of four old windows and six new windows were tested for performance.

IG unit performance was tested in accordance with NFRC 102-2010 in a thermal test chamber. The two sides of the chamber were simulated for standard exterior (-0.4˚F at 15mph wind speed) and interior (70˚F) environment. Interior conditions were maintained using an electric heater whose output can be measured. IG unit U-factor was calculated using measured heat loss and delta-T.

Whole window (IG unit and frame) performance was evaluated using a combination of gas fill test and industry standard computer simulation. Gas fill tests were performed using a standard gas chromatograph device.

SHGC tests were performed using a window energy profiler device (WP4500) that measures ultraviolet, visible light, infrared transmission values and SHGC.

Results from the testing were used to generate the following eQUEST Model inputs that determine the ECM savings.

Page 19: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 1 13

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Storefront (U-value/SHGC) 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82

102nd Floor 1.03 / 0.82 1.01 / 0.48 1.01 / 0.48 1.01 / 0.48 1.01 / 0.48

86th Floor 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82

North (U-value/SHGC) 0.48 / 0.645 0.365 / 0.448 0.58 / 0.645 0.365 / 0.448 0.344 / 0.448

East (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325

South (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325

West (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325

Window Infiltration Multiplier 4 2 4 2 2

Table 1.1.4.1: Windows ECM Model Inputs

1.1.5 PY ECM Performance Savings ECM target performance (per contract) and the PY Baseline adjustments set the 2012 ECM target savings at $361,629.

Using ECM performance (per M&V) and the PY Baseline adjustments, Johnson Controls calculated the PY ECM performance savings to be $391,648.

Page 20: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 2 14

2. ECM 2: RADIATOR INSULATION AND STEAM TRAP RETROFIT

2.1 ECM 2.1: RADIATOR INSULATION

2.1.1 ECM Description This ECM involved the installation of 6,514 insulated reflective barriers behind radiator units located on the perimeter of the building. In addition, the radiator was cleaned and the thermostat was repositioned to the front side of the radiator. This ECM will reduce the thermal heat loss through the exterior building wall.

2.1.2 Pre-Installation System Conditions Pre-Installation “wall+no-insulation” U-Value was estimated to be 0.209. Post-Installation "wall+insulation" U-Value was estimated to be 0.122. All radiator insulation in the exterior envelope of the building reduces heat loss.

2.1.3 Post-Installation System Conditions Radiator insulation in the exterior envelope was installed. Johnson Controls was unable to install the barriers in broadcasting spaces because those spaces were overheating and the radiator assemblies were removed. There will be additional savings than the tests demonstrated because of the reflective layer on the insulation.

2.1.4 ECM M&V Methodology Radiator Insulation boards were sent to an independent testing agency (ATI) for evaluation of thermal performance.

ATI, located in York, PA, is a fenestration testing company that possesses extensive experience in the field of fenestration testing. ATI is accredited by several agencies including National Fenestration Rating Council, American National Standards Institute, Insulating Glass Certification Council, American Architectural Manufacturers Association and the Window and Door Manufacturers Association. Extensive information about ATI, ATI’s work, testing facility and certificate of accreditations is given in the attached test report.

A total of ten radiator insulation locations were tested for performance.

Page 21: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 2 15

Figure 2.1.4.1: Insulation Testing Equipment at ATI

Radiator Insulation was tested using American Society for Testing and Materials (ASTM) C 518, Standard Test Method for Steady State Heat Flux Measurements and Thermal Transmission Properties by Means of Heat Flow Meter Apparatus. The test method covers the measurement of steady state thermal transmission through flat specimens using heat flow meter apparatus. This is a comparative method of measurement and was be calibrated to a specimen traceable to National Institute of Materials supplied material.

The cold plate was maintained at a nominal 50˚F and the hot plate was maintained at a nominal 100˚F. Heat flux transducer was introduced on the warm side. Insulation U-factor was calculated using measured heat loss and delta-T.

Results from the testing were used to generate the following eQUEST® Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Radiative Wall U Value 0.209 0.122 0.209 0.122 0.102

Table 2.1.4.1: Radiator Insulation ECM Model Inputs

Page 22: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 2 16

2.2 ECM 2.2: STEAM TRAP RETROFIT

2.2.1 ECM Description The purpose of a steam trap is to prevent steam from passing its point of use and to allow condensate to be expelled as soon as it forms. They behave like automatic valves. Steam traps open, close or modulate automatically. Over time, internal parts of steam traps wear out and result in failure to open and close properly. While an open trap would result in loss of live steam, a closed trap could result in loss of heat transfer to the area and water hammering. Water hammering can eventually damage the valves and other components in steam systems, which could result in steam leaks.

All the steam radiators at ESB are fitted with thermostatic steam traps. Thermostatic traps use a diaphragm or bellows, within which is a volatile liquid, sealed under vacuum. The trap opens and closes in a modulating manner dependent upon the temperature affecting it. The trap’s normal state is wide open to expel air and condensate. When surrounded by steam at saturated temperature, the volatile fill flashes, creating an internal pressure equal to the surrounding pressure. This equalization of pressures allows the bellows to expand to its natural length or “closed” position, preventing steam from passing. The presence of condensate sufficiently cools the bellows to condense the vapor within. Once again the external pressure is greater and the bellows reverts back to its contracted, or “open” position, allowing the condensate to drain from the trap, permitting more steam to enter the radiator and thus, modulating action of the trap.

There were several Pre-Installation traps that failed at ESB. The failure resulted in steam loss and equipment operational issues. Retrofitting all the steam traps helped reduce steam wastage.

2.2.2 Pre-Installation System Conditions All of the steam radiators at ESB are fitted with thermostatic steam traps. There were several Pre-Installation traps that failed at ESB.

2.2.3 Post-Installation System Conditions As part of the performance contract, all radiator steam traps were retrofitted.

2.2.4 ECM M&V Methodology The savings for this ECM is stipulated upon installation of the steam traps. A summary of steam trap savings from Johnson Controls’ change order with ESB is shown below:

Steam Trap Calculated Savings $520,180

Steam Trap Guaranteed Savings $320,000

Steam Trap Guaranteed Steam Savings 10,059,100 Mlbs

Table 2.2.4.1: Steam Trap Stipulated Savings

Page 23: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 2 17

The change order energy savings calculation showed an annual steam savings of 16,351,695 Mlbs due to the steam trap retrofit. Johnson Controls was conservative in discounting the projected savings by 38.5%.

During PY2, stipulated savings equivalent to 10,059,100 Mlbs is claimed by Johnson Controls. The energy savings (in $) is calculated using the stipulated Mlbs savings and 2012 Summer Steam Rate.

2.2.5 PY ECM Performance Savings ECM target performance (per contract) and the PY Baseline adjustments set the 2012 ECM target savings at $496,887.

Using ECM performance (per M&V) and the PY Baseline adjustments, Johnson Controls calculated the PY ECM performance savings to be $558,255.

Page 24: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 3 18

3. ECM 3: BAS RETROFIT

3.1 ECM 3.1: BAS DAMPER RETROFIT AND DEMAND CONTROLLED VENTILATION

3.1.1 ECM Description Prior to retrofit, sample spaces were tested and it was found that the building’s overall outside air intake was 0.25 cfm/sf. The goal of the ECM was to reduce the building’s overall outside air intake by retrofitting the non-Alerton Air-Handling Unit (AHU) with DCV and modulating dampers. Johnson Controls used American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE) calculations to estimate that the minimum outside air ventilation requirement is 0.12 cfm/SF for an office building with 7 persons per 1,000SF. Minimum outside air ventilation is possible when CO2 based DCV is combined with the ability to open dampers just enough to satisfy the ventilation demand. This cannot be achieved with the old two position dampers, but can be achieved with CO2 based DCV controls and modulating dampers.

Demand controlled ventilation is used to modulate outside air ventilation based on real time occupancy. DCV reduces unnecessary over-ventilation that may result when existing AHUs are set to provide ventilation for a maximum assumed occupancy. DCV saves energy while ensuring that ASHRAE Standard 62 ventilation rates are maintained at all times. Johnson Controls retrofitted non-Alerton AHUs with CO2 sensors on the return air duct. DCV was programmed for outside air activation at 800 ppm ‘return air CO2’ threshold.

Johnson Controls retrofitted non-Alerton AHU units by replacing their two-position pneumatic damper system with new dampers (if broken), new actuators and DDC controls. The new damper system has the capability to modulate between 0% to 100% open/close position.

Reducing outside air intake reduces the load on the building’s HVAC system and generates energy savings.

3.1.2 Pre-Installation System Conditions Prior to the retrofit, non-Alerton AHUs in the building were equipped with pneumatic dampers and actuators. Also, there was no DCV on the non-Alerton AHUs. Sample spaces were tested and it was found that the building’s average outside air intake was 0.25 cfm/SF.

3.1.3 Post-Installation System Conditions Johnson Controls retrofitted non-Alerton AHUs with CO2 sensors on the return air duct. DCV was programmed for outside air activation at 800 ppm ‘return air CO2’ threshold. Johnson Controls also installed the new DDC damper system that is maintained at 10% minimum open position when the outside air temperature is higher than 68°F. During other times the damper modulates in accordance with the supply valve position. Controls were programmed so that the DCV takes precedence to temperature based damper control when return air CO2 reaches threshold.

Page 25: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 3 19

3.1.4 ECM M&V Methodology The performance contract required that Johnson Controls retrofit the two-position pneumatic damper system in non-Alerton AHU units with new dampers (if broken), new actuators, DCV and DDC controls (ECM Target).

The new dampers, new actuators, DCV and DDC controls were verified to be operational (ECM Performance).

The new dampers, new actuators, DCV and DDC controls were operated in the field as designed (Actual Performance).

The analyzed plots are presented in Appendix 1. The data for the analysis was retrieved from the Metasys® trend repository and from Facility Performance Indexing‘s (FPI) trend archive. Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Outside Air (cfm/sf) 0.25 0.12 0.25 0.12 0.12

Table 3.1.4.1: BAS Retrofit ECM Model Inputs

Page 26: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 3 20

3.2 ECM 3.3: FAN SCHEDULING

3.2.1 ECM Description The building has fans to provide AHU supply air, exhaust toilet space air and to exhaust building space air. Prior to the performance contract, the fans were manually turned On/Off and did not have DDC controls to automatically schedule On/Off. Johnson Controls installed DDC controls on the AHU fans to automatically schedule On/Off. The reduced fan run time resulted in:

• Reduced fan motor electric power consumption

• Reduced outside air intake, thereby reducing the need to condition it

As part of the BAS retrofit, all non-Alerton AHUs were connected to the newly installed Johnson Controls field controllers. These field controllers communicate with Network Automation Engines (NAEs) that tie into ESB’s central Application and Data Server (ADX). ESB’s Metasys operator workstation allows building operations’ personnel to program, monitor and change HVAC schedules.

3.2.2 Pre-Installation System Conditions Prior to the performance contract, the fans did not have DDC controls to automatically schedule On/Off. The fans were manually turned On/Off. The following table shows the manually operated Pre-Installation schedule.

Fan Type Manually Operated Pre-Installation ON Time

AHU Supply Fan (MZ and HZ) 18hrs/7d (ON-Time)

General Exhaust & Toilet Exhaust Fans 24hrs/7d (ON-Time)

Table 3.2.3.1: Pre-Installation Schedule

3.2.3 Post-Installation System Conditions As part of the BAS retrofit, all non-Alerton AHU supply fans were connected to BAS and the scheduling feature was enabled. The following table shows the Post-Installation conditions.

Fan Type Automatically Scheduled Post-Installation ON Time

(Target)

Automatically Scheduled Post-Installation ON Time (ECM

Performance)

AHU Supply Fan (MZ and HZ) 15hrs/7d (ON-Time) 14hrs/7d (ON-Time)

General Exhaust & Toilet Exhaust Fans 24hrs/7d (ON-Time) 24hrs/7d (ON-Time)

Table 3.2.2.2: Post-Installation Target and ECM Performance Schedule

Page 27: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 3 21

3.2.4 ECM M&V Methodology The data for the analysis was retrieved from Metasys scheduling BAS page, Metasys® trend repository and from FPI’s trend archive. The analyzed information is presented in this Report’s Appendix. Results from the BAS analysis were used to generate the following eQUEST® Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

High/Mid Fans 18hrs/7d (ON-Time)

15hrs/7d (ON-Time)

18hrs/7d (ON-Time)

15hrs/7d (ON-Time)

14hrs/7d (ON-Time)

General Exhaust and Toilet Exhaust Fans

24hrs/7d (ON-Time)

24hrs/7d (ON-Time)

24hrs/7d (ON-Time)

24hrs/7d (ON-Time)

24hrs/7d (ON-Time)

Table 3.2.4.1: Fan Scheduling ECM Model Inputs

3.2.5 PY ECM Performance Savings ECM target performance (per contract) and the PY Baseline adjustments set the 2012 ECM target savings at $771,345.

Using ECM performance (per M&V) and the PY Baseline adjustments, Johnson Controls calculated the PY ECM performance savings to be $929,871.

Page 28: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 22

4. ECM 4: CHILLER PLANT RETROFIT

4.1 ECM 4.1: CHILLER TUBES AND CHILLER VFD RETROFIT

4.1.1 ECM Description There were four constant speed electric chillers at ESB. This ECM provided for a retrofit of these chiller compressors with Variable Speed Drives (VSDs) and replaced chiller tubes.

Chiller VSD Retrofit

A constant-speed chiller reacts to lower load or lower entering-condenser-water temperature by closing its pre-rotation vanes, which throttle the refrigerant flow through the compressor in an effort to economize the energy consumption. As the vanes continue to close, they create frictional losses that affect the chiller’s efficiency and limit the energy-saving potential of this approach.

Use of a VSD will allow the compressor speed to modulate, in response to load, evaporator pressure, and condenser pressure. Despite the small power penalty attributed to the Variable Frequency Drive (VFD), this control measure for the chiller yields outstanding overall efficiency improvement. Most chillers operate at part-load nearly 99% of the time which enhances the overall value of this retrofit. Additionally, the soft start feature, provided by the VFD, provides additional maintenance related value from less stress on compressor motor, gears and electrical components than a traditional motor starter.

With its patented Adaptive Capacity Control, the VSD drive learns and remembers optimum speeds for various load and operational conditions. Unlike constant-speed chillers, a variable-speed chiller also maintains a stable power factor.

Chiller Tubes Retrofit

Pre-Installation chillers at ESB were about 18 years old. The evaporator and condenser tubes were significantly degraded over time, thereby increasing the fouling factor of the tubes. Fouling impedes heat transfer, which in turn impacts chiller capacity and efficiency. Johnson Controls replaced the evaporator and condenser tubes with new tubes, thereby increasing chiller capacity, chiller efficiency and chiller life.

4.1.2 Pre-Installation System Conditions There were four constant speed electric chillers in the building. The evaporator and condenser tubes were 18 years old and were significantly fouled over time.

4.1.3 Post-Installation System Conditions The four constant speed electric chillers in the building were retrofitted with VSDs. Johnson Controls replaced the fouled evaporator and condenser tubes with new tubes.

4.1.4 ECM M&V Methodology Department of Energy (DOE) electric chiller curves available in eQUEST were used to simulate target performance. The curves were customized for ESB by adjusting them for York prescribed full-load performance at Air-Conditioning and Refrigeration Institute (ARI) conditions 100% load at 44°F Chilled Water (CHW) temperatures and 85°F Condenser Water (CW) temperatures (ECM Target).

Page 29: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 23

Post-Installation chiller efficiency (kw/ton) was measured at the following conditions (ECM Performance):

• Load conditions: 100%, 75%, 50% and 25%

• CHW temperatures: 42°F , 44°F and 46°F

• CW temperatures: 65°F, 75°F and 85°F

In the case of the chiller retrofit ECM, the ECM Performance and Actual Performance is one and the same. The data analysis is presented in Appendix 2. The data for the analysis was retrieved from the Metasys® trend repository and from FPI’s trend archive.

The following eQUEST® Model inputs were used to determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Chiller #1 (Elec) Capacity 750 Ton (Constant Speed)

750 Ton (VFD)

750 Ton (Constant Speed)

750 Ton (VFD)

750 Ton (VFD)

Chil ler #1

Performance *See Baseline Chil ler Curves

*See Target Chil ler Curves

*See Baseline Chil ler Curves

*See Actual Data

*See Actual Data

Chil ler #4 (Elec) Capacity 1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (VFD)

Chil ler #4 Performance

*See Baseline Chil ler Curves

*See Target Chil ler Curves

*See Baseline Chil ler Curves

*See Actual Data

*See Actual Data

Chil ler #5 (Elec) Capacity 1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (VFD)

Chil ler #5 Performance

*See Baseline Chil ler Curves

*See Target Chil ler Curves

*See Baseline Chil ler Curves

*See Actual Data

*See Actual Data

Chil ler #6 (Elec) Capacity 1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (Constant Speed)

1000 Ton (VFD)

1000 Ton (VFD)

Chil ler #6 Performance

*See Baseline Chil ler Curves

*See Target Chil ler Curves

*See Baseline Chil ler Curves

*See Actual Data

*See Actual Data

Table 4.1.4.1: Chiller Retrofit ECM Model Inputs

Page 30: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 24

4.2 ECM 4.2: CHW SUPPLY TEMPERATURE RESET

4.2.1 ECM Description Chiller performance improves when higher temperature CHW is produced. For example, a typical centrifugal chiller's efficiency can be 15 to 25% better when producing CHW at 55°F versus 42°F. In addition, using medium temperature CHW is a common method of preventing uncontrolled dehumidification while conditioning the sensible loads. It significantly improves the savings available from free cooling waterside economization.

Low CHW temperatures are required to meet the building load during hot summer days. Chiller performance improvisation, without compromising capacity requirements, can be improved by incorporating CHW supply temperature reset controls. The BAS will automatically reset CHW supply temperature setpoint in response to outside air temperature conditions. Internal operation of the chiller remains within the factory supplied Chiller Plant Controls.

However, an increase in CHW supply temperature results in increased variable CHW pumping system energy consumption. This penalty can be minimized by tuning the system to maintain minimum design flow through the AHU coils.

4.2.2 Pre-Installation System Conditions The CHW supply temperature setpoint was manually maintained at a constant 44°F temperature during most of the operating times.

4.2.3 Post-Installation System Conditions The performance contract requires Johnson Controls to install a functional CHW supply temperature reset control system that is capable of achieving 42°F to 50 °F reset (ECM Target).

Johnson Controls verified that the CHW supply temperature reset controls were not installed (ECM Performance).

Trending analysis shows that, in 2012, the building operation personnel maintained 42°F CHW supply temperature setpoint during summer and performed manual setpoint increases during shoulder season (Actual Operation).

4.2.4 ECM M&V Methodology The implementation of CHW supply temperature reset controls was verified by analyzing CHW supply temperature vs. outside air temperature plots. Actual building operation was verified by analyzing CHW supply temperature vs. time. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Page 31: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 25

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

LZ CHWST 44 42 44 42 44

LZ CHW Control Fixed Reset to 50°F Fixed Reset to 50°F Fixed

MZ CHWST 44 42 44 42 44

MZ CHW Control Fixed Reset to 50°F Fixed Reset to 50°F Fixed

HZ CHWST 44 42 44 42 44

HZ CHW Control Fixed Reset to 50°F Fixed Reset to 50°F Fixed

Table 4.2.4.1: CHW Reset ECM Model Inputs

Page 32: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 26

4.3 ECM 4.3: CHW LOOP DELTA-T ENHANCEMENT

4.3.1 ECM Description During design operating conditions, Pre-Installation CHW loop was running less than 10°F CHW delta-T conditions. Lower CHW delta-T increases chiller efficiency. But, for any given load condition, lowering the delta-T also increases CHW pump flow and hence, its electric power consumption. A low delta-T also inhibits the ability of the chiller to operate at peak capacity. Hence, increasing the CHW loop delta-T to an optimal design setting was desired.

CHW loop delta-T was increased by:

• Changing the three-way valves to two-way valves in the Pre-Installation AHUs that were included in project

• Minimizing CHW flow rate using CHW pump VFD automation

Post-Installation CHW loop delta-T was targeted to operate close to 10°F at design conditions. This ECM generates energy savings by increasing chiller efficiency and also improves operational capability by increasing chiller capacity.

4.3.2 Pre-Installation System Conditions The following conditions were observed during the Pre-Installation building audit.

• Low Zone CHW loop design condition delta-T: less than 7.8°F

• Mid Zone CHW loop design condition delta-T: less than 6°F

• High Zone CHW loop design condition delta-T: less than 6.9°F

4.3.3 Post-Installation System Conditions In order to achieve the objective of this ECM, the performance contract required Johnson Controls to:

• Change the three-way valves to two-way valves in the Pre-Installation AHUs that were included in project.

• Minimize CHW flow rate using CHW pump VFD automation (ECM Target).

The above scope was verified to be implemented by Johnson Controls (ECM Performance).

Trending analysis shows that, in 2012, the steam chillers were run during peak load conditions. Johnson Controls’ CHW loop delta-T instrumentation is located on the electric chillers and hence, design delta-T could not be trended. However, Johnson Controls trended the loop delta-T under part-load conditions and the summary of the results are shown below (Actual Operation). The details of the analysis are shown in the Appendix 3.

• Low Zone CHW loop part-load condition delta-t: 3°F -6°F

• Mid Zone CHW loop part-load condition delta-t: 3°F -9°F

• High Zone CHW loop part-load condition delta-t: 3°F -9°F

Page 33: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 27

4.3.4 ECM M&V Methodology The implementation of CHW loop delta-T was verified by checking the two-way valve implementation and the CHW VFD automation implementation. Actual building operation was verified by analyzing CHW loop delta-T vs. time. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

The following eQUEST® Model inputs were used to determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

LZ Loop Delta T 7.8°F (At Design Load)

10°F (At Design Load)

7.8°F (At Design Load)

10°F (At Design Load)

3°F to 9°F (At Part Load)

MZ Loop Delta T <6°F (At Design Load)

10°F (At Design Load)

<6°F (At Design Load)

10°F (At Design Load)

3°F to 8°F (At Part Load)

HZ Loop Delta T <6°F (At Design Load)

10°F (At Design Load)

<6°F (At Design Load)

10°F (At Design Load)

2°F to 9°F (At Part Load)

Table 4.3.4.1: CHW Loop Delta-T Enhancement ECM Model Inputs

4.4 ECM 4.4: CHW PUMP VFD AUTOMATION

4.4.1 ECM Description This ECM automated the manually controlled variable flow CHW system into an automatically controlled variable flow CHW system. The pump flow will be automatically controlled to meet the CHW loop differential pressure setpoint. The installed system was tuned in the field to find the correct differential pressure setpoint that helps the system meet varying building load conditions.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW), which may result in both comfort improvement and electrical energy savings.

Varying the speed of the motor is generally accomplished by varying voltage and frequency to the motor. The motor is connected to the CHW pump. As the system’s load changes, consequently so does the required motor driven output. A control program and the VFD will modulate the speed of the motor and match the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3 where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

Page 34: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 28

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Figure 4.4.1.1: The generic pump characteristic plot illustrates that generic pump power

consumption reduces with reduction in VFD speed Two-way valves on the cooling coils ensure that CHW is supplied only when there is demand at the AHU. Hence, two-way valves create differential pressure variation in the CHW loop. The VFD speed can be reduced when loop differential pressure decreases and the loop minimum flow can still be maintained.

In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the bearings.

4.4.2 Pre-Installation System Conditions All CHW pumps were equipped with VFDs. But the drives were not set up to adjust speed automatically with varying building differential pressure. All VFDs were operating at constant full speed during most of the operating times.

4.4.3 Post-Installation System Conditions The performance contract requires Johnson Controls to install a functional CHW pump VFD automation system that is capable of automatically varying VFD Speed between 100% and 50% (min) to meet building differential pressure setpoint (ECM Target).

The CHW pump VFD automation system was fully installed and is capable of automatically varying VFD speed between 100% and 50% (min) to meet building differential pressure setpoint (ECM Performance).

Trending analysis shows that, in 2012, the CHW pump VFDs were run in the manual mode at reduced speeds (Actual Operation). The verification indicates that:

• Low Zone pumps were operating at 67% speed from July to October and at 58% speed during rest of the time.

• Mid Zone pumps were operating at 67% speed from July to December and at 58% speed during rest of the time.

• High Zone pumps were operating at 67% speed from October to December and at 58% speed during rest of the time.

Page 35: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 29

4.4.4 ECM M&V Methodology The implementation of CHW pump VFD automation was verified by checking the Metasys software. Actual building operation was verified by analyzing VFD speed vs. time. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Flow Ctrl /Min VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (67% (July 1 to October

22nd); 58% Rest of the Time)

Flow Ctrl /Min VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (67% (July 1 to October

22nd); 58% Rest of the Time)

Flow Ctrl /Min VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (100% Speed

All Times)

VFD Auto (100% to 50%

Min)

VFD Manual (67% (July 1 to October

22nd); 58% Rest of the Time)

Table 4.4.4.1: CHW Pump VFD Automation ECM Model Inputs

4.5 ECM 4.5: CONDENSER WATER SUPPLY TEMPERATURE RESET

4.5.1 ECM Description Chiller performance increases significantly at lower CW temperatures. CW supply temperature reset strategy was implemented to provide low temperature CW, to the extent allowed by the chiller manufacturer. Cooling tower fan power increases to produce lower temperature CW but chiller efficiency gains typically dominate the economic considerations of this optimization strategy.

Most of the energy consumed by a chiller is used to move refrigerant vapor from the evaporator (low pressure) to the condenser (high pressure). As the pressure differential between the evaporator and condenser increases, the compressor must work harder to move the refrigerant. Lowering CW temperature decreases this pressure differential, so the compressor does less work. Electric chiller efficiency improves with decreased CW supply temperature.

Cooling tower controls are initially set to achieve 70°F tower water during design conditions. When ambient conditions are appropriate, the controls can be reset to produce water that is cooler than 70°F. The Cooling Tower Water Supply Temperature (CTWST) was reset to achieve 5°F cooling tower approach above ambient wet-bulb temperature and it will generate significant energy savings without wasting cooling tower fan energy. The reset was programmed to be 60°F to 75°F, when OAWBT was between 55°F and 70°F.

Page 36: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 30

4.5.2 Pre-Installation System Conditions The CTWST temperature setpoint was manually maintained at a constant 70°F temperature during most of the operating times.

4.5.3 Post-Installation System Conditions The performance contract requires Johnson Controls to install a functional CW reset control system that is capable of achieving 65°F to 70°F reset (ECM Target).

Johnson Controls verified that the CW reset controls were installed and programmed to be 60°F to 75°F, when OAWBT was between 55°F and 70°F (ECM Performance).

Trending analysis shows that, in 2012, the building operation personnel manually maintained CW supply temperature at 55°F to 70°F. Johnson Controls also installed a program to automatically set 71°F CW supply temperature when the steam chiller mode is selected (Actual Operation).

4.5.4 ECM M&V Methodology The implementation of CW supply temperature reset controls was verified by analyzing Metasys programming. Actual building operation was verified by analyzing CW supply temperature vs. time trends. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

Setpoint Control 70°F Fixed 65°F to 70°F Reset 70°F Fixed 60°F to 75°F

Reset

60°F to 75°F Reset (Actual); 65°F Fixed

(Modeled)

Table 4.5.4.1: CW Supply Temperature Model Inputs

4.6 ECM 4.6: COOLING TOWER FAN VFD AUTOMATION

4.6.1 ECM Description The cooling tower has ten cells and each of them is fitted with a separate cooling fan. Eight of the fans are single speed On/Off type. Two of the fans were fitted with manually controllable VFD.

This ECM automated the manually controlled cooling tower VFD system into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the Cooling Tower Water Leaving Temperature (CTWLT) setpoint. In addition, controls were installed to automatically stage the two fan VFDs.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW) which may result in both comfort improvement and electrical energy savings.

Page 37: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 31

Varying the speed of the motor is generally accomplished by varying voltage and frequency to the fan motor. As the system load changes, consequently, so does the required motor driven output. A control program and the VFD will modulate the speed of the motor and match the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3

where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Figure 4.6.1.1: The generic pump characteristic plot illustrates that generic pump power

consumption reduces with reduction in VFD speed In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the bearings.

4.6.2 Pre-Installation System Conditions The cooling tower has ten cells and each of them is fitted with a separate cooling fan. Eight of the fans are single speed ON/OFF type. Two of the fans were fitted with manually controllable VFD.

4.6.3 Post-Installation System Conditions The performance contract requires Johnson Controls to install an automatic cooling tower VFD system (ECM Target).

Page 38: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 32

Johnson Controls verified that the manually controlled cooling tower VFD system was converted into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the CTWLT setpoint. In addition, controls were installed to automatically stage the two fan VFDs (ECM Performance).

Trending analysis shows that, in 2012, the ECM was operated as designed (Actual Operation).

4.6.4 ECM M&V Methodology The implementation of cooling tower fan VFD automation was verified by analyzing VFD speed trends. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM Performance PY Actual Operation

Tower Fan VFD One Speed Fan VFD on TWRS 4 and 5 One Speed Fan VFD on TWRS 4 and 5 VFD on TWRS 4 and 5

Table 4.6.4.1: Cooling Tower Fan VFD Automation ECM Model Inputs

4.7 ECM 4.7: CW PUMP VFD AUTOMATION

4.7.1 ECM Description This ECM automated the manually controlled variable flow CW system into an automatically controlled variable flow CW system. The pump flow will be automatically controlled to meet CW flow setpoint determined by the electric chiller the loading conditions.

Varying the speed of a motor to match the actual load improves control as well as reduces electrical motor power (kW) which may result in both comfort improvement and electrical energy savings.

Varying the speed of the motor is generally accomplished by varying voltage and frequency to the motor. The motor is connected to the CW pump. As the system load changes, consequently, so does the required motor driven output. A control program and the VFD will modulate the speed of the motor and match the output to the load. By reducing the speed of an electric motor, the energy required by the motor is reduced significantly. The actual power required is proportional to the cube of the speed. For example, if a motor’s speed is reduced to 80%, the motor’s energy consumption is decreased by approximately 50%. The theoretical energy savings through speed reduction is shown in the general relationship below:

(bhp2/bhp1)= (W2/W1)^3

where:

w2 = VFD controlled motor speed (varies)

w1 = motor/fan/pump existing speed (constant)

bhp2 = VFD controlled motor brake horsepower (varies)

bhp1 = Brake horsepower required before VFD is installed

Page 39: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 33

The generic pump characteristic plot below illustrates that generic pump power consumption reduces with reduction in VFD speed. For example, reducing the VFD speed by 10% reduces pump energy usage by 27%.

Figure 4.7.1.1: The generic pump characteristic plot illustrates that generic pump power

consumption reduces with reduction in VFD speed In addition to the energy savings, this ECM increases equipment reliability and decreases operating cost by reducing the load on the pump bearings.

4.7.2 Pre-Installation System Conditions All CW pumps were equipped with VFDs but the drives were not set up to adjust speed automatically with varying chiller load. All VFDs were operating at constant full speed during most of the operating times.

4.7.3 Post-Installation System Conditions The savings from this ECM were not guaranteed in the contract (ECM Target).

Johnson Controls installed a functional CW pump VFD automation system that is capable of automatically varying VFD Speed to meet CW flow requirements set by the electric chiller load conditions. CW pump VFD automation cannot be used when the steam chillers are operational (ECM Performance).

Trending analysis shows that, in 2012, the CW pump VFDs were run in the manual mode between 50% and 62% speed (Actual Operation).

4.7.4 ECM M&V Methodology The implementation of CW pump VFD automation was verified by checking the Metasys software. Actual building operation was verified by analyzing VFD speed vs. time. The analyzed plots are presented in this Report’s Appendix. The data for the analysis was retrieved from the Metasys trend repository and from FPI’s trend archive.

Results from the trending analysis were used to generate the following eQUEST Model inputs that determine the ECM savings.

Page 40: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 4 34

Contract Baseline Contract Target PY Adjusted

Baseline PY ECM

Performance PY Actual Operation

CW Pump Control CV CV CV CV VFD Auto (100% to 50% Min)

Table 4.4.4.1: CW Pump VFD Automation ECM Model Inputs

4.7.5 PY ECM Performance Savings ECM target performance (per contract) and the PY Baseline adjustments set the 2012 ECM target savings at $527,851.

Using ECM performance (per M&V) and the PY Baseline adjustments, Johnson Controls calculated the PY ECM performance savings to be $446,904.

Page 41: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 5 35

5. ECM 5: TENANT ENERGY MANAGEMENT PORTAL

5.1 ECM 5: TEM PORTAL

5.1.1 ECM Description Johnson Controls setup an improvised energy dashboard for the customer. The dashboard was developed using Johnson Controls’ Gridlogix software and is a web-based tool that displays a number of energy use variables.

Johnson Controls provides a connection to the building controls system with automatic data transfers of electric submeter data. The dashboard shows energy use compared to relevant variables. The dashboard provides information for each floor of the building and is password protected. A series of alarms are triggered if energy use exceeds expected ranges on any tenant floor. The tenant is able to view current energy consumption in kilowatts along with associated metrics (kW/sq. ft., kW, kWh etc.) as well as historical consumption. The tenant is able to view their comparative consumption relative to other tenants who are under the same ownership structure.

A web-based portal displaying tenant specific electric utility consumption is metered building-wide using a Satec BFM136 utility grade smart-meter network, endorsing energy-efficient practices within the tenant space.

The EnNET®/AEM platform provides 15 minute meter data and creates a normalized data base that can be used to support Time Series profiling, reporting to ISO and future integration with property management software for creating a bill based on current meter read should a tenant terminate a lease.

5.1.2 Pre-Installation System Conditions Johnson Controls’ Gridlogix verified the connectivity to each meter. Johnson Controls’ Gridlogix was not responsible for the physical connection (wired or wireless) to the existing main/sub meters or a third party device required to collect the 15 minute pulse data. The data was in a protocol format that Johnson Controls supports such as Modbus, BACnet®, SNMP. Data protocol was BACnet which fully supported auto discovery. Johnson Controls’ Gridlogix commissioned and verified the EnNET software connection and read the meter data properly. Johnson Controls’ Gridlogix established the rules base and monitored notifications for successfully creating, archiving and ensuring quality of service. Johnson Controls’ Gridlogix commissioned the AEM application and built the web pages to properly display metering data, time series analysis, real-time metering information and created notifications based on usage parameters.

5.1.3 Post-Installation System Conditions The deployment of TEM was completed in Year 2011. Due to increasing installation of submeters and requests to contemporized existing TEM, Johnson Controls proceeded with development of enhanced TEM. During third quarter of Year 2012, a new dashboard, TEM2, went in production to meet and exceed the growing platform at the site. TEM2 platform includes customer facing interactive applications such as:

• A green kiosk on how to save energy tips

• Building/industry tweets

Page 42: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 5 36

• Sustainability trending

• Information on various retrofit performed at site

• Tenant specific dashboard to display various matrices

• Reporting module – tenant and administration based

• Energy analyzer with ability to view sub-metering at a granular level

5.1.4 ECM M&V Methodology The basis of savings is a combination of temperature controls by building and energy monitoring by individual tenant. By using TEM, tenants can consistently monitor and take a proactive approach in reducing the demand and consumption by utilizing various avenues mentioned in TEM.

The following measurements were performed to determine whether the TEM metering achieves the Guaranteed Annual Savings Amount:

• Johnson Controls trends the space temperature setpoints and enters the values in the eQUEST Model. The setpoints in the room can be adjusted upward during summer and downward during winter. Johnson Controls trends the difference between site standard temperature setpoint and the tenant selected setpoint. The tenants have access to a thermostat with a slider that can change the zone setpoints by a user selected value. The slider is set so that in the summer the tenant can only select between the building standard setpoint and a higher setpoint. In winter, the tenant is able to select between the building standard setpoint and a lower setpoint.

• Johnson Controls inspects the tenant utility meter screens from a common sense point of view. Any newly added tenant meter screens are verified. It is the responsibility of the customer to add new meters to the system.

The Customer agrees to operate the conditioned spaces in the Site within the temperature ranges scheduled in the Temperature Control table below. Operating conditions outside the range specified in this table shall constitute a Cause for Adjustment. In the event that an adjustment to the Baseline is sought, Johnson Controls shall submit the proposed Baseline adjustments to the Customer and describe the reasons for the adjustment as part of the prior year calculations described in Schedule B.

Page 43: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

ECM 5 37

Temperature Control

Occupied room temperature during heating season: 70°F (+/- 2°F)

Unoccupied low temperature l imit during heating season: 55°F

Heating season is: November 1 to April 30

Occupied room temperature during cooling season: 74°F (+/- 2°F)

Unoccupied high temperature l imit during cooling season: N/A °F

Cooling season is: May 1 to October 31

5.1.5 PY ECM Performance Savings ECM target performance (per contract) and the PY Baseline adjustments set the 2012 ECM target savings at $25,755.

Using ECM performance (per M&V) and the PY Baseline adjustments, Johnson Controls calculated the PY ECM performance savings to be $0.

Page 44: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 38

Appendix List Appendix 1: BAS Retrofit Data Analysis

Appendix 2: Chiller Retrofit Data Analysis

Appendix 3: Chiller Plant Retrofit Data Analysis

Appendix 4: Steam Chiller Usage Data Analysis

Appendix 5: Occupancy Modeling Methodology

Appendix 6: ESB eQUEST Model Input Table

Appendix 7: Utility Analysis

Appendix 8: FPI

Page 45: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 39

Appendix 1: BAS Retrofit Data Analysis DATA ANALYSIS

Damper Retrofit and DCV The goal of the ECM was to reduce the building’s overall outside air intake by retrofitting the non-Alerton AHU with DCV and modulating dampers. Minimum outside air ventilation is possible when CO2 based DCV is combined with the ability to open dampers just enough to satisfy the ventilation demand. This cannot be achieved with the old two position dampers, but can be achieved with CO2 based DCV controls and modulating dampers.

Demand controlled ventilation is used to modulate outside air ventilation based on real time occupancy. DCV reduces unnecessary over-ventilation that may result when existing AHUs are set to provide ventilation for a maximum assumed occupancy.

Johnson Controls retrofitted non-Alerton AHUs with CO2 sensor on the return air duct. DCV was programmed for outside air activation at 800 ppm ‘return air CO2’ threshold. Also, Johnson Controls retrofitted non-Alerton AHU units by replacing their two-position pneumatic damper system with new dampers (if broken), new actuators and DDC controls. The new damper system has the capability to modulate anywhere between 0% to 100% open/close position.

Outside air damper position % and return air CO2 ppm level data for High Zone AHUs-52.5, 52.4 and Mid Zone AHU -39.4, Low Zone AHU15.8 were taken from Metasys data repository server. The analyzed data trends (shown below) indicated that outside damper position increased when the CO2 ppm in the return air increased above the threshold level of 800ppm. The data trends demonstrate that the DCV system was installed and is operational. The data was taken from January 2012 to December 2012 period.

Outside Air Damper Position increased when CO2 level was increased> 800ppm

Page 46: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 40

Figure A.1.1: AHU 52.5 Outside Air Damper Position maintains minimum damper position (10%) and modulates when CO2 level rises.

Figure A.1.2: AHU 52.2 Outside Air Damper Position maintains minimum damper position

(10%) and modulates when CO2 level rises.

Outside Air Damper Position increased when CO2 level was increased >800ppm

Outside Air Damper Position increased when CO2 level was increased >800ppm

Page 47: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 41

Figure A.1.3: AHU 39.4 Outside Air Damper Position maintains minimum damper position (10%) and modulates when CO2 level rises.

Figure A.1.4: AHU 15.8 Outside Air Damper Position maintains minimum damper position

(10%) and modulates when CO2 level rises.

The following charts show the outside air damper position percentage and CO2 ppm level trends during building occupied hours. The trends indicate that outside air dampers modulate between 0% to 100%. Also, these plots show that the outside air damper position was fixed when outside air temperature goes above 68°F.

Outside Air Damper Position increased when CO2 level was increased >800ppm

OA Position increase when CO2 level increased

OA Position was at 10% @OAT>68F

Page 48: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 42

Figure A.1.5: Outside air damper position percentage and CO2 ppm level

trends during building occupied hours.

Fan Scheduling The building has fans to provide AHU supply air, exhaust toilet space air and to exhaust building space air. Prior to the performance contract, the fans did not have the DDC controls to automatically schedule On/Off. Johnson Controls installed DDC controls on the AHU’s to automatically schedule On/Off.

As part of the BAS retrofit, all non-Alerton AHU supply fans were connected to BAS and the scheduling feature was enabled.

AHU Supply Fan Scheduling:

Supply fan run status data for AHU 15-7, 15-8, 39-4 and 48-4 was taken from the Metasys data server and the trend data for each unit are shown below. The data clearly indicate that the units were operating for 12 hours/day during most of the time. A few of units operated for 15 hours/day from June to Oct. The following lists the average operating hours:

OA Position was at 10% @OAT>68F

OA Position increase when CO2 level increased

Page 49: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 43

• Contract Baseline: 18 hours/day

• Contract Target: 15 hours/Day

• ECM Performance and Actual: 13.25 Hours/Day (12 Hours/day 42% of the Time and 15 Hours/day 58% of the Time)

Figure A.1.6: AHU 15-7 daily run hours trend.

Figure A.1.7: AHU 1-.7 daily run hours trend.

0

4

9

14

19

0

Ope

rati

ng H

ours

/day

AHU 15-8 Daily Run Hours Trend

Operating at 12 hours/day

Operating at 12 hours/day

Page 50: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 44

Figure A.1.8: AHU 39-4 daily run hours trend.

Figure A.1.9: AHU 48-4 daily run hours trend.

The following Figure shows the average run hour histogram for a typical AHU (AHU 15-7).

Operating at 12 hours/day

Operating at 12 hours/day

Page 51: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 1: BAS Retrofit Data Analysis 45

Figure A.1.10: AHU 15.7 Monthly Average Run Hours Summary

Similar analysis was carried out for more sample AHU’s and the observation reflected the results.

The table on the following page shows the vacancy rate calculations by level and CHW zone.

Page 52: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 46

Appendix 2: Chiller Retrofit Data Analysis Chiller Curve fit Modeling Methodology

Trended chiller data was used to create custom chiller performance curves in eQUEST to best-fit the data. The data that was used to calculate chiller performance includes:

• VSD Input kW

• VSD Output Frequency (used for comparison and trouble shooting)

• Leaving CHWT

• Entering CHWT (used for comparison and trouble shooting)

• CHW Flow Rate

• Leaving CWT (used for comparison and trouble shooting)

• Entering CWT

From the trended data, several output values were calculated, including

• Chiller load (tons)

• Adjusted chiller capacity, to account for CHWT and CWT impacts - this was calculated using the default eQUEST capacity adjustment curve, which is typical for most centrifugal chillers

• % Full-Load, using calculated adjusted capacity and calculated load

• Chiller Efficiency (kW/ton)

To compare the DOE2 default curves to the actual trended chiller data, the chiller kW was calculated for the given trend conditions for all of the data points which was then compared to the trended chiller kW by calculating the Mean Bias Error (MBE) and the Root Mean Square Error (RMSE). For the entire data set, an overall MBE and coefficient of variation for the RSME was then calculated.

MBE = 𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑−𝑘𝑊𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑

𝐶𝑉(𝑅𝑀𝑆𝐸) =�∑ �𝑘𝑊𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑−𝑘𝑊𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑�

2𝑛1𝑛

𝑘𝑊�����𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑

To determine the best fit for the data, the solver function in Excel® was used to minimize the Coefficient of Variation for the data set while using constraints to maintain the specified full-load ARI condition efficiency. Part of fitting the data was to estimate each chiller's full-load efficiency at ARI conditions. For many of the chillers, limited or no data was available at full-loading conditions and ARI conditions (note that ARI rating conditions are 100% load at 85°F CWT and 44°F CHWT). This was due to the chiller staging strategy utilized in 2012 which involved base loading the steam chiller during on-peak electrical hours to limit the building demand. For the chillers with no trended points at ARI conditions, engineering judgment was used to determine an acceptable ARI rating for the chiller. This involved finding the full-load points available and adjusting the measured performance at that point to account for the variance in conditions from ARI rating conditions (e.g. a chiller operating at full-load with 75°F CWT typically has a lower kW/ton than the same chiller operating at 85°F CWT).

Page 53: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 47

After finding a best-fit for the data by solving for the curves to minimize the coefficient of variation, these custom curves and estimated ARI chiller efficiency ratings were used to calculate the FIM performance. Target and FIM performance fit information for each chiller is shown on the following pages.

Low Zone CH-1 Mid Zone CH-4 Mid Zone CH-5 High Zone CH-6Rated Efficiency at ARI

conditions (kW/ton)0.799 0.711 0.711 0.817

CurvesDefault DOE2 Centrifugal

VSD CurvesDefault DOE2 Centrifugal

VSD CurvesDefault DOE2 Centrifugal

VSD CurvesDefault DOE2 Centrifugal

VSD CurvesSource Contract Contract Contract Contract

Rated Efficiency at ARI conditions (kW/ton)

0.55 0.58 0.60 0.55

CurvesCustom to best-fit

trended dataCustom to best-fit

trended dataCustom to best-fit

trended dataCustom to best-fit

trended data

Source

0.55 kW/ton point comes from trended data - no

points were available at ARI conditions, closest

points were full load, 42 CHWT, 75 CWT at 0.50

kW/ton, so this performance was

degraded 10% to account for this

0.58 kW/ton comes from trended point at 100%

load, 42.1 CHWT, 81.3 CWT

0.60 kW/ton point comes from trended data - no

points were available at ARI conditions, closest

points were full load, 42 CHWT, 68 CWT at 0.50

kW/ton, so this performance was

degraded 20% to account for this

0.55 kW/ton point comes from trended data - no

points were available at ARI conditions, closest

points were full load, 42 CHWT, 75 CWT at 0.50

kW/ton, so this performance was

degraded 10% to account for this

Target

FIM Performance

Page 54: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 48

Low Zone Electric CH-1 Target Contract Efficiency and default eQUEST curves (0.799 kW/ton at ARI)

Low Zone Electric CH-1 FIM Performance Best-fit curve solutions (0.55 kW/ton at ARI)

CWT MBE Cv(RSME)

60.00 -22% 38%

65.00 -5% 15%

70.00 0% 14%

75.00 -2% 12%

80.00 3% 13%

85.00 11% 15%

Overall -0.02% 14%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%Eff

icien

cy (k

W/to

n)Load (%)

CH-1 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-1, 750 ton centrifugal chiller at 0.74 kW/ton full load ARI- 0.655 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled Target Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/to

n

Chiller Part Loading (%)

Modeled Target Chiller Performance 65 degF CWT75 degF CWT85 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

85 CWT (Trended Data)85 CWT (Modeled Target Performance)

CWT MBE Cv(RSME)

60.00 -18% 41%

65.00 -3% 14%

70.00 1% 13%

75.00 0% 10%

80.00 2% 8%

85.00 -4% 8%

Overall 0.10% 11%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effic

ienc

y (kW

/ton

)

Load (%)

CH-1 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-1, 750 ton centrifugal chiller at 0.74 kW/ton full load ARI- 0.655 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled FIM Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/to

n

Chiller Part Loading (%)

Modeled FIM Chiller Performance 65 degF CWT75 degF CWT85 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

85 CWT (Trended Data)85 CWT (Modeled FIM Performance)

Page 55: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 49

Mid Zone Electric CH-4 Target Contract Efficiency & default eQUEST curves (0.711 kW/ton ARI)

Mid Zone Electric CH-4 FIM Performance Best-fit curve solutions (0.58 kW/ton at ARI)

CWT MBE Cv(RSME)

60.00 #DIV/0! #DIV/0!

65.00 9% 27%

70.00 8% 26%

75.00 7% 25%

80.00 4% 18%

85.00 12% 35%

Overall 6.65% 24%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effic

ienc

y (kW

/ton

)

Load (%)

CH-4,5 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-4,5, 1000 ton centrifugal chiller at 0.72 kW/ton full load ARI- 0.638 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled Target Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/t

on

Chiller Part Loading (%)

Modeled Target Chiller Performance 65 degF CWT75 degF CWT85 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

85 CWT (Trended Data)85 CWT (Modeled Target Performance)

CWT MBE Cv(RSME)

60.00 #DIV/0! #DIV/0!

65.00 -4% 10%

70.00 0% 8%

75.00 0% 10%

80.00 0% 7%

85.00 2% 11%

Overall 0.10% 9%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effic

ienc

y (kW

/ton

)

Load (%)

CH-4,5 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-4,5, 1000 ton centrifugal chiller at 0.72 kW/ton full load ARI- 0.638 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled FIM Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/t

on

Chiller Part Loading (%)

Modeled FIM Chiller Performance 65 degF CWT75 degF CWT85 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

85 CWT (Trended Data)85 CWT (Modeled FIM Performance)

Page 56: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 50

Mid Zone Electric CH-5 Target Contract Efficiency & default eQUEST curves (0.711 kW/ton ARI)

Mid Zone Electric CH-5 FIM Performance Best-fit curve solutions (0.68 kW/ton ARI)

CWT MBE Cv(RSME)

60.00 -79% 79%

65.00 -57% 60%

70.00 -50% 52%

75.00 -42% 47%

80.00 -27% 30%

85.00 -17% 17%

Overall -45.36% 49%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effici

ency

(kW

/ton)

Load (%)

CH-4,5 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-4,5, 1000 ton centrifugal chiller at 0.72 kW/ton full load ARI- 0.638 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled Target Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/to

n

Chiller Part Loading (%)

Modeled Target Chiller Performance 65 degF CWT75 degF CWT80 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

80 CWT (Trended Data)80 CWT (Modeled Target Performance)

CWT MBE Cv(RSME)

60.00 -56% 56%

65.00 -1% 15%

70.00 0% 15%

75.00 -3% 20%

80.00 7% 12%

85.00 8% 8%

Overall 0.10% 16%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effici

ency

(kW

/ton)

Load (%)

CH-4,5 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-4,5, 1000 ton centrifugal chiller at 0.72 kW/ton full load ARI- 0.638 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled FIM Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/to

n

Chiller Part Loading (%)

Modeled FIM Chiller Performance 65 degF CWT75 degF CWT80 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

80 CWT (Trended Data)80 CWT (Modeled FIM Performance)

Page 57: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 2: Chiller Retrofit Data Analysis 51

High Zone Electric CH-6 Target Contract Efficiency & default eQUEST curves (0.817 kW/ton ARI)

High Zone Electric CH-6 FIM Performance Best-fit curve solutions (0.55 kW/ton at ARI)

CWT MBE Cv(RSME)

60.00 -13% 41%

65.00 -15% 22%

70.00 -10% 17%

75.00 -3% 11%

80.00 -1% 9%

85.00 -13% 13%

Overall -7.35% 15%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%Eff

icien

cy (k

W/to

n)Load (%)

CH-6 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-6, 1000 ton centrifugal chiller at 0.85 kW/ton full load ARI- 0.748 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled Target Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/t

on

Chiller Part Loading (%)

Modeled Chiller Target Performance 65 degF CWT75 degF CWT80 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled Target Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

80 CWT (Trended Data)80 CWT (Modeled Target Performance)

CWT MBE Cv(RSME)

60.00 9% 12%

65.00 -2% 11%

70.00 0% 8%

75.00 2% 9%

80.00 -3% 8%

85.00 -27% 27%

Overall 0.10% 8%0.00

0.50

1.00

1.50

2.00

2.50

3.00

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%

Effici

ency

(kW

/ton)

Load (%)

CH-6 BaselineCurves

eQUEST Default Centrifugal 65 CWTeQUEST Default Centrifugal 75 CWTeQUEST Default Centrifugal 85 CWT

- CH-6, 1000 ton centrifugal chiller at 0.85 kW/ton full load ARI- 0.748 kW/ton calculated IPLV from eQUEST curves

0.00

0.50

1.00

1.50

2.00

2.50

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

kW/t

on

Chiller Part Loading (%)

Trended Data vs. Modeled FIM Chiller Performance Trended Data85 degF CWT65 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 20% 40% 60% 80% 100%

kW/t

on

Chiller Part Loading (%)

Modeled Chiller FIM Performance 65 degF CWT75 degF CWT80 degF CWT

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

65 CWT (Trended Data)65 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

75 CWT (Trended Data)75 CWT (Modeled FIM Performance)

0.00

0.50

1.00

1.50

2.00

2.50

0% 50% 100%

kW/t

on

Chiller Part Loading (%)

80 CWT (Trended Data)80 CWT (Modeled FIM Performance)

Page 58: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 52

Appendix 3: Chiller Plant Retrofit Data Analysis 3.1 CHWST Reset Chiller performance improves when higher temperature CHW is produced. Low CHW temperatures are required to meet the building load during hot summer days. Chiller performance improvisation, without compromising capacity requirements, can be achieved by incorporating CHW supply temperature reset controls. Increase in CHW supply temperature results in increased variable CHW pumping system energy consumption. This penalty can be minimized by tuning the system to maintain minimum design flow through the AHU coils.

Johnson Controls verified that the CHW supply temperature reset controls were not installed and hence, no savings were claimed in 2012.

Chiller 1: CHWST vs. Outside Air Temperature

Figure A.3.1.1 shows the CHWST during various outside air temperature conditions for Chiller 1. The plot indicates that the CHWST did not vary with outside air temperature and it does not indicate any co-relation with outside air temperature. It also indicates the setpoint was manually adjusted by the operating personnel. The manually operated CHWST range was between 42°F and 50°F.

Figure A.3.1.1: CHWST during Various Outside Air Temperature Conditions for Chiller 1

Chiller 1: CHWST, Outside Air Temperature vs. Time

Figure A.3.1.2 shows Chiller 1 CHWST trend during summer 2012 conditions. The plot demonstrates that the outside air temperature varied from 56°F to 85°F and CHWST was maintained constant irrespective of outside air temperature change. It also demonstrated that the CHWST setpoint was operated manually.

Page 59: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 53

Figure A.3.1.2: Chiller 1 CHWST Trend during Summer 2012 Conditions

Chiller 4: CHWST vs. Outside Air Temperature

Figure A3.1.3 shows the CHWST during various outside air temperature conditions for Chiller 4. The plot indicates that CHWST did not vary with outside air temperature and it does not indicate any co-relation with outside air temperature. It also indicates the setpoint was manually adjusted by the operating personnel. The manually operated CHWST range was between 42°F and 50°F.

Figure A.3.1.3: CHWST during Various Outside Air Temperature Conditions for Chiller 4

Chiller 4: CHWST, Outside Air Temperature vs Time

Figure A.3.1.4 shows Chiller 4 CHWST trend during summer 2012 conditions. The plot demonstrates that the outside air temperature varied from 45°F to 90°F and CHWST was maintained constant irrespective of outside air temperature change. It also demonstrated that the CHWST setpoint was operated manually.

Page 60: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 54

Figure A.3.1.4: Chiller 4 CHWST Trend during Summer 2012 Conditions

Chiller 5: CHWST vs. Outside Air Temperature

Figure A.3.1.5 shows the CHWST during various outside air temperature conditions for Chiller 5. The plot indicates that the CHWST did not vary with outside air temperature and it does not indicate any co-relation with outside air temperature. It also indicates the setpoint was manually adjusted by the operating personnel. The manually operated CHWST range was between 42°F and 50°F.

Figure A.3.1.5: CHWST during Various Outside Air Temperature Conditions for Chiller 5

Chiller 5: CHWST, Outside Air Temperature vs. Time

Figure A.3.1.6 shows Chiller 5 CHWST trend during summer 2012 conditions. The plot demonstrates that the outside air temperature varied from 50°F to 90°F and CHWST was maintained constant irrespective of outside air temperature change. It also demonstrated that the CHWST setpoint was operated manually.

Page 61: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 55

Figure A.3.1.6: Chiller 5 CHWST Trend during Summer 2012 Conditions

Chiller 6: CHWST vs Outside Air Temperature

Figure A.3.1.7 shows the CHWST during various outside air temperature conditions for Chiller 6. The plot indicates that the CHWST did not vary with outside air temperature and it does not indicate any co-relation with outside air temperature. It also indicates the setpoint was manually adjusted by the operating personnel. The manually operated CHWST range was between 42°F and 50°F.

Figure A.3.1.7: CHWST during Various Outside Air Temperature Conditions for Chiller 6

Chiller 6: CHWST, Outside Air Temperature vs Time

Figure A.3.1.8 shows Chiller 6 CHWST trend during summer 2012 conditions. The plot demonstrates that the outside air temperature varied from 50°F to 90°F and CHWST was maintained constant irrespective of outside air temperature change. It also demonstrated that the CHWST setpoint was operated manually.

Page 62: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 56

Figure A.3.1.8: Chiller 6 CHWST Trend during Summer 2012 Conditions

3.2 CHW Loop Delta-T Enhancement Lower CHW delta-T increases chiller efficiency. But for any given load condition, lowering the delta-T also increases CHW pump flow and hence, its electric power consumption. A low delta-T also inhibits the ability of the chiller to operate at peak capacity. Hence, increasing the CHW loop delta-T to an optimal design setting was desired. Post-Installation CHW loop delta-T was targeted to operate close to 10°F under design conditions.

CHW loop delta-T was increased by:

• Changing the three-way valves to two-way valves in the Pre-Installation AHUs that were included in project

• Minimizing CHW flow rate using CHW pump VFD automation

Trending analysis shows that, in 2012, the steam chillers were run during peak load conditions. Johnson Controls’ CHW loop delta-T instrumentation is located on the electric chillers and hence, design delta-T could not be trended. However, Johnson Controls trended the loop delta-T under part-load conditions and the summary of the results are shown below.

Chiller 1: CHW Delta-T vs Outside Air Temperature

Figure A.3.2.1 shows the CHW delta-T levels for Chiller 1. Figure A.3.2.2 shows the CHW delta-T during various outside air temperature conditions for Chiller 1. Figure A.3.2.3 shows Chiller 1 CHW delta-T Trend during summer 2012 conditions. These plots demonstrate that the Low Zone delta-T was operating mostly between 3°F to 6°F.

Page 63: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 57

Figure A.3.2.1: CHW Delta-T Levels for Chiller 1

Figure A.3.2.2: CHW Delta-T during Various Outside Air Temperature Conditions for Chiller 1

Page 64: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 58

Figure A.3.2.3: Chiller 1 CHW Delta-T Trend during Summer 2012 Conditions

Chiller 4 CHW Delta-T vs. Outside Air Temperature

Figure A.3.2.4 shows the CHW delta-T levels for Chiller 4. Figure A.3.2.5 shows the CHW delta-T during various outside air temperature conditions for Chiller 4. Figure A.3.2.6 shows Chiller 4 CHW delta-T Trend during summer 2012 conditions. These plots demonstrate that the Mid Zone delta-T was operating mostly between 3°F to 9°F.

Figure A.3.2.4: CHW Delta-T Levels for Chiller 4

Page 65: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 59

Figure A.3.2.5: CHW Delta-T during Various Outside Air Temperature Conditions for Chiller 4 The graph indicates that the CHW delta-T was varying from 3°F to 9°F. The trend data of CHW delta-T and outside air temperature was plotted and shown below.

Figure A.3.2.6: Chiller 4 CHW Delta-T Trend during Summer 2012 Conditions

Page 66: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 60

Chiller 5 CHW Delta-T vs. Outside Air Temperature

Figure A.3.2.7 shows the CHW delta-T levels for Chiller 5. Figure A.3.2.8 shows the CHW delta-T during various outside air temperature conditions for Chiller 5. Figure A.3.2.9 shows Chiller 5 CHW delta-T trend during summer 2012 conditions. These plots demonstrate that the Mid Zone delta-T was operating mostly between 3°F to 8°F.

Figure A.3.2.7: CHW Delta-T Levels for Chiller 5

Figure A.3.2.8: CHW Delta-T during Various Outside Air Temperature Conditions for Chiller 5

Page 67: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 61

The trend data of CHW delta-T and outside air temperature was plotted and shown below.

Figure A.3.2.9: Chiller 5 CHW Delta-T Trend during Summer 2012 Conditions

Chiller 6 CHW Delta-T vs. Outside Air Temperature

Figure A.3.2.10 shows the CHW delta-T levels for Chiller 6. Figure A.3.2.11 shows the CHW delta-T during various outside air temperature conditions for Chiller 6. Figure A.3.2.12 shows Chiller 6 CHW delta-T trend during summer 2012 conditions. These plots demonstrate that the High Zone delta-T was operating mostly between 3°F to 9°F.

Figure A.3.2.10: CHW Delta-T Levels for Chiller 6

Page 68: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 62

Figure A.3.2.11: CHW Delta-T during Various Outside Air Temperature

Conditions for Chiller 6 The trend data of CHW delta-T and outside air temperature was plotted and shown below.

Figure A.3.2.12: Chiller 6 CHW Delta-T Trend during Summer 2012 Conditions

Page 69: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 63

3.3 CHW Pump VFD Automation This ECM automated the manually controlled variable flow CHW system into an automatically controlled variable flow CHW system. The pump flow will be automatically controlled to meet the CHW loop differential pressure setpoint. Two-way valves on the cooling coils ensure that CHW is supplied only when there is demand at the AHU. Hence, two-way valves create differential pressure variation in the CHW loop. The VFD speed can be reduced when loop differential pressure decreases and the loop minimum flow can still be maintained.

The CHW pump VFD automation system was fully installed and is capable of automatically varying VFD speed between 100% and 50% (min) to meet building differential pressure setpoint. However, the trending analysis shows that, in 2012, the CHW pump VFDs were run in the manual mode at reduced speeds.

Low Zone CHW Pump VFD Speed

Figure A.3.3.1 shows the VFD speed levels for the Low Zone CHW pumps. This histogram demonstrates that all Low Zone pumps were operating in the manual mode either at 58% speed or at 67% speed.

Figure A.3.3.1: VFD Speed Levels for the Low Zone CHW Pumps Mid Zone CHW Pump VFD Speed

Figure A.3.3.2 shows the VFD speed levels for the Mid Zone CHW pumps. This histogram demonstrates that all Mid Zone pumps were operating in the manual mode between 53% to 70% speed.

Page 70: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 64

Figure A.3.3.2: VFD Speed Levels for the Mid Zone CHW Pumps High Zone CHW Pump VFD Speed

Figure A.3.3.3 shows the VFD speed levels for the High Zone CHW pumps. This histogram demonstrates that all High Zone pumps were operating in the manual mode either at 58% speed or at 67% speed.

Figure A.3.3.3: VFD Speed Levels for the High Zone CHW Pumps

3.4 CW Supply Temperature Reset Chiller performance increases significantly at lower CW temperatures. CW supply temperature reset strategy was implemented to provide low temperature CW, to the extent allowed by the chiller manufacturer. Cooling tower fan power increases to produce lower temperature CHW but chiller efficiency gains typically dominate the optimization.

Page 71: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 65

Cooling tower controls are initially set to achieve 70°F tower water during design condition. When ambient conditions are appropriate, the controls can be reset to produce water that is cooler than 70°F. The CTWST was reset to achieve 5°F cooling tower approach above ambient wet-bulb temperature and it will generate significant energy savings without wasting cooling tower fan energy. The reset was programmed to be 60°F to 75°F when OAWBT was between 55°F and 70°F.

Figure A.3.4.1: CTWLT during Various OAWBT Temperature Conditions

Figure A.3.4.2: CTWLT Trend during Summer 2012 Conditions

Figure A.3.4.1 shows the CTWLT during various OAWBT temperature conditions. Figure A.3.4.2 shows the CTWLT trend during summer 2012 conditions. Trending analysis shows that, in 2012, the building operation personnel manually maintained CW supply temperature at 55°F to 70°F. Johnson Controls also installed a program to automatically set 71°F CW supply temperature when the steam chiller mode is selected.

Page 72: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 66

3.5 Cooling Tower Fan VFD Automation The cooling tower has ten cells and each of them is fitted with a separate cooling fan. Eight of the fans are single speed On/Off type. Two of the fans were fitted with manually controllable VFD.

This ECM automated the manually controlled cooling tower VFD system into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the CTWLT setpoint. In addition, controls were installed to automatically stage the two fan VFDs.

Johnson Controls verified that the manually controlled cooling tower VFD system was converted into an automatically controlled cooling tower VFD system. The fan speed is now automatically controlled to meet the CTWLT setpoint. In addition, controls were installed to automatically stage the two fan VFDs. Trending analysis shows that, in 2012, the ECM was operated as designed (Actual Operation).

Figure A.3.5.1: VFD Speed Levels for the CT Variable Speed Fans

Figure A.3.5.1 shows the VFD speed levels for the CT variable speed fans. This histogram demonstrates that the CT fan VFDs are operational. The analysis also demonstrated that the VFDs were modulating 64% of the operational time.

0

200

400

600

800

1000

1200

1400

No.

of O

ccur

ence

CT VFD Speed (%)

Cooling Tower Fan VFD Speed Vs No. of Occurrence

Twr5

Twr4

Page 73: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 67

Figure A.3.5.2: CT Fan VFD Speed Trend during Summer 2012 Conditions

Figure A.3.5.2 shows the cooling tower fan VFD speed trend during summer 2012 conditions. The plots demonstrate the automatic modulation of the VFD speed.

Date / Time CT5 VFD CT4 VFD

10/19/12 5:50 PM 57.0% 57.0%

10/19/12 4:41 PM 48.1% 48.1%

10/19/12 3:40 PM 45.7% 45.7%

10/19/12 2:30 PM 47.9% 47.9%

10/19/12 1:20 PM 43.0% 43.0%

10/19/12 12:10 PM 44.9% 44.9%

10/19/12 11:00 AM 41.2% 41.2%

10/19/12 9:50 AM 41.6% 41.6%

10/19/12 8:40 AM 39.8% 39.8%

10/19/12 7:30 AM 58.3% 58.3%

Table A.3.5.1: Sample One-Day Profile of CT Fan VFD Speed Table A.3.5.1 shows the sample one-day profile of CT Fan VFD Speed and demonstrates that both of the tower fans are ramping up at the same speeds as load increases.

3.6 CW Pump VFD Automation This ECM automated the manually controlled variable flow CW system into an automatically controlled variable flow CW system. The pump flow will be automatically controlled to meet CW flow setpoint determined by the electric chiller the loading conditions.

Johnson Controls installed a functional CW pump VFD automation system that is capable of automatically varying VFD Speed to meet CW flow requirements set by the electric chiller load conditions. CW pump VFD automation cannot be used when the steam chillers are operational.

Page 74: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 68

Figure A.3.6.1 through Figure A.3.6.6 shows the CW Pump-1 VFD speed trend. The trending analysis shows that, in 2012, all the CW pump VFDs were run in the manual mode between 50% and 62% speed.

Figure A.3.6.1: CW Pump-1 VFD Speed Trend

Figure A.3.6.2: CW Pump-2 VFD Speed Trend

0%

10%

20%

30%

40%

50%

60%

VFD

Spee

d

Date / Time

Condenser Pump 1 VFD Speed VsTime

0%

10%

20%

30%

40%

50%

60%

70%

VFD

Spee

d

Date / Time

Condenser Pump 2 VFD Speed VsTime

Page 75: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 69

Figure A.3.6.3: CW Pump-3 VFD Speed Trend

Figure A.3.6.4: CW Pump-4 VFD Speed Trend

Page 76: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 3: Chiller Plant Retrofit Data Analysis 70

Figure A.3.6.5: CW Pump-5 VFD Speed Trend

Figure A.3.6.6: CW Pump-6 VFD Speed Trend

0%

10%

20%

30%

40%

50%

60%

70%

VFD

Spee

d

Date / Time

Condenser Pump 5 VFD Speed VsTime

0%

10%

20%

30%

40%

50%

60%

70%

VFD

Spee

d

Date / Time

Condenser Pump 6 VFD Speed VsTime

Page 77: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 71

Appendix 4: Steam Chiller Usage Data Analysis ESB predominately uses steam for heating system and to run the steam operated chiller for cooling load. The building receives steam from ConEdison Company (ConEd) from their district heating system. There are five steam meters for the entire building and sum of all these meters gives the total steam usage.

Steam usage (lbs/hr) from all five steam meters was collected from the ConEd and was analyzed as shown below. The hourly profile indicates that the overall consumption varies from 2,000 lbs/hour in night to 40,000 lbs/hour in day time.

Figure A.4.1: Steam Usage Hourly Trend

The chart below indicates that building average base winter load varies from 3,000 to 7,000 lbs/hr during night time and average peak winter load vary from 26,000 to 34,000 lbs/hour during day time.

During summer, the base summer load was around 2,000 lbs/hr to 3,000 lbs/hr during night time and 7,000 to 18,000 lbs/hr during day time.

Further, the chart indicates the daytime consumption increased at around 5 a.m. in summer and 8 a.m. in winter. The further analysis as indicated in the subsequent section shows that the steam mainly used to operate steam chillers during the day time from 8 a.m. to 4 p.m.

Page 78: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 72

Figure A.4.2: ESB Monthly Average Hourly Steam Usage Profile

Note: Monthly Average Hourly Steam Usage = Sum of usage at a particular hour from “all” the months/No of days in the month

The below histogram indicate the ton-hour against the hour of the day. These two plots shows that the steam chillers were operated mainly from 8 a.m. to 4 p.m. All remaining hours electric chillers were in operation.

Figure A.4.3: Chiller Ton-Hour Histogram (5AM to 4PM)

Maximum Usage in Jan @9:00AM

Base Winter Usage

Base Summer Usage

Page 79: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 73

Figure A.4.4: Chiller Ton-Hour Histogram (5PM to 4AM) The following graph indicates the monthly steam usage details vs. HDD. The chart includes utility bill steam usage and the ConEd hourly steam usage. Both data almost matched except for some variations due to overalapping days in the bill. This chart indicates high steam usage during winter and low usage during summer period.

Figure A.4.5 Monthly Total Steam Usage Vs HDD

Page 80: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 74

Appendix 5: Occupancy Modeling Methodology PY building occupancy data was provided by ESB’s leasing agent, Newmark Knight Frank. Actual move-in and move-out dates from the quarterly planbook were utilized to accurately calculate the vacancy rate of the building as of April, July, November, and December. Usable square feet metric from the plan book was used as the basis for the percentage calculations. The following calculation method was utilized to estimate floor level vacancy rate:

Floor (n) Vacancy Rate (%) = (Total Vacant Square Feet on Floor (n))/ (Total Square Feet on Floor (n))

Where, (n) represents a specific floor.

These April, July, November, and December vacancy rates were extrapolated to estimate month by month averages, which were used to calculate a total annual average vacancy per floor. The annual average vacancy rates were then used to determine an overall average vacancy rate per CHW zone based on average level vacancy rates and modeled usable square footages per level. The low CHW zone serves the concourse level through Level 5, the mid CHW zone serves Levels 6 through 41, and the high CHW zone serves Levels 42 through 103. Based on the total annual average per CHW zone, an annual vacant square footage is determined.

A number of modeled levels are assumed to be vacant to match this annual vacant square footage, which is indicated by the highlighted floors in the tables on the following pages. The vacant levels have been modeled with no internal loads due to tenants (lighting and equipment), and the vacant tenant levels are assumed to have HVAC setbacks to 85°F for cooling and 60°F for heating in the tenant areas, as well as the corridors, restrooms, and building core support spaces on the vacant levels.

Vacancy rate was applied to the "modeled tenant SF" and the resulting vacant spaces were setback. Non-tenant SF (=Total SF –Tenant SF) was assumed to be conditioned, but not setback.

Johnson Controls physically measured all the floor spaces in ESB and calculated the total building SF to be 2,575,565 SF (this includes tenant space, corridors, mechanical rooms, elevator shafts, stairwells, etc). Newmark Knight Frank’s plan book shows that, as much as 2,070,966 SF is used as tenant spaces. These numbers compares closely with the modeled square feet which were based on building floor plans.

In the model, the vacant tenant SF is setback 24/7. In the model, occupied tenant SF, elevator shaft, corridors and stairwells are all setback per the AHU supply fan schedule.

The table on the following page shows the vacancy rate calculations by level and CHW zone.

Page 81: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 75

Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12CM 41175.75 55926.5 Low 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 49.4% 0.0%CO 41175.75 55926.5 Low 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 12.0% 5.0% 11.4% 0.0%LL 46043.4 106210 Low 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 1.4% 1.4% 1.0% 0.0%001 50441.6 80587 Low 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 5.2% 0.0%002 46661.4 80587 Low 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%003 60817.2 80587 Low 50.9% 50.9% 50.9% 50.9% 50.9% 50.9% 62.4% 62.4% 62.4% 62.4% 64.5% 0.0% 51.6% 100.0%004 61532.3 80587 Low 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%005 51508.9 80587 Low 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%006 30545.7 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%007 30490.3 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%008 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%009 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%010 31291.1 45239 Mid 84.7% 84.7% 84.7% 84.7% 84.7% 84.7% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 42.3% 100.0%011 31291.1 45239 Mid 0.2% 0.2% 0.2% 0.2% 0.2% 0.2% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.2% 0.0%012 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%013 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%014 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%015 31291.1 45239 Mid 0.8% 0.8% 0.8% 0.8% 0.8% 0.8% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 0.9% 0.0%016 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%017 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%018 31291.1 45239 Mid 35.7% 35.7% 35.7% 35.7% 35.7% 35.7% 37.9% 37.9% 37.9% 37.9% 61.4% 61.4% 40.7% 0.0%019 31291.1 45239 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%020 31291.1 45239 Mid 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%021 23774.2 35070 Mid 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%022 20324 35070 Mid 98.2% 98.2% 98.2% 98.2% 98.2% 98.2% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 99.1% 100.0%023 23774.2 35070 Mid 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 0.0% 0.0% 83.3% 100.0%024 20324 35070 Mid 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 0.0% 0.0% 0.0% 0.0% 25.6% 25.6% 17.0% 100.0%025 20455.9 28685 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%026 20455.9 28685 Mid 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 23.4% 0.0%027 18012.7 28685 Mid 17.8% 17.8% 17.8% 17.8% 17.8% 17.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 8.9% 0.0%028 18012.7 28685 Mid 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 6.7% 5.2% 14.5% 0.0%029 20406.8 28685 Mid 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%030 15354.1 22454 Mid 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% 26.9% 26.9% 21.1% 0.0%031 15354.1 22454 Mid 45.8% 45.8% 45.8% 45.8% 45.8% 45.8% 22.4% 22.4% 22.4% 22.4% 22.4% 22.4% 34.1% 0.0%032 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%033 15354.1 22454 Mid 9.0% 9.0% 9.0% 9.0% 9.0% 9.0% 9.0% 9.0% 9.0% 9.0% 0.0% 0.0% 7.5% 0.0%034 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%035 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%036 15354.1 22454 Mid 12.3% 12.3% 12.3% 12.3% 12.3% 12.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 6.2% 0.0%037 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%038 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%039 15354.1 22454 Mid 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.1% 68.3% 68.1% 0.0%040 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 5.4% 8.7% 1.2% 0.0%041 15354.1 22454 Mid 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Modeled Vacancy

FloorVacancy RateModeled

Tenant SFAnnual Average

Modeled Total SF

CHW Zone

% Difference

-2.2%

2.4%

14.9%

20.9%

Annual Average

Calculated Vacant

Modeled Vacant SF

60,817

171,185

59,526

175,425

Page 82: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 5: Occupancy Modeling Methodology 76

Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12042 15014.5 22454 High 18.1% 18.1% 18.1% 18.1% 18.1% 18.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 9.0% 0.0%043 15014.5 22454 High 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 23.6% 0.0%044 15014.5 22454 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%045 14705.8 22454 High 25.7% 25.7% 25.7% 25.7% 25.7% 25.7% 25.7% 25.7% 25.7% 25.7% 65.7% 65.7% 32.4% 0.0%046 14705.8 22454 High 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 19.4% 0.0%047 16736.8 22454 High 34.8% 34.8% 34.8% 34.8% 34.8% 34.8% 34.8% 34.8% 34.8% 34.8% 3.3% 18.4% 30.8% 0.0%048 16736.8 22454 High 14.6% 14.6% 14.6% 14.6% 14.6% 14.6% 7.4% 7.4% 7.4% 7.4% 7.4% 7.4% 11.0% 0.0%049 16736.8 22454 High 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 30.2% 0.0%050 16736.8 22454 High 29.4% 29.4% 29.4% 29.4% 29.4% 29.4% 29.6% 29.6% 29.6% 29.6% 29.6% 29.6% 29.5% 0.0%051 16736.8 22454 High 14.8% 14.8% 14.8% 14.8% 14.8% 14.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 7.4% 0.0%052 16736.8 22454 High 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 56.3% 100.0%053 16736.8 22454 High 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 28.3% 0.0%054 16699.4 22454 High 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 62.9% 100.0%055 16297.8 22454 High 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 0.0%056 16297.8 22454 High 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 25.6% 0.0%057 16297.8 22454 High 74.4% 74.4% 74.4% 74.4% 74.4% 74.4% 74.4% 74.4% 74.4% 74.4% 100.0% 100.0% 78.7% 100.0%058 16297.8 22454 High 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%059 17191.3 22454 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%060 16046.4 22454 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%061 16046.4 22454 High 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%062 16046.4 22454 High 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 70.7% 100.0%063 16046.4 22454 High 35.3% 35.3% 35.3% 35.3% 35.3% 35.3% 35.3% 35.3% 35.3% 35.3% 14.2% 14.2% 31.8% 0.0%064 16046.4 22454 High 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 71.2% 100.0%065 17326.5 22454 High 45.1% 45.1% 45.1% 45.1% 45.1% 45.1% 45.1% 45.1% 45.1% 45.1% 20.7% 20.7% 41.0% 0.0%066 17326.5 22454 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%067 17326.5 22454 High 34.0% 34.0% 34.0% 34.0% 34.0% 34.0% 57.1% 57.1% 57.1% 57.1% 83.1% 83.1% 49.9% 100.0%068 17326.5 22454 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%069 17326.5 22454 High 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 100.0%070 18383.7 22454 High 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 0.0% 0.0% 83.3% 100.0%071 18383.7 22454 High 55.8% 55.8% 55.8% 55.8% 55.8% 55.8% 55.8% 55.8% 55.8% 55.8% 0.0% 0.0% 46.5% 100.0%072 14949.5 18891 High 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 48.8% 100.0%073 14949.5 18891 High 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 60.3% 100.0%074 14949.5 18891 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%075 14949.5 18891 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%076 14949.5 18891 High 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 66.9% 66.9% 94.5% 100.0%077 15102.3 18891 High 15.8% 15.8% 15.8% 15.8% 15.8% 15.8% 34.4% 34.4% 34.4% 34.4% 34.4% 34.4% 25.1% 0.0%078 15102.3 18891 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%079 15102.3 18891 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%080 14949.5 18891 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%081 9127.3 13618 High 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 12.7% 0.0%082 8849.2 13618 High 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 7.1% 17.2% 7.9% 0.0%083 8789.9 13618 High 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 21.4% 0.0%084 9256.9 13618 High 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%085 9305.8 12240 High 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 14.9% 18.3% 15.2% 0.0%

Modeled Vacancy

FloorVacancy RateModeled

Tenant SFAnnual Average

Modeled Total SF

CHW Zone

-1.0%

% Difference

33.8%

Annual Average

Calculated Vacant

Modeled Vacant SF

230,440228,058

Page 83: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 77

Appendix 6: ESB eQUEST Model Inputs and Outputs eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

% 20% 20% 23% - per CHW Zone

23% - per CHW Zone

23% - per CHW Zone 23% - per CHW Zone

Lighting, Equipment Loads Reduced Yes Yes Yes Yes Yes Yes

HVAC Setbacks No No Yes Yes Yes Yes

Mechanical Rooms, Stairwells, Elevator shafts Conditioned No No Yes Yes Yes Yes

AHU Cooling Mar 1- Nov 30 Mar 1- Nov 30 Mar 1- Nov 30 Mar 1- Nov 30 Mar 1- Nov 30 Mar 1- Nov 30AHU Heating Dec 1- Feb 28 Dec 1- Feb 28 Dec 1- Feb 28 Dec 1- Feb 28 Dec 1- Feb 28 Dec 1- Feb 28Baseboard Nov 1- Apr 30 Nov 1- Apr 30 Nov 1- Apr 30 Nov 1- Apr 30 Nov 1- Apr 30 Nov 1- Apr 30DHW Year Round Year Round Year Round Year Round Year Round Year Round

Weather Location, Year NY, 2007 NY, 2007 NY, 2012 NY, 2012 NY, 2012 NY, 2012

Electric Utility Rate Year 2007 2007 2007, Escalated 3.02%

2007, Escalated 3.02%

2007, Escalated 3.02% 2012

Steam Utility Rate Year 2007 2007 2007, Escalated 3.02%

2007, Escalated 3.02%

2007, Escalated 3.02% 2012

Cooling Setpoint 76°F 76°F 76°F 76°F 76°F 76°FLighting w/sf 0.67 0.67 0.67 0.67 0.67 0.67Equipment w/sf 0.33 0.33 0.33 0.33 0.33 0.33Roof Absorptance 0.7 0.7 0.7 0.7 0.7 0.7R-Value 14.3 14.3 14.3 14.3 14.3 14.3R-value R-5 R-5 R-5 R-5 R-5 R-5Radiative Barrier na Yes na Yes Yes YesNumber of Radiative Barriers Installed 0 6400 0 6400 6400 6400

Radiative Wall U Value 0.209 0.122 0.209 0.122 0.102 0.102

Season

Utility Data

Corridor

Contract 2012 Performance Year

Vacancy

Roof

Exterior Walls

Page 84: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 78

eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

Storefront (U-value/SHGC) 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82102nd Floor 1.03 / 0.82 1.01 / 0.48 1.01 / 0.48 1.01 / 0.48 1.01 / 0.48 1.01 / 0.4886th Floor 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82 1.03 / 0.82North (U-value/SHGC) 0.48 / 0.645 0.365 / 0.448 0.58 / 0.645 0.365 / 0.448 0.344 / 0.448 0.344 / 0.448East (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325 0.397 / 0.325South (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325 0.397 / 0.325West (U-value/SHGC) 0.48 / 0.645 0.384 / 0.325 0.58 / 0.645 0.384 / 0.325 0.397 / 0.325 0.397 / 0.325Window Infiltration Multiplier 4 2 4 2 2 2

Plug Loads Tenant Plug Density 1.5 w/sf 1.5 w/sf 1.5 w/sf 1.5 w/sf 1.5 w/sf 1.5 w/sfBroadcasting kW 3310 3310 2672 2672 2672 2672Elevator kW 1000 1000 685 685 685 685Exterior Lighting kW 211 211 225 225 225 225Tenant Spaces 1.2 1.2 1.2 1.2 1.2 1.2

Restrooms 1.0 1.0 1.0 1.0 1.0 1.0

Tenant Improvement Spaces 1.2 1.2 1.2 1.2 1.2 0.52

Levels served n/a n/a n/a n/a n/aLevels

11,12,13,24,27,31,33,40,42,53,65,71,75

Chiller Plant Parameters Low Loop Chiller #1 (Elec) Capacity 750 750 VFD 750 750 VFD 750 VFD 750 VFD

kW/ton See Baseline Chiller Curves

See Target Chiller Curves

See Baseline Chiller Curves

See Target Chiller Curves

Custom Curves from Trended

Data

Custom Curves from Trended Data

Chiller #2 (STM) Capacity 1000 1000 1000 1000 1000 1000

Overall COP 1.01 1.01

hp/ton 0.709 0.709lbm/tonhr 13.9 13.9

Chiller Staging Baseload Electric Chiller

Baseload Electric Chiller

Electric Chiller Only

Electric Chiller Only

Electric Chiller Only Electric Chiller Only

Contract 2012 Performance Year

York Chiller Curves

York Chiller Curves

York Chiller Curves York Chiller Curves

Windows

Process Loads

Lighting Power (Watts/sqft)

Page 85: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 79

eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

Chiller Plant Parameters CHW Pumping

Flow Ctrl /MinVFD Manual

(100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Manual (100% Speed All

Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 50% Min)

VFD Manual Modeled (64% Fixed); Actual

((67% (July 1 to October 22nd); 58% Rest of the Time))

Pump Power (kW) 161 161 161 161 161 161Total Pump Head (Feet) 258 258 258 258 258 258Flow (gpm) 2310 /2 2310 /2 2310 /2 2310 /2 2310 /2 2310 /2

CHWST 44F (Fixed) 42F Reset to 50F 44F (Fixed) 42F Reset to

50F 44F (Fixed)

Modeled (Automatic Reset 42F to 50F);

Actual : (Manual Reset 42F to 50F)

Loop Delta T 7.8F (At Design Load)

10F (At Design Load)

7.8F (At Design Load)

10F (At Design Load)

10F (At Design Load)

Modeled (9F (At Design Load)); Actual

(3F to 9F (At Part Load))

Mid Loop Chiller #3 (Stm) Capacity 2000 2000 2000 2000 2000 2000Overall COP 1.09 1.09hp/ton 0.665 0.665lbm/tonhr 13.8 13.8 Chiller #4 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD

Chiller Curves See Baseline Chiller Curves

See Target Chiller Curves

See Baseline Chiller Curves

See Target Chiller Curves

Custom Curves from Trended

Data

Custom Curves from Trended Data

Chiller #5 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD

Chiller Curves See Baseline Chiller Curves

See Target Chiller Curves

See Baseline Chiller Curves

See Target Chiller Curves

Custom Curves from Trended

Data

Custom Curves from Trended Data

Chiller Staging Baseload Electric Chillers

Baseload Electric Chillers

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Contract 2012 Performance Year

York Chiller Curves

York Chiller Curves

York Chiller Curves York Chiller Curves

Page 86: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 80

eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

Chiller Plant Parameters CHW Pumping

Flow Ctrl /MinVFD Manual

(100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Manual (100% Speed All

Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 50% Min)

VFD Manual Modeled (64% Fixed); Actual

(67% (July 1 to October 22nd); 58%

Rest of the Time)

Pump Power (kW) 382 382 382 382 382 382Total Pump Head (Feet) 263 263 263 263 263 263Flow (gpm) 8000 / 4 8000 / 4 8000 / 4 8000 / 4 8000 / 4 8000 / 4

CHWST 44F (Fixed) 42F Reset to 50F 44F (Fixed) 42F Reset to

50F 44F (Fixed)

Modeled (Automatic Reset 42F to 50F);

Actual : (Manual Reset 42F to 50F)

Loop Delta T <6F (At Design Load)

10F (At Design Load)

<6F (At Design Load)

10F (At Design Load)

10F (At Design Load)

Modeled (8F (At Design Load)); Actual

(3F to 8F (At Part Load))

High Loop Chiller #6 (Elec) Capacity 1000 1000 VFD 1000 1000 VFD 1000 VFD 1000 VFD

Chiller Curves See Baseline Chiller Curves

See Target Chiller Curves

See Baseline Chiller Curves

See Target Chiller Curves

Custom Curves from Trended

Data

Custom Curves from Trended Data

Chiller #7 (Stm) Capacity 1000 1000 1000 1000 1000 1000Overall COP 1.03 1.03hp/ton 0.724 0.724lbm/tonhr 13.4 13.4

Chiller Staging Baseload Electric Chillers

Baseload Electric Chillers

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Steam chillers from 7a - 4p

Contract 2012 Performance Year

York Chiller Curves

York Chiller Curves York Chiller CurvesYork Chiller

Curves

Page 87: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 81

eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

Chiller Plant Parameters CHW PumpingVFD Manual

(100% Speed All Times)

VFD Auto (100% to 50% Min)

VFD Manual (100% Speed All

Times)

VFD Auto (100% to 50% Min)

VFD Auto (100% to 50% Min)

VFD Manual Modeled (64% Fixed); Actual

(67% (July 1 to October 22nd); 58%

Rest of the Time)

Pump Power (kW) 252 252 252 252 252 252Total Pump Head (Feet) 268 268 268 268 268 268Flow (gpm) 3000 / 2 3000 / 2 3000 / 2 3000 / 2 3000 / 2 3000 / 2

CHWST 44F (Fixed) 42F Reset to 50F 44F (Fixed) 42F Reset to

50F 44F (Fixed)

Modeled (Automatic Reset 42F to 50F);

Actual : (Manual Reset 42F to 50F)

Loop Delta T 6.9F (At Design Load)

10F (At Design Load)

6.9F (At Design Load)

10F (At Design Load)

10F (At Design Load)

Modeled (10F (At Design Load)); Actual

(2F to 10F (At Part Load))

Number of Cells 10 10 10 10 10 10CW Loop min flow ratio 1 1 0.05 0.05 0.05 0.05

Setpoint Control 70 F Fixed Reset (65 F Min) Fixed (70 F) Reset (65 F Min) Reset (60 F Min)Modeled (Reset (60F

Min)); Actual (60 to 75F Manual)

Tower Fan VFD One Speed Fan VFD on TWRS 4 &5 One Speed Fan VFD on TWRS 4

&5VFD on TWRS 4

&5 VFD on TWRS 4 &5

CW Pump Control CV CV CV CV VFD Auto (100% to 50% Min)

VFD Manual Modeled (56% Fixed); Actual

(50% to 62%)

Contract 2012 Performance Year

Condenser Water System

Page 88: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 82

eQUEST Model Input

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

System Type Single Zone AHU's

Single Zone AHU's

Single Zone AHU's

Single Zone AHU's

Single Zone AHU's Single Zone AHU's

AHU Heat Source Hot Water Hot Water Hot Water Hot Water Hot Water Hot WaterPerimeter Baseboard Steam Steam Steam Steam Steam SteamFan Control CV CV CV CV CV CVOA Reduction - Damper Retrofit (cfm/sf) 0.25 0.15 0.25 0.15 0.15 0.15

OA Reduction - DCV (cfm/sf) 0.15 0.12 0.15 0.12 0.12 0.12

High/Mid Fans 18hrs / 7d (ON-Time)

15hrs / 7d (ON-Time)

18hrs / 7d (ON-Time)

15hrs / 7d (ON-Time)

14hrs / 7d (ON-Time) 13hrs / 7d (ON-Time)

General Exhaust & Toilet Exhaust Fans

24hrs / 7d (ON-Time)

19hrs / 7d (ON-Time)

24hrs / 7d (ON-Time)

19hrs / 7d (ON-Time)

19hrs / 7d (ON-Time) 19hrs / 7d (ON-Time)

Low Zone fan Schedule 5am-12pm (7 d/w)

5am-12pm (7 d/w)

5am-12pm (7 d/w)

5am-12pm (7 d/w)

5am-12pm (7 d/w)

24hrs / 7d (ON-Time) No setback

Cooling Setpoint 76°F 76°F 76°F 76°F 76°F 76°FHeating Setpoint 70°F 70°F 70°F 70°F 70°F 70°FPerimeter Heating Setpoint 70°F 70°F 70°F 70°F 70°F 70°F

System Type Single Zone AHU's

Single Zone AHU's

Single Zone AHU's

Single Zone AHU's

Single Zone AHU's VAV AHUs

AHU Heat Source Hot Water Hot Water Hot Water Hot Water Hot Water Hot WaterPerimeter Baseboard Steam Steam Steam Steam Steam SteamFan Control CV CV CV CV CV CVOA Reduction - Damper Retrofit (cfm/sf) 0.25 0.15 0.25 0.15 0.15 0.15

OA Reduction - DCV (cfm/sf) 0.15 0.12 0.15 0.12 0.12 0.12

Levels served n/a n/a n/a n/a n/aLevels

11,12,13,24,27,31,33,40,42,53,65,71,75

High/Mid Fans 18hrs / 7d (ON-Time)

15hrs / 7d (ON-Time)

18hrs / 7d (ON-Time)

15hrs / 7d (ON-Time)

14hrs / 7d (ON-Time) 13hrs / 7d (ON-Time)

General Exhaust & Toilet Exhaust Fans

24hrs / 7d (ON-Time)

19hrs / 7d (ON-Time)

24hrs / 7d (ON-Time)

19hrs / 7d (ON-Time)

19hrs / 7d (ON-Time) 19hrs / 7d (ON-Time)

Cooling Setpoint 76°F 76°F 76°F 76°F 76°F 76°FHeating Setpoint 70°F 70°F 70°F 70°F 70°F 70°FPerimeter Heating Setpoint 70°F 70°F 70°F 70°F 70°F 70°F

Contract 2012 Performance Year

Typical Floor AHUs (Office)

Tenant Improvement Floor AHUs (Office)

Page 89: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 83

Contract Baseline Contract Target PY Adjusted

Baseline PY Target PY FIM Performance PY Actual Operation

System Type Water-Source Heat Pump

Water-Source Heat Pump

Water-Source Heat Pump

Water-Source Heat Pump

Water-Source Heat Pump

Water-Source Heat Pump

Cooling Source DX DX DX DX DX DXHeating Source Heat-Pump Heat-Pump Heat-Pump Heat-Pump Heat-Pump Heat-Pump

Fan Control Constant Volume Constant Volume Constant Volume Constant Volume Constant Volume Constant Volume

CDW Valve 3-Way 3-Way 3-Way 3-Way 3-Way 3-WayCooling Setpoint 76°F 76°F 76°F 76°F 76°F 76°FHeating Setpoint 70°F 70°F 70°F 70°F 70°F 70°F

System Type Single Zone AHU

Single Zone AHU

Single Zone AHU

Single Zone AHU

Single Zone AHU Single Zone AHU

Cooling Source CHW Plant CHW Plant CHW Plant CHW Plant CHW Plant CHW Plant

Heating Source HW & Baseboards

HW & Baseboards

HW & Baseboards

HW & Baseboards

HW & Baseboards HW & Baseboards

Fan Control Constant Volume Constant Volume Constant Volume Constant Volume Constant Volume Constant Volume

Coil Valve 3-Way 3-Way 3-Way 3-Way 3-Way 3-WayOA Economizer No No No No No NoDCV No No No No No NoCooling Setpoint 76°F 76°F 76°F 76°F 76°F 76°FHeating Setpoint 70°F 70°F 70°F 70°F 70°F 70°F

Heating Assumption Steam Baseboards

Steam Baseboards

n/a - compensated by broadcast

equipment loads

n/a - compensated by

broadcast equipment loads

n/a - compensated by

broadcast equipment loads

n/a - compensated by broadcast equipment

loads

Cooling Assumption DX DXn/a - accounted for in broadcast

kW

n/a - accounted for in broadcast

kW

n/a - accounted for in broadcast

kW

n/a - accounted for in broadcast kW

Contract 2012 Performance Year

Broadcast Floors

2nd Floor / Gift Shop

Concourse / First Level Tenants

Page 90: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 84

2012 Target Model Output

Run Lights HVAC Total Heating Total Electricity SteamConstruction

Period (kW) (W/SF) (kWh) (kWh) (kWh) (klbs) (klbs) ($) ($) ($/SF)

B-0 Base Design 13448 6.69 10,030,865 18,422,049 53,441,964 52,587 75,747 $10,650,964 $2,530,686 $13,181,650 $61 0+Steam Chiller Baseline Adjustment 12720 6.33 10,030,865 18,007,026 53,026,948 52,587 99,332 $10,572,946 $3,088,034 $13,660,980 $6

A1.1 1+2012 Actual Adjusted Vacancy 12309 6.12 9,822,561 17,792,559 52,262,348 47,212 92,104 $10,368,297 $2,867,696 $13,235,993 $6A1.2 A1.1+Condition All Corridors 12234 6.08 8,036,742 17,808,055 50,734,496 49,133 94,414 $10,128,410 $2,942,973 $13,071,383 $6A1.3 A1.2+Extended Cooling Season (May-Oct to Mar-Nov) 12234 6.08 8,036,742 18,963,306 51,889,748 47,991 98,901 $10,361,916 $3,090,218 $13,452,134 $6A1.6 A1.3+All Support Spaces Conditioned 12385 6.16 8,036,742 19,599,042 52,525,496 49,590 100,797 $10,489,286 $3,153,893 $13,643,179 $6A1.7 A1.6+Broadcast Areas to unconditioned 12279 6.11 8,036,742 19,072,289 51,998,724 47,823 99,146 $10,385,146 $3,098,281 $13,483,427 $6A1.8 A1.7+CW Loop Adjustment 12237 6.09 8,036,742 18,132,999 51,059,444 47,823 98,614 $10,225,744 $3,085,645 $13,311,389 $6E-2 A1.8+Radiative Barrier 12237 6.09 8,036,742 18,132,999 51,059,444 42,956 93,126 $10,225,744 $2,905,289 $13,131,033 $6M-3 E-2+Balance of DDC (All Units) 11748 5.84 8,036,742 16,691,702 49,618,156 29,744 80,799 $9,942,098 $2,482,473 $12,424,571 $5M-4 M-3+DCV (All Units) 11637 5.79 8,036,742 16,712,385 49,638,852 26,828 77,880 $9,919,832 $2,381,331 $12,301,163 $5M-5 M-4+Window Option SC75 & TC88 10833 5.39 8,036,742 15,621,885 48,548,344 25,240 73,830 $9,657,624 $2,261,573 $11,919,197 $5M-6 M-5+Chiller (kW/ton and VFD) 10569 5.26 8,036,742 15,267,477 48,193,936 25,240 73,827 $9,565,870 $2,261,512 $11,827,382 $5M-7a M-6+New Plant (CHWL dT) 10658 5.30 8,036,742 14,496,792 47,423,252 25,240 72,403 $9,435,565 $2,221,400 $11,656,965 $5M-7b M-7a+New Plant (CHWL CHW Reset) 10120 5.03 8,036,742 13,930,007 46,856,468 25,240 70,496 $9,276,056 $2,171,341 $11,447,397 $5M-7c M-7b+New Plant (CHWL VSD Pumping and 2-way valves) 10057 5.00 8,036,742 13,740,246 46,666,708 25,240 69,886 $9,232,534 $2,154,399 $11,386,933 $5M-7d M-7c+New Plant (CW Reset to 65F min) 9991 4.97 8,036,742 13,652,466 46,578,932 25,240 69,568 $9,209,289 $2,143,856 $11,353,145 $5M-7e M-7d+New Plant (CWL VSD Pumping) 9991 4.97 8,036,742 13,652,466 46,578,932 25,240 69,568 $9,209,289 $2,143,856 $11,353,145 $5S-1 M-7e+VAV AHUs - 2010,2011 10043 5.00 8,036,742 13,197,672 46,124,124 26,107 70,473 $9,131,993 $2,168,959 $11,300,952 $5S-2 S-1+Reduced Tenant Lighting - 2010,2011 9797 4.87 7,480,470 13,163,088 45,533,272 26,964 70,645 $8,994,068 $2,178,972 $11,173,040 $5S-3 S-2+VAV AHUs - 2012 9798 4.87 7,480,470 12,741,645 45,111,832 27,642 71,609 $8,916,224 $2,206,508 $11,122,732 $5S-4 S-3+Reduced Tenant Lighting - 2012 9570 4.76 6,936,104 12,705,122 44,530,936 28,430 71,800 $8,784,558 $2,216,837 $11,001,395 $5S-5 S-2+Steam Trap Savings 9570 4.76 6,936,104 12,705,122 44,530,936 18,371 82,409 $8,784,558 $1,896,837 $10,681,395 $5

Empire State Building - New York

SteamElectric EnergyPeak

Electric

Utility Costs

Typical Year Costs ($)

Total

Page 91: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 85

2012 Target Model Output

Run Lights HVAC Total Heating Total Electricity SteamConstruction

Period (kW) (W/SF) (kWh) (kWh) (kWh) (klbs) (klbs) ($) ($) ($/SF)

Savings Relative to Previous Measure1 0+Steam Chiller Baseline Adjustment 728 0.36 - 415,023 415,016 - (23,585) $78,018 -$557,348 -$479,330 $0

A1.1 1+2012 Actual Adjusted Vacancy 411 0.20 208,304 214,467 764,600 5,374 7,229 $204,649 $220,338 $424,987 $0A1.2 A1.1+Condition All Corridors 76 0.04 1,785,819 (15,496) 1,527,852 (1,920) (2,310) $239,887 -$75,277 $164,610 $0A1.3 A1.2+Extended Cooling Season (May-Oct to Mar-Nov) - - - (1,155,251) (1,155,252) 1,142 (4,487) -$233,506 -$147,245 -$380,751 $0A1.6 A1.3+All Support Spaces Conditioned (151) (0.08) - (635,736) (635,748) (1,599) (1,897) -$127,370 -$63,675 -$191,045 $0A1.7 A1.6+Broadcast Areas to unconditioned 106 0.05 - 526,753 526,772 1,767 1,651 $104,140 $55,612 $159,752 $0A1.8 A1.7+CW Loop Adjustment 42 0.02 - 939,290 939,280 - 532 $159,402 $12,636 $172,038 $0E-2 A1.8+Radiative Barrier - - - - - 4,867 5,488 $0 $180,356 $180,356 $0M-3 E-2+Balance of DDC (All Units) 489 0.24 - 1,441,297 1,441,288 13,212 12,327 $283,646 $422,816 $706,462 $0M-4 M-3+DCV (All Units) 111 0.06 - (20,683) (20,696) 2,916 2,919 $22,266 $101,142 $123,408 $0M-5 M-4+Window Option SC75 & TC88 804 0.40 - 1,090,500 1,090,508 1,587 4,050 $262,208 $119,758 $381,966 $0M-6 M-5+Chiller (kW/ton and VFD) 264 0.13 - 354,408 354,408 - 3 $91,754 $61 $91,815 $0M-7a M-6+New Plant (CHWL dT) (88) (0.04) - 770,685 770,684 - 1,424 $130,305 $40,112 $170,417 $0M-7b M-7a+New Plant (CHWL CHW Reset) 537 0.27 - 566,785 566,784 - 1,907 $159,509 $50,059 $209,568 $0M-7c M-7b+New Plant (CHWL VSD Pumping and 2-way valves) 63 0.03 - 189,761 189,760 - 610 $43,522 $16,942 $60,464 $0M-7d M-7c+New Plant (CW Reset to 65F min) 66 0.03 - 87,780 87,776 - 318 $23,245 $10,543 $33,788 $0M-7e M-7d+New Plant (CWL VSD Pumping) - - - - - - - $0 $0 $0 $0S-5 S-2+Steam Trap Savings - - - - - 10,059 (10,609) $0 $320,000 $320,000 $0

SteamElectric EnergyPeak

Electric

Utility Costs

Typical Year Costs ($)

Total

Page 92: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 86

2012 ECM Model Output

Run Lights HVAC Total Heating Total Electricity SteamConstruction

Period(kW) (W/SF) (kWh) (kWh) (kWh) (klbs) (klbs) ($) ($) ($/SF)

B-0 Base Design 13448 6.69 10,030,865 18,422,049 53,441,964 52,587 75,747 $10,650,964 $2,530,686 $13,181,650 $61 0+Steam Chiller Baseline Adjustment 12720 6.33 10,030,865 18,007,026 53,026,948 52,587 99,332 $10,572,946 $3,088,034 $13,660,980 $6

A1.1 1+2012 Actual Adjusted Vacancy 12309 6.12 9,822,561 17,792,559 52,262,348 47,212 92,104 $10,368,297 $2,867,696 $13,235,993 $6A1.2 A1.1+Condition All Corridors 12234 6.08 8,036,742 17,808,055 50,734,496 49,133 94,414 $10,128,410 $2,942,973 $13,071,383 $6A1.3 A1.2+Extended Cooling Season (May-Oct to Mar-Nov) 12234 6.08 8,036,742 18,963,306 51,889,748 47,991 98,901 $10,361,916 $3,090,218 $13,452,134 $6A1.6 A1.3+All Support Spaces Conditioned 12386 6.16 8,036,742 19,611,297 52,537,736 49,612 100,807 $10,496,350 $3,154,377 $13,650,727 $6A1.7 A1.6+Broadcast Area HVAC adjustment 12280 6.11 8,036,742 19,079,384 52,005,844 47,845 99,197 $10,391,406 $3,099,732 $13,491,138 $6A1.8 A1.7+CW Loop Adjustment 12239 6.09 8,036,742 18,206,587 51,133,052 47,845 98,634 $10,227,077 $3,086,381 $13,313,458 $6E-2 A1.8+Radiative Barrier 12239 6.09 8,036,742 18,206,587 51,133,052 41,857 91,882 $10,227,077 $2,864,491 $13,091,568 $6M-3 E-2+Balance of DDC (All Units) 11761 5.85 8,036,742 16,281,167 49,207,636 28,359 79,457 $9,869,021 $2,436,814 $12,305,835 $5M-4 M-3+DCV (All Units) 11650 5.79 8,036,742 16,300,433 49,226,892 25,599 76,635 $9,849,944 $2,339,012 $12,188,956 $5M-5 M-4+Window Option SC75 & TC88 10846 5.39 8,036,742 15,258,567 48,185,024 23,960 72,502 $9,591,902 $2,216,887 $11,808,789 $5M-6 M-5+Chiller (kW/ton and VFD, Custom Curves) 10489 5.22 8,036,742 15,024,417 47,950,880 23,960 72,496 $9,504,082 $2,216,742 $11,720,824 $5M-7a M-6+New Plant (CHWL dT) 10450 5.20 8,036,742 14,103,998 47,030,456 23,960 70,635 $9,335,255 $2,165,313 $11,500,568 $5M-7b M-7a+New Plant (CHWL Load Reset) 10450 5.20 8,036,742 14,103,998 47,030,456 23,960 70,635 $9,335,255 $2,165,313 $11,500,568 $5M-7c M-7b+New Plant (CHWL VFD Pumping and 2-way valves) 10393 5.17 8,036,742 13,893,614 46,820,076 23,960 69,985 $9,293,963 $2,147,256 $11,441,219 $5M-7d M-7c+New Plant (CW Reset to 60) 10327 5.14 8,036,742 13,757,858 46,684,324 23,960 69,797 $9,261,931 $2,140,849 $11,402,780 $5M-7e M-7d+New Plant (CWL VFD Pumping) 10123 5.04 8,036,742 13,621,297 46,547,756 23,960 70,998 $9,205,259 $2,169,727 $11,374,986 $5S-1 M-7e+VAV AHUs - 2010,2011 10090 5.02 8,036,742 13,197,719 46,124,184 24,733 71,824 $9,122,013 $2,192,332 $11,314,345 $5S-2 S-1+Reduced Tenant Lighting - 2010,2011 9869 4.91 7,480,470 13,159,910 45,530,100 25,572 71,918 $8,986,612 $2,200,440 $11,187,052 $5S-3 S-2+VAV AHUs - 2012 9830 4.89 7,480,470 12,780,690 45,150,884 26,141 72,876 $8,912,282 $2,226,791 $11,139,073 $5S-4 S-3+Reduced Tenant Lighting - 2012 9636 4.79 6,936,104 12,741,379 44,567,204 26,904 72,974 $8,783,459 $2,234,743 $11,018,202 $5S-5 S-2+Steam Trap Savings 9636 4.79 6,936,104 12,741,379 44,567,204 16,845 62,915 $8,783,459 $1,914,743 $10,698,202 $5

Empire State Building - New York

SteamElectric EnergyPeak

Electric

Utility Costs

Typical Year Costs ($)

Total

Page 93: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 6: ESB eQUEST Model Input Table 87

2012 ECM Model Output

Run Lights HVAC Total Heating Total Electricity SteamConstruction

Period(kW) (W/SF) (kWh) (kWh) (kWh) (klbs) (klbs) ($) ($) ($/SF)

Savings Relative to Previous Measure1 0+Steam Chiller Baseline Adjustment 728 0.36 - 415,023 415,016 - (23,585) $78,018 -$557,348 -$479,330 $0

A1.1 1+2012 Actual Adjusted Vacancy 411 0.20 208,304 214,467 764,600 5,374 7,229 $204,649 $220,338 $424,987 $0A1.2 A1.1+Condition All Corridors 76 0.04 1,785,819 (15,496) 1,527,852 (1,920) (2,310) $239,887 -$75,277 $164,610 $0A1.3 A1.2+Extended Cooling Season (May-Oct to Mar-Nov) - - - (1,155,251) (1,155,252) 1,142 (4,487) -$233,506 -$147,245 -$380,751 $0A1.6 A1.3+All Support Spaces Conditioned (153) (0.08) - (647,991) (647,988) (1,621) (1,906) -$134,434 -$64,159 -$198,593 $0A1.7 A1.6+Broadcast Area HVAC adjustment 106 0.05 - 531,913 531,892 1,767 1,610 $104,944 $54,645 $159,589 $0A1.8 A1.7+CW Loop Adjustment 42 0.02 - 872,797 872,792 - 563 $164,329 $13,351 $177,680 $0E-2 A1.8+Radiative Barrier - - - - - 5,988 6,752 $0 $221,890 $221,890 $0M-3 E-2+Balance of DDC (All Units) 477 0.24 - 1,925,420 1,925,416 13,498 12,426 $358,056 $427,677 $785,733 $0M-4 M-3+DCV (All Units) 111 0.06 - (19,266) (19,256) 2,760 2,821 $19,077 $97,802 $116,879 $0M-5 M-4+Window Option SC75 & TC88 804 0.40 - 1,041,866 1,041,868 1,639 4,133 $258,042 $122,125 $380,167 $0M-6 M-5+Chiller (kW/ton and VFD, Custom Curves) 357 0.18 - 234,150 234,144 - 6 $87,820 $145 $87,965 $0

M-7a M-6+New Plant (CHWL dT) 39 0.02 - 920,419 920,424 - 1,861 $168,827 $51,429 $220,256 $0M-7b M-7a+New Plant (CHWL Load Reset) - - - - - - - $0 $0 $0 $0M-7c M-7b+New Plant (CHWL VFD Pumping and 2-way valves) 56 0.03 - 210,384 210,380 - 650 $41,292 $18,057 $59,349 $0M-7d M-7c+New Plant (CW Reset to 60) 66 0.03 - 135,756 135,752 - 187 $32,032 $6,407 $38,439 $0M-7e M-7d+New Plant (CWL VFD Pumping) 204 0.10 - 136,561 136,568 - (1,201) $56,672 -$28,878 $27,794 $0S-5 S-2+Steam Trap Savings - - - - - 10,059 10,059 $0 $320,000 $320,000 $0

SteamElectric EnergyPeak

Electric

Utility Costs

Typical Year Costs ($)

Total

Page 94: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 7: Utility Analysis 88

Appendix 7: Utility Analysis Degree Day Analysis:

Figure A.7.1: Reduction in ESB’s 2007 Baseline Electric Utility Consumption during Performance Period

Analyzing the electric profile which compares electric usage from the Baseline year of 2007 and Year 2 (2012) as a function of CDD clearly validates improved building performance as the Post-Installation slope is lower than the Pre-Installation and the y-intercept is lower as well. The fact that the Year 2 curve has a lower slope than the Baseline year, the building electric savings will increase during warmer ambient conditions in the summer season. For example, during a typical shoulder month of 200 CDD, the building electric savings equates to 1,263,000 kWh or $265,222 utilizing the $.21/kWh rate. In addition, during a typical summer month of 400 CDD, the electric savings would equal 1,526,000 kWh with a cost savings of $320,443 utilizing the $.21/kwh rate.

The lower electric base load consumption level (y-intercept) for the Post-Installation conditions indicates a performance improvement during non-cooling conditions as well.

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

0 50 100 150 200 250 300 350 400 450 500

Elec

tric

Con

sum

ptio

n(k

Wh)

CDD

Electric Consumption Vs CDD

2007 Electric

2011 Electric

2012 Electric

29% Reduction in BaseConsumption

34% Reduction Duringthe Hottest Month

Page 95: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 7: Utility Analysis 89

Figure A.7.2: Reduction in ESB’s 2007 Baseline Steam Utility Consumption during Performance Period

Analyzing the thermal profile graph which compares the Baseline year (2007) and the Year 2 (2012) total building steam usage (Mlbs) as a function of HDD clearly indicates improved building performance throughout the heating seasons. The Year 2 curve has a lower slope than the Baseline curve which indicates that during colder ambient periods the building consumes less steam to maintain proper building temperature conditions. In addition, as the ambient temperature gets colder the savings rise substantially due to the improved performance of the building. For example, during a typical shoulder month of 400 heating degree days, the steam savings calculated would equate to 3325 Mlbs or $99,739 utilizing the rate of $30/Mlb. Additionally, the steam savings would elevate to a level of $214,430 during a typical winter month of 800 HDD with a $30/Mlb utility rate.

The steam usage base load for the building during the non-HDD periods can be attributed to the operation of the steam chillers for cooling. The deviation in the y-intercept (steam base load) between the plotted years can be referenced back to the variation in occupancy and weather during the cooling seasons.

The steam usage patterns for January and February of 2012 are significantly higher than expected due to the steam trap failures diagnosed last year and the overheating of construction areas with limited temperature control capabilities.

EUI Analysis

Energy Use Intensity is a measure of a building’s total energy consumption compared to its size. At the Empire State Building, both electrical (kWh) and thermal steam (Mlb) have been yearly totalized and converted to kBtu. Adjusting for weather, this energy is then divided by ESB’s square feet to represent EUI. When comparing ESB against other office buildings in Manhattan and around NYC, ESB is a leader. Results prove that the energy efficient steps being made at ESB have made a significant impact.

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

0 200 400 600 800 1000 1200

Stea

m C

onsu

mpt

ion

(mlb

s)

HDD

Winter Steam Consumption Vs HDD

2007 Winter Steam Usage

2011 Winter Steam Usage

2012 Winter Steam Usage

7% to 31% Reduction in Consumption During the Coldest Month

Page 96: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 7: Utility Analysis 90

For the purpose of calculating ESB’s EUI the following assumptions were made: a) Total square feet of 2,750,847 was used for floors LL to 84 building area. b) The broadcasting floor electric usage was deducted from total electric utility c) It was assumed that the broadcasting equipment generates a lot of heat and that minimal steam

is used for space heating. d) Annual EUI was normalized for ‘30 year normal’ (1971-2000) degree days from NOAA (Nation

Oceanic & Atmospheric Administration). New York City Central Park weather Station data was used and a 65°F Base was assumed. Monthly degree day data taken from degreedays.net

Figure A.7.3: Reduction in ESB’s EUI during Performance Period

Figure A.7.4: Median NYC Office Building EUI = 213.3 (Source: NYC Local Law 84

Benchmarking Report Aug ’12 - nyc.gov)

Page 97: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 7: Utility Analysis 91

Figure A.7.3 shows ESB’s EUI during the project PYs. Figure A.7.4 shows the EUI for median NYC office buildings. Comparing ESB's EUI against a typical office space is not an apples-to-apples comparison due to the variance introduced by broadcasting, lower level, concourse, observation deck usage patterns. But, there is still some value in comparing them as long as this variance is understood.

Although LL and Concourse do not reflect normal office conditions, sensitivity analysis shows that the abnormality does not affect the overall EUI much. Figure A.7.4 histogram suggests that ESB's EUI lies within the 5% to 10% of the sample. ESB has an active energy and maintenance program that validates this level of performance.

General Utility Analysis: 2007 2008 2011 2012

Customer Charge ($/day) $2.13 $2.13

G&T Demand $/kW $5.81 $5.92 $8.00 $6.43

Energy Charges $/kWh $0.1564 $0.1648 $0.1262 $0.1303

Primary Demand (Jun - Sep) $/kW $10.78 $10.76 $14.97 $17.80

Secondary Demand (Jun - Sep) $/kW $12.16 $12.14 $16.06 $19.55

Primary Demand (Oct - May) $/kW $7.98 $7.97 $11.04 $11.04

Secondary Demand (Oct - May) $/kW $3.87 $3.87 $5.15 $5.15

Table A.7.1: Baseline and Performance Period Electric Utility Rate Comparison

2007 2008

Monthly Charge $/month $2,722.18 $2,722.18

General Demand Charge $/therm/hr $10.526 $10.526

Steam Demand Peak $/therm/hr $99.62 $99.623

Summer Steam Consumption

First 2,500 Mlbs $/therm $2.176 $2.176

Next 7,500 Mlbs $/therm $2.428 $2.428

All additional Mlbs $/therm $2.363 $2.363

Winter Steam Consumption

First 2,500 Mlbs $/therm $2.187 $2.187

Next 12,500 Mlbs $/therm $3.226 $3.226

Next 35,000 Mlbs $/therm $3.106 $3.106

Next 200,000 Mlbs $/therm $3.044 $3.044

All additional Mlbs $/therm $2.953 $2.953

Swing Steam Consumption

First 2,500 Mlbs $/therm $2.275 $2.275

Page 98: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 7: Utility Analysis 92

2007 2008

Next 12,500 Mlbs $/therm $3.661 $3.661

Next 35,000 Mlbs $/therm $3.500 $3.500

Next 200,000 Mlbs $/therm $3.418 $3.418

All additional Mlbs $/therm $3.297 $3.297

Table A.7.2: 2007 and 2008 Steam Utility Rate Structure

2011 2012

Customer Charge* $/day $207.71 $232.90

On Peak Demand Charge* $/Mlb/hr $151.029 $170.031

All time Peak Demand Charge* $/Mlb/hr $1,453.868 $1,636.708

Summer Steam Consumption

All additional Mlbs (already includes GRT, taxes) $/Mlb $16.7038 $15.1898

Winter Steam Consumption

All additional Mlbs (already includes GRT, taxes) $/Mlb $32.4182 $32.3476

Swing Steam Consumption

All additional Mlbs (already includes GRT, taxes) $/Mlb $35.6835 $34.0221

*GRT taxes 2.4808% 2.8144%

*State and City Taxes 8.8750% 8.8750%

Table A.7.3: 2011 and 2012 Steam Utility Rate Structure

Page 99: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 8: FPI 93

Appendix 8: FPI Delivered by Johnson Controls Building Efficiency, JCFPI is a Web-Based, user-friendly performance and diagnostics information management system that continuously measures the operating characteristics of heating and air conditioning systems. Using this information, facility owners and maintenance personnel can identify energy saving opportunities as well as identify equipment deficiencies before failure events occur. This information can be used to drive and focus a facility maintenance program.

JCFPI simplifies complex, and often obscure data, into usable information that any user can instantly understand. Armed with JCFPI measurements, intelligent decisions regarding capital expenditures and maintenance activities can be made. Using the intuitive web-based user-interface and the built-in report generator, JCFPI can quickly recognize and then prioritize the under-performing systems. Personnel can then make adjustments and use JCFPI to verify the success of changes with immediate feedback. JCFPI provides a continuous and consistent relative-performance measurement. JCFPI is a “Commission as You Go” tool that transforms the traditional calendar-based maintenance strategy to a proactive condition-based strategy. The Chiller Performance analysis compares actual chiller performance to a software model of the manufacturer’s part-load performance curve. The JCFPI system can be installed behind the customer’s Firewall or be located in the Cloud. JCFPI can also e-Mail JCFPI Reports to any e-Mail address on a daily, weekly or monthly basis. To ensure data integrity, JCFPI now is capable of emailing a daily heartbeat notification or, should it occur, a data collection failure notification to the user(s). With JCFPI, managing facilities and managing the associated data becomes easier.

ESB FPI Features Johnson Controls Facility Performance Indexing (JCFPI) consists of up to five available sections: HVAC & Utility Meter Performance monitoring, Chiller Performance Analysis, Measurement & Verification Reporting and Metasys® BAS Diagnostics’.

Performance Monitoring

Johnson Controls has developed patented algorithms to evaluate and measure system and facility performance. This continuous condition assessment is an extremely valuable management tool that provides facilities management with the knowledge to manage the life cycle and maintenance costs of the assets effectively. Managers will have the data they need to achieve optimum performance, increase reliability, reduce unnecessary maintenance, sustain useful asset life and improve life cycle cost.

Continuous Measurement

Data is continuously collected from the BAS. That data is stored in an SQL database, where the performance algorithms calculate the performance indices. Consistent performance parameters are used allowing for an ‘apples-to-apples’ comparisons of system performance.

Data Simplified

Today’s BAS systems produce tremendous amounts of data. JCFPI simplifies the vast amounts of data, and focuses the end-user on what is really important. The data is accessed thru a simple to use web page. JCFPI uses an intuitive red, yellow, green color format on the performance web page along with a zero to100-based performance index. Instead of the traditional single-point failure alarm, JCFPI evaluates the entire control strategy of each individual piece of HVAC equipment (including air handlers, chillers, boilers, roof top units, heat exchangers, variable air volume boxes, and more) using benchmarks

Page 100: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 8: FPI 94

established in the twelve years of JCFPI’s development. JCFPI easily evaluates large quantities of equipment and simplifies complex data for everybody - regardless of experience.

Measurement and Verification Reporting

JCFPI collects data from the BAS and stores that data in the JCFPI server database. The data is accessible thru the JCFPI web page. Using the calendar controls of the web pages, the user can easily select the data they need and then off-load that data in various formats directly to their computers. The trended data can be viewed as charts or in tabular formats. This data can include trended information, system runtimes and energy meter totalization. This data can then be utilized to prove energy savings and identify energy waste. The data can also be used to support the continuous measurement requirements of LEED EB certification.

Advantages of ESB FPI JCFPI is used for continuous commissioning of existing buildings and for commissioning of new facilities. Unlike traditional methods for commissioning which involve limited “point in time” data collection, JCFPI collects and analyzes data continuously. JCFPI can be used for continuous commissioning to earn additional LEED points when applying for LEED EB certification.

JCFPI will:

• Identify problems before typical alarm or failure events occur

• Identify problems you were unaware of

• Provide root-cause analysis

• Confirm existing problems

• Provide something unique; a relative measurement

• Easily identify opportunities for improving control and performance

• Help prioritize maintenance activities

• Identify when maintenance is required

• Enable a shift to condition-based maintenance strategies

• Provide a simple, easy-to-use web-based interface

• Provide immediate feedback as changes are implemented

• Validate the success or failure of maintenance or control changes

• Provide a Baseline performance measurement

• Generate performance reports based on user selections identifying the poorest performers for the period of time selected

• Utilize the existing points in the control system

• Automatically update JCFPI software

JCFPI will not:

• Generate alarms

• Fix problems -It identifies problems

Page 101: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 8: FPI 95

ESB FPI Dashboard A snapshot of the live FPI system at ESB is shown in Figure A6.1. This dashboard shows both the Systems and Components level summary of the building and the associated performance index range at that time. During 2012, further customer training has been completed at ESB (Nov 27th), as well as a FPI system update. This update includes the addition of any new building systems (since completion of base project 2010) associated with the ongoing floor build-outs at ESB. The current system is analyzing 1,883 systems, 10,420 components, and 20,853 points.

Figure A.8.1: Screenshot Showing ESB FPI Dashboard

BAS System Compliance with FPI A snapshot of a sample compliance report that is generated by FPI is shown in Figure A6.2. This particular report is from 11AM 12/19/12. The compliance report provides a way to identify “poor” performing systems and helps indicate the reason for underperformance. This includes, but not limited to, deviation from setpoint or command status, and helps prioritize where to focus corrective actions within the building. As ESB optimizes their building, the system compliance scores will increase and turn “green”.

Page 102: Performance Year 2 M&V Report - esbnyc.com€¦ · Empire State Building PY 2 M&V Report . Empire State Building Performance Year 2 M&V Report . March 1, 2013 Rev.1 (August 15, 2013)

Appendix 8: FPI 96

Figure A.8.2: Screenshot Showing ESB FPI System Compliance

ESB FPI System Diagnostics The example below shows FPI tracking zone temperature and comparing it to zone setpoint. This zone (46th floor) is achieving poor performance as the space temperature is much higher than setpoint. Identifying problem areas like these can help ESB mitigate tenant complaints, possibly before they happen and also help to save energy.

Figure A.8.3: Screenshot Showing ESB FPI System Diagnostics